Kissimmee Basin ProjectsJan 2005Jan 2005
Kissimmee Basin ProjectsJan 2005Jan 2005
Kissimmee Basin Projects Kissimmee Basin Projects Kissimmee River Restoration Project
(KRR) Kissimmee Chain of Lakes Long Term
Management Plan (KCOL LTMP) Kissimmee Basin Modeling and
Operations Study (Model) EIS for Modification of Kissimmee
Basin Structure Operating Criteria (EIS)
Kissimmee River Restoration Project (KRR)
Kissimmee Chain of Lakes Long Term Management Plan (KCOL LTMP)
Kissimmee Basin Modeling and Operations Study (Model)
EIS for Modification of Kissimmee Basin Structure Operating Criteria (EIS)
Kissimmee River Restoration Project
Kissimmee River Restoration Project
Goal is to restore ecological integrity to the central region of the Kissimmee river and floodplain
Projected cost = $578 million 50/50 cost share USCOE/SFWMD Backfill 22 mi of C-38 canal Recarve/reconnect more than 40 mi
of river channel Remove 2 water control structures
(one has been removed) Headwaters Revitalization Project
provides additional water storage from headwater lakes for river restoration
Comprehensive restoration evaluation program
Goal is to restore ecological integrity to the central region of the Kissimmee river and floodplain
Projected cost = $578 million 50/50 cost share USCOE/SFWMD Backfill 22 mi of C-38 canal Recarve/reconnect more than 40 mi
of river channel Remove 2 water control structures
(one has been removed) Headwaters Revitalization Project
provides additional water storage from headwater lakes for river restoration
Comprehensive restoration evaluation program
KRR Comprehensive Restoration Evaluation Program ComponentsKRR Comprehensive Restoration Evaluation Program Components
Hydrology Geomorphology Dissolved Oxygen and
Water Quality Plant communities Invertebrate
communities Reptile and Amphibian
communities Fish communities Bird communities Threatened and
Endangered species
Hydrology Geomorphology Dissolved Oxygen and
Water Quality Plant communities Invertebrate
communities Reptile and Amphibian
communities Fish communities Bird communities Threatened and
Endangered species
Kissimmee River Restoration Project Status
Kissimmee River Restoration Project Status
Phase I construction completed - 2001
Initiation of next backfilling phase – by 2006
All construction completed - 2012
Headwaters Revitalization Project – underway, will be completed in 2010
Restoration Evaluation - through 2017
Phase I construction completed - 2001
Initiation of next backfilling phase – by 2006
All construction completed - 2012
Headwaters Revitalization Project – underway, will be completed in 2010
Restoration Evaluation - through 2017
Real Estate
Headwaters
Phase I
Phase II/III
Phase IVa
Phase IVb
Restoration Evaluation
1990 20202000 2010
Kissimmee Chain of Lakes Long Term Management Plan
Kissimmee Chain of Lakes Long Term Management Plan
Purpose: improve, enhance and/or sustain ecosystem health of regulated lakes in the Kissimmee Upper Basin while balancing basin impacts
Collaborative effort SFWMD, USCOE, FFWCC,
USFWS, EPA, DEP, FDACS local governments, and other stakeholders
Purpose: improve, enhance and/or sustain ecosystem health of regulated lakes in the Kissimmee Upper Basin while balancing basin impacts
Collaborative effort SFWMD, USCOE, FFWCC,
USFWS, EPA, DEP, FDACS local governments, and other stakeholders
1) Assess Status Ecosystem Health / Develop Performance Measures2) Determine Baseline Conditions3) Identify opportunities for individual action by stakeholder agencies for situations where Baseline Conditions do not meet Performance Measures
Kissimmee Chain of Lakes Long Term Management Plan -
Products
Kissimmee Chain of Lakes Long Term Management Plan -
Products Stakeholder values survey
Conceptual ecosystem model
Assessment of current (baseline) and reference characteristics of lakes
Assessment performance measures that describe desired characteristics of lakes Examples: wading bird reproduction, invertebrate
community composition, desired fluctuation levels, etc.
Stakeholder values survey
Conceptual ecosystem model
Assessment of current (baseline) and reference characteristics of lakes
Assessment performance measures that describe desired characteristics of lakes Examples: wading bird reproduction, invertebrate
community composition, desired fluctuation levels, etc.
Kissimmee Chain of Lakes Long Term Management Plan -
Products
Kissimmee Chain of Lakes Long Term Management Plan -
Products Monitoring plan
Review of existing monitoring data
Address knowledge gaps
Are performance measures being met?
Agency action plans How can agency
mandates and resources be applied to achieve unmet performance measures?
Monitoring plan Review of existing
monitoring data Address knowledge
gaps Are performance
measures being met?
Agency action plans How can agency
mandates and resources be applied to achieve unmet performance measures?
Kissimmee Basin Modeling and Operations Study
Kissimmee Basin Modeling and Operations Study
Flows through the Kissimmee Chain of Lakes and Kissimmee River are regulated by control structures
Goal: assess whether existing operations can be modified to achieve a better balance among
Flood control
Water supply
Aquatic plant management
Kissimmee Basin natural resources (KRR, KCOL)
Downstream discharge area (Lake Okeechobee)
Flows through the Kissimmee Chain of Lakes and Kissimmee River are regulated by control structures
Goal: assess whether existing operations can be modified to achieve a better balance among
Flood control
Water supply
Aquatic plant management
Kissimmee Basin natural resources (KRR, KCOL)
Downstream discharge area (Lake Okeechobee)
Kissimmee Basin Modeling and Operations Study - Approach
Kissimmee Basin Modeling and Operations Study - Approach
Geographic scope includes entire Kissimmee Basin
Hydrologic/hydraulic simulation model
Simulate a suite of regulation schedules for 13 structures in the Kissimmee Basin
Use performance measures to evaluate and select “best” operational criteria
Recommend regulation changes based on operational criteria selected
Geographic scope includes entire Kissimmee Basin
Hydrologic/hydraulic simulation model
Simulate a suite of regulation schedules for 13 structures in the Kissimmee Basin
Use performance measures to evaluate and select “best” operational criteria
Recommend regulation changes based on operational criteria selected
KB Modeling & Operations Study
Flood Control
Water Supply
Aquatic Plant Management
Natural Resources
Downstream Ecosystems
KB Modeling & Operations Study
Flood Control
Water Supply
Aquatic Plant Management
Natural Resources
Downstream Ecosystems
Progress to dateProgress to date Completed Basin Assessment and model implementation
strategy
3 Modeling Tools will be developed
Screening Tool
Alternative Formulation / Evaluation Tool
Performance Measure Evaluation Tool
Reconnaissance and data collection efforts for modeling tool implementation are complete
Design for tool implementation is 80% complete.
Tool implementation 10% complete
Beginning alternative plan formulation process
Completed Basin Assessment and model implementation strategy
3 Modeling Tools will be developed
Screening Tool
Alternative Formulation / Evaluation Tool
Performance Measure Evaluation Tool
Reconnaissance and data collection efforts for modeling tool implementation are complete
Design for tool implementation is 80% complete.
Tool implementation 10% complete
Beginning alternative plan formulation process
EIS for Modification of Kissimmee Basin
Structure Operating Criteria
EIS for Modification of Kissimmee Basin
Structure Operating Criteria
Parallel project with KB Modeling & Operations Study
Perform NEPA work associated with developing EIS USACE & USFWS
Parallel project with KB Modeling & Operations Study
Perform NEPA work associated with developing EIS USACE & USFWS
PurposePurpose
Provide a balanced approach to formulating and evaluating modifications to Kissimmee Basin operating criteria
Approach will take into account flood control, water supply, aquatic plant management, and natural resource requirements
Provide a balanced approach to formulating and evaluating modifications to Kissimmee Basin operating criteria
Approach will take into account flood control, water supply, aquatic plant management, and natural resource requirements
GoalGoal
Seek an alternative that maximizes benefits while minimizing potential adverse impacts
Seek an alternative that maximizes benefits while minimizing potential adverse impacts
Major ActivitiesMajor Activities Evaluate alternatives relative to potential beneficial and
adverse effects on Flood control Navigation Water quality Water supply Wetlands and fish and wildlife habitats and values Endangered and threatened species Historical or archaeological resources Public use and recreation
Evaluate alternatives relative to potential beneficial and adverse effects on Flood control Navigation Water quality Water supply Wetlands and fish and wildlife habitats and values Endangered and threatened species Historical or archaeological resources Public use and recreation
Kissimmee
EIS
Geographic
Scope
Kissimmee EIS StatusKissimmee EIS Status Project Management Plan, Kissimmee
Basin, Modification of Kissimmee Basin Structure Operating Criteria, USACE, July 2005
Notice of Intent to Prepare a Draft Environmental Impact Statement, USACE, July 2005
Scoping Letter, Modification of Kissimmee Basin Structure Operating Criteria, July 2005
Currently working on DRAFT EIS
Project Management Plan, Kissimmee Basin, Modification of Kissimmee Basin Structure Operating Criteria, USACE, July 2005
Notice of Intent to Prepare a Draft Environmental Impact Statement, USACE, July 2005
Scoping Letter, Modification of Kissimmee Basin Structure Operating Criteria, July 2005
Currently working on DRAFT EIS
Questions?