LHCC meeting, Nov 25, 2002 Slide 2
Torre Wenaus, BNL/CERN
Initiation of AA Work via SC2-RTAGS
Applications Area prerequisite and priority for initiating work: RTAGs successfully addressing common projects And SC2 turning over project mandates to the PEB-AA
Initial round of project mandates emerged from RTAGs in April Software process Persistency framework Math libraries
Second round emerging now Architecture blueprint (guidance for all projects; work for
several) Event generators Detector description Simulation
Translation into AA projects…
LHCC meeting, Nov 25, 2002 Slide 3
Torre Wenaus, BNL/CERN
Apps Area Project Status
Apr: Software process and infrastructure (SPI) – Alberto Aimar
Apr: Persistency framework (POOL) – Dirk Duellmann
Jun: Math libraries – Fred James Oct: Core libraries and services (CLS) – Pere Mato Nov: Physicist Interface (PI) – Vincenzo Innocente Event generators (Project activity pending) Detector description (RTAG complete; SC2 deliberating) Simulation (RTAG complete; SC2 deliberating)
Status relative to preliminary plans at March Launch Week…
LHCC meeting, Nov 25, 2002 Slide 4
Torre Wenaus, BNL/CERN
Top Priorities from March – A Current Look
1. Establish process and infrastructure project (Active)
2. Address core areas essential to building a coherent architecture, and develop the architecture
Object dictionary (Active) Persistency (Active) Interactive frameworks (Launched), analysis tools (Partially
launched)
3. Address priority common project opportunities Driven opportunistically by a combination of experiment need,
appropriateness to common project, and ‘the right moment’ (existing but not entrenched solutions in some experiments)
Detector description and geometry model (RTAG complete; SC2 deliberating)
Driven by need and available manpower Simulation tools (RTAG complete; SC2 deliberating)
Initiate: First half 2002
LHCC meeting, Nov 25, 2002 Slide 5
Torre Wenaus, BNL/CERN
Near term priorities from March
Build outward from the core top tier components Conditions database (Pending, but common tool exists) Framework services, class libraries (Launched)
Address common project areas of less immediate priority Math libraries (Active) Physics packages (Mandate received by PEB-AA)
Extend and elaborate the support infrastructure Software testing and distribution (Active)
Initiate: Second half 2002
Deliver: fall/late 2002: basic working persistency framework (On schedule)
LHCC meeting, Nov 25, 2002 Slide 6
Torre Wenaus, BNL/CERN
Medium term priorities from March
The core components have been addressed, architecture and component breakdown laid out, work begun. Grid products have had another year to develop and mature. Now explicitly address physics applications integration into the grid applications layer.
Distributed production systems. End-to-end grid application/framework for production.
Distributed analysis interfaces. Grid-aware analysis environment and grid-enabled tools.
Blueprint RTAG recommends prompt attention (RTAG) Under SC2 consideration
Some common software components are now available. Build on them.
Lightweight persistency, based on persistency framework Release LCG benchmarking suite
Initiate: First half 2003
LHCC meeting, Nov 25, 2002 Slide 7
Torre Wenaus, BNL/CERN
02Q1 02Q2 02Q3 02Q4 03Q1 03Q2 03Q3 03Q4 04Q1 04Q2Simulation tools XDetector description & model XConditions database XData dictionary XInteractive framew orks XStatistical analysis XDetector & event visualization XPhysics packages XFramew ork services XC++ class libraries XEvent processing framew ork XDistributed analysis interfaces XDistributed production systems XSmall scale persistency XSoftw are testing XSoftw are distribution XOO language usage XLCG benchmarking suite XOnline notebooks X
Candidate RTAG timeline from March
Blue: RTAG/activity launched or (light blue) imminent
LHCC meeting, Nov 25, 2002 Slide 8
Torre Wenaus, BNL/CERN
Apps area planning materials on web
Planning page linked from applications area page: in development Applications area plan spreadsheet: overall project plan
http://lcgapp.cern.ch/project/mgmt/AppPlan.xls High level schedule, personnel requirements
Applications area plan document: overall project plan http://lcgapp.cern.ch/project/mgmt/AppPlan.doc Incomplete draft
Personnel spreadsheet http://lcgapp.cern.ch/project/mgmt/AppManpower.xls Currently available/foreseen apps area personnel, activities
Planning materials – PBS, milestones, personnel resources http://atlassw1.phy.bnl.gov/Planning/lcgPlanning.html
LHCC meeting, Nov 25, 2002 Slide 9
Torre Wenaus, BNL/CERN
Apps Area Milestones
Level 2 milestones developed for existing and anticipated projects Except for small projects, not done yet (math libs, generators) At least until mid 2003 Milestones in the existing projects have been either defined by or
OK’d by the project managers Project data maintained in XProject (in-house tool for software
project planning) And exported to MS Project for integration with other areas,
Gantt display, etc.
LHCC meeting, Nov 25, 2002 Slide 10
Torre Wenaus, BNL/CERN
Apps Area Milestones
State of the AA milestones reflects the state of the AA projects L1 milestones are only in project areas which were defined or
foreseeable early Persistency and grid interfaces Nonetheless, we probably have the right set of L1 milestones,
unless our mandate in simulation warrants L1 milestone(s) L2 milestones are detailed only in the one software development
project that has been active for >1 month and has developed a work plan: persistency
Other development projects were initiated in Oct, Nov or are still pending
Will be filling out the L2 milestones and delivering work plans to the PEB+SC2 over the next several months
Detailed milestone descriptions are shown on the web, but not on these slides
LHCC meeting, Nov 25, 2002 Slide 11
Torre Wenaus, BNL/CERN
L1 Milestones (1)
LHCC meeting, Nov 25, 2002 Slide 12
Torre Wenaus, BNL/CERN
L1 Milestones (2)
LHCC meeting, Nov 25, 2002 Slide 13
Torre Wenaus, BNL/CERN
MS Project – Gantt Schedule for POOL
LHCC meeting, Nov 25, 2002 Slide 14
Torre Wenaus, BNL/CERN
Pool Release Schedule
End September – V0.1 (Released on schedule) Core components for navigation
“End October” (Nov 15) – V0.2 (Released on schedule) First collection implementation
“End November” (Dec 15) – V0.3 (First public release) EDG/Globus FileCatalog integrated Persistency for general non-ROOT C++ classes Event meta data annotation and query
End Feb – Interface-complete release For experiment software integration
Mid Apr – Pre-production release Feature-complete with respect to June; bug fix release
June 2003 – Public Production Release (L1 milestone)
LHCC meeting, Nov 25, 2002 Slide 15
Torre Wenaus, BNL/CERN
POOL L1, L2 Milestones
LHCC meeting, Nov 25, 2002 Slide 16
Torre Wenaus, BNL/CERN
Software Process and Infrastructure Milestones
LHCC meeting, Nov 25, 2002 Slide 17
Torre Wenaus, BNL/CERN
Core Libraries and Services Milestones
LHCC meeting, Nov 25, 2002 Slide 18
Torre Wenaus, BNL/CERN
Physicist Interface Milestones
LHCC meeting, Nov 25, 2002 Slide 19
Torre Wenaus, BNL/CERN
Concluding Remarks
Applications area schedule in rapid evolution as new projects come into scope
Level 1 milestones, set last spring, still seem appropriate and attainable
Their definitions were tightened up as much as possible given present knowledge
And tightening them further as new (e.g. RTAG) info comes in has been built into the schedule
Level 2 milestones establish the detailed program of work and provide project tracking
Granularity ~1/month for the major projects, for ~1yr out; less frequent beyond 1yr
Will be fleshed out for the new projects over next ~2 months