Loraine IndependentSchool District

• Campus Improvements• Construction Update

• January 21, 2012

PROJECT STATUS

Budgeted Amount

Cost Savings

GMP Total

Amount Billed

Through December

% Comp

Owner's Contingency

Contractor Contingency

$10,800,000 $83,599 $10,716,401 $1,899,230   17% $106,287 $214,328

 

PLANS

PLANS

SCHEDULE

Underground Plumbing And Electrical Rough-in Is Complete In All Areas

Concrete Slabs Have Been Poured In All Areas That Are Ready At This Time.

Masonry is 90% Complete In Locker Room Areas And Has Begun At The Gymnasium.

Steel Erection Is In Progress at the Gymnasium, Locker Room And JH/HS Classroom Areas

Bus Barn Concrete Has Been Poured

SCHEDULE STATUS

Masonry at Gymnasium

Gymnasium Steel Structure

Masonry and Steel at Gym

Steel at JH/HS Classroom Wing

Masonry Will Continue Over The Next Month Steel Erection Will Continue In All Areas Exterior Drywall Framing And Sheathing Will Begin MEP Wall And Ceiling Rough-In Will Follow CMU And

Drywall Framing The Bus Barn Structure Will Deliver By Mid February