managing production across the supply chain chapter 12

Post on 17-Dec-2015

231 Views

Category:

Documents

1 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Managing Production across the Supply Chain

Chapter 12

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 2

12 Chapter ObjectivesBe able to:Explain the activities that make up planning and control in a typical manufacturing environment.Explain the linkage between sales and operations planning (S&OP) and master scheduling. Complete the calculations for the master schedule record and interpret the results. Explain the linkage between master scheduling and material requirements planning (MRP). Complete the calculations for the MRP record and interpret the results. Discuss the role of production activity control and vendor order management and how these functions differ from higher-level planning activities. Explain how distribution requirements planning (DRP) helps synchronize the supply chain and complete the calculations for a simple example.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 3

12 Planning and Control

Planning and control – A set of tactical and execution-level business activities that includes master scheduling, material requirements planning, and some form of production activity control and vendor order management.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 4

12 Top-Down Model of Manufacturing Planning and Control Systems

Figure 12.1

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 5

12 Master Scheduling

Master Scheduling – A detailed planning process that tracks production output and matches this output to actual customer orders. Controls the timing and quantity of production for

products or product families. Serves as the primary interface point for actual customer

orders. Coordinates forecasted demand and actual orders with

production activity. Serves as a tool for agreement between marketing and

operations (but at a different level than S&OP).

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 6

12 Link between S&OP and MPS

Month: January February MarchOutput: 200 300 400

Push Mowers 25 25 25 25Self-propelled 35 40Riding 12 13

January (weeks) 1 2 3 4

S&OP

MPS

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 7

12 Master Schedule Record

Forecasted demand Booked orders Projected inventory levels Production quantities Units still available to meet customer needs

(Available to Promise)

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 8

12 Forecasted Demand vs. Booked Orders

Forecasted demand – A company’s best estimate of the demand in any period.

Booked orders – Confirmed demand for products

Projected Requirements = Maximum (Forecasted demand, Booked orders)

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 9

12 Master Production Schedule (MPS)

Master Production Schedule (MPS) – The amount of product that will be finished and available for sale at the beginning of each week. The MPS quantities drive more detailed planning

activities, such as material requirements planning.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 10

12 Ending Inventory

Projected Ending Inventory – Best estimate of what inventory levels will look like at the end of each week based on current information.

),max(1 ttttt OBFMPSEIEI

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 11

12 Available to Promise (ATP)

Available to Promise – A field in the master schedule record that indicates the number of units that are available for sale each week, given those that have already been promised to customers.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 12

12 Available to Promise (ATP)

Calculating ATP for the first week of the master schedule record:

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 13

12 Available to Promise (ATP)

Calculating ATP for any subsequent week in which MPS > 0:

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 14

12 Partial Master Schedule Record(Snowblowers)

Figure 12.4

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 15

12 Calculating ATP

Figure 12.5

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 16

12 Calculating ATP

Figure 12.6

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 17

12 Complete Master Schedule Record(Snowblowers)

Figure 12.7

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 18

12 MPS Example (Backpacks)

Now Calculate Projected Ending Inventory and Available to Promise

Figure 12.8

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 19

12 Calculations (Backpacks)

Calculating Ending Inventory:

Calculating ATP:

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 20

12 MPS Example (Backpacks) with ATP

What are the implications of the Master Production Schedule?Figure 12.9

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 21

12 Planning Horizon

Planning Horizon – The amount of time the master schedule record or MRP record extends into the future. The longer the production and supplier lead times,

the longer the planning horizon must be.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 22

12 Material Requirements Planning

Material Requirements Planning (MRP) – A planning process that translates the master production schedule into planned orders for the actual parts and components needed to produce the master schedule items. Manages dependent demand inventory

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 23

12 Material Requirements Planning

MRP is based on: The bill of material (BOM)

Backward Scheduling

Explosion of the bill of material

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 24

12 Bill of Material for Chair

Bill of material (BOM) – A listing of all the subassemblies, intermediates, parts, and raw materials that go into a parent assembly showing the quantity of each required to make an assembly.

© 2010 APICS Dictionary

Figure 12.12

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 25

12 Product Structure Tree

Planning Lead Time – The time from when a component is ordered until it arrives and is ready to use.

Figure 12.13

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 26

12 Lead Time

ChairAssembly

(1 week)

Week 5Week 4

If final assembly takes one week, then we must startthe assembly at the beginningof Week 4 . . .

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 27

12 Lead Time

ChairAssembly

BackAssembly

LegAssembly

(1 week)

(1 week)

(1 week)

Seats (2 weeks)

Week 5Week 4Week 3Week 2Whichmeans thatthe majorsubassembliesand seats must bedone by thebeginningof Week 4 ...

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 28

12 Lead Time

ChairAssembly

BackAssembly

LegAssembly

(1 week)

(1 week)

(1 week)

Back Slats (2 weeks)

Legs (2 weeks)

Side Rails (2 weeks)

Crossbar (2 weeks)

Crossbar (2 weeks)

Seats (2 weeks)

Week 5Week 4Week 3Week 2Week 1

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 29

12 Lead-Time Key Points

• To have finished chairs at the beginning of Week 5 with no work in progress or finished inventory, we must begin production and order materials in Week 1.

• “Exploding” the bill of materials tells us when to order things and how many to order.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 30

12 Material Requirements Planning (MRP)

Requires: Bill of material (BOM) Inventory record Master schedule

to determine what should be ordered when, and how much to order.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 31

12 Material Requirements Planning (MRP)

Gross Requirements Scheduled Receipts Projected Ending Inventory Net Requirements Planned Receipts Planned Orders

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 32

12 Calculating the MRP Record for Seats

Figure 12.16

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 33

12 Calculating the MRP Record for Seats (Key)

A: Mgmt needs 500 chairs at the beginning of week 5. B: Because the planning lead time is 1 week, the workers

need to start assembling the chairs in week 4. C: The Gross Requirement for weeks 1-3 is zero because no

chairs need to be assembled in those weeks. D: The Gross Requirement for week 4 is 500 from the MPS

Start quantity in week 4. E: The Net Requirements for week 4 =

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 34

12 Calculating the MRP Record for Seats (Key)

F: Managers should plan on ordering enough to meet the net requirement in week 4.

G: There is a two-week planning lead time, so they must release the order for seats in week 2.

H: Ending Inventory for week 4 =

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 35

12 MRP Records for Level 1 Components

Figure 12.17

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 36

12 Calculating the MRP Record Quantities (Key)

I: There are 25 leg assemblies in inventory beginning in week 1.

J: An order for 1000 is placed even though the net requirements are 475 units because 1000 is the minimum order quantity.

K: No order is placed because there is more inventory (525) than the gross requirements (400) in week 5.

L: There is a scheduled receipt for 250 units in week 1.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 37

12 Partial MRP Records

From Figure 12.18

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 38

12 Calculating the MRP Record Quantities (Key)

M: Because each leg assembly requires two legs, the gross requirements for legs in week 3 is 2,000 legs.

N: Each back assembly requires two side rails. Therefore, there is a planned order for 300 back assemblies in week 5 that results in a gross requirement of 600 side rails in the same week.

Crossbar Gross Requirements:

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 39

12 Advantages of MRP

MRP is directly tied to the master production schedule and indicates the exact timing and quantity of orders for all components.

MRP allows managers to trace every order for lower-level items through all the levels of the BOM, up to the Master Production schedule.

MRP tells a firm and its suppliers precisely what needs to be made when.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 40

12 Special Considerations

Organizational discipline Accurate information Uncertainty MRP nervousness – A term used to refer to the

observation that any change, even a small one, in the requirements for items at the top of the bill of material can have drastic effects on items further down the bill of material.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 41

12 Production Activity Control and Vendor Order Management

Emphasis shifts from planning to execution with capabilities to: Route and prioritize jobs going through the supply

chain. Coordinate the flow of goods and materials

between a facility and other supply chain partners.

Provide supply chain partners with performance data on operations and supply chain activities.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 42

12 Job Sequencing

Job sequencing rules – Rules used to determine the order in which jobs should be processed when resources are limited and multiple jobs are waiting to be done. First come, first served Earliest due date Critical ratio• Calculated as:

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 43

12 Job Sequencing

Critical Ratio – One way to determine the order in which jobs should be sequenced. Critical Ratio = 1• Amount of task time equals the amount of time left.

Critical Ratio < 1 • The job is going to be late unless something changes.

Jobs with the lowest Critical Ratio are scheduled to go first.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 44

12 Job Sequencing – Example 12.7

Table 12.1

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 45

12 Job Sequencing – Example 12.7

First come, first served

From Table 12.2

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 46

12 Job Sequencing – Example 12.7

Earliest Due Date

From Table 12.2

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 47

12 Job Sequencing – Example 12.7

Critical Ratio

From Table 12.2

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 48

12 Distribution Requirements Planning (DRP)

Distribution requirements planning (DRP) – A time-phased planning approach similar to MRP that uses planned orders at the point of demand (customer, warehouse, etc.) to determine forecasted demand at the source level (often a plant).

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 49

12 Synchronized Planning and Control

Figure 12.22

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 50

12 DRP Example(Snowblowers)

Figure 12.24

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 51

12 Downstream Supply Chain

Figure 12.23

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 52

12 DRP Example(Snowblowers)

Records are almost identical to MRP records with one exception: Instead of gross requirements, they show

forecasted demand.• Forecasted demand – the number of snowblowers each

center expects to ship to retail customers each week. Activities at distribution centers are synchronized

when the total weekly planned orders become forecasted demand in the factory’s master schedule.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 53

12 Impact of Forecast Changes

Figure 12.25

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 54

12 Impact of Forecast Changes

When forecasted demand changes, managers will need to increase the master production schedules accordingly.

DRP quickly translates downstream demand into upstream production decisions.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 55

12 Synchronizing Plans in the Supply Chain

Figure 12.26

12 - 56Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall

Managing Production Case Study

The Realco Breadmaster

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 12 - 57

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or

otherwise, without the prior written permission of the publisher. Printed in the United States of America.

top related