Manual for theconstruction of
ALP System ducts
la conduzione dell'aria
UNI EN ISO 9002
CERT.N9091 ALP0
ISO 9002
-
8/12/2019 Manuale Alp Gbr
2/52
Introduction
Practical Manual
Dear collaborator,
this manual has been conceived and developed as a basic practical guide for ALP Technicians.
It is intended to fulfil two main requirements:
in the first place it shall be an easy practical handbook for those who approach the ALP system
for the first time and in the second place it shall be a practical manual for technical / operational
advice for those who actively work with our System.
We have tried to achieve the best result and to offer an overview - as detailed as possible -
about construction and assembly features of ALP products.
We would be pleased if you could give us tips or any kind of material useful for future editions.
Our sincere thanks to those who have contributed to the creation of this practical manual.
Technical - Commercial Department
CONSTRUCTION SYSTEM - 3
-
8/12/2019 Manuale Alp Gbr
3/52
-
8/12/2019 Manuale Alp Gbr
4/52
Table of contents
EQUIPMENT PAG. 6
THE CONSTRUCTION OF DUCTS 7
1 - STRAIGHT DUCT 8
2 - STRAIGHT DUCT - TRANSITION 15
3 - STRAIGHT DUCT - OFFSET 16
4 - STANDARD BRANCH 17
5 - SYMMETRIC ELBOW 18
6 - ASYMMETRIC ELBOW 23
7 - TWO-WAY WYE JUNCTION 24
8 - THREE-WAY WYE JUNCTION 25
9 - PROFILES 26
10 - ACCESSORIES 40
CONSTRUCTION SYSTEM - 5
-
8/12/2019 Manuale Alp Gbr
5/52
HOW TO ORGANIZE THE WORKSHOP
Here below you will find a list of basic tools, materials and accessories necessary for the
construction of ALP System ducts.
Equipment
- Work table 4000 x 1200 mm Art. 601
- Multiblock rule 4000 mm Art. 602 / A
- Multiblock rule 1200 mm Art. 602 / B
- Square 1200 mm Art. 603 / A
- Square 700 mm Art. 603 / B
- Rule 1200 mm Art. 604
- Compass - Large Art. 605
- Tool-kit case Art. 607
- Manual bending machine Art. 608
- Pneumatic pistol for silicone Art. 609
- Pneumatic glue spreader Art. 610
The equipment set may be completed by adding other tools described by the ALP General Catalogue.
Consumption materials and accessories
- Aluminium tape Art. 201
- Special glue Art. 202
- Silicone Art. 203
- Adhesive gasket Art. 204
- Corners in nylon-glass Art. 205
- Corner plates Art. 206/ A
- Corner covers Art. 206/ B
Profiles
Equipment
6 - CONSTRUCTION SYSTEM
art. 301 art. 302 art. 303 art. 304 art. 305 art. 306 art. 307
art. 308 art. 309 art. 310 art. 311 art. 312 art. 313
-
8/12/2019 Manuale Alp Gbr
6/52
The construction
of ducts
For the construction of ALP System ducts keep in mind as follows:
the measurements of ducts shall always be understood as internal measurements;
the marking of ducts shall always be based on internal measurements;
the procedure to be followed for construction is given here below:
marking - cutting
gluing
assemblysilicone application
aluminium tape application
profiles application
CONSTRUCTION SYSTEM - 7
-
8/12/2019 Manuale Alp Gbr
7/52
1 - Straight duct
STRAIGHT DUCT WITH A 4 M CUTTING SYSTEM
Use the Double 45 jack-plane (art. 701/ A) and the Multiblock rule (art. 602/ A) for the
construction of straight ducts.
8 - CONSTRUCTION SYSTEM
40 2040 4020
1200
art. 602/ A
art. 701/ A
4 m duct
The sum total of 4 sides of the duct is equal or below 1040 mm.
When the sum total of the sides the duct is composed of is either equal or below 1040 mm, it
will be possible to build a max. 4 m long duct by making use of a single panel.
-
8/12/2019 Manuale Alp Gbr
8/52
-
8/12/2019 Manuale Alp Gbr
9/52
10 - CONSTRUCTION SYSTEM
b
h
b
40
40
h + 90
56
4
20
b 90
b + 90
20 20 50
20
FOLLOWING CUTS
Internal section h
-
8/12/2019 Manuale Alp Gbr
10/52
CONSTRUCTION SYSTEM - 11
GLUING
Before spreading the glue, eliminate any dust
residue which might hinder a perfect gluing.
The glue shall be spread in a uniform way on
both surfaces by completely covering the
foam.
ASSEMBLY
When the glue is dry, close the duct. Follow
the general rules given here below:
when joining panels, always start from thesame border so as to trim only the duct side
opposite the starting side;
always take the internal side of the duct as a
reference so as to perfectly join corners
check the perpendicularity of sides.
Assembly is completed by pressing the corners
by means of a stiff spatula (art. 704).
1
2
43
5
-
8/12/2019 Manuale Alp Gbr
11/52
12 - CONSTRUCTION SYSTEM
SILICONE APPLICATION
A thin coat of silicone shall be applied in all
internal corners of the duct for its hermetic
seal. Prevent the air from coming into contact
with the insulating foam.
N.B.
To make profile application easier, when
spreading silicone keep it at a distance of
ab out 4 0 / 5 0 m m from the end of the duct.
After having applied profiles, apply silicone
in the remaining parts.
4050mm
4050mm
2 m long pneumatic pistol for silicone (art. 609)
-
8/12/2019 Manuale Alp Gbr
12/52
CONSTRUCTION SYSTEM - 13
TAPE APPLICATION
Taping shall perform two functions:
a technical function since it restores the
vapour barrier and avoids the formation of
condensate in the foam;
an aesthetical function since it hides cut and
pressed parts from view.
To apply the aluminium tape in a straight way,
use the tape marker to mark along the edges
of the duct (art. 706).
Press by making use of a soft spatula (art. 705)
to avoid the formation of any air bubble which
might cause the tape to come off.
N.B.
The tape sha ll be a pplied on clea n surfaces.
N ever touch the adhesive side of the tape.
1
2
3
-
8/12/2019 Manuale Alp Gbr
13/52
-
8/12/2019 Manuale Alp Gbr
14/52
CONSTRUCTION SYSTEM - 15
20 2040 202040
2
3
1
Pieghe
Pieghe
2 - Straight duct
Transition
Bends
Bends
-
8/12/2019 Manuale Alp Gbr
15/52
16 - CONSTRUCTION SYSTEM
1 4 3
2 3
Mouth 1
20
Mouth 2
8
8
7
5
6
7
Mouth 2Offset
Mouth 1 Offset
Offsets are ducts intended to connect two
ducts placed on different axes.
Carry out the operations described by the
figure:
To mark and cut lateral sides, follow the
procedure adopted for transitions. Assemble
and complete as usual.
3 - Straight duct
Offset
-
8/12/2019 Manuale Alp Gbr
16/52
1 2 3
150
X+150
150
50
X
600
HOW TO J OIN BRANCH PROFILES
CONSTRUCTION SYSTEM - 17
Standard branches are ducts directly connected
to the main duct intended to deviate the air flow
without making use of two-way wye junctions.
To make assembly easy, their length shall never
exceed 600 mm. To avoid the formation of
turbulences as well as the danger of high flow
resistances, these branches shall have a partinclined at an angle of 45 and intended to let
the air in more easily. Its dimensions remain
constant (150 mm) even if the ducts dimensions
change.
For the construction, act as follows:
mark 3 sides (1 - 2 - 3) of the branch at the
same time;
cut the panel and leave sharp corners alongoffset;
make cuts on the cover by means of the
Double 22.5 jack-plane (art. 701/ B) so as
to bend the cover at an angle of 45.
art. 313 art. 304/ B art. 303 art. 206/ A
art. 701/ B
4 - Standard branch
Double 22.5 jack-plane
art. 206/ B
art. 204/ B
-
8/12/2019 Manuale Alp Gbr
17/52
18 - CONSTRUCTION SYSTEM
Symmetric elbows have an entry section which is just the same
as the exit section.
To build elbows, use single-blade jack-planes (art. 702/ A -
702/ B - 702/ C), the compass (art. 707), the squares (art. 603/ A
- 603/ B) and the manual bending machine (art. 608).
From a building point of view, elbows are made of sides and
covers.
Cover
Side
5 - Symmetric
elbow
art. 702/ A
art. 702/ C
art. 707
art. 603/ A
art. 603/ B
art. 702/ B
N.B.
It is impor tant to build elbow s prope rly so a s to avoidthe formation of turbolences and high flow resistance.
art. 608
-
8/12/2019 Manuale Alp Gbr
18/52
CONSTRUCTION SYSTEM - 19
5
20
4
2
1
1.2
00
3
h
6
hb
hb
h
20
Minimo 100 m
5 = Internal radius
6 = External radius
NOTE:
If possible, alw a ys use the overall w idth of
the pa nel for the construction of e lbow s.
Alwa ys leave a min. 10 0 mm neck betw een
the end of the rad ius a nd the entry / exit of
the elbow .
Internal Radius
h
600 mm
r
150 mm
250 mm300 mm
MARKING
Carry out the operations described by the figure:
Minimum
1 0 0 m m
-
8/12/2019 Manuale Alp Gbr
19/52
20 - CONSTRUCTION SYSTEM
CUTTING
The single-blade jack-plane, free-hand used, shall always be pulled.
The two vertical lines on the front side of the jack-plane indicate the ends of the cut.
Art.702/A
Art.702/C
Art.702/Bart. 702/ A art. 702/ B
art. 702/ C
X
X
X
It is recommended to mark both the sides and the covers for a
perfect connection during assembly.
-
8/12/2019 Manuale Alp Gbr
20/52
CONSTRUCTION SYSTEM - 21
THE BENDING OF COVERS
X
X
X
Side curvature
radius
300 mm
20 mm
35 mm
50 mm
35 mm
50 mm
70 mm
Distan ce betw een bend s
Int. cover Ex t. cover
External cover Internal cover
art. 608
GLUING AND ASSEMBLY
External cover assembly Internal cover assembly
-
8/12/2019 Manuale Alp Gbr
21/52
22 - CONSTRUCTION SYSTEM
ELBOW FINISHING
After having assembled the elbow, finish the duct. Carry out the same operations described for
the straight duct.
NOTE:
The a luminium tap e sha ll be a pplied on clea n surfaces. N ever touch the adhesive side of the tape.
Pressing M a rk ing
Ta pe a pplica tion Silicone a pplica tion
-
8/12/2019 Manuale Alp Gbr
22/52
CONSTRUCTION SYSTEM - 23
20
4
2
1
5
h1
1.2
00
3
7
6
h1
h
h1
h
b
h b
20
6 - Asymmetric
elbow
Internal Radius
h
600 mm
r
150 mm
250 mm300 mm
Asymmetric elbows have an entry section
which is different in size from the exit section.
MARKING
Carry out the operations described by the figure:
How to position the centre to mark the external
radius:
Calculate the width of the external radius
(Ir + h1) (6)
Start from the larger section (h) to mark the
external radius (7).
For the following operations see the previousparagraph: "SYMMETRIC ELBOW".
-
8/12/2019 Manuale Alp Gbr
23/52
Re
1 2
3
40
Ri
4040
1 2 5 4 3
12
13
14
15Min.
150m
m
1.2
00
6 8 9 7 10 11
16
24 - CONSTRUCTION SYSTEM
After having spread the glue, assemble every single element in the following order. It is
important to cut the base of the damper at an angle of 45 so that the air goes in two different
directions. Put some aluminium tape to prevent the foam from coming into contact with the air.
1 - Transition cover/ damper
2 - External radius cover
3 - Internal radius cover
7 - Two-way
wye junctionTransition
Asymmetric
elbowTwo-way wye junctions convey the air in two
different directions of the plant.
It is recommended to mark the three sides of the
duct all together so as to make assembly easier.
Carry out the operations described by the
figure:
-
8/12/2019 Manuale Alp Gbr
24/52
CONSTRUCTION SYSTEM - 25
Min.
150mm
111 122
6
9 2 10
8
5
7
16
15
14
13
344040
1200
4
2
3
5
1
23
4
8 - Three-way
wye junction
Three-way wye junctions convey the air in
three different directions of the plant.
Carry out the operations described by the
figure:
After having properly marked, cut
and prepare all lateral covers. It is
no use marking the upper cover of
the duct; just follow the internal
borders of the lower cover you have
already cut to copy it.
After gluing, assemble the duct in
the above mentioned order.
Complete as usual.
1 - Lower cover
2 - Transition cover/ damper
3 - External radius cover
4 - Internal radius cover
5 - Upper cover
Asymmetric elbows
-
8/12/2019 Manuale Alp Gbr
25/52
4
1
2
3
6
67
5
26 - CONSTRUCTION SYSTEM
9 - Profiles
PROFILES APPLICATION
Apply the corners on the duct to make it stiffer
and stronger.
How to glue the profile
How to glue the part the profile
will be applied to
How to assemble the profile by exerting a
slight pressure through the special hammer
art. 205
-
8/12/2019 Manuale Alp Gbr
26/52
CONSTRUCTION SYSTEM - 27
art. 303
art. 206/ A
1
2
3
4
5
6
6
7
PROFILES APPLICATION
Invisible flan ge
How to apply the corner plates
on the duct corners.
How to glue the profile
How to glue the part the profile
will be applied to
How the assemble the profile by exertinga slight pressure with the special hammer
-
8/12/2019 Manuale Alp Gbr
27/52
28 - CONSTRUCTION SYSTEM
USE OF PROFILES
Flange / slide-in channel joint
This type of joint occurs by applying an
adhesive gasket on one of the two flanges for
its hermetic seal.
art. 301-302
art. 304
art. 204/ A
-
8/12/2019 Manuale Alp Gbr
28/52
CONSTRUCTION SYSTEM - 29
art. 303
art. 204/ B
art. 304/ B
art. 206/ B
USE OF PROFILES
Invisible flange joint
This type of joint occurs by applying
an adhesive gasket on one of the two
flanges for its hermetic seal.
-
8/12/2019 Manuale Alp Gbr
29/52
30 - CONSTRUCTION SYSTEM
USE OF PROFILES
"F Profile" joint - Fire Damper
art. 501
art. 307
art. 204/ A
-
8/12/2019 Manuale Alp Gbr
30/52
CONSTRUCTION SYSTEM - 31
USE OF PROFILES
"F Profile" joint - Volume Control Damper
art. 501
art. 307
art. 204/ A
-
8/12/2019 Manuale Alp Gbr
31/52
32 - CONSTRUCTION SYSTEM
USE OF PROFILES
"F Profile" joint - Rectang ular Silencer
art. 501
art. 307
art. 204/ A
-
8/12/2019 Manuale Alp Gbr
32/52
-
8/12/2019 Manuale Alp Gbr
33/52
34 - CONSTRUCTION SYSTEM
USE OF PROFILES
"F Profile" joint - A ir Ha ndling Unit
art. 501
art. 307
art. 204/ A
-
8/12/2019 Manuale Alp Gbr
34/52
35 - CONSTRUCTION SYSTEM
USE OF PROFILES
"Cha ir Profile" joint - A ir Ha ndling Unit
art. 205
art. 308
-
8/12/2019 Manuale Alp Gbr
35/52
36 - CONSTRUCTION SYSTEM
USE OF PROFILES
Profiles for Grilles
Two series of profiles may be used for
this type of application: "U Profile"
(art. 309) or "Profile for
Grille" (art. 310).
art. 205 art. 309
art. 309
art. 205 art. 310
art. 201
-
8/12/2019 Manuale Alp Gbr
36/52
CONSTRUCTION SYSTEM - 37
art. 312
USE OF PROFILES
Profile for Filter
-
8/12/2019 Manuale Alp Gbr
37/52
When a duct is very large, it is built by joining panels through
"Double F Profile" (art. 306), instead of using 45 cut.
To extend the surface, panels are flat-joined by following an
analogous procedure. In this case the profile used is a "H Profile"
(art. 305).
N.B.
Before cutting profiles, ta ke thelength of the du ct minus 8 0 mm so
as to be able to apply profiles at
both ends.
38 - CONSTRUCTION SYSTEM
1200
X
40
art. 306
art. 205art. 301
art. 305
USE OF PROFILES
Construction of a duct by making use of a "Double F Profile"
and a "H Profi le"
art. 306
art. 305
-
8/12/2019 Manuale Alp Gbr
38/52
CONSTRUCTION SYSTEM - 39
USE OF PROFILES
Profile for Screen
NOTE:
It is recomm ended to use a 2 0 0 / 8 0 m icron panels
for the construction of gooseneck to be installedoutdoor.
Cut profiles at an angle of 45.
art. 311
-
8/12/2019 Manuale Alp Gbr
39/52
40 - CONSTRUCTION SYSTEM
STIFFENING SYSTEM FOR DUCTS
Bars shall be cut 4 mm less than the internal
section of the duct.
10 - Accessories
art. 514
art. 508
art. 507
art. 506
-
8/12/2019 Manuale Alp Gbr
40/52
800
1200
800
1200
4000
800
2400
800
4000
1
1
1
1
1
2
2
2
2
2
2
1
1
1
1
1
1
1
2
2
2
2
2
2
1
1
1
2
2
2
2
2
2
2
2
2
2
1
1
2
2
2
2
2
2
2
2
2
2
2
2
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
1
1
1
1
1
2
2
2
2
2
2
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
PA
0-150
PA
310-450
PA
460-600
PA
610-750
PA
960-1000
PA
1010-1250
PA
1260-1500
PA
1760-2000
PA
760-950
PA
160-300
PA
1510-1750
CONSTRUCTION SYSTEM - 41
DUCT
SIDEmm
PRESSURE
0 - 400
410 - 500
510 - 600
610 - 700
710 - 800
810 - 900
910 - 1000
1010 - 1100
1110 - 1200
1210 - 1300
1310 - 1400
1410 - 1500
1510 - 1600
1610 - 1700
1710 - 1800
1810 - 1900
1910 - 2000
Table for the calculation of stiffening
Lo ng Pi tch 8 0 0 - 2 4 0 0 - 8 0 0
Sh o r t Pi tch 8 0 0 - 1 2 0 0 - 1 2 0 0 - 8 0 0
M e th o d A:
Method B:
M e th o d A e x a m p le:Section Pressure
1000 x 1000 400 PA
Method B example:Section Pressure
1300 x 550 1000 PA
-
8/12/2019 Manuale Alp Gbr
41/52
42 - CONSTRUCTION SYSTEM
art. 510
art. 509
L
Glue the turning vanes on the sides
Assemble the turning vanes
Mark the outline of the vane-plate on the
side of the elbowTURNING VANES
Legend for Turning vanes
L m m
Up to 300
300 500
500 1000
Over 1000
N o.of vanes
0
1
2
3
W IDTH O F ANY AIR FLOW AS A
FRACTION OF "L"
(from the inside to the outside)
L
1/ 3-2/ 3
1/ 6-1/ 3-1/ 2
1/ 12-1/ 6-1/ 4-1/ 2
-
8/12/2019 Manuale Alp Gbr
42/52
50mm
A
B
A
B
A+B+A+B+70mm 50 mm
B
B
A
A
A-5
mm
B-5
mm
CONSTRUCTION SYSTEM - 43
FLEXIBLE DUCT CONNECTOR - QUICK CLUTCH SYSTEM
art. 505/ B
art. 505/ Cart. 505/ A
art. 309art. 205
1
2
34
5 6
-
8/12/2019 Manuale Alp Gbr
43/52
44 - CONSTRUCTION SYSTEM
ROUND TUBE FOR DIFFUSER AND FLEXIBLE DUCT
art. 405
art. 504
art. 606
art. 406
art. 407
-
8/12/2019 Manuale Alp Gbr
44/52
CONSTRUCTION SYSTEM - 45
PLATE FOR TEMPERATURE CHECK
PLATE FOR HUMIDISTAT
art. 511
art. 511
-
8/12/2019 Manuale Alp Gbr
45/52
46 - CONSTRUCTION SYSTEM
INSPECTION DOOR
art. 308
art. 512
art. 309
-
8/12/2019 Manuale Alp Gbr
46/52
CONSTRUCTION SYSTEM - 47
HANGER SYSTEMS
MAX 4000
MAX 4000
MAX 4000
Traditional, by means of threaded bars and channels
By means of self-adhesive duct support
By means of duct support
art. 504
art. 503
-
8/12/2019 Manuale Alp Gbr
47/52
-
8/12/2019 Manuale Alp Gbr
48/52
CONSTRUCTION SYSTEM - 49
ANCHORAGE SYSTEMS FOR OUTDOOR DUCTS
Anchorage
to steel beam
art. 503
Direct anchorage
to concrete basement
art. 503
-
8/12/2019 Manuale Alp Gbr
49/52
100 mm
100 mm
N O TE:
Clean and dry before apply ing the product
Do not dilute the product with water or other substances Cur ing time: about 48 hours
50 - CONSTRUCTION SYSTEM
PROTECTING LINING FOR OUTDOOR DUCTS
art. 515
-
8/12/2019 Manuale Alp Gbr
50/52
CONSTRUCTION SYSTEM - 51
HOW TO J OIN PANELS
If the pressure is not high or ducts are small or medium-sized you may join panel strips from
waste. Just make cuts at an angle of 45, glue the two parts and then apply the aluminium tape
on both ends of the panel.
Glue
Tape
1
2
-
8/12/2019 Manuale Alp Gbr
51/52
52 - CONSTRUCTION SYSTEM
HOW TO JOIN PANELS
-
8/12/2019 Manuale Alp Gbr
52/52