mie school feb 18th 2011
Post on 08-Apr-2018
214 Views
Preview:
TRANSCRIPT
-
8/7/2019 MIE School Feb 18th 2011
1/16
left wall
MIE School 2011
right wall
front of school
-
8/7/2019 MIE School Feb 18th 2011
2/16
right wall
front of school
left wall
-
8/7/2019 MIE School Feb 18th 2011
3/16
left wall
chalkboard
room partition
right wallremoved
depressed
area
in concrete
in veranda
veranda
front of school
-
8/7/2019 MIE School Feb 18th 2011
4/16
Make this depressed area in
the concrete approximately 2.5feet x 2.5 feet square and
depressed by 2 inches. This is a
place for playing with paint,
which can be washed away
easily. Use a wooden board tomake this depressed area.
Make a canal from the depressed
area to the edge of the concrete
foundation to allow water inside the
depressed area to flow out freely.
veranda
-
8/7/2019 MIE School Feb 18th 2011
5/16
front of
14 inches
16 inches
14 inches
12 inches
midlineofh
ouse
2 inches off-
midline of
house
Placement of the 12 PVC segments in concrete to support the frame bamboo poles
All measurements are from the center of the PVC segments
veranda
14 inches
ee
17 feet5 feet
sc oo
14 inches
12 inches
14 inches
16 inches
depressed
area in
concrete
14 inches 14 inches
14 inches
2 inches off-
midline of
house
-
8/7/2019 MIE School Feb 18th 2011
6/16
front of
midlineofhouse
Placement of the grooves in concrete to support the wall bamboo poles
These grooves (in yellow) should be 1.5 inches wide and 1.5 inches deep
veranda
12 inches 12 inches
10 inches 14 inches
ee
17 feet5 feet
sc oo
10 inches
depressed
area in
concrete
12 inches 12 inches
14 inches
12 inches 12 inches
-
8/7/2019 MIE School Feb 18th 2011
7/16
front of
midlineofhouse
Placement of the grooves in concrete to support wall partitions and easels
All measurements are from the center of the poles
veranda
grooves in concrete
1 inch wide, 3 inches deep
ee
17 feet5 feet
sc oo
depressed
area in
concrete
-
8/7/2019 MIE School Feb 18th 2011
8/16
front of
midlineofhouse
veranda
holes in concrete
1 inch diameter, 3 inches deep
Placement of the holes in concrete into which thin bamboo poles can be inserted
to reinforce the wall partitions and easels
ee
17 feet5 feet
sc oo
depressed
area in
concrete
-
8/7/2019 MIE School Feb 18th 2011
9/16
front of
midlineofhouse
veranda
holes in concrete
1 inch diameter, 3 inches deep
Placement of the holes in concrete into which thin bamboo poles can be inserted
to create frame of fence for the veranda
ee
17 feet5 feet
sc oo
depressed
area in
concrete
-
8/7/2019 MIE School Feb 18th 2011
10/16
front of
midlineof
house
veranda
holes in concrete
1 inch diameter, 3 inches deep
Placement of large hooks whose base should be imbedded in the concrete in theperimeter of the concrete, with their eyes exposed and protruding above the surface of the concrete.
Useful for tying down tarps.
ee
17 feet5 feet
sc oo
depressed
area in
concrete
-
8/7/2019 MIE School Feb 18th 2011
11/16
Insert a PVC segment that is
approximately 1 inch in diameter
larger than the bamboo pole for
the frame of the school into the
concrete foundation, a few minutes
after the concrete is poured. This
should be done for each of the 12
large frame bamboo poles.
PVC segment is 14
inches in height. 10inches of it should
be buried in the
concrete
foundation.
Make sure that the
PVC segments point
straight up. Use a
builders level to do
this.
cap at
bottom of
PVC segment
concrete foundation
Drill a small hole in
the center of the
PVC cap to allow
any moisture to
flow away from thebamboo.
10 inches
buried in
concrete, 4
inches protrudeabove concrete.
2 inches of space
between bottom of PVC
cap and bottom of
concrete.
PVC segment
atleast12inchesdeep
-
8/7/2019 MIE School Feb 18th 2011
12/16
Pour sand to fill 2 inches ofdepth in PVC segment in
each of the 12 PVC
segments.
-
8/7/2019 MIE School Feb 18th 2011
13/16
Insert one of the
frame bamboo
poles into the PVC
segment.
The bamboo pole
should rest on the
2 inch layer of
sand.
2 inches layer of sand.
-
8/7/2019 MIE School Feb 18th 2011
14/16
After inserting a
bamboo pole, pourmore sand into the
PVC segments until
the sand reaches
the top of the PVC
segments. Thisstep will stabilize
the frame
bamboo poles.
It may be helpfulto shake (rock back
and forth) the
poles as they are
filled with sand.
-
8/7/2019 MIE School Feb 18th 2011
15/16
Do this for each of
the 12 frame
bamboo poles.
-
8/7/2019 MIE School Feb 18th 2011
16/16
Then build the rest of the MIE school
frame and roof.