muon campus controls update brian drendel 8/6/13
Post on 11-Jan-2016
217 Views
Preview:
TRANSCRIPT
Muon Campus Controls Update
Brian Drendel8/6/13
Recent Reviews
• Independent Design Review of AIP and the Accelerator portion of g-2 (June 5-7)– Controls Talk: GM2-doc-1039– Technical Review– Closeout presentation – GM2-doc-1113
• Director’s Review for g-2 (July 23-25)– Controls Talk: GM2-doc-1151– Cost Review– Close-out presentation - http://goo.gl/1Zv2ep
Independent Design ReviewControls and Safety• Findings
– The new accelerator components will be controlled through the standard Fermilab Accelerator controls system and controls devices. During the construction of the Muon Campus communication signals from the accelerator complex will be disconnected to the entire area and reconfigured. Only the portion of the work involving MC-1 is charged under the g-2 project.
– Personnel and equipment safety will be handled through the existing safety systems for the accelerator complex.
– The radiological environment for g-2 throughout the complex will be at or well below the historical levels of this area. The beam power on target will be 20% of the power on target for antiproton production. The beam power in the tunnels and in the Delivery Ring will be 1% of that under previous running conditions.
– The shielding design for M4 and M5 enclosures and shielding upgrades to the Delivery Ring straight sections are driven by Mu2e, not g-2, considerations. The enclosures are not part of the g-2 project.
– All radiation safety parameters for the g-2 muon experiment are well within acceptable limits. • Comments
– Appropriate consideration is being given to the delivery of control signals and communications to the Muon Campus, in particular re-routing of signals to the Delivery Ring and its service buildings and to MC-1.
– Radiation and personnel safety issues have been appropriately addressed. • Recommendations
– None.
What worked
• Detailed BoEs.• Plain English
Documentation of plan and costing.
• Vendor Quotes and Sample PO’s.
Beams-doc-4327
Mu2e
Any Delivery Ring, Beam Line or Mu2e controls specific to Mu2e• Beam Transport Controls
– Mu2e-doc-1572– Charge to “AD-Mu2e-Accelerator PED 475-475.011”
• Delivery Ring Controls – Mu2e-doc-1468– Charge to “AD-Mu2e-Accelerator PED 475-475.014”
• External Beam Line Controls– Mu2e-doc-2136– Charge to “AD-Mu2e-Accelerator PED 475-475.102”
Muon g-2Controls, Communications and Safety System to the MC-1 Service Building . Charge all time to “AD-g-2 Ctrls-Instrmt CD 476-476.A005”• MC-1 Controls and Communications
– GM2-doc-728
• MC-1 Safety System– GM2-doc-896
Delivery Ring AIPBeam Transport AIP
Reestablish Controls to existing Muon Campus service buildings (AP10, AP30, AP50, AP0, F23 and F27)• Delivery Ring Controls (Beams-doc-4338):
Charge to “AD-Delivery Ring AIP CD 20-20.12.16.19.”
• Beam Transport Controls (Beams-doc-4377): Charge to TBD (charge to the other AIP for now, and we will fix the charges later).
Cyro AIP
Establish Cryo controls to the MC-1 Cryo room.• Cryo AIP Controls (Beams-doc-4327): Charge
to “AD-
9
Accelerator Controls Scope•New controls and communication connectivity will be established from the cross gallery to the MC-1 service building.
Brian Drendel, Muon g-2 CD1 Director's Review, July 24-26 2013
Utility Tunnel
CUB
CUB to CMH34
10
Accelerator Controls Scope• Controls Ethernet•Hot-Link Rack Monitors• Timing Link• Beam Synch Link• Beam Abort Link• Site Emergency Warning
System• Fire and Utility System• RADMUX• Phone
Brian Drendel, Muon g-2 CD1 Director's Review, July 24-26 2013
11
Accelerator Interlocks Scope
Brian Drendel, Muon g-2 CD1 Director's Review, July 24-26 2013
• Pbar-style interlocks– Delivery Ring enclosure extended.– New Extraction enclosure.
• Rack Mounted Safety System (RMSS)– MC-1 Experimental Hall
• Oxygen Deficiency Hazard (ODH) system for MC-1.
Controls and Communications to AP30
• Controls and communications signals will enter AP30 via the existing and unused Cryo duct.
Cryo Duct
Controls to AP30
• Controls and communications cables enter AP30 and go to nearby racks.
Cryo Duct
Reserved Rack Space
Near Term Schedule
• September 13th: All PO’s for cable and hardware purchases turned in. Both for AP30 and MC-1 pulls.
• September - October: Cleaning up Cryo Duct• October 1: Order cable and hardware• November – December?: Inner duct pulls,
cable pulls and terminations.
Mu2e Accelerator L3 Meeting 15
Mu2e Schedule• July 2014 CD-2/3 signoff• May 2014 DOE CD-2/3 review• Mar. 2014 Director’s Review• Feb. 2014 Documentation complete• Dec. 2013 L2 documentation complete
• Nov. 2013 L3 documentation input completeBackground simulations complete
• Aug. 2013 CD-2 configuration completely defined.
Ron Ray
Tim
e
8/1/2013
Other Mu2e Project Management
• Schedule is updated Monthly– Mu2e-doc-3001
• Earned Value Management System (EVMS)– Requires monthly progress reports on the schedule
• Start dates• Finish dates• Resources• %Complete• Hours remaining
• New BoE form specific to Mu2e is on the way (Mu2e-doc-3181)
Funding profile and current lab guidance
• An additional site power feeder ($1.1M) is included here; if needed in 2017 or 2018, it will actually have to be done as a new GPP
• Beam Transport and Delivery Ring AIPs have not been baselined yet
• Muon Campus AIPs and g-2 have been given high priority for Accelerator Division manpower in FY14
17
Fiscal Year 2012 2013 2014 2015 2016 2017 Total
MC-1 Building GPP 0.5 7.5 1.0 9.0Beamline Enclosure GPP 0.4 3.7 5.6 9.7MC Infrastructure GPP 0.5 0.5 1.1 2.1Cryo AIP 1.1 5.1 1.3 0.8 1.4 9.7Recycler RF AIP 0.6 1.0 3.9 3.2 8.7Beam Transport AIP 0.3 2.3 3.5 0.1 6.2Delivery Ring AIP 0.2 1.8 2.6 4.2 0.5 9.3Muon Campus TPC 0.5 10.1 15.4 17.4 8.3 3.0 54.7Guidance 10.1 15.4 17.4
M Convery, Muon g-2 CD1 Director's Review, July 23-25 2013
Muon g-2 Accelerator ScheduleCD-0
ForecastKPPs Satisfied
CD-1 CD-2/3a CD-3 CD-4
Conceptual Design
Prelim/Final Design - Accelerator
Safety system
AP2/AP3 disassembly
M2/M3 installation
M4/M5 installation
D30 Straight Section reconfiguration
DR extraction installation
Prelim/Final Design – Ring &
Detector (& D30)
Target Station
Ctrls to MC-1
may shift based on funding
Instrumentation, magnets, stands, etc, not shown but will be prepared prior to installation. Beamline power supply work also not shown and may be ongoing throughout implementation phase.
Beam Studies
Lehman CD-1 ReviewSept. 17-19
Path to CD-1 Lehman Review for g-2
• Lehman Review: September 17-19• All material posted: Tuesday, September 3• Freeze schedule: Tuesday, August 13
Questions from Chris Jensen• I need to verify that there are sufficient spares of the Camac cards that he needs
at MI50, AP30 and AP50 {total cards = C479 (x4), C284 (x4), C217 (x5)}. I'd like to reserve the cards that he needs for his use if possible.
• I need labor estimates (engineer and technician) for both (design and implementation) to implement the Camac controls for each of Chris' kicker systems.
• Chris would prefer HRMs at MI-52, AP30 and AP50 for the analog readbacks. Since we don't have HRMs planned for these buildings, this would mean additional cost. From previous cost estimates I have this as $15.5K per HRM, with labor of Electrical Engineer (1 week/HRM), Electrical Technician (1 week/HRM) an Computer Professional (1 week/HRM).
• Chris needs to verify that beam synch clock at the MC-1 service building for the kicker into the g-2 ring. I know we will be providing beam synch via one of the multimode fiber pairs that run from cross gallery to MC-1. I need to verify that our HRMs at MC-1 will be able to decode beam synch, since we have no Camac in that service building.
Questions from Cryo
• Need to verify Cryo schedule
WBS Name Dur Start Finish M&S Resource HoursCryo1.04.07 Cryo Interconnect Electrical & Controls 367 d 6/17/13 12/1/14 $0 880 hrsCryo1.04.07.01 Procure Xgallery Fiber Connection 24 d 10/1/13 11/1/13 $16,670 FNAD_MECH_TASK_MNGR[8%] 16 hrsCryo1.04.07.02 Run Fiber Cable between A0 & MC-1 49 d 11/4/13 1/17/14 $10,000 FNAD_MECH_TASK_MNGR[16%] 64 hrsCryo1.04.07.03 Interconnect Electrical & Controls Engineering 162 d 10/1/13 5/23/14 $0 FNAD_ELEC_TECH[62%] 800 hrsCryo1.04.07.04 Refrig Syst - First Award for DCS (FY13) 1 d 6/17/13 6/17/13 $0 0 hrsCryo1.04.07.05 Refrig Syst - 1st DCS Delivery Received 43 d 7/2/13 8/30/13 $120,000 0 hrsCryo1.04.07.06 Refrig Syst - Second Award for DCS (FY15) 1 d 10/1/13 10/1/13 $0 0 hrsCryo1.04.07.07 Refrig Syst - 2nd DCS Delivery Received 287 d 10/9/13 12/1/14 $27,307 0 hrs
Updates
Go around the room and get updates:
Summary
• We have a busy schedule ahead with – Preparing g-2 for CD-1• Lehman Review• Fall/Winter Beam Studies
– Preparing Mu2e for CD-2• EVMS• New BoEs• Reviews
– Getting the AIP’s approved