my home abhra status report as on 11th nov 2013
Post on 24-May-2015
813 Views
Preview:
DESCRIPTION
TRANSCRIPT
Project Progress – 11th Nov 2013
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 11.11.13
1.1st Till 11th Floor Slab s: Completed2.12th Floor Slab : Flat No 1 & 2 shuttering work in progress
3.Brick Work: 4th Floor Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 11.11.13
1.1st To 10th Floor Slabs : Completed2.11th Floor Slab : Except 3rd flat Remain all flats Completed,3rd flat Bar Bending work in progress
3.Brick Work: 4th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 11.11.13
1.1st To Till 9th Floor Slabs : Flat No 01 Slab Bar bending work in progress
2. Brick Work: 4th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”D” As On 11.11.13
1.1st To Till 11th Floor Slabs : Completed2.12th Floor Slab : Flat No 1 and 2 Completed,4 and 5 flat Shuttering Work Progress,3rd Flat Columns work In
Progress3.Brick Work: 6th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”E” As On 11.11.13
1.1st To Till 11th Floor Slabs : Completed2.12th Floor Slab : Flat No 1 & 2 Slab Completed ,4 & 5 flats Shuttering and Bar Bending work Under
Progress, 3rd Flat Columns Completed 3. Brick Work: 6th Floor External walls in Progress