NB Cell Changes. Kick-off meeting ORE Garching 10/10/2006 A.Tanga. Main points of NB cell. Design Review in progress 14.06 and next in November, new baseline in 2007. Interfaces critically important RH-maintenance considerations Definition of scenarios Need of input data/assumptions. - PowerPoint PPT Presentation

TRANSCRIPT

NB Cell Changes

Kick-off meeting ORE

Garching 10/10/2006

A.Tanga

Main points of NB cell

• Design Review in progress 14.06 and next in November, new baseline in 2007.

• Interfaces critically important

• RH-maintenance considerations

• Definition of scenarios

• Need of input data/assumptions

Non RH Activities

• NB cell extra beams: Inspections, Leak test, pipe disconnection, (pump replacement), cable-bus bar disconnection/connection, exchange of equipment, VVPSS rupture disc inspection-exchange, valve replacement.

• NB cell top tubes. To be specified.NB: Remove/re-install shield, remove/re-install

connections, bring in equipment for safety such as barrier, tents, disassemble the high voltage line of the DNB, revision of the scheduled maintenance of the source due to RF choice and elimination of filaments, only Cs oven re-filling.

NB: Accident recovery scenario such as water leak in an injector.

Conclusions

• The work on NB cell integration to be finalized by year end to make the new baseline. Next year more detailed analysis.

• Basic activities can be defined at this stage.

• Interface with RH task.

top related