NICS RP UpdateTeraGrid Round Table
March 10, 2011
Ryan BrabyNICS HPC Operations Group Lead
Management changes· Patricia Kovatch is the Interim NICS Project
Director.· Ryan Braby is the new HPC Operations and
Technology Integration Group Lead.– Started Jan 1st.– Over 12 years experience in HPC Systems
Administration and Integration.– Experienced with large IBM Power based systems,
BlueGene systems, Linux clusters, and Lustre.
Kraken XT5 Specifications
Compute processor type AMD 2.6 GHz Istanbul-6
Compute cores 112,896
Compute sockets 18,816
Compute nodes 9,408
Memory per node 16 GB (1.33 GB/core)
Total memory 147 TB
Peak system performance 1.17 PF
Interconnect topology 25 x 16 x 24 Torus/Seastar2+
Parallel file system space 3.3 PB (raw) 2.4 PB (usable)
Parallel file system peak performance 30 GB/s
Athena XT4 Specifications
Compute processor type AMD 2.3 GHz Barcelona-4Compute cores 18,048Compute sockets 4,512 quad-coreCompute nodes 4,512Memory per node 4 GB (1 GB/core) Total memory 17.6 TBPeak system performance 0.166 PFInterconnect topology 12 x 16 x 24 Torus/SeastarParallel file system space 100 TB (raw) 85 TB (usable)Parallel file system peak performance 10 GB/s
Nautilus SGI UltraViolet Specs
Compute processor type Intel ~2.0 GHz NehalemCompute cores 1024Compute sockets (nodes) 128 oct-coreMemory per core 4 GBTotal memory 4 TB (NUMA)Accelerators 16 NVIDIA Fermi GPUs (8 active)Peak system performance 8.2 TFInterconnect topology NUMAlink5Parallel file system space 1 PB (960 TB useable, GPFS)Parallel file system peak performance 24 GB/s
Kraken Job Mix - Annual
Kraken Job Mix – Jan 2011
14
816
2432
4048
5660
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
6312
725
551
1
1023
2047
4095
8191
8256
63
127
255
511
1023
2047
4095
8191
8256Number of Nodes
WallclockHours
Number of NodesCORE-Hours
HPC Ops Report Jan 2011
Kraken and Athena Utilization
%
Month
HPC Ops Report Jan 2011
Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-110
10
20
30
40
50
60
70
80
90
100
87 84 82
92
90 87
96
93
96 95 9796
93 94
85
90
9398
95
95
9295 94 93
Kraken XT5 UtilizationAthena Utilization
9
Cycles Provided to TeraGrid
Upcoming Events / Work at NICS· Kraken upgrade to CLE 2.2 Update 3
– March 23rd, 8am to 5pm.– No changes required by users.– Should improve system stability.
· Annual power outage / electrical maintenance– Target is April 2nd, currently planned for 16 hours.