Overview of NTPC
NTPC was set up in the central sector in the 1975.
NTPC has installed capacity of 29,394 MW. It plans to be a
75,000 MW company by 2017.
NTPC Badarpur station has also bagged ISO 9001/ ISO 14001
certification.
Today NTPC contributes more than 3 / 5th of the total power
generation in India
-
8/10/2019 NTPC Badarpur Mechanical PPT
3/15
Click to edit the outline
text format
Second Outline
Level
Third Outline
Level
Fourth OutlineLevel
Fifth
Outline
Level
Overview of NTPC
-
8/10/2019 NTPC Badarpur Mechanical PPT
4/15
NTPC Badarpur
-
8/10/2019 NTPC Badarpur Mechanical PPT
5/15
Overview of BTPS
BTPS MEETS MORE THAN 24% OF DELHIS
ELECTRICITY CONSUMPTION
INSTALLED CAPACITY = 720 MW
DERATED CAPACITY = 705 MW (3x95 + 2x210MW) OWNED BY GOVT. OF INDIA, MINISTRY OF
POWER.
BEING MANAGED BY NTPC FOR THE LAST 26
YEARS SINCE 1st APRIL 1978. NTPC adjudged as the 3rd best employer in India
-
8/10/2019 NTPC Badarpur Mechanical PPT
6/15
NTPC Badarpur
BTPS was conceived in 1965 to meet the growing
electricity demand of Northern Region.
The site construction activities started in 1968.
The plant became operational with the
commissioning of its first unit on 26th July 1973, 2nd
unit in ;74 , 3rd unit in 75 , 4th unit in 78 & 5th unit
in 81.
-
8/10/2019 NTPC Badarpur Mechanical PPT
7/15
Basic Principle
There are basically three main units of a thermal power plant:
1. Steam Generator or Boiler
2. Steam Turbine
3. Electric Generator
-
8/10/2019 NTPC Badarpur Mechanical PPT
8/15
Electricity from Coal
-
8/10/2019 NTPC Badarpur Mechanical PPT
9/15
BOILER MA INTAINENCE DEPARTMENT
Internally Fire Tube Boiler- 52m height, 60mm diameter.
Powder Coal is air blown into furnace forming the fire required
Water changes into steam at 370 Degree Celsius.
The saturated steam introduced into superheat tubes as the exit from
the furnace.
The superheated steam goes to the 210 MW turbine generator to
generate electricity.
-
8/10/2019 NTPC Badarpur Mechanical PPT
10/15
AUXILLARIES OF THE BOILER
Furnace
Boiler Drum
Water Walls
Reheater
Superheater
Economizer
Air pre-heater
Pulvariser
-
8/10/2019 NTPC Badarpur Mechanical PPT
11/15
PLANT AUXILLARY MAINATINENCE
It con sists o f 6 sub - depar tments:
Water circulation system- a) Natural Circulation system
b) Controlled Circulation system
Ash Handling plant- a) Hydraulic ash handling plant
b) Fly ash collection
Water Treatment Plant- a) Pre- treatment section
b) Demineralization section
Draught system
Fans- a) ID Fans
b) FD Fans
Compressor House-a) Air Drying Unit
b) Air Compressor
-
8/10/2019 NTPC Badarpur Mechanical PPT
12/15
TURBINE MA INATA INENCE DEPARTMENT
Two types of turbines are used in BTPS, i.e., 95 MW and 210 MW.
Generally compounding of turbine is done by using an IP turbine.
Specif icat ions o f turbine used:
Tandem compound 3 cylinder reheated type
Power= 210 MW
Number of stages= 12 in HP, 11 in IP and 8 in LP.
Type of governing: Nozzle governing
-
8/10/2019 NTPC Badarpur Mechanical PPT
13/15
Vacuum Systems
Condensers: 2 for 210 MW at exhaust of LP Turbine.
Ejectors: Total 3 ejectors are used connected
to the condenser.
CW Pumps: It is used to pump water to
the boiler. The pump system is equipped with
LP heaters, deaeriators.
-
8/10/2019 NTPC Badarpur Mechanical PPT
14/15
COAL HANDLING DEPARTMENT
Coal handl ing system
Path A: From hooper to boiler
Path B: From hooper to stockyard
Path C: From stockyard to boiler
Main Coal handl ing Equ ipment
Pulley
Conveyor Belt
Vibrating Screen
Crusher
Magnetic Separator
Vibrating Feeder
-
8/10/2019 NTPC Badarpur Mechanical PPT