ÖBB - Foundation

Rammfundierung bei nder ÖBB 2

Up to 75 m

Contact WireCatenary Wire

Cantilever orBracket Arm

Rammfundierung bei nder ÖBB 3

Standard Types of MastsRectangular Concrete Mast Rectangular Steel Mast

Rammfundierung bei nder ÖBB 4

Concrete Pad Foundation

• Concrete Quantity: 1,2m³ to 12,8m³

• Quiver for Mast Footing • Fastening of Mast by

compacted split gravel

of Rectangular Concrete Mast

Split Gravel

Rammfundierung bei nder ÖBB 5

Development of Piling Technology

Rammfundierung bei nder ÖBB 6

Austropile

Contact Patch/Area

Cutting

Box-Section Frame consists of 4 steel plates with defined contact areas

Rammfundierung bei nder ÖBB 7

Piling Process

Cavity for mast remains

unfilled

NO EXCAVATION

Rammfundierung bei nder ÖBB 8

Advantages of Austropiles• Set-up of foundation in

one step• No excavation• Immediately loadable• Modular concept allows

delivery and installation on short notice

• Construction of foundation at inadmissible location

• Additional earth connection

Rammfundierung bei nder ÖBB 9

Piling Rig

Firstly operated at Rail Station Wörgl

in 1992

Rammfundierung bei nder ÖBB 10

Hydraulic Hammer

• Weight of hammer 1500kg

• Total Weight 2700kg

• Rate of Fall max 4,7m/s

• Blowenergy 16,5 kNm

• Blowrate 60-100/min.

Rammfundierung bei nder ÖBB 11

Advantages of Piling Rig• Operation underneath

existing lines and networks

• Unconstrained operation of subsidiary track

• Self-propelled (no locomotive)

Rammfundierung bei nder ÖBB 12

Advantages of Piling Rig

• Rail-Road Vehicle(minimized travel time)

• Hydraulic Hammer(simplified handling/ adjustable to ground conditions)

• Average Piling Time approx. 25 Minutes(at hardground conditions up to 1 hour)

Rammfundierung bei nder ÖBB 13

Work Flow

Rammfundierung bei nder ÖBB 14

Functional Range of Astropiles

• Mastfoundation of Catenary Systems

• Foundation of Sound Barrier Supports

• Foundation of Signal Masts

• Foundation of Floodlight Tower

Rammfundierung bei nder ÖBB 15

Mast Mounting Device

• Crane Momentum

75 mtons

• Dead Weight 120 tons

• Unconstrained operation of subsidiary track

• Existing Catenary System does not impede operation

Rammfundierung bei nder ÖBB 17

Client‘s Advantages • Optimized Use of Processing Time

• Execution without Locomotives

• Minimized Documentation of Client required ... hence beginning of construction works at short notice

• Optimized Economical Production Costs of Foundation

Rammfundierung bei nder ÖBB 18

Special Operation

Joint Operation of Foundation and Installation Gangs in the Area of Haag

Mission Possible

by using

EUROPTEN - Technology

Rammfundierung bei nder ÖBB 19

Special OperationRailstation Meidling

Foundation Works closed to Platforms

80 Foundation completed in 13

Workingdays under full Operation of

Railtraffic

Rammfundierung bei nder ÖBB 21

• For the further information please contact:

• Mr. Wolfgang Schlesinger

• wolfgang.schlesinger@europten.at

• Marko Marijanovic

• marko.marijanovic@porr.at

Rammfundierung bei nder ÖBB 22

EUROPTEN

an innovative Company

Your PARTNER for the future !