overview of polish carbon capture...
Post on 11-Jul-2020
3 Views
Preview:
TRANSCRIPT
Overview of Polish carbon capture
research
Adam Tatarczuk, Institute for Chemical Processing of Coal
tatarczuk@ichpw.zabrze.pl
Carbon Capture
Forum
18th November 2014
Strategic Programme
2
Advanced Technologies of Energy Generation
Planned co-financing from
National Research and Development Center (Poland)
in 2010-2015 about PLN 300 000 000
Overall Target :
Development of the technologies which implementation will
have an impact on achievement of the EU 3x20 goals:
These targets, set three key objectives for 2020:
• A 20% improvement in the EU's energy efficiency;
• Raising the share of EU energy consumption produced
from renewable resources to 20%;
• A 20% reduction in EU greenhouse gas emissions from
1990 levels.
Gerard Lipiński „ Strategic Programme: Advanced Technologies of Energy Generation", Forum Energetyków
GRE 2014.
The main technology options for CO2
capture from power plant
3
Pre combustion
4
Project No. 3:
Development of coal gasification technology for highly efficient
production of fuels and electricity
Contractors:
AGH University of Science and Technology (Leader),
Główny Instytut Górnictwa (GIG), Institute for Chemical Processing of Coal
(IChPW), Silesian University of Technology, KGHM Polska Miedź S.A.,
Katowicki Holding Węglowy S.A., TAURON Polska
Energia S.A., TAURON Wytwarzanie S.A., TAURON
Wydobycie S.A., Grupa Azoty - ZAK S.A.
Co-financing PLN 80 000 000
Budget PLN 80 000 000 + non-financial and voluntary
contractors contribution
Gerard Lipiński „ Strategic Programme: Advanced Technologies of Energy Generation", Forum Energetyków
GRE 2014.
Project No. 3 – selected research
5 A. Strugała, P. Burmistrz, K. Kogut„ Zadanie badawcze nr 3: „Opracowanie technologii zgazowania węgla dla
wysokoefektywnej produkcji paliw i energii elektrycznej”, Forum Energetyków GRE 2014.
Pressurized CFB pilot gasifier
Institute for Chemical Processing of
Coal (IChPW)
Capacity: 100 kg coal per hour
Underground gasification pilot plant
Central Mining Institute
Capacity: 600 kg coal per hour
Oxy combustion
6
Project No. 2:
Development of a technology of oxy - fuel combustion for
pulverized fuel and fluidized-bed furnaces integrated with CO2 capture
system
Contractors:
Częstochowa University of Technology (Leader),
Silesian University of Technology,
Wrocław University of Technology,
Institute for Chemical Processing of Coal (IChPW), TAURON-Wytwarzanie
S.A., Institute of Power Engineering, PGE S.A. /
Turów Powerstation, Foster Wheeler Energia
Polska Sp. z o.o.
Co-financing PLN 80 000 000
Budget approx. PLN 87 400 000
Gerard Lipiński „ Strategic Programme: Advanced Technologies of Energy Generation", Forum Energetyków
GRE 2014.
Project No. 2 – Oxy combustion main
research
7 T. Czakiert, W. Nowak„ Spalanie tlenowe dla kotłów pyłowych i fluidalnych zintegrowanych z wychwytem CO2–
Projekt Strategiczny NCBR”, Forum Energetyków GRE 2014.
Pressurized CFB oxy combustion
pilot reactor (0,2 MW)
Institute for Chemical Processing of
Coal (IChPW)
Capacity: 25 kg coal per hour
PC pilot boiler for oxy combustion
research (0,5 MW)
Institute of Power Engineering
Project No. 2 – Oxy combustion selected
research
8 T. Czakiert, W. Nowak„ Spalanie tlenowe dla kotłów pyłowych i fluidalnych zintegrowanych z wychwytem CO2–
Projekt Strategiczny NCBR”, Forum Energetyków GRE 2014.
VPSA CO2 capture mobile pilot
plant
Częstochowa
University of Technology / Tauron
Flue gas capacity: 100 m3/h
Air separation mobile pilot plant
Wrocław University of Technology
Post combustion and efficiency improvement
9
Project No. 1:
Development of technology for highly efficient “zero-emission”
coal units integrated with CO2 capture from exhaust gases.
Contractors:
Silesian University of Technology (Leader),
Wrocław University of Technology, Institute for Chemical Processing of Coal
(IChPW),
Kraków University of Technology, Częstochowa University of Technology,
Łódź University of Technology, Warsaw University of
Technology, Institute of Flow Machinery of the Polish
Academy of Sciences, AGH University of Science and
Technology, RAFAKO S.A., TAURON-Wytwarzanie S.A.
Co-financing PLN 69 965 500
Budget approx. PLN 73 000 000
Gerard Lipiński „ Strategic Programme: Advanced Technologies of Energy Generation", Forum Energetyków
GRE 2014.
Project No. 1 – Post combustion research
10
Column diameter: 300 mm
Column height: 15,0 m
Number of devices: 40
Measurements: 180 points
Solvent: 30% MEA
solution
Solvent stream: up to1600 dm3/h
Gas stream: up to 200 m3n/h
Tested gas:
Flue gases from
coalfired boiler
Bussines partner - TAURON
11
Jaworzno Power Plant
Electric power installed: 1535
MWe
Maximal thermal power: 371,6
MWt
Łaziska Power Plant
Electric power installed: 1155
MWe
Maximal thermal power: 196 MWt
IChPW CO2 capture process scale-up
strategy
12
Lab stand for CO2 capture process – 5 m3/h
PDU for CO2 capture process – 100 m3/h (IChPW Zabrze)
The Mobile Pilot Plant – 200 m3/h
Experimental apparatus of CO2 absorption kinetics and equilibrums in amine blends
Pilot plant assembly at Jaworzno Power
Plant – 15.04.2014
13
Pilot plant commissioning at Jaworzno –
5.05.2014
14
15
Deep desulphurization
module
Amine scrubbing module
The Mobile Pilot Plant flow diagram
Split streams versus single stream amine
configuration-streams CO2 fraction
16
Inlet stream
Middle of theabsorber
Outlet stream
0
2
4
6
8
10
12
14
Lean strem to topand semi-lean to
middle of absorberLean stream directedto top and middle of
absorberLean stream to top of
absorber
13.48 13.48 13.44 10.45
7.01
6.18 1.84 1.99 2.69
CO
2 f
racti
on
[%
vo
l.]
Case A Case B
Case C
91.4
84.4
11.26 11.21
3.80 3.90
0
2
4
6
8
10
12
14
16
18
20
0
20
40
60
80
100
With regenerator internal heaters Without regenerator internal heaters Re
gen
era
tio
n e
nerg
y d
em
an
d [
MJ/k
gC
O2]
CO
2 in
let
str
eam
co
ncen
trati
on
[%
vo
l.]
CO
2 r
em
oval
rate
[%
vo
l.]
Effect of regenerator internal heating on
removal efficiency and regeneration energy
17
Reg. energy
demand
CO2 concentration
CO2 removal rate
Operational difficulties
18
• CO2 concentration fluctuations in inlet flue
gas stream
• Additional Venturi scrubber demister due to
flue gases moisture
• Rapid corrosion
in blower
ok. 1,85 [% vol.] CO2 inlet concentration
[% vol.]
Inlet flue gas stream [kg/h]
Outlet stream [kg/h]
CO2 outlet concentration [%
vol.]
Mobile Pilot Plant research summary at
TAURON facilities
19
• The pilot plant campaigns successfully demonstrated reliable operation allowing the removal of over 55
000 kg of CO2 from real flue gas.
• The energy requirement for MEA as solvent was found about 3,6 MJ/kgCO2 with 90% CO2 removal
efficiency due to the application of technological modifications.
• The completed test campaigns can become a baseline for extended comparisons with world data
• Operational experience was gained during test campaigns which can be helpful in designing amine
installations on a larger scale
Parameter Value
Number of campaigns 23
Number of tests 300
Operation time 1400 h
CO2 removed approx. 55 000 kg
Block diagram of demo CCS PLANT
20
ChłodzenieOdsiarczanie
Dmuchawa AbsorberWymiana ciepła
ChłodzenieRegeneratorRekupertor
Chłodzenie CO2 Sprężanie Osuszanie TSAASR ASR
AGR
AN
AGR
AN
Reclaimer
Wyparka
Oczyszczony AGR
AGR
AGR AGR
Spaliny
Gazoczyszczony do
komina
Woda do oczyszczalni
Roztwór odsiarczający
Zużyty roztwór odsiarczający
Kondensat Para
Para Kondensat
ChemikaliaZużyty roztwór amin
Woda chłodząca zasilanie
Woda chłodząca powrót
CO2
Do zatłaczania
1
Kondensat
4 7 8
6
910111216
3
Woda demin do uzupełnienia
Wodachłodząca zasilanie
Woda Chłodzącapowrót
1314
5
Kondensat
Odsiarczanie Usuwanie CO2 Sprężanie CO2
Odsiarczony gaz do komina
2
Woda do oczyszczalni
15
Amine
scrubbing
Desulfurizatio
n
CO2
compression
Integration with Power
Plant
Demo Plant Capacity = 175 tonnes of CO2/h
21
Clean Coal Technology Centre
in Zabrze (Upper Silesia, Poland)
Testing plant
for solid
fuels
gasification Testing plant for CO2
removal in absorption
process
Testing plant for pressure oxy-combustion of
solid fuels
in Circulating Fluidized Bed
Acknowledgments
22
• Presented results were obtained from research work co-financed by the National Centre of Research and
Development in the framework of Contract SP/E/1/67484/10 – Strategic Research Programme –
Advanced technologies for energy generation: Development of a technology for highly efficient zero-
emission coal-fired power units integrated with CO2 capture.
23
”A journey of a thousand miles
begins with a single step”
• Chinese philosopher Laozi (604 bc - 531 bc)
Thank you for
attention.
top related