OZCO Project #287 - Pergola 8x10 with 4x4 Posts
Menards Overview 2V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
OZCO Project #287 - Pergola 8x10 with 4x4 Posts14Menards Overview
V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
196977.50
243896.00
245696.69
= =
2648
104.25
231691.19
= =
3048
120.00
2564
100.94
51768
51717
OZCOMenards Overview V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available
as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
12
51707
5662751775
2 great stylessame functionality
choose your connection lifestyle
both styles available for most productsIronwood
(517XX series)Laredo Sunset(566XX series)
Laredo Sunsetvs.
Ironwood
Menards Overview 13V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
Suggested Tools(others may be required)
14Menards Overview V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
2x6 Beam (all lengths)
512.00 X 45°
Cutlist1Menards Pergola Cutlist
V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
2x4 Purlin (all lengths) 25
1.00 X 45°
4x4 Support (all lengths)
45° 45°
2648
104.25
3299
129.90
196977.50
8x10 siteMenards Site Plan
V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
if site is not level,see Ozco SiteLevelinginstruction
Locate desiredcenter of structure
(HCN)
3/8" DriverTool Required
(OWT Timber Screw)
flush
= =
use this procedure for allsize Pergola's (8x8 shown).same construction stepsand techniques apply.repeat on all sides.
Building your Canopy6Menards Pergola Beams
V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
ITEM NO. QTY. PART
NUMBER DESCRIPTION
1 2 2x6 Board 2x6x120.00
2 4 4x4 Support 4x4x24.00
3 1 517684” Flush Inside 45 (FI45-IW-4)
4 0.32 56627OWT Timber Screw 3-3/4"
OZCO Project #287 - Pergola 8x10 with 4x4 PostsMenards Pergola Beams V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available
as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
4
1
3
2
3/8" Driver
(HCN)
Tool Required
(OWT Timber Screw)
install on both ends
of all rafters
); see your CLconfiguration for quantity and
use this procedure for all
flush
same construction steps
repeat on all sides.
beam
size Pergola's (8x8 shown).
and techniques apply.
CLspacing for subsequent rafters
install this rafter on beam centerline (
Installing your Rafters & Supports6Menards Pergola Rafters
V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
34413.5 typ
ITEM NO. QTY. PART
NUMBER DESCRIPTION1 9 2x4 Board 2x4x96.02 4 4x4
Support 4x4x29.5
3 1 51768 4” Flush Inside 45 (FI45-IW-4)
4 0.32 56627 OWT Timber Screw 3-3/4"
5 1Menards Pergola Beams
12x12 Beams
6 1.8 517172" Standard Rafter Clip (RC-IW-2)
OZCO Project #287 - Pergola 8x10 with 4x4 Posts6Menards Pergola Rafters V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available
as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
1
2
4
3
6
CL = =
1024.0 typ
CL
beam
install with nails or screws
use this procedure for allsize Pergola's (8x8 shown).same construction stepsand techniques apply.repeat on all sides.
Purlins6Menards Pergola Purlins
V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
install first purlin on beam centerline (CL ); see your configuration for quantity of purlins
OZCO Project #287 - Pergola 8x10 with 4x4 Posts6Menards Pergola Purlins V2.00 - Installation Instructions, Specifications and Project Plans are effective May 1, 2015 and reflects information that available
as of April 10, 2014. This information is updated periodically and should not be relied upon after October 15, 2016. Please visit www.OZCOBP.com to get current information.
ITEM NO. QTY. PART
NUMBER DESCRIPTION
1 23 1x2 Board 1x2x120.0
1