planning for large scale solar pv in...
Post on 09-Jun-2018
221 Views
Preview:
TRANSCRIPT
April 2010 - Feed in Tariff
• Anticipated a large number of applications for 5MW solar farms
• Dedicated team of planning officers• Training for elected Members• Planning guidance• Planning Performance Agreements• 250 sites screened
August 2011 – Our achievements
• 36 planning applications submitted• 36 granted planning permission• 130MW (50MW installed)• No refusals
http://www.cornwallsolardirectory.co.uk/inward-investment.php
Community Gain
• 4MW solar farm• Community benefit £20-25,000 per year for 25 years• Direct to Parish Councils to be spent in the community• Sustainable energy production, energy demand reduction
and awareness raising
• Landscape/visual impact • Agriculture• Ground maintenance• Ecology• Ground Anchors• Historic environment• Drainage• Security• Glint & glare• Duration of planning
permission
Planning Guidance for Large Scale Solar PV Arrays
The Golden Rules
• Avoid BMV agricultural land• Ground maintenance• Landscape & visual/cumulative
impact• Ecological
opportunities/enhancement• Longevity/permanence/reversibility
Adrian Lea Manager; Natural Resources Planning Team alea@cornwall.gov.uk 01872 224504
top related