11 June 2018 1 / 17

Progress Photos for New PUWYPS Campus at Pak Fuk Road as at 11 June 2018

11 June 2018 2 / 17

Chiller for Assembly Hall

delivered to Site

Adjacent School B

Transformer Room and

Ball Court Area

11 June 2018 3 / 17

Covered Playground

Emergency Access into

Adjacent Park

View of Ball Court Area from

Covered Playground

11 June 2018 4 / 17

Covered Playground

Tuck Shop

Covered Playground

11 June 2018 5 / 17

Handwashing Basin next to

Tuck Shop G/F Store Room next to

Hub Room

Area in front of

Guidance Activity Room

11 June 2018 6 / 17

11 June 2018 7 / 17

G/F Administration Office

11 June 2018 8 / 17

Store Room within Administration Office

11 June 2018 9 / 17

Assembly Hall

11 June 2018 10 / 17

View of Assembly Hall

From

Stduent Acivity Area

underneath the Balcony

Corridor outside

Assembly Hall and

Student Activity Area

Main Gate

Guard House

11 June 2018 11 / 17

2/F Classrooms

at East Wing

Computer Asst

Learning Room No. 1

on 2/F

4/F Language Room

11 June 2018 12 / 17

View of East Wing from

4/F of North Wing

Seatings outside 4/F

Corridor of North Wing

5/F Classroom

11 June 2018 13 / 17

Multi-purpose Area at

5/F North Wing

Prep Room

View of East Wing and

Main Entrance

4/F seatings

6/F Visual Art Room

11 June 2018 14 / 17

Prep Room of

6/F Visual Art Room

6/F Computer Assist

Learning Room No. 2

11 June 2018 15 / 17

6/F Music Room

11 June 2018 16 / 17

&

7/F Flushing & Potable

Water Pump Room

7/F Planter

7/F Outdoor Playing Area

No. 1

11 June 2018 17 / 17

Upper Roof and Outdoor

Playing Area No. 2

Outdoor Playing Area

No. 2

Top Roof