DESCRIPTION

Opencast Contract Mining, Drill, Blast, Load, Haul

TRANSCRIPT

www.construction.murrob.com

BEESHOEK Northern Cape, Postmasburg

PROJECT TYPE: OPENCAST MINING

CLIENT:

Assmang Iron Ore

VALUE:

R722 Million

CONSULTANTS:

None

PROJECT DURATION:

34 Months

DATE OF PROJECT:

1 November 2011

PROJECT DESCRIPTION:

50% Joint Venture with Basil Read for the

contract mining of iron ore.

Approximate volumes for the project:-

Total mining depth will be 190m.

• Total over burden 48,000,000 tons

• Total iron ore 5,500,000 tons