REM Back Flushing (MFBF)
Applies to:
SAP SCM-Production Planning. For more information, visit the Supply Chain Management homepage.
Summary
REM Back flushing is the process used in production/process industries for automatic goods receipt/issue purposes.
Author: Saraswati Chandra Srivastava
Company: Intelligroup
Created on: 30 Dec’ 2010
Author Bio
Saraswati Chandra Srivastava Working as Senior Associate consultant, SAP SCM.
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 2
Table of Contents
REM Back flushing ( MFBF ) ............................................................................................................................. 3
Back Flush Manual Activity Changes ................................................................................................................. 9
Document Cancellation ..................................................................................................................................... 11
Related Content ................................................................................................................................................ 13
Disclaimer and Liability Notice .......................................................................................................................... 14
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 3
REM Back flushing ( MFBF )
REM (Repetitive Manufacturing) Back Flushing:
Double click the selection to move to REM Confirmation screen
So, the following screen is for REM Confirmation:
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 4
This slide is only for your Information:
REM Back flushing With Stock:
Example: We have A095037 Header material with BOM as illustrated below-
We have stock for all the above material as:
A095037 (PR01): 0 Nos
A057092 (PR01): 2000 Nos
G058029 (PR01): 2000 Nos
We have planned order No as 15268 with 1479 Nos
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 5
All the Details regarding the Planned order are fetched in the following screen:
1. Enter the
Planned order
No & Press
Enter
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 6
So, Material stocks are updated, as well as the activities are posted
automatically. The Activity values are set in Routing. So, the document is posted.
1. Enter the
Planned order
No & Press
Enter 2. Click to
save the
posting
document
2. Enter the
Date of Manufacturing
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 7
This slide is only for your Information:
We have now updated stock for all the BOM material as:
A095037 (PR01): 1400 Nos available for Quality inspection (Goods receipt)
A057092 (PR01): 600 Nos (Goods Issue)
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 8
G058029 (PR01): 600 Nos (Goods Issue)
So, we have seen the REM back flushing with available Stock, & with automatic activity back flush.
Also we have seen the impact on stock at receiving & Issue storage locations.
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 9
Back Flush Manual Activity Changes
In last transaction we have done activity back flush automatically,
If we want to do it manually, we have to do following steps:
For same order 15268 we would carry out the manual Activity back flush:
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 10
See the following selection screen:
In following screen you can put actual values of activities recorded for the production as illustrated below-
See the message on task bar
So, A095037 stock (PR01): 1479 Nos
A057092 stock (PR01): 511 Nos
G058029stock (PR01): 511 Nos
2. Click to move
to activity posting screen
1. Select
the row
1. We can put actual values here.
2. Save the
document
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 11
Document Cancellation
(This is to be done only with request by authorized person)
1. Select to move to document cancellation screen
3. Select to see the document list
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 12
So, all the documents are exploded as:
See the following message on task bar:
So, again the stock is reversed
A095037 stock (PR01): 1400 Nos
A057092 stock (PR01): 600 Nos
G058029stock (PR01): 600 Nos
1. Put the cursor on the document
which you want to reverse
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 13
Related Content
For more information, visit the Supply Chain Management homepage
REM Back Flushing (MFBF)
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 14
Disclaimer and Liability Notice
This document may discuss sample coding or other information that does not include SAP official interfaces and therefore is not supported by SAP. Changes made based on this information are not supported and can be overwritten during an upgrade.
SAP will not be held liable for any damages caused by using or misusing the information, code or methods suggested in this document, and anyone using these methods does so at his/her own risk.
SAP offers no guarantees and assumes no responsibility or liability of any type with respect to the content of this technical article or code sample, including any liability resulting from incompatibility between the content within this document and the materials and services offered by SAP. You agree that you will not hold, or seek to hold, SAP responsible or liable with respect to the content of this document.
top related