Michael Kearney | ELECTRICAL ESTIMATES,
Aberystwyth University &Ceredigion County Council.
RISK ASSESSMSENTS & METHOD STATEMENT,
Automatic Doors and Barriers
Service Contract:
SITE SPECIFIC RISK ASSESSMENT WORKSHEET, VARIOUS LOCATIONS THROUGHOUT CEREDIGION.
Carried out by: Michael Kearney Date: 10/11/15
Details of activity: Service contract, for Automatic Doors & Barriers, For Aberystwyth University & Ceredigion County Council.
Staff/contractors involved in activity: Michael Kearney, Matthew Klemencic, Darren Conway, Matthew Conway, Paul Thomas, Jordan Payne
Victoria Kearney CLO
HAZARD RISK WHO IS AT RISK? ACTIVITIES WHERE RISK
MAY BE ENCOUNTERED
CONTROL MEASURES IN
PLACE
FURTHER ACTION REQUIRED
Work at height.
Whilst Carrying out
High level Works
Falling from height
Dropping objects
from height.
Dust/ Debris falling
from height around
working position.
Electrical
Estimates Staff
CCC & AU Staff.
Members of
Public.
Students
Working on top of the
Access Equipment,
incorporating Ladders
Steps, and Mobile
Scaffolding when
operation
Bump Hats worn by all
staff working above &
beneath the working
area, as to protect
Staff.
Standby man working
below Ladders.
Restrictive access to
working areas by
Physical Barrier and
Warning Notices.
Initial first day Risk assessment
carried out by Engineer in
attendance on the day of
starting, to ascertain if
conditions have changed
from the formal Risk
Assessment.
Regular Monitoring of site
Environments,
Regular monitoring of signage
and restrictive access
measures,
Working at Height
From ladders
Falling from Ladder
Dropping of Debris,
tools and materials
from Ladder
Electrical
Estimates Staff
CCC & AU Staff.
Members of
Public.
Students
Servicing of Door
motor and Sensors.
Bump hats worn by all
staff working beneath
and around the
working area.
Barriers to perimeter
Areas off,
Lock doors, restrict
access.
Permit to work, in
certain areas.
Good housekeeping,
Only using tools required whilst
on ladders,
Use of permitted tool belt,
Use of ladders with wide
treads, for no more than 20
mins at a time, with 10 min
breaks in between.
Employees
Personal Protection
Damage to hands
Damage to eyes
Damage to body
Damage to hearing
Damage to
respiratory system
Electrical
estimates staff
Whilst carrying out all
works within this
contract
Bump hats to be worn
Hi viz to be worn
Safety eye wear to be
worn, where required
Safety shoes to be
worn
Safety ear protection
to be worn (if req)
PPE to be worn
FFP3 masks to be
worn, should
employees see fit.
Monitoring of staff by running
supervisor,
Checking and confirmation of
PPE prior to commencement
of any works.
RISK ASSESSMENT WORKSHEET (CONTINUED)
HAZARD RISK WHO IS AT RISK? ACTIVITIES WHERE RISK
MAY BE ENCOUNTERED
CONTROL MEASURES IN
PLACE
FURTHER ACTION REQUIRED
Working with
electricity
Electrocution
Burns
Fire
Electrical
Estimates Staff
CCC & AU Staff.
Members of
Public.
Students
Live testing
Open fuse board
Opening of sockets &
switches
We will where
practicable hinder
contact with only
energised circuits,
Lock off procedures in
place, complete
isolation of all supplies
to electrical fittings is
to take place prior to
commencement of
any works,
Keys held with site
supervisor.
Locking system will be
used in this instance.
Staff will use insulated
tools when carrying
out work.
Regular monitoring of
Environment, based on work
type,
Use of Skilled personnel,
Parking, Egress &
Ingress to contract.
Risk of maintenance
staff being hit by
moving vehicles.
Risk of damaging
parked vehicles.
Electrical
Estimates Staff
CCC & AU Staff.
Members of
Public.
Students
Entering & exiting the
site Car park
Designated parking
areas,
Reduction of speed to
4 miles per hour when
entering and exiting
the site.
Reduction in company
vehicles on site, as to suit
contract size,
Wearing of Hi-Viz PPE
Sign written vehicle,
Parking in designated areas
Health and safety
Internal Training
No risk Present Electrical
estimates staff
Tool box meeting may
be required by client,
Monitoring by CCC
employees, that all
electrical estimates
staff, have and
currently.
All employees from electrical
estimates,
Regular monitoring and
welfare checks from the CLO
and Project Manager.
Use of testing
equipment
Electrocution
Burns
Electrical
estimates staff
Live testing
2 man working
Test leads meeting
GS38
Calibrated test
instrument
Qualified staff
Regular monitoring of staff,
Working within limitation
guidelines
Regular consultation with
client’s representative.
Pat testing of all equipment.
Electrical Testing &
Certification
Electrocution
Burns
Fire
Electrical
estimates staff
Live testing of new
circuits, to gain Zs, and
polarity confirmation.
Testing will take place
in 2 half’s, Dead
Testing to confirm
Insulation Resistance
on cable is
Acceptable, and
Dead Testing Once
the circuit is energised
Skilled engineer to carry out
testing
2 man working
Calibrated test equipment,
Damage to body
from Cutting
actions, installation
of Dampers in
metal work.
Cuts
Loss of digits
bleeding
Electrical
estimates staff
Use of Stanley/utility &
open blades, whilst
working on electrical
installation works,
No fixed blades to be
used
No blades over 2”
Wearing of cut gloves
level 3, at all times
when using knifes
Monitoring of cut gloves use,
Issue of cut gloves level 3,
Monitoring of fixed blades
within staff tool boxes.
Damage to
Body/Skin from
using silicon’s and
sealants.
Skin rash
Skin irritation
Eye damage
Ingestion
Electrical
estimates staff
Sealing rooms and
subfloors with sealants
Use of eye protection
Use of disposable
gloves
Use of correct
application
equipment
Installation as per
manufacturer’s
instructions
Regular monitoring of
Environment, based on work
type,
Damage to Body
or individual’s
Whilst carrying out
Service Contract,
through Crushing
or trapping actions
Trapping of Limbs
and body
Severing/Damage
of limbs and body
parts
Crushing of limbs or
body parts
Electrical
Estimates Staff
Setting up of control
and safety circuits,
Testing of door and
setting door
parameters.
Isolation of Door under
service works, where
practicable
The use of Specifically
designed Test body
Box approved by
ADSA,
Ensuring Monitored
Sensors are in
operation for the door
system.
Ensure all opening
and closing activation
buttons are operating
correctly
Ensure correct Newton
Pressure is set to the
door opening and
closing action.
Ensure Permanent
Restrictive barriers are
in place for all
crushing and walk into
zones.
Ensure that if required
Pressure sensitive
Safety edges are
installed
Ensure that where
required figure guards
Regular monitoring of
Environment, based on work
type,
Regular consultation of EN
regulations,
Regular consultation with
ADSA, and door control gear
manufacturers.
are placed on all
appropriate positions.
BRIEFING TITLE: Tool Box, Briefing Contract: Door Service contract, Various locations throughout
Ceredigion, for Aberystwyth University and Ceredigion County Council,
Work to be Carried Out:
Door Service Contract.
Applicable Risk Assessments and Method Statements:
As Detailed within Folder.
Briefing Given By: Mick Kearney Date: TBC
Ref. Employees Name Signature Comments
1 Michael Kearney
2 Mathew Klemencic
3 Darren Conway
4 Matthew Conway
5 Victoria Kearney
6 Paul Thomas
7 Jordan Payne
8
9
10
11
12
13
14
15
Method Statement Specific.
Description of the Task/Activity: Door Service Contract. Aberystwyth University & Ceredigion County Council.
Project Name: Door Service Contract Project Ref: 8791 (CCC) & 8792 (AU)
Site Address/ Location:
Various Locations, Throughout Ceredigion, Aberystwyth University and CCC Building’s
Start Date/Time:
Proposed 16/12/15
Finish Date/Time:
TBC
Personnel involved:
Name Role/Trade
Michael Kearney Manager
Victoria Kearney CLO
Matthew Klemencic Contract manager
Darren Conway Electrician & ADSA Engineer
Paul Thomas Electrician & ADSA Engineer
Matthew Conway Improver
Jordan Payne Improver
Steve Hulme Electrician & ADSA Engineer (back up and on call)
Works Supervisor: Michael Kearney
Role: Manager Tel: 07815843177
Key Plant and Tools Required:
Hilti 24v Battery SDS drill, 24v battery drill, 24v 110v site festoon lighting, Cree Torches, 110v leads, 110v sds drills,
general hand tools, Walkey talky, Force Meter, Barriers,
Podium steps, Ladders fibre Glass, Signage.
Key Materials Required: Fluke Tester, Force measurement Tester, Labels, Lock off kits, Fluke test equipment, Tablet, & Sundries
Other Essential Equipment:
Signage, Warning signs, Podiums, Ladders, Walkey Talkies
Test Equipment,
Specific Identified Residual Hazards: (or refer to the task specific risk assessment(s))
Please refer to the preface of this form.
Specific Staff Training Requirements:
This Contract in a nut shell is to Service the Automatic door stock of Aberystwyth University and Ceredigion County Council,
throughout Ceredigion, a detailed location chart can be found on electrical estimates Service 1 proposed date Sheet,
The Purpose of these works is to ensure the safe running of all doors, and provide the client with a list of all defective /
obsolete parts within the frame work.
Method of working
1. after being inducted within the offices of electrical estimates, all personnel will ensure all works carried out, will be carried
out in a safe and professional manner, and will in no way effect any other trades in the vicinity of works being carried out or
hinder the day to day workings of the office staff present within the building/s, visiting trades or operatives working within the
designated site, employees will be told that the contract will start with identification of any sensitive works & Areas, and the
engineers will have a tool box meeting on site to run through the contract with the client should this be required. The use of
Barriers and protection of floor coverings where drilling may be required and the engineers will be made aware of the
importance of this, together with safe isolation procedures and the use of lock off kits and complete isolation of Door Sets,
and installation of temporary warning notices and identification notices,
2. Once ready, the Service team will attend the specific site and report to the clients chosen log in point, once satisfied the
engineer/s will attend there place of work, once Parked safely within the designated parking areas, inform the Manager or
Caretaker in attendance of works being carried out together with the length of time the proposed service should Take.
3. Checking of the Asbestos Register, Non Sensitive and paper work are to be carried out in the first instance as to allow the
engineers to get a feel for the site and the working conditions, a Secondary Risk assessment will be carried out by the
Engineer prior to commencement of any works, should they feel there are new Risks present they will inform the Office in the
first instance and all works will be halted until all parties are satisfied.
4. When ready and satisfied the engineer/s will commence to barrier the working position of as to hinder ingress from the
members of public into the proposed working environment.
5. Commencement of the Service contract will begin and Special attention will be observed when working over the
equipment, should there be any concerns, the immediate supervisor from AU or CCC will be informed, and EE engineers will
await for further instruction.
Sequence of Operations:
6, works programme will be as follows
A, Check/Log in to site
B, Arrive at place of work and park safely
C, inform Manager or caretaker of arrival and detail location and length of proposed works.
D, read asbestos register, and carry out non-intrusive paper work
E, Prepare site with barriers and dust sheets, install temporary warning labels and notices at all point leading towards the
proposed works.
F, Carry out Service and checking required within the contract.
G, Once complete re-install all components and housing’s back to the Automatic door
H, Clean Working area, and remove barriers from service,
I, Prepare Service Sheet for issue, and digitally send to the office, for confirmation.
J, Re-energise door and inform Manager / Caretaker all works are complete, explaining is required of any issues the door
may have, and detail any additional that may be required with a second visit needed at a later stage.
Cont:
7, the client will be informed at regular intervals how the testing is proceeding, and of any issues arisen from the work being
carried out, and works requiring a Quotation will be issued within 3 working days.
8, Regular site visits will be carried out by electrical estimates managers to ascertain the programme and to provide the
client with the regular updates.
9. As with all large contracts this summary in not exhaustive, we will update these documents as the contract is rolling along if
we feel amendments or additional RAMS are required.
End.
Mike Kearney
Method of Access and Egress to the work area:
Vehicles will be parked in the Buildings Car park to the side of the building, and all employees will report to the site reception
and sign in, submission of daily RA’s will be issued to the attending site Forman or attending manger, Egress from site, all
employees will prior to leaving site, report to the site reception, and sign out, any problems on site or special requirements will
be relayed to the site Forman or on duty Manager in the first instance. Any speed restrictions will be adhered to, too and from
the main road.
Fall Protection Measures: If applicable.
Generally high control methods will be in place on all works at height and risk assessed out where possible, Guard Rails/Toe
Boards/Brick Guards/Safety Harnesses/Exclusion Zones, time working on ladders will be restricted to 20mins per session with 10
min breaks unless podium steps are being used on the contract.
Hazardous Substances: (Attach COSHH Assessments and MSDS)
Hazardous substances of this site will be limited to
Silicon & Caulks.
Greases
Tallow
Fine Dust.
This list is not exhaustive, and will be upgraded when and if additional substances are needed,
Very Toxic
Harmful/ Irritant
Corrosive
Dangerous for
the environment
Oxidising
Highly
flammable
Explosive
Applicable: No Yes No No No no No
Delivery’s to Site:
All suppliers that are based locally to the contract, in this instance Aberystwyth suppliers, covering, CEF, Edmondson’s, Links,
will be informed of the protocol, and told to inform the site electrician form via telephone, that a delivery is on site and ready
for off-loading, the delivery drivers will be informed that just walking on site will not be tolerated under any circumstances.
Required Personnel Protective Equip.: Safety Boots Hard Hats Safety
Gloves Hearing
Protection Respiratory Protection
Eye Protectio
n
Other: 1. Hi-Viz 2. Coveralls 3. glasses 4.bump hats 5.gloves grade 3 6.disposable silicon gloves for Greases 7. Cleaning Rags and papers.
Yes Yes Yes Yes Where
Applicable Yes
Emergency Procedures:
Initially, the emergency procedures of this site will be carried out as required by the building manager, sequence of events
and reporting will be as laid down as detailed within the site induction meeting.
First Aid Facilities:
Name of On-Site First Aider:
Paul Thomas / Darren Conway
First Aid Box Location: Site office, or engineers NV200 Van.
Location of Nearest Hospital:
Bronglais Hospital, Aberystwyth
Other Information & Comments:
None at this time
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the company’s Health and Safety Policy. Prepared by: M Kearney Position: Manager Date: 10/11/15 Reviewed by: Matthew Klemencic Position: Compliance Manager Date: