R/V Marcus Langseth

R/V Marcus LangsethProject Start

R/V Marcus Langseth

● USCG

● ABS

● Multibeam Acceptance

● DP Acceptance

○ NSF Ship Inspection (Now)

○ Transfer of Ownership to NSF (Soon)

○ Shakedown and Calibration (Nov 16 – into Jan 08)

○ Operations (Early 08)

R/V Marcus LangsethUSCG COI ABS Class

R/V Marcus LangsethEM120 1º x 1º Multibeam Acceptance

EM120 1º x 1º

Transducer Array

48 Modules

each with 18 Elements

Receive Array

16 Modules

each with 8

Transducer Staves

Calibration Acceptance Plan

Langseth Multibeam Acceptance

Alaminos Canyon

Langseth Multibeam Acceptance

Langseth Multibeam Acceptance

Surface

Sound

Speed

Velocity

Langseth DP Acceptance

Langseth DP Acceptance

R/V Marcus LangsethNSF Ship Inspection Transfer of Ownership

R/V Marcus LangsethShakedown and Calibration

R/V Marcus LangsethMCS Paravane Towing – Example of What Needs to Go Right

R/V Marcus LangsethMCS Paravane Towing – Example of Why

R/V Marcus LangsethGoing Forward

Money & Technicians & Technicians & Technicians