s tatus of the machines over x-mas standby period,
Post on 17-Jan-2016
32 Views
Preview:
DESCRIPTION
TRANSCRIPT
status of the machines over X-mas standby period, services required and plans for rapid start-up
OP Group Meeting
KH
• cooling circuits require 200-300 kW heat load in order not to freeze• circuits of the equipment must not be separated from the main cooling circuit • for the temperature surveillance (BE/OP/TI) alarms must be available
cooling circuits
KH
facility cooling circuit load (present or required)
Linacs and LEIR FDED-00049 enough heat load
PSB + TT2 FDED-00065 need to generate load
PSB F$FSEG-00361 need to generate load
PS FDED-00050 centre anneau need to generate load
PS FDED-00032 aimant PS need to generate load
PS F$FSEG-00355 need to generate load
PS FTEB-00046 POPS need to generate load
SPS enough heat load
North Area enough heat load
Machine Circuits Status Rem :
LEIR - LINAC FDED-00049 Running Source of Linac 3 running
PS Main magnetFDED-00032
Stopped and drained
Difficult to keep it loaded
PS Central buildingFDED-00050
Running Load from EPC
PS POPSFTEB-00046
Stopped and drained
Difficult to keep it loaded
PS + Linac Chilled water PSF$FSEG-00355
Running Linac3 running
PSB Booster + TT2FDED-00065
Running Load from EPC
PSB Chilled water BoosterF$FSEG-00361
Running Loaded with the ventilation
SPS SPS ringFQSTR-00003
Running Cryo machine sector 1-2
North area NAFQSTR-0002
Running Cryo North Area
cooling circuits - IEFC 19/10/12
• CV will intensify the rounds during the closure especially if the weather is cold.
• On Monday January 7th , CV will restart :• PS : FDED-00032 PS Magnet• POPS: FTEB-00046
• POPS will be fully operational on Tuesday.
S.Deleval – IEFC 19/10/12
cooling circuits - IEFC 19/10/12
6. February 2012: a good example
• Extremely cold and windy weather • All the primary circuits were running with a reduced load. • Large amount of problems on drinkable and fire hydrant circuits but the
primary circuits had well resisted • POPS start up was delayed because the filling circuit was frozen →
corrective work acheived.
IEFC 19 October 2012 S.Deleval – IEFC 19/10/12
Linac2 (see EDMS 1235164):• source pulsing, beam on source beam stopper• most converters on• RF off• vacuum maintainedPSB:• some TT2 converters on• all other converters off• RF off• vacuum maintainedPS:• converters off• RF off• vacuum maintainedSPS:• power converters off• RF power amplifiers on (dampers, TWC800, TWC200, IOT prototype in BB3) • vacuum maintained• cooling stays on
proton machines, status
KH
machine BE/OP BE/ABP TE/EPC BE/RF BE/CO,IT
TE/VSC access RP EN/CV* EN/EL*
Linac2 TI SV X X X X X X X
PSB TI + SV X X X X X X X
PS TI + SV X X X X X X X
SPS SV X X X X X X X
proton machines, services
KH
* EN/CV and EN/EL provide always piquet service
• ‘best effort’ service during working hours, but somebody must be reachable• piquets which are not required (magnets, kickers, LL RF, … do not appear)• magnets: in case of water leaks best effort
OP: TI plus support from beam operators plus supervisor
Linac3 (see EDMS 1235164):• source pulsing, beam on source beam stopper• most converters on• RF off• vacuum maintained
LEIR:• all converters off• RF off• magnetic cycle prepared in case of re-start• vacuum maintained
ion machines, status
KH
machine BE/OP BE/ABP TE/EPC BE/CO,IT
TE/VSC access RP EN/CV* EN/EL*
Linac3 TI SV X X X X X X X
LEIR TI + SV X X X X X X
ion machines, services
KH
* EN/CV and EN/EL provide always piquet service
• ‘best effort’ service during working hours, but somebody must be reachable• piquets which are not required (magnets, kickers, LL RF, … do not appear)• magnets: in case of water leaks best effort
GS: • roads cleared• fire brigade informed• lifts• DSO coverage
references:Linacs: EDMS 1235164
other services
KH
2013 start-up
KH
06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan
L2 set up beam 2 PSB PSB set up beam 2 PS PS set up beam 2 SPS SPS set up beam 2 LHC
L3 source re-fill set up beam 2 LEIR LEIR set up beam 2 PS PS set up beam 2 SPS SPS set up beam 2 LHC
beam to be given downstream as soon as readybeam parameters to be confirmed well before X-mas