s20 – september checklist h&smr03 · s20 – september checklist h&smr03 health &...

Post on 20-Apr-2020

2 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

S20 – September Checklist H&SMR03 - 1 / 1 Produced in association with The Institute of Quarrying

Issue 1 : Revision 1 - September 2012 © QMJ Publishing Ltd

S20 – September Checklist H&SMR03

Health & Safety Risk

Management System

Ensure no tasks are being undertaken without appropriate risk assessments and safe systems of work in place.

Non-compliancetransferred ontomanagement

Item Checked action plan

VDUs

Are the assessments up to date and have identified actions been implemented? Yes O No O Yes O No O

Visitors

Is a visitors book held at the site reception? Yes O No O Yes O No O

Are visitors rules available for issue? Yes O No O Yes O No O

Is there suitable evidence that the book is being used and rules issued? Yes O No O Yes O No O

Asbestos

Has an asbestos survey been undertaken on the site? Yes O No O Yes O No O

Has an asbestos management plan been put into place? Yes O No O Yes O No O

Is a site plan available showing locations of asbestos? Yes O No O Yes O No O

Is asbestos clearly marked out on the site? Yes O No O Yes O No O

Is there a good system for monitoring and review in place? Yes O No O Yes O No O

Signatures

Responsible manager Date Comment

...................................................................................... ............... .......................................................................

Senior manager Date Comment

...................................................................................... ............... .......................................................................

top related