Safety of transport
of dangerous goods
by rail
The view of the Belgian
Infrastructure Manager
Robert BOOGAERTS – I.TMS.12
Risk Manager
26th November 2014
Agenda
• Legal context
• Assessing the risk
• Prevention of accidents
• Mitigation of the consequences of accidents
• REx of incidents
26.11.2014 Transport of DG by Rail 2
26.11.2014 Transport of DG by Rail 3
Infrabel: Facts & Figures (I)
• NV / SA under public law
• Infrastructure manager of the Belgian
rail network since 2005
• 12.564 employees
• 15 clients – operators
• Investments 1,153 billion euro (2013)
0. WHO IS INFRABEL ?
26.11.2014 Transport of DG by Rail 4
Infrabel: Facts & Figures (II)
6.472 km main line tracks
(2284 km secondary tracks)
10.060 track devices
(points, crossings, …)
78 traction substations 3kV
+ 7 traction substations 25kV
177 signal houses
1 Traffic control
10.466 main signals
12.609 civil works
0. WHO IS INFRABEL ?
26.11.2014 Transport of DG by Rail 5
Consignor
Tank container
operator
Loader/ filler Carrier Consignee
Railway Infrastructure manager = Infrabel
Requirements for
construction and testing
(part 6 RID) : safety
valves; wall thickness …
Correct use:
choice of tank wagon,
filling ratio, …
(part 4 RID)
• ascertain (visually) that wagons
comply with RID;
halt the consignment if
infringement is observed.
• ensure that information on
dangerous goods is available for
the infrastructure manager
Info on dangerous
goods in the train
Placarding +
transport document
RID 1.4.3.
1. LEGAL CONTEXT
Obligations of the IM
in the context of the RID
26.11.2014 Transport of DG by Rail 6
1. The IM shall ensure that he has a rapid and unrestricted access to
the following information at any time during carriage :
• the composition of the train …
• the UN numbers of the dangerous goods being carried in or on
each wagon, or if only dangerous goods packed in limited
quantities are being carried, information indicating their presence
...,
• the position of each wagon in the train (wagon order).
2. The IM shall ensure that internal emergency plans for marshalling
yards are prepared.
1. LEGAL CONTEXT
Activities of Infrabel regarding
Risk analysis and evaluation (1)
26.11.2014 Transport of DG by Rail 7
2. ASSESSING THE RISK
1. Mapping of the transport flows of DG;
26.11.2014 Transport of DG by Rail 8
Activities of Infrabel regarding
Risk analysis and evaluation (1)
26.11.2014 Transport of DG by Rail 9
2. ASSESSING THE RISK
1. Mapping of the transport flows of DG;
2. Analysis of accident statistics (determine probability of accidents);
3. Quantitative assessment of the risk level for the sections of the
network with the highest transport flows;
10
Line 27A – satellite photo
26.11.2014 Transport of DG by Rail
11
Isorisk contours
for line 27A
10-6 : 13 m 10 m
Distance between the
isorisk contours and the tracks
in 2014 forecast 2016
10-7 : 241 m 198 m
10-8 : 953 m 710 m
26.11.2014
2. ASSESSING THE RISK
Transport of DG by Rail
Activities of Infrabel regarding
Risk analysis and evaluation (1)
26.11.2014 Transport of DG by Rail 12
2. ASSESSING THE RISK
1. Mapping of the transport flows of DG;
2. Analysis of accident statistics (determine probability of accidents);
3. Quantitative assessment of the risk level for the sections of the
network with the highest transport flows;
4. Development of a model (matrix) to classify the marshalling yards
according to their level of risk;
5. Risk analysis of marshalling yards :
Modernisation Monceau (project abandoned);
Antwerpen-Noord (with/without remote control of locs);
Zeebrugge-Zwankendamme (extension of the yard);
Generic : localisation of the hazards (in line with SNCF study).
Activities of Infrabel regarding
Risk analysis and evaluation (2)
26.11.2014 Transport of DG by Rail 13
6. Risk analysis of the transport of DG (bow-tie model):
Causes for derailments and collisions
(= type of accidents that could lead to a release of DG);
Factors that could aggravate the consequences.
7. Participation in the “TWOL-studies” of the Flemish Authorities,
department LNE for the building of a
‘Risicoanalysesysteem voor transport van gevaarlijke stoffen’
(Risk analysis system for the transport of dangerous goods)
CAUSES CONSEQUENCES
EVENT
2. ASSESSING THE RISK
Measures by the Infrastructure manager
to prevent accidents with DG
26.11.2014 Transport of DG by Rail 14
1. Concrete sleepers
2. Long welded rails
3. Hot-box detection
4. Installation of Automatic Train Protection Systems TBL1+ and ETCS
5. Restrictions : transport of DG not allowed in some tunnels :
• Brussels N-S-junction : no DG;
• Antwerp N-S-junction and Diabolo-tunnel : no freight trains;
future :
• Antwerp Kennedytunnel : no DG (from december 2015);
• Brussels Schuman-Josephat (new) : no freight trains.
3. PREVENTION OF ACCIDENTS
Measures by the Infrastructure manager
to mitigate consequences of accidents
26.11.2014 Transport of DG by Rail 15
1. Infrabel Internal Emergency Plan (new release 2014)
2. Specific Emergency Plans
(e.g. for Kennedy tunnel and Liefkenshoek Rail Link)
3. Upgrade of Emergency equipment for Kennedytunnel
4. Roadshow RID for Authorities and Emergency services (2014-2015)
5. Application “Fill-In” (train compositions)
4. MITIGATION OF THE CONSEQUENCES OF AN ACCIDENTS
26.11.2014 Transport of DG by Rail 16
26.11.2014 Transport of DG by Rail 17
26.11.2014 Transport of DG by Rail 18
Measures by the Infrastructure manager
to mitigate consequences of accidents
26.11.2014 Transport of DG by Rail 19
1. Infrabel Internal Emergency Plan (new release 2014)
2. Specific Emergency Plans
(e.g. for Kennedy tunnel and Liefkenshoek Rail Link)
3. Upgrade of Emergency equipment for Kennedytunnel
4. Roadshow RID for Authorities and Emergency services (2014-2015)
5. Application “Fill-In” (train compositions)
6. Specific Emergency Plans for marshalling yards (work in progress)
7. Upgrade of the (Emergency) equipment of marshalling yards
(actions started for Saint-Ghislain, Gent-Zeehaven and
Antwerpen-Noord)
4. MITIGATION OF THE CONSEQUENCES OF AN ACCIDENTS
26.11.2014 Transport of DG by Rail 20
Critical
Medium
critical
Non critical
Legend:
Coefficient for
transport 1
< 5
Coefficient for
transport 2
5 < X < 15
Coefficient for
transport 3
15 < X < 50
Coefficient de
transport 4
> 50
Environmental
coefficient 1
Pas habitation à moins de
100m
Feluy-Zoning
Antw-Oorderen
Antw-Oudendijk
Antw-Petrol
Antwerpen-
Waaslandhaven
Bundel-Zuid
Environmental
coefficient 2
Pas de noyau résidentiel à
moins de 100m
Zeebrugge-
Vorming
Antw-Noord
Environmental
coefficient 3
Pas d’endroits vulnérables
à moins de 200m
Muizen-
Goederen
(Kortrijk-
Goederen)
Environmental
coefficient 4
Endroits vulnérables
à moins de 200m
Saint-Ghislain
(Tessenderlo)
(Kinkempois)
Gent-Zeehaven
(Monceau)
Number of
transports
of DG
Environment
4. MITIGATION OF THE CONSEQUENCES OF AN ACCIDENTS
Marshalling yards : Risk matrix for classification
26.11.2014 Transport of DG by Rail 21
Marshalling
yard
Measures
Critical
Medium critical
Non
Critical
Emergency plans
(work in progress) Specific
(with scenarios)
Specific (with scenarios)
General (without scenario)
Investments
for safety
Extended (*)
Extended (*)
Elementary (*)
(*) Taking into account the needs of the Emergency Services
4. MITIGATION OF THE CONSEQUENCES OF AN ACCIDENTS
Marshalling yards : Approach
bac de rétention
26.11.2014 Transport of DG by Rail 22
Critical
marshalling yards
Medium critical
marshalling yards
Ph
ase 1
Ph
ase 2
Non critical
marshalling yards
chemins d’accès
parking déploiement
clôtures -portiques
éclairage
signalétique
hydrants
manche
à air
bac de rétention mise aux rails
des caténaires à
distance
contrôle d’accès
sirène
éclairage signalétique manche
à air sirène
Surveillance
caméra
chemins d’accès
parking déploiement
éclairage
signalétique
hydrants
manche
à air contrôle d’accès
sirène
clôtures -portiques
mise aux rails
des caténaires à
distance
Surveillance
caméra
4. MITIGATION OF THE CONSEQUENCES OF AN ACCIDENTS
Marshalling yards : Investments for Safety
Learning from Events
26.11.2014 Transport of DG by Rail 23
5. REX OF INCIDENTS
1. Accident investigation
2. Rex meetings with Authorities and other stakeholders
26.11.2014 Transport of DG by Rail 24
QUESTIONS