zWill require caulk joint. Advise in field if top base is projecting too far out from wall, will need to return in
same manner as base stone
if so - unlikely. Oklahoma Capitol Restoration Project
2300 N Lincoln Blvd. Oklahoma City, OK 73105
June 2019 – Monthly Progress Report
MONTHLY OVERVIEW
� Level 1 Rotunda – Terrazzo
in-laid State Seal has been
removed. Level 1 floor has
been cut.
� Visitor Entry – Concrete
foundations are 75%
complete.
� Supreme Court – Decorative
painting is nearing
completion.
� Level 2, 3, 4 Rotunda –
Erection of scaffold is
underway.
� House Level 2, 3, 4, 5 – Move
out complete. Demolition
underway.
REPORT CONTENTS
Cover Letter
Executive Summary
Preconstruction Status
Construction Schedule
Request for Information
Submittal Log
Construction Photos
410 N. Walnut, Suite 105, Oklahoma City, OK 73104 | t 405.254.1050 f 405.254.1055 | www.manhattanconstruction.com
Manhattan Job #
3707
Design/Builder:
Project Owner:
Oklahoma Capitol Restoration
2300 N. Lincoln Blvd. Oklahoma City, OK 73105
June 2019 –
Monthly Progress Report
Cover Letter
Tab 1 Executive Summary
Tab 2 Preconstruction Status
• Document deliverable status
Tab 3 Construction Schedule
• Schedule narrative
• Critical Items
• Schedule Update
Tab 4 Requests for Information (RFIs)
• RFI Summary Log
Tab 5 Submittal Log
• Submittal Package Summary Log
Tab 6 Construction Photos
• Detailed progress photos – current month
EXECUTIVE SUMMARY
SECTION 1
Monthly Progress Report – Oklahoma Capitol Restoration
June 2019
1-1
Monthly Progress Report For
Oklahoma Capitol Restoration
June 2019 On May 31, 2019, the Manhattan Construction team began removal of 14’ terrazzo State Seal in-laid in the level 1 Rotunda floor. Following the removal of the State Seal, a scaffold platform installed tight to the bottom of the level 1 floor was erected to prevent any debris from falling during demolition. Finally, the level 1 structural slab was saw cut and removed. As pictured on Page 1 of this Report, the Historic Rotunda of the State Capitol now opens up to the Ground Level for the first time in history. Manhattan is currently procuring the large bronze State Seal that will be inlaid in the same position at the Ground Level. The beginning of June saw the mass move-out of the House of Representative Offices located in the West Wing at Levels 2, 3, 4, 5, and 6. Next, construction crews began the mass demolition and abatement at Levels 3, 4, 5 and 6. Currently, demolition is 100% complete on level 5 and 4 and working its way downward. The West Wing of Level 2 was recently remodeled and construction in this area is less invasive. New millwork in this area has been delivered. Below is a recap of the major construction & design milestones that are upcoming and completion status:
New Storm Drain Install Begins Achieved July 19, 2019
Move-Out – House of Representative Level 2, 3, 4, 5, 6 Achieved June 2, 2019
Cut Hole in Level 1 Rotunda @ State Seal Achieved June 3, 2019
Structural Steel Erection – Visitor Entry Projected August 11, 2019
Loading Dock North & South Complete Projected August 1, 2019
Ground Level Public Restroom – Final Inspection & Turnover
Projected September 16, 2019
Supreme Court – Final Inspection & Turnover Projected October 23, 2019
Governor Suite – Final Inspection & Turnover Projected November 8, 2019
House Level 2, 3, 4, 6 – Final Inspection & Turnover Projected August 1, 2019
Install 14’ State Seal at Ground Level Projected August 1, 2020
Prime Contract Status The prime contract has been updated with Contract Amendment #2 to include funding for the entirety of the Priority 1 scope. Priority 2 funding bill HB 3168 was passed on May 26, 2016. On February 15, 2017, Contract Amendment #3 was executed to incorporate Priority 2 design & the reallocation of construction sequences to seamlessly integrate Priority 1 & 2 scopes of work into the overall project. The Priority 2 construction budget was submitted on 6/26/18 and Amendment #4 was fully executed on August 28, 2018. Amendment #4 includes all funding to complete the full restoration of the interior of the State Capitol.
EXECUTIVE SUMMARY
SECTION 1
Monthly Progress Report – Oklahoma Capitol Restoration
June 2019
1-2
Design Status The design team has completed & submitted all 100% drawings for all construction phases complete. AE1 has returned the Phase 5.0 100% Construction Documents to OMES/AE1 with comments. Buyout Status June 4, 2019 was bid day for Bid Package 1A consisting of the marble restoration scope for the vast majority of the project. Although, several potential bidders had visited the project prior to bidding and attended the pre-bid conference, Elevated Paver Systems was the single bidder for this scope of work. Manhattan will conduct a meeting with OMES to review the results and make selection related to bid alternates. Construction Progress & Schedule Status Priority 1 Scope The Priority 1 scope of work was completed as of January 2019. Priority 2 Scope At the Loading Dock, HVAC and lighting installation is in progress. The new overhead door will be installed beginning July 15, 2019. Progress has been steady at the new Northeast Egress stair. Manhattan has procured and released for fabrication the final metal handrails to be installed in late Summer. Final paint has also begun in this area. In the Northeast Doghouse, all structural steel infills are complete. The Level 6 new slab has been placed. The Level 6 stairway to the elevator machine room will be delivered on 7/18/19. The new elevator cab is scheduled to begin installation in September. Finally, at the Governor’s Suite, installation of cabinets and granite countertops is nearing completion. Erection of the hydro-elevator is underway. The carpet in this area will be delivered in early July. Request for Information (RFI’s) Current RFI Summary Log attached in Tab 4. Submittals Current Submittal Log attached in Tab 5. Cost Events & Authorization Requests There are currently no open proposals for the project.
Prepared by: Lucy Lambert, Project Manager
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration
June 2019
2-1
Document Deliverables:
• All 100% Design deliverables have been submitted to the State.
• ASI 031 detailing changes to the Treasurer’s Office has been issued.
• 3D sketches of requested changes to the Court of Criminal Appeals have been distributed.
• Low Roof documents are pending.
Design Status Report:
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
2-2
HISTORIC PRESERVATION
Historic Preservation Consultant Stephen Kelley will continue to conduct pre-demo and post-
demo inspections as required for the Historic Preservation of the State Capitol. Mr. Kelley is
scheduled to be on site July 29, 2019 to perform Post Demo inspections on the House Floors 2
thru 6, The State Treasurer’s Suite, The Lt. Governor’s Office, The Governor’s Conference
Room, and the Supreme Court hallways.
End of Report
CONSTRUCTION SCHEDULE
SECTION 3
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
3-1
Intermediate Construction Milestones in 2019
Schedule Status: The decorative paint scope of work is nearly complete in the Supreme Court. The large scaffold will soon be dismantled. Plumbing rough-in in the restroom in this area is complete. The elevated floor slab in this area is ready to be poured pending final decision making on the behalf of the House of Representatives. Construction of the Level 4 North Senate wing is wrapping up after the move out of the Health Nut in March. Carpet installation in this area is complete. Doors will be installed in early July. Manhattan in-house pre-inspection process is underway. The Senate will move into these offices in July. Finally, at the Court of Criminal Appeals, the design team has submitted 3D renderings of proposed floor plan options for the Senate review. Critical Schedule Events: Nearly all critical schedule events correlate with material procurement items. Below is a tracking log of all major material delivery items currently on the schedule:
Item Description Estimated Installation Date
Estimated Delivery Date
Actual Delivery Date
Structural Steel - Visitor’s Entry 7/15/19 7/15/19 7/18/19
Limestone – Visitor’s Entry 9/17/19 9/17/19
Millwork – House of Reps – West Wing 9/15/19 9/15/19
NE Doghouse – New Elevator 9/23/19 9/23/19
Historic Light Fixtures – Supreme Court 10/1/19 10/1/19
House of Representative Level 4 - Millwork 10/1/19 7/15/19
Exterior Landscape Granite – Visitor’s Entry
1/6/2020 1/6/2020
Milestone Description Baseline Schedule
Last Month’s Update
Current Month Update
Gain or Loss this Month
NE Stairs Complete 12/1/18 8/15/19 10/1/19 +47 Demolition – House Level 2, 3, 4, 5 6/17/19 6/17/19 6/17/19 0
Loading Dock – Turnover/Move-In 7/15/19 7/15/19 8/14/19 +27
Supreme Court - Turnover/Move-In 9/28/19 9/28/19 10/23/19 +25
West Security Entrance Shut Down 8/2/19 8/2/19 First Public Restroom Re-Opens 9/6/19 9/6/19
Governor – Turnover/Move-In 11/8/19 11/8/19 House of Representatives Level 3, 4, 5 – Turnover/Move-In
1/15/2020 1/15/2020
Activity ID Activity Name Orig Dur
RemDur
Start Finish
DesignDesign507 507 04-Feb-20 02-Feb-22
Master PlanMaster Plan507 507 04-Feb-20 02-Feb-22
Master Plan MilestonesMaster Plan Milestones507 507 04-Feb-20 02-Feb-22
Legislative Session MilestonesLegislative Session Milestones507 507 04-Feb-20 02-Feb-22
M-M01-1025 2020 Session Starts (Construction Ends) 0 0 04-Feb-20
M-M01-1030 2020 Session Ends (Construction Starts) 0 0 02-Jun-20
M-M01-1035 2021 Session Starts (Construction Ends) 0 0 02-Feb-21
M-M01-1040 2021 Session Ends (Construction Starts) 0 0 02-Jun-21
M-M01-1045 2022 Session Begins (Construction Ends) 0 0 02-Feb-22
SequencesSequences996 365 24-Oct-16 A 24-Nov-20
Sequence 1Sequence 1862 192 24-Oct-16 A 23-Mar-20
Material ProcurementMaterial Procurement826 187 24-Oct-16 A 16-Mar-20
Procurement Phase SummariesProcurement Phase Summaries519 271 24-Oct-16 A 16-Mar-20
S-S01-1070 Procurement - Sequence 1 519 271 24-Oct-16 A 16-Mar-20
Public CorridorPublic Corridor240 187 15-Mar-19 A 16-Mar-20
P-S01-1640 Fab & Deliver - H8 Light Fixture 240 187 15-Mar-19 A 16-Mar-20
P-S01-1680 Fab & Deliver - H3 Light Fixture 120 67 15-Mar-19 A 24-Sep-19
ConstructionConstruction5 5 17-Mar-20 23-Mar-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 23-Mar-20 23-Mar-20
M-S01-1090 Sequence 1 New Construction Ends 0 0 23-Mar-20
Public CorridorPublic Corridor5 5 17-Mar-20 23-Mar-20
C-S01-4360 Install Historic Lights 5 5 17-Mar-20 23-Mar-20
Sequence 2Sequence 2444 95 26-Jan-18 A 01-Nov-19
Material ProcurementMaterial Procurement40 17 29-Apr-19 A 15-Jul-19
Loading Dock Phase 1Loading Dock Phase 140 17 29-Apr-19 A 15-Jul-19
P-S02-1405 Fab & Deliver - OVHD Door 40 17 29-Apr-19 A 15-Jul-19
ConstructionConstruction444 95 26-Jan-18 A 01-Nov-19
Schedule Driven MilestonesSchedule Driven Milestones25 25 19-Sep-19 24-Oct-19
M-S02-1025 Interim Substantial Completion - Public Restrooms 0 0 19-Sep-19
M-S02-1027 Interim Substantial Completion - West Entry Vestibule 0 0 24-Oct-19
M-S02-1015 Sequence 2 New Construction Ends 0 0 24-Oct-19
Construction Phase SummariesConstruction Phase Summaries360 127 26-Jan-18 A 24-Oct-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
2020 Session Starts (Construction Ends)
2020 Session Ends (Construction Starts)
2021 Session Starts (Construction Ends)
2021 Session Ends (Construction Starts)
2022 Session Begins (Construc
Procurement - Sequence 1
Fab & Deliver - H8 Light Fixture
Fab & Deliver - H3 Light Fixture
Sequence 1 New Construction Ends
Install Historic Lights
Fab & Deliver - OVHD Door
Interim Substantial Completion - Public Restrooms
Interim Substantial Completion - West Entry Vestibule
Sequence 2 New Construction Ends
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 1 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
S-S02-1000 Construction - Sequence 2 360 127 26-Jan-18 A 24-Oct-19
Food Service - KitchenFood Service - Kitchen10 10 20-Jun-19 03-Jul-19
C-S02-8509 Install Permanent Guardrail / Balustrades - Kitchen Exhaust Bldg 10 10 20-Jun-19 03-Jul-19
Public RestroomsPublic Restrooms67 64 20-Jun-19 19-Sep-19
C-S02-8449 Final Paint 5 5 20-Jun-19 26-Jun-19
C-S02-2030 Install Marble Wall Tile 8 8 20-Jun-19 01-Jul-19
C-S02-2031 Install Tile Floors 8 8 02-Jul-19 12-Jul-19
C-S02-2033 Grind/Polish Marble Floors 3 3 15-Jul-19 17-Jul-19
C-S02-2034 Install Counter Tops, Vanity's & Mirrors 4 4 18-Jul-19 23-Jul-19
C-S02-2036 Install Toilet Partitions 5 5 13-Aug-19 19-Aug-19
C-S02-2039 Install Doors and Hardware 1 1 20-Aug-19 20-Aug-19
C-S02-2037 Install Plumbing Fixtures 10 10 20-Aug-19 03-Sep-19
C-S02-2040 Install Drinking Fountains 3 3 04-Sep-19 06-Sep-19
C-S02-2042 Final Clean 2 2 09-Sep-19 10-Sep-19
C-S02-2043 Complete MCC / FSB Punch List 5 5 11-Sep-19 17-Sep-19
C-S02-2045 Complete AE1 / Owner Punch List 10 7 11-Sep-19 19-Sep-19
C-S02-2046 100% Fire Marshal Inspection 0 0 19-Sep-19
Loading Dock Phase 1Loading Dock Phase 142 7 08-Apr-19 A 28-Jun-19
C-S02-2108 Install New Fire Pump 10 1 08-Apr-19 A 20-Jun-19
C-S02-2120 Install Exposed Ductwork 5 7 15-May-19 A 28-Jun-19
C-S02-2110 Demo Old Fire Pump and Assoc Systems 4 3 19-Jun-19 A 24-Jun-19
C-S02-2115 50% Fire Marshal Inspection 0 0 20-Jun-19
Loading Dock Phase 2Loading Dock Phase 236 36 25-Jun-19 14-Aug-19
C-S02-8499 Final Paint 5 5 25-Jun-19 01-Jul-19
C-S02-2135 Install FRP Walls 2 2 02-Jul-19 03-Jul-19
C-S02-2123 Trim Out MEP 6 6 02-Jul-19 10-Jul-19
C-S02-2136 Install Plumbing Fixtures 2 2 05-Jul-19 08-Jul-19
C-S02-2133 Install OH Door 3 3 15-Jul-19 17-Jul-19
C-S02-8475 Complete MCC / FSB Punchlist 5 5 18-Jul-19 24-Jul-19
C-S02-8474 100% Fire Marshal Inspection 0 0 24-Jul-19
C-S02-8476 Complete AE1 / Owner Punchlist 5 5 25-Jul-19 31-Jul-19
C-S02-2138 Owner Move In 1 1 01-Aug-19 01-Aug-19
C-S02-8473 Set Up Security Systems / Equipment 10 10 01-Aug-19 14-Aug-19
C-S02-2130 Loading Dock Opens / Close West Public Entrance 0 0 14-Aug-19*
West Entry VestibuleWest Entry Vestibule65 65 02-Aug-19 01-Nov-19
C-S02-2139 Make Safe 3 4 02-Aug-19 07-Aug-19
C-S02-2141 Selective Demo at Ceiling for MEP Raceways 5 5 08-Aug-19 14-Aug-19
C-S02-2145 Trench & Install UG Electrical at Security Desk 3 3 15-Aug-19 19-Aug-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Construction - Sequence 2
Install Permanent Guardrail / Balustrades - Kitchen Exhaust Bldg
Final Paint
Install Marble Wall Tile
Install Tile Floors
Grind/Polish Marble Floors
Install Counter Tops, Vanity's & Mirrors
Install Toilet Partitions
Install Doors and Hardware
Install Plumbing Fixtures
Install Drinking Fountains
Final Clean
Complete MCC / FSB Punch List
Complete AE1 / Owner Punch List
100% Fire Marshal Inspection
Install New Fire Pump
Install Exposed Ductwork
Demo Old Fire Pump and Assoc Systems
50% Fire Marshal Inspection
Final Paint
Install FRP Walls
Trim Out MEP
Install Plumbing Fixtures
Install OH Door
Complete MCC / FSB Punchlist
100% Fire Marshal Inspection
Complete AE1 / Owner Punchlist
Owner Move In
Set Up Security Systems / Equipment
Loading Dock Opens / Close West Public Entrance
Make Safe
Selective Demo at Ceiling for MEP Raceways
Trench & Install UG Electrical at Security Desk
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 2 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S02-2147 RI Overhead 5 5 15-Aug-19 21-Aug-19
C-S02-2144 Demo Existing Terrazzo Floors 10 10 15-Aug-19 28-Aug-19
C-S02-2150 Pour Back Trench 2 3 20-Aug-19 22-Aug-19
C-S02-8504 50% Fire Marshal Inspection 0 0 21-Aug-19
C-S02-2151 Restore Existing Base 3 3 23-Aug-19 27-Aug-19
C-S02-2148 Patch & Paint Ceilings & Walls 5 5 23-Aug-19 29-Aug-19
C-S02-2153 Install Marble Floors 25 24 30-Aug-19 03-Oct-19
C-S02-2154 Install Security Desk / Equipment 10 10 04-Oct-19 17-Oct-19
C-S02-8505 Complete MCC / FSB Punchlist 5 5 18-Oct-19 24-Oct-19
C-S02-8506 100% Fire Marshal Inspection 0 0 24-Oct-19
C-S02-8507 Complete AE1 / Owner Punchlist 5 5 25-Oct-19 31-Oct-19
C-S02-8508 Owner Move In 1 1 01-Nov-19 01-Nov-19
Sequence 3Sequence 3349 252 04-Feb-19 A 16-Jun-20
Material ProcurementMaterial Procurement225 157 15-Mar-19 A 03-Feb-20
OAU & Heat PumpsOAU & Heat Pumps40 15 15-May-19 A 11-Jul-19
P-S03-1285 Fab & Deliver - Heat Pumps 40 15 15-May-19 A 11-Jul-19
SteelSteel40 17 12-Apr-19 A 15-Jul-19
P-S03-1255 Fab & Deliver - Structural Steel 40 17 12-Apr-19 A 15-Jul-19
Historic Light FixturesHistoric Light Fixtures225 157 15-Mar-19 A 03-Feb-20
P-S03-1300 Fab & Deliver - Historic Light Fixtures 225 157 15-Mar-19 A 03-Feb-20
Doors / HardwareDoors / Hardware70 70 20-Jun-19 27-Sep-19
P-S03-1080 MCC Receive / Review Submittal - Doors & Hardware 5 5 20-Jun-19 26-Jun-19
P-S03-1160 AE2 (FSB) Receive / Review Submittal - Doors & Hardware 10 10 27-Jun-19 11-Jul-19
P-S03-1240 AE1 (Mass) Receive / Review Submittal - Doors & Hardware 15 15 12-Jul-19 01-Aug-19
P-S03-1320 Fab & Deliver - Doors & Hardware 40 40 02-Aug-19 27-Sep-19
GlazingGlazing110 110 20-Jun-19 22-Nov-19
P-S03-1035 MCC Receive / Review Submittal - Exterior Glazing 5 5 20-Jun-19 26-Jun-19
P-S03-1115 AE2 (FSB) Receive / Review Submittal - Exterior Glazing 10 10 27-Jun-19 11-Jul-19
P-S03-1195 AE1 (Mass) Receive / Review Submittal - Exterior Glazing 15 15 12-Jul-19 01-Aug-19
P-S03-1275 Fab & Deliver - Exterior Glazing 80 80 02-Aug-19 22-Nov-19
LandscapeLandscape50 50 03-Sep-19 11-Nov-19
P-S03-1020 MCC Receive / Review Submittal - Landscaping 5 5 03-Sep-19* 09-Sep-19
P-S03-1100 AE2 (FSB) Receive / Review Submittal - Landscaping 10 10 10-Sep-19 23-Sep-19
P-S03-1180 AE1 (Mass) Receive / Review Submittal - Landscaping 15 15 24-Sep-19 14-Oct-19
P-S03-1260 Fab & Deliver - Landscaping 20 20 15-Oct-19 11-Nov-19
PaversPavers90 90 20-Jun-19 25-Oct-19
P-S03-1025 MCC Receive / Review Submittal - Pavers 5 5 20-Jun-19 26-Jun-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
RI Overhead
Demo Existing Terrazzo Floors
Pour Back Trench
50% Fire Marshal Inspection
Restore Existing Base
Patch & Paint Ceilings & Walls
Install Marble Floors
Install Security Desk / Equipment
Complete MCC / FSB Punchlist
100% Fire Marshal Inspection
Complete AE1 / Owner Punchlist
Owner Move In
Fab & Deliver - Heat Pumps
Fab & Deliver - Structural Steel
Fab & Deliver - Historic Light Fixtures
MCC Receive / Review Submittal - Doors & Hardware
AE2 (FSB) Receive / Review Submittal - Doors & Hardware
AE1 (Mass) Receive / Review Submittal - Doors & Hardware
Fab & Deliver - Doors & Hardware
MCC Receive / Review Submittal - Exterior Glazing
AE2 (FSB) Receive / Review Submittal - Exterior Glazing
AE1 (Mass) Receive / Review Submittal - Exterior Glazing
Fab & Deliver - Exterior Glazing
MCC Receive / Review Submittal - Landscaping
AE2 (FSB) Receive / Review Submittal - Landscaping
AE1 (Mass) Receive / Review Submittal - Landscaping
Fab & Deliver - Landscaping
MCC Receive / Review Submittal - Pavers
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 3 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-S03-1105 AE2 (FSB) Receive / Review Submittal - Pavers 10 10 27-Jun-19 11-Jul-19
P-S03-1185 AE1 (Mass) Receive / Review Submittal - Pavers 15 15 12-Jul-19 01-Aug-19
P-S03-1265 Fab & Deliver - Pavers 60 60 02-Aug-19 25-Oct-19
RailingRailing110 110 20-Jun-19 22-Nov-19
P-S03-1030 MCC Receive / Review Submittal - Railings 5 5 20-Jun-19 26-Jun-19
P-S03-1110 AE2 (FSB) Receive / Review Submittal - Railings 10 10 27-Jun-19 11-Jul-19
P-S03-1190 AE1 (Mass) Receive / Review Submittal - Railings 15 15 12-Jul-19 01-Aug-19
P-S03-1270 Fab & Deliver - Railings 80 80 02-Aug-19 22-Nov-19
RoofingRoofing57 38 11-Jun-19 A 13-Aug-19
P-S03-1120 AE2 (FSB) Receive / Review Submittal - Roofing 10 3 11-Jun-19 A 24-Jun-19
P-S03-1200 AE1 (Mass) Receive / Review Submittal - Roofing 15 15 25-Jun-19 16-Jul-19
P-S03-1280 Fab & Deliver - Roofing 20 20 17-Jul-19 13-Aug-19
LimestoneLimestone63 44 19-Jun-19 A 21-Aug-19
P-S03-1145 AE2 (FSB) Receive / Review Submittal - Limestone 10 9 19-Jun-19 A 02-Jul-19
P-S03-1225 AE1 (Mass) Receive / Review Submittal - Limestone 15 15 03-Jul-19 24-Jul-19
P-S03-1305 Fab & Deliver - Limestone 20 20 25-Jul-19 21-Aug-19
Waterproofing / SubstrateWaterproofing / Substrate20 1 26-Mar-19 A 20-Jun-19
P-S03-1310 Fab & Deliver - Waterproofing 20 1 26-Mar-19 A 20-Jun-19
Snow MeltSnow Melt60 13 15-Apr-19 A 09-Jul-19
P-S03-1315 Fab & Deliver - Snow Melt System 60 13 15-Apr-19 A 09-Jul-19
NE Dog HouseNE Dog House50 50 23-Jul-19 01-Oct-19
P-S03-1362 MCC Receive / Review Submittal - Doors & Hardware 5 5 23-Jul-19 29-Jul-19
P-S03-1363 AE2(FSB) Receive / Review Submittal - Doors & Hardware 10 10 30-Jul-19 12-Aug-19
P-S03-1365 Fab & Deliver - Doors & Hardware 35 35 13-Aug-19 01-Oct-19
NE Dog House (Elevator)NE Dog House (Elevator)100 65 01-May-19 A 20-Sep-19
P-S03-1369 Fab & Deliver - Elevator 100 65 01-May-19 A 20-Sep-19
P-S03-1378 MCC Receive / Review Submittal - Bus Duct 5 5 20-Jun-19 26-Jun-19
P-S03-1379 AE2(FSB) Receive / Review Submittal - Bus Duct 10 10 27-Jun-19 11-Jul-19
P-S03-1381 Fab & Deliver - Bus Duct 7 7 12-Jul-19 22-Jul-19
ConstructionConstruction349 252 04-Feb-19 A 16-Jun-20
Schedule Driven MilestonesSchedule Driven Milestones92 92 22-Jan-20 01-Jun-20
M-S03-1002 Interim Substantial Completion - NE Dog House 0 0 22-Jan-20
M-S03-1000 Sequence 3 New Construction Ends 0 0 01-Jun-20
M-S03-1001 Interim Substantial Completion - Visitors Entrance 0 0 01-Jun-20*
Construction Phase SummariesConstruction Phase Summaries481 348 04-Feb-19 A 01-Jun-20
S-S03-1000 Construction - Sequence 3 481 348 04-Feb-19 A 01-Jun-20
Visitors Entrance - Foundation & StructureVisitors Entrance - Foundation & Structure163 140 06-Jun-19 A 09-Jan-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
AE2 (FSB) Receive / Review Submittal - Pavers
AE1 (Mass) Receive / Review Submittal - Pavers
Fab & Deliver - Pavers
MCC Receive / Review Submittal - Railings
AE2 (FSB) Receive / Review Submittal - Railings
AE1 (Mass) Receive / Review Submittal - Railings
Fab & Deliver - Railings
AE2 (FSB) Receive / Review Submittal - Roofing
AE1 (Mass) Receive / Review Submittal - Roofing
Fab & Deliver - Roofing
AE2 (FSB) Receive / Review Submittal - Limestone
AE1 (Mass) Receive / Review Submittal - Limestone
Fab & Deliver - Limestone
Fab & Deliver - Waterproofing
Fab & Deliver - Snow Melt System
MCC Receive / Review Submittal - Doors & Hardware
AE2(FSB) Receive / Review Submittal - Doors & Hardware
Fab & Deliver - Doors & Hardware
Fab & Deliver - Elevator
MCC Receive / Review Submittal - Bus Duct
AE2(FSB) Receive / Review Submittal - Bus Duct
Fab & Deliver - Bus Duct
Interim Substantial Completion - NE Dog House
Sequence 3 New Construction Ends
Interim Substantial Completion - Visitors Entrance
Construction - Sequence 3
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 4 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S03-1055 FRP Structural Retaining Wall Footing 15 5 06-Jun-19 A 26-Jun-19
C-S03-8523 FRP Structural Retaining Walls 10 10 27-Jun-19 11-Jul-19
C-S03-1065 Install UG MEP (Inside New Building) 15 15 12-Jul-19 01-Aug-19
C-S03-8543 Install UG MEP (Outside New Building) 8 8 26-Jul-19 06-Aug-19
C-S03-8530 Waterproofing Structural Retaining Walls 5 5 12-Jul-19 18-Jul-19
C-S03-8531 Subsurface Drainage Structural Retaining Walls 2 2 19-Jul-19 22-Jul-19
C-S03-8533 Refeed Existing West Storm Drain 5 5 23-Jul-19 29-Jul-19
C-S03-8532 Backfill Structural Retaining Walls 5 5 30-Jul-19 05-Aug-19
C-S03-8527 Excavate Footings @ Bench Seating 3 3 07-Aug-19 09-Aug-19
C-S03-8528 FRP Footings @ Bench Seating 3 3 12-Aug-19 14-Aug-19
C-S03-8529 FRP Bench Seating 15 15 15-Aug-19 05-Sep-19
C-S03-8540 Subsurface Drainage @ Bench Seating 2 2 06-Sep-19 09-Sep-19
C-S03-8542 Backfill @ Bench Seating 5 5 10-Sep-19 16-Sep-19
C-S03-1075 Install from Existing Manhole to 7 & Tie Into Manhole 8 50 90 15-Jul-19 18-Nov-19
C-S03-1050 Install Manhole 8 (Matherly) 10 10 02-Aug-19 15-Aug-19
C-S03-8524 Excavate Footings @ Remaining Walls & Steps 10 10 17-Sep-19 30-Sep-19
C-S03-8525 FRP Footings @ Remaining Walls & Steps 10 10 23-Sep-19 04-Oct-19
C-S03-8526 FRP Remaining Walls & Steps 20 20 30-Sep-19 25-Oct-19
C-S03-8537 Waterproofing @ Remaining Walls & Steps 15 15 09-Oct-19 29-Oct-19
C-S03-8538 Subsurface Drainage @ Remaining Walls & Steps 10 10 18-Oct-19 31-Oct-19
C-S03-8539 Backfill @ Remaining Walls & Steps 15 15 21-Oct-19 08-Nov-19
C-S03-8545 FR @ Ramps and Stairs 15 15 11-Nov-19 03-Dec-19
C-S03-1245 Install Snow Melt System 40 20 04-Dec-19 02-Jan-20
C-S03-8546 Place Concrete @ Ramps and Stairs 5 5 03-Jan-20 09-Jan-20
C-S03-1105 FRP Slab on Grade 5 5 16-Aug-19 22-Aug-19
C-S03-1095 Erect Structural Steel 20 15 23-Aug-19 13-Sep-19
C-S03-1115 Install Roof Framing 15 15 09-Sep-19 27-Sep-19
C-S03-1120 Install Exterior Framing & Sheathing 20 15 16-Sep-19 04-Oct-19
C-S03-1125 Install Roof Drainage System 5 5 07-Oct-19 11-Oct-19
C-S03-1130 Install Roof Curbs for Slope Glazing 10 10 07-Oct-19 18-Oct-19
C-S03-1155 Install Slope Glazing 10 10 21-Oct-19 01-Nov-19
C-S03-1160 Install Roof 20 20 21-Oct-19 15-Nov-19
C-S03-1165 Dry In 0 0 04-Nov-19
C-S03-1190 50% Fire Marshal Inspections 0 0 15-Nov-19
Visitors Entrance - Interior FinishesVisitors Entrance - Interior Finishes143 143 04-Nov-19 27-May-20
C-S03-1170 In Wall Rough In 5 5 04-Nov-19 08-Nov-19
C-S03-1180 Install Heat Pumps 10 10 04-Nov-19 15-Nov-19
C-S03-1185 Install OVHD MEP 25 25 04-Nov-19 10-Dec-19
C-S03-1195 Complete Mech Room 15 15 18-Nov-19 10-Dec-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
FRP Structural Retaining Wall Footing
FRP Structural Retaining Walls
Install UG MEP (Inside New Building)
Install UG MEP (Outside New Building)
Waterproofing Structural Retaining Walls
Subsurface Drainage Structural Retaining Walls
Refeed Existing West Storm Drain
Backfill Structural Retaining Walls
Excavate Footings @ Bench Seating
FRP Footings @ Bench Seating
FRP Bench Seating
Subsurface Drainage @ Bench Seating
Backfill @ Bench Seating
Install from Existing Manhole to 7 & Tie Into Manhole 8
Install Manhole 8 (Matherly)
Excavate Footings @ Remaining Walls & Steps
FRP Footings @ Remaining Walls & Steps
FRP Remaining Walls & Steps
Waterproofing @ Remaining Walls & Steps
Subsurface Drainage @ Remaining Walls & Steps
Backfill @ Remaining Walls & Steps
FR @ Ramps and Stairs
Install Snow Melt System
Place Concrete @ Ramps and Stairs
FRP Slab on Grade
Erect Structural Steel
Install Roof Framing
Install Exterior Framing & Sheathing
Install Roof Drainage System
Install Roof Curbs for Slope Glazing
Install Slope Glazing
Install Roof
Dry In
50% Fire Marshal Inspections
In Wall Rough In
Install Heat Pumps
Install OVHD MEP
Complete Mech Room
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 5 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S03-1210 80% Fire Marshal Inspections 0 0 10-Dec-19
C-S03-1205 Conditioned Air Available 0 0 11-Dec-19
C-S03-1220 Install Sheetrock 7 7 11-Dec-19 19-Dec-19
C-S03-1225 Tape Bed Paint 15 15 20-Dec-19 13-Jan-20
C-S03-1230 Install Limestone Columns 15 15 30-Dec-19 20-Jan-20
C-S03-1240 Install Mud Bed for Marble Floors 15 15 21-Jan-20 10-Feb-20
C-S03-1235 Trim Out MEP 3 3 04-Feb-20 06-Feb-20
C-S03-1255 Install Marble Floors 40 40 04-Feb-20 30-Mar-20
C-S03-1270 Install Granite Base 5 5 31-Mar-20 06-Apr-20
C-S03-1275 Grind / Polish Floors 15 15 07-Apr-20 27-Apr-20
C-S03-1280 Install Doors & Hardware 10 10 28-Apr-20 11-May-20
C-S03-1290 Complete MCC/ FSB Punchlist 5 5 12-May-20 18-May-20
C-S03-1295 Final Clean 1 1 19-May-20 19-May-20
C-S03-1300 Complete AE1 / Owner Punchlist 5 5 20-May-20 27-May-20
Visitors Entrance - Exterior FinishesVisitors Entrance - Exterior Finishes177 177 07-Oct-19 16-Jun-20
C-S03-1140 Install Exterior Limestone 45 45 07-Oct-19 10-Dec-19
C-S03-1175 Install Vestibule Steel Structure 10 10 04-Nov-19 15-Nov-19
C-S03-1135 Install Landscaping 30 30 19-Nov-19 03-Jan-20
C-S03-1215 Install Vestibule Glazing System 30 30 11-Dec-19 23-Jan-20
C-S03-1250 Install Exterior Pavers 45 45 10-Jan-20 12-Mar-20
C-S03-1265 Install Railings 30 30 09-Mar-20 17-Apr-20
C-S03-1260 Install Exterior Lighting 5 5 13-Mar-20 19-Mar-20
C-S03-1285 Rough Clean Exterior 10 10 20-Apr-20 01-May-20
C-S03-1305 Q/C Testing 10 10 04-May-20 15-May-20
C-S03-1310 Complete MCC/ FSB Punchlist 10 10 18-May-20 01-Jun-20
C-S03-1315 100% Fire Marshal Inspections 0 0 01-Jun-20
C-S03-1320 Final Clean 1 1 02-Jun-20 02-Jun-20
C-S03-1325 Complete AE1 / Owner Punchlist 10 10 03-Jun-20 16-Jun-20
NE Dog HouseNE Dog House98 94 14-Jun-19 A 31-Oct-19
C-S03-1021 Install Vertical IT / Low Voltage Pathways - G through 5 5 1 14-Jun-19 A 20-Jun-19
C-S03-1041 Install Door Frames - G through 5 5 1 14-Jun-19 A 20-Jun-19
C-S03-1033 Install Drinking Fountains - G through 5 5 5 20-Jun-19 26-Jun-19
C-S03-1034 Install Fire Risers - G through 5 7 7 20-Jun-19 28-Jun-19
C-S03-1022 Hang, Tape & Finish - G through 5 5 5 21-Jun-19 27-Jun-19
C-S03-1023 Prime & 1st Coat - G through 5 5 5 28-Jun-19 05-Jul-19
C-S03-1036 Install Hose Cabinets - G through 5 5 5 01-Jul-19 08-Jul-19
C-S03-1024 Surface Mount All Electrical / MEP - G through 5 10 10 08-Jul-19 19-Jul-19
C-S03-1028 Final Paint - G through 5 5 5 22-Jul-19 26-Jul-19
C-S03-1018 Install Bus Duct G through 5 21 21 23-Jul-19 20-Aug-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
80% Fire Marshal Inspections
Conditioned Air Available
Install Sheetrock
Tape Bed Paint
Install Limestone Columns
Install Mud Bed for Marble Floors
Trim Out MEP
Install Marble Floors
Install Granite Base
Grind / Polish Floors
Install Doors & Hardware
Complete MCC/ FSB Punchlist
Final Clean
Complete AE1 / Owner Punchlist
Install Exterior Limestone
Install Vestibule Steel Structure
Install Landscaping
Install Vestibule Glazing System
Install Exterior Pavers
Install Railings
Install Exterior Lighting
Rough Clean Exterior
Q/C Testing
Complete MCC/ FSB Punchlist
100% Fire Marshal Inspections
Final Clean
Complete AE1 / Owner Punchlist
Install Vertical IT / Low Voltage Pathways - G through 5
Install Door Frames - G through 5
Install Drinking Fountains - G through 5
Install Fire Risers - G through 5
Hang, Tape & Finish - G through 5
Prime & 1st Coat - G through 5
Install Hose Cabinets - G through 5
Surface Mount All Electrical / MEP - G through 5
Final Paint - G through 5
Install Bus Duct G through 5
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 6 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S03-1044 OMES Install LV Cabling 10 10 21-Aug-19 04-Sep-19
C-S03-1026 Install Sub Panels G through 5 36 36 21-Aug-19 10-Oct-19
C-S03-1027 Install Transformer G through 5 36 36 21-Aug-19 10-Oct-19
C-S03-1029 Energize New Electric G through 5 2 2 11-Oct-19 14-Oct-19
C-S03-1031 Install Stone Hard Flooring - G through 5 5 5 11-Oct-19 17-Oct-19
C-S03-1032 De-Energize & Remove Temp Power G through 5 3 3 15-Oct-19 17-Oct-19
C-S03-1037 Complete MCC / FSB Punchlist G through 5 5 5 18-Oct-19 24-Oct-19
C-S03-1042 Install Doors - G through 5 5 5 18-Oct-19 24-Oct-19
C-S03-1039 Complete AE1 / Owner Punchlist G through 5 5 5 25-Oct-19 31-Oct-19
C-S03-1046 OMES Activate Security and Card Access 5 5 25-Oct-19 31-Oct-19
NE Dog House (Elevator)NE Dog House (Elevator)149 149 20-Jun-19 22-Jan-20
C-S03-8506 Install Sump Pit Piping 2 2 20-Jun-19 21-Jun-19
C-S03-8508 Install Elevator Cab & Motor 50 50 23-Sep-19 03-Dec-19
C-S03-8509 Install Hoistway Lighting 2 2 04-Dec-19 05-Dec-19
C-S03-8511 Install Hoistway Smoke/Heat Detection 2 2 04-Dec-19 05-Dec-19
C-S03-8510 Install Hoistway Fire Suppression 3 3 04-Dec-19 06-Dec-19
C-S03-8512 Install Elevator Door Fronts 25 25 09-Dec-19 14-Jan-20
C-S03-8513 Install Elevator Cab Finishes 20 20 16-Dec-19 14-Jan-20
C-S03-8514 Elevator Test & Balance 5 5 15-Jan-20 21-Jan-20
C-S03-8515 DOL Final Inspection 1 1 22-Jan-20 22-Jan-20
C-S03-8516 100% Fire Marshal Inspections 0 0 22-Jan-20
NE Dog House (Structure)NE Dog House (Structure)16 16 20-Jun-19 12-Jul-19
C-S03-2023 Stair Submittal to MCC 1 1 20-Jun-19 20-Jun-19
C-S03-2024 Release to Sub 1 1 21-Jun-19 21-Jun-19
C-S03-2025 Fabricate Stairs 10 10 24-Jun-19 08-Jul-19
C-S03-2018 Install Steel / Platform & Grating - 6th Floor 2 2 20-Jun-19 21-Jun-19
C-S03-2019 Install Steel Stringers - 6th Floor 3 3 24-Jun-19 26-Jun-19
C-S03-2022 FRP Concrete - 6th Floor 1 1 27-Jun-19 27-Jun-19
C-S03-2020 Install Threads - 6th Floor 1 1 09-Jul-19 09-Jul-19
C-S03-2021 Install Railings - 6th Floor 3 3 10-Jul-19 12-Jul-19
Sequence 4Sequence 4285 340 21-Dec-19 24-Nov-20
ConstructionConstruction285 340 21-Dec-19 24-Nov-20
Construction Phase SummariesConstruction Phase Summaries285 340 21-Dec-19 24-Nov-20
S-S04-1000 Construction - Sequence 4 285 340 21-Dec-19 24-Nov-20
CoreCore881 583 22-Dec-17 A 05-Oct-21
Attic SpaceAttic Space700 545 20-Jun-19 15-Dec-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
OMES Install LV Cabling
Install Sub Panels G through 5
Install Transformer G through 5
Energize New Electric G through 5
Install Stone Hard Flooring - G through 5
De-Energize & Remove Temp Power G through 5
Complete MCC / FSB Punchlist G through 5
Install Doors - G through 5
Complete AE1 / Owner Punchlist G through 5
OMES Activate Security and Card Access
Install Sump Pit Piping
Install Elevator Cab & Motor
Install Hoistway Lighting
Install Hoistway Smoke/Heat Detection
Install Hoistway Fire Suppression
Install Elevator Door Fronts
Install Elevator Cab Finishes
Elevator Test & Balance
DOL Final Inspection
100% Fire Marshal Inspections
Stair Submittal to MCC
Release to Sub
Fabricate Stairs
Install Steel / Platform & Grating - 6th Floor
Install Steel Stringers - 6th Floor
FRP Concrete - 6th Floor
Install Threads - 6th Floor
Install Railings - 6th Floor
Construction - Sequence 4
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 7 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
ConstructionConstruction700 545 20-Jun-19 15-Dec-20
Construction Phase SummariesConstruction Phase Summaries700 545 20-Jun-19 15-Dec-20
S-C02-1000 Construction - Attic Space 700 545 20-Jun-19 15-Dec-20
North East StairsNorth East Stairs508 128 22-Dec-17 A 20-Dec-19
Material ProcurementMaterial Procurement60 110 20-Jun-19 22-Nov-19
HandrailsHandrails60 110 20-Jun-19 22-Nov-19
P-C03-1120 MCC Receive / Review Shop Drawings - Handrail 5 5 20-Jun-19 26-Jun-19
P-C03-1125 AE2 (FSB) Receive / Review Submittal - Handrail 10 10 27-Jun-19 11-Jul-19
P-C03-1130 AE1 (Mass) Receive / Review Submittal - Handrail 15 15 12-Jul-19 01-Aug-19
P-C03-1015 Fab & Deliver - Handrail 30 80 02-Aug-19 22-Nov-19
ConstructionConstruction508 128 22-Dec-17 A 20-Dec-19
Schedule Driven MilestonesSchedule Driven Milestones0 0 20-Dec-19 20-Dec-19
M-C03-1000 Interim Substantial Completion - North East Stairs 0 0 20-Dec-19
Construction Phase SummariesConstruction Phase Summaries730 184 22-Dec-17 A 20-Dec-19
S-C03-1000 Construction - North East Stairs 730 184 22-Dec-17 A 20-Dec-19
NE Stairs Finishes - Basement FloorNE Stairs Finishes - Basement Floor13 13 25-Nov-19 13-Dec-19
C-C03-2470 Install Stair Guardrails and Handrails - Basement 5 5 25-Nov-19 03-Dec-19
C-C03-2480 Final Paint - Basement 2 2 04-Dec-19 05-Dec-19
C-C03-2365 Install Door and Hardware - Basement 1 1 06-Dec-19 06-Dec-19
C-C03-2495 Final Clean - Basement 2 2 09-Dec-19 10-Dec-19
C-C03-2505 Complete MCC/ FSB Punchlist - Basement 3 3 11-Dec-19 13-Dec-19
NE Stairs Finishes - 1st FloorNE Stairs Finishes - 1st Floor10 10 25-Nov-19 10-Dec-19
C-C03-2485 Install Stair Guardrails and Handrails - LVL 1 5 5 25-Nov-19 03-Dec-19
C-C03-2510 Final Paint - LVL 1 2 2 04-Dec-19 05-Dec-19
C-C03-2445 Install Door and Hardware - LVL 1 1 1 06-Dec-19 06-Dec-19
C-C03-2515 Final Clean - LVL 1 2 2 09-Dec-19 10-Dec-19
NE Stairs Finishes - 2nd FloorNE Stairs Finishes - 2nd Floor10 10 25-Nov-19 10-Dec-19
C-C03-2490 Install Stair Guardrails and Handrails - LVL 2 5 5 25-Nov-19 03-Dec-19
C-C03-2520 Final Paint - LVL 2 2 2 04-Dec-19 05-Dec-19
C-C03-2521 Install Door and Hardware - LVL 2 1 1 06-Dec-19 06-Dec-19
C-C03-2530 Final Clean - LVL 2 2 2 09-Dec-19 10-Dec-19
NE Stairs Finishes - 3rd FloorNE Stairs Finishes - 3rd Floor18 18 25-Nov-19 20-Dec-19
C-C03-2500 Install Stair Guardrails and Handrails - LVL 3 5 5 25-Nov-19 03-Dec-19
C-C03-2525 Final Paint - LVL 3 2 2 04-Dec-19 05-Dec-19
C-C03-2471 Install Door and Hardware - LVL 3 1 1 06-Dec-19 06-Dec-19
C-C03-2535 Final Clean - LVL 3 2 2 09-Dec-19 10-Dec-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Construction - Attic Space
MCC Receive / Review Shop Drawings - Handrail
AE2 (FSB) Receive / Review Submittal - Handrail
AE1 (Mass) Receive / Review Submittal - Handrail
Fab & Deliver - Handrail
Interim Substantial Completion - North East Stairs
Construction - North East Stairs
Install Stair Guardrails and Handrails - Basement
Final Paint - Basement
Install Door and Hardware - Basement
Final Clean - Basement
Complete MCC/ FSB Punchlist - Basement
Install Stair Guardrails and Handrails - LVL 1
Final Paint - LVL 1
Install Door and Hardware - LVL 1
Final Clean - LVL 1
Install Stair Guardrails and Handrails - LVL 2
Final Paint - LVL 2
Install Door and Hardware - LVL 2
Final Clean - LVL 2
Install Stair Guardrails and Handrails - LVL 3
Final Paint - LVL 3
Install Door and Hardware - LVL 3
Final Clean - LVL 3
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 8 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C03-2540 Complete MCC/ FSB Punchlist Floors 1 - 4 8 8 11-Dec-19 20-Dec-19
NE Stairs Finishes - 5th FloorNE Stairs Finishes - 5th Floor7 7 25-Nov-19 05-Dec-19
C-C03-2460 Install Stair Guardrails and Handrails - LVL 6-5 NE 5 5 25-Nov-19 03-Dec-19
C-C03-2475 Final Clean - LVL 6-5 NE 2 2 04-Dec-19 05-Dec-19
South East StairsSouth East Stairs83 148 07-Dec-18 A 21-Jan-20
ConstructionConstruction83 148 07-Dec-18 A 21-Jan-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 21-Jan-20 21-Jan-20
M-C04-1000 Interim Substantial Completion - South East Stairs 0 0 21-Jan-20
Construction Phase SummariesConstruction Phase Summaries121 216 07-Dec-18 A 21-Jan-20
S-C04-1010 Construction - South East Stairs 121 216 07-Dec-18 A 21-Jan-20
Stair Risers 6 - 5Stair Risers 6 - 520 20 23-Dec-19 21-Jan-20
C-C04-1125 Restoration of Existing Stairs and Handrails LVL 6-5 20 20 23-Dec-19 21-Jan-20
Public RestroomsPublic Restrooms545 175 17-Jun-19 A 27-Feb-20
Material ProcurementMaterial Procurement50 37 17-Jun-19 A 12-Aug-19
Toilet Partitions & AccessoriesToilet Partitions & Accessories50 37 17-Jun-19 A 12-Aug-19
P-C05-1000 Fab & Deliver - Toilet Partitions 50 37 17-Jun-19 A 12-Aug-19
ConstructionConstruction507 150 26-Jul-19 27-Feb-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 26-Feb-20 26-Feb-20
M-C05-1000 Interim Substantial Completeion - Public Restrooms 0 0 26-Feb-20
Public RestroomsPublic Restrooms730 216 26-Jul-19 26-Feb-20
S-C05-1005 Construction - Public Restrooms 730 216 26-Jul-19 26-Feb-20
Restrooms - 5th FloorRestrooms - 5th Floor30 30 26-Jul-19 06-Sep-19
C-C05-1006 Build Temp Wall 1 1 26-Jul-19 26-Jul-19
C-C05-1007 Protect Marble Floors 1 1 29-Jul-19 29-Jul-19
C-C05-1009 Pre-Demo Conference 1 1 30-Jul-19 30-Jul-19
C-C05-1008 Make Safe 2 2 30-Jul-19 31-Jul-19
C-C05-1010 Remove / Salvage Toilet Partitions 2 2 30-Jul-19 31-Jul-19
C-C05-1011 Demo 1 1 01-Aug-19 01-Aug-19
C-C05-1012 Abatement 1 1 02-Aug-19 02-Aug-19
C-C05-1013 Post Abatement Demo 1 1 05-Aug-19 05-Aug-19
C-C05-1014 Rough-In In-Wall MEP 3 3 06-Aug-19 08-Aug-19
C-C05-1015 Rough-In OVHD Mechanical Duct 2 2 07-Aug-19 08-Aug-19
C-C05-1016 Install In-Wall Block ing 1 1 09-Aug-19 09-Aug-19
C-C05-1017 Insulate 1 1 09-Aug-19 09-Aug-19
C-C05-1018 In-Wall Inspections 1 1 12-Aug-19 12-Aug-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Complete MCC/ FSB Punchlist Floors 1 - 4
Install Stair Guardrails and Handrails - LVL 6-5 NE
Final Clean - LVL 6-5 NE
Interim Substantial Completion - South East Stairs
Construction - South East Stairs
Restoration of Existing Stairs and Handrails LVL 6-5
Fab & Deliver - Toilet Partitions
Interim Substantial Completeion - Public Restrooms
Construction - Public Restrooms
Build Temp Wall
Protect Marble Floors
Pre-Demo Conference
Make Safe
Remove / Salvage Toilet Partitions
Demo
Abatement
Post Abatement Demo
Rough-In In-Wall MEP
Rough-In OVHD Mechanical Duct
Install In-Wall Block ing
Insulate
In-Wall Inspections
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 9 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C05-1019 Rough-In OVHD Electrical 2 2 12-Aug-19 13-Aug-19
C-C05-1020 Rough-In OVHD Fire Suppression 1 1 14-Aug-19 14-Aug-19
C-C05-1021 OVHD Inspection 1 1 15-Aug-19 15-Aug-19
C-C05-1022 Hang Sheetrock 1 1 16-Aug-19 16-Aug-19
C-C05-1023 Tape / Bed / Paint 3 3 19-Aug-19 21-Aug-19
C-C05-1025 Trim Out MEPF 1 1 22-Aug-19 22-Aug-19
C-C05-1026 Install Crown 1 1 22-Aug-19 22-Aug-19
C-C05-1024 Refinish Existing Base / Floors 3 3 22-Aug-19 26-Aug-19
C-C05-1027 Install Wet Wall Marble 1 1 27-Aug-19 27-Aug-19
C-C05-1029 Install Doors and Hardware 1 1 27-Aug-19 27-Aug-19
C-C05-1028 Install Toilet Partitions 2 2 27-Aug-19 28-Aug-19
C-C05-1030 Install Vanities 1 1 28-Aug-19 28-Aug-19
C-C05-1031 Install Plumbing Fixtures 3 3 28-Aug-19 30-Aug-19
C-C05-1032 Install Restroom Accessories 1 1 29-Aug-19 29-Aug-19
C-C05-1033 Install Mirrors 1 1 29-Aug-19 29-Aug-19
C-C05-1034 Final Paint 2 2 30-Aug-19 03-Sep-19
C-C05-1035 Final Clean 1 1 03-Sep-19 03-Sep-19
C-C05-1036 Complete MCC / FSB Punch List 1 1 04-Sep-19 04-Sep-19
C-C05-1037 Complete AE1 / Owner Punch List 1 1 05-Sep-19 05-Sep-19
C-C05-1038 Owner Move In 1 1 06-Sep-19 06-Sep-19
Restrooms - 4th FloorRestrooms - 4th Floor30 30 09-Sep-19 18-Oct-19
C-C05-1039 Build Temp Wall 1 1 09-Sep-19 09-Sep-19
C-C05-1040 Protect Marble Floors 1 1 10-Sep-19 10-Sep-19
C-C05-1041 Pre-Demo Conference 1 1 11-Sep-19 11-Sep-19
C-C05-1042 Make Safe 2 2 11-Sep-19 12-Sep-19
C-C05-1043 Remove / Salvage Toilet Partitions 2 2 11-Sep-19 12-Sep-19
C-C05-1044 Demo 1 1 13-Sep-19 13-Sep-19
C-C05-1045 Abatement 1 1 16-Sep-19 16-Sep-19
C-C05-1046 Post Abatement Demo 1 1 17-Sep-19 17-Sep-19
C-C05-1047 Rough-In In-Wall MEP 3 3 18-Sep-19 20-Sep-19
C-C05-1048 Rough-In OVHD Mechanical Duct 2 2 19-Sep-19 20-Sep-19
C-C05-1049 Install In-Wall Block ing 1 1 23-Sep-19 23-Sep-19
C-C05-1050 Insulate 1 1 23-Sep-19 23-Sep-19
C-C05-1051 In-Wall Inspections 1 1 24-Sep-19 24-Sep-19
C-C05-1052 Rough-In OVHD Electrical 2 2 24-Sep-19 25-Sep-19
C-C05-1053 Rough-In OVHD Fire Suppression 1 1 26-Sep-19 26-Sep-19
C-C05-1054 OVHD Inspection 1 1 27-Sep-19 27-Sep-19
C-C05-1055 Hang Sheetrock 1 1 30-Sep-19 30-Sep-19
C-C05-1056 Tape / Bed / Paint 3 3 01-Oct-19 03-Oct-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Rough-In OVHD Electrical
Rough-In OVHD Fire Suppression
OVHD Inspection
Hang Sheetrock
Tape / Bed / Paint
Trim Out MEPF
Install Crown
Refinish Existing Base / Floors
Install Wet Wall Marble
Install Doors and Hardware
Install Toilet Partitions
Install Vanities
Install Plumbing Fixtures
Install Restroom Accessories
Install Mirrors
Final Paint
Final Clean
Complete MCC / FSB Punch List
Complete AE1 / Owner Punch List
Owner Move In
Build Temp Wall
Protect Marble Floors
Pre-Demo Conference
Make Safe
Remove / Salvage Toilet Partitions
Demo
Abatement
Post Abatement Demo
Rough-In In-Wall MEP
Rough-In OVHD Mechanical Duct
Install In-Wall Block ing
Insulate
In-Wall Inspections
Rough-In OVHD Electrical
Rough-In OVHD Fire Suppression
OVHD Inspection
Hang Sheetrock
Tape / Bed / Paint
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 10 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C05-1057 Trim Out MEPF 1 1 04-Oct-19 04-Oct-19
C-C05-1058 Install Crown 1 1 04-Oct-19 04-Oct-19
C-C05-1059 Refinish Existing Base / Floors 3 3 04-Oct-19 08-Oct-19
C-C05-1060 Install Wet Wall Marble 1 1 09-Oct-19 09-Oct-19
C-C05-1061 Install Doors and Hardware 1 1 09-Oct-19 09-Oct-19
C-C05-1062 Install Toilet Partitions 2 2 09-Oct-19 10-Oct-19
C-C05-1063 Install Vanities 1 1 10-Oct-19 10-Oct-19
C-C05-1064 Install Plumbing Fixtures 3 3 10-Oct-19 14-Oct-19
C-C05-1065 Install Restroom Accessories 1 1 11-Oct-19 11-Oct-19
C-C05-1066 Install Mirrors 1 1 11-Oct-19 11-Oct-19
C-C05-1067 Final Paint 2 2 14-Oct-19 15-Oct-19
C-C05-1068 Final Clean 1 1 15-Oct-19 15-Oct-19
C-C05-1069 Complete MCC / FSB Punch List 1 1 16-Oct-19 16-Oct-19
C-C05-1070 Complete AE1 / Owner Punch List 1 1 17-Oct-19 17-Oct-19
C-C05-1071 Owner Move In 1 1 18-Oct-19 18-Oct-19
Restrooms - 3rd FloorRestrooms - 3rd Floor30 30 21-Oct-19 03-Dec-19
C-C05-1072 Build Temp Wall 1 1 21-Oct-19 21-Oct-19
C-C05-1073 Protect Marble Floors 1 1 22-Oct-19 22-Oct-19
C-C05-1074 Pre-Demo Conference 1 1 23-Oct-19 23-Oct-19
C-C05-1075 Make Safe 2 2 23-Oct-19 24-Oct-19
C-C05-1076 Remove / Salvage Toilet Partitions 2 2 23-Oct-19 24-Oct-19
C-C05-1077 Demo 1 1 25-Oct-19 25-Oct-19
C-C05-1078 Abatement 1 1 28-Oct-19 28-Oct-19
C-C05-1079 Post Abatement Demo 1 1 29-Oct-19 29-Oct-19
C-C05-1080 Rough-In In-Wall MEP 3 3 30-Oct-19 01-Nov-19
C-C05-1081 Rough-In OVHD Mechanical Duct 2 2 31-Oct-19 01-Nov-19
C-C05-1082 Install In-Wall Block ing 1 1 04-Nov-19 04-Nov-19
C-C05-1083 Insulate 1 1 04-Nov-19 04-Nov-19
C-C05-1084 In-Wall Inspections 1 1 05-Nov-19 05-Nov-19
C-C05-1085 Rough-In OVHD Electrical 2 2 05-Nov-19 06-Nov-19
C-C05-1086 Rough-In OVHD Fire Suppression 1 1 07-Nov-19 07-Nov-19
C-C05-1087 OVHD Inspection 1 1 08-Nov-19 08-Nov-19
C-C05-1088 Hang Sheetrock 1 1 11-Nov-19 11-Nov-19
C-C05-1089 Tape / Bed / Paint 3 3 12-Nov-19 14-Nov-19
C-C05-1090 Trim Out MEPF 1 1 15-Nov-19 15-Nov-19
C-C05-1091 Install Crown 1 1 15-Nov-19 15-Nov-19
C-C05-1092 Refinish Existing Base / Floors 3 3 15-Nov-19 19-Nov-19
C-C05-1093 Install Wet Wall Marble 1 1 20-Nov-19 20-Nov-19
C-C05-1094 Install Doors and Hardware 1 1 20-Nov-19 20-Nov-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Trim Out MEPF
Install Crown
Refinish Existing Base / Floors
Install Wet Wall Marble
Install Doors and Hardware
Install Toilet Partitions
Install Vanities
Install Plumbing Fixtures
Install Restroom Accessories
Install Mirrors
Final Paint
Final Clean
Complete MCC / FSB Punch List
Complete AE1 / Owner Punch List
Owner Move In
Build Temp Wall
Protect Marble Floors
Pre-Demo Conference
Make Safe
Remove / Salvage Toilet Partitions
Demo
Abatement
Post Abatement Demo
Rough-In In-Wall MEP
Rough-In OVHD Mechanical Duct
Install In-Wall Block ing
Insulate
In-Wall Inspections
Rough-In OVHD Electrical
Rough-In OVHD Fire Suppression
OVHD Inspection
Hang Sheetrock
Tape / Bed / Paint
Trim Out MEPF
Install Crown
Refinish Existing Base / Floors
Install Wet Wall Marble
Install Doors and Hardware
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 11 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C05-1095 Install Toilet Partitions 2 2 20-Nov-19 21-Nov-19
C-C05-1096 Install Vanities 1 1 21-Nov-19 21-Nov-19
C-C05-1097 Install Plumbing Fixtures 3 3 21-Nov-19 25-Nov-19
C-C05-1098 Install Restroom Accessories 1 1 22-Nov-19 22-Nov-19
C-C05-1099 Install Mirrors 1 1 22-Nov-19 22-Nov-19
C-C05-1100 Final Paint 2 2 25-Nov-19 26-Nov-19
C-C05-1101 Final Clean 1 1 26-Nov-19 26-Nov-19
C-C05-1102 Complete MCC / FSB Punch List 1 1 27-Nov-19 27-Nov-19
C-C05-1103 Complete AE1 / Owner Punch List 1 1 02-Dec-19 02-Dec-19
C-C05-1104 Owner Move In 1 1 03-Dec-19 03-Dec-19
Restrooms - 2nd FloorRestrooms - 2nd Floor30 30 04-Dec-19 16-Jan-20
C-C05-1105 Build Temp Wall 1 1 04-Dec-19 04-Dec-19
C-C05-1106 Protect Marble Floors 1 1 05-Dec-19 05-Dec-19
C-C05-1107 Pre-Demo Conference 1 1 06-Dec-19 06-Dec-19
C-C05-1108 Make Safe 2 2 06-Dec-19 09-Dec-19
C-C05-1109 Remove / Salvage Toilet Partitions 2 2 06-Dec-19 09-Dec-19
C-C05-1110 Demo 1 1 10-Dec-19 10-Dec-19
C-C05-1111 Abatement 1 1 11-Dec-19 11-Dec-19
C-C05-1112 Post Abatement Demo 1 1 12-Dec-19 12-Dec-19
C-C05-1113 Rough-In In-Wall MEP 3 3 13-Dec-19 17-Dec-19
C-C05-1114 Rough-In OVHD Mechanical Duct 2 2 16-Dec-19 17-Dec-19
C-C05-1115 Install In-Wall Block ing 1 1 18-Dec-19 18-Dec-19
C-C05-1116 Insulate 1 1 18-Dec-19 18-Dec-19
C-C05-1117 In-Wall Inspections 1 1 19-Dec-19 19-Dec-19
C-C05-1118 Rough-In OVHD Electrical 2 2 19-Dec-19 20-Dec-19
C-C05-1119 Rough-In OVHD Fire Suppression 1 1 23-Dec-19 23-Dec-19
C-C05-1120 OVHD Inspection 1 1 24-Dec-19 24-Dec-19
C-C05-1121 Hang Sheetrock 1 1 26-Dec-19 26-Dec-19
C-C05-1122 Tape / Bed / Paint 3 3 27-Dec-19 31-Dec-19
C-C05-1123 Trim Out MEPF 1 1 02-Jan-20 02-Jan-20
C-C05-1124 Install Crown 1 1 02-Jan-20 02-Jan-20
C-C05-1125 Refinish Existing Base / Floors 3 3 02-Jan-20 06-Jan-20
C-C05-1126 Install Wet Wall Marble 1 1 07-Jan-20 07-Jan-20
C-C05-1127 Install Doors and Hardware 1 1 07-Jan-20 07-Jan-20
C-C05-1128 Install Toilet Partitions 2 2 07-Jan-20 08-Jan-20
C-C05-1129 Install Vanities 1 1 08-Jan-20 08-Jan-20
C-C05-1130 Install Plumbing Fixtures 3 3 08-Jan-20 10-Jan-20
C-C05-1131 Install Restroom Accessories 1 1 09-Jan-20 09-Jan-20
C-C05-1132 Install Mirrors 1 1 09-Jan-20 09-Jan-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Install Toilet Partitions
Install Vanities
Install Plumbing Fixtures
Install Restroom Accessories
Install Mirrors
Final Paint
Final Clean
Complete MCC / FSB Punch List
Complete AE1 / Owner Punch List
Owner Move In
Build Temp Wall
Protect Marble Floors
Pre-Demo Conference
Make Safe
Remove / Salvage Toilet Partitions
Demo
Abatement
Post Abatement Demo
Rough-In In-Wall MEP
Rough-In OVHD Mechanical Duct
Install In-Wall Block ing
Insulate
In-Wall Inspections
Rough-In OVHD Electrical
Rough-In OVHD Fire Suppression
OVHD Inspection
Hang Sheetrock
Tape / Bed / Paint
Trim Out MEPF
Install Crown
Refinish Existing Base / Floors
Install Wet Wall Marble
Install Doors and Hardware
Install Toilet Partitions
Install Vanities
Install Plumbing Fixtures
Install Restroom Accessories
Install Mirrors
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 12 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C05-1133 Final Paint 2 2 10-Jan-20 13-Jan-20
C-C05-1134 Final Clean 1 1 13-Jan-20 13-Jan-20
C-C05-1135 Complete MCC / FSB Punch List 1 1 14-Jan-20 14-Jan-20
C-C05-1136 Complete AE1 / Owner Punch List 1 1 15-Jan-20 15-Jan-20
C-C05-1137 Owner Move In 1 1 16-Jan-20 16-Jan-20
Restrooms - 1st FloorRestrooms - 1st Floor30 30 17-Jan-20 27-Feb-20
C-C05-1138 Build Temp Wall 1 1 17-Jan-20 17-Jan-20
C-C05-1139 Protect Marble Floors 1 1 20-Jan-20 20-Jan-20
C-C05-1140 Pre-Demo Conference 1 1 21-Jan-20 21-Jan-20
C-C05-1141 Make Safe 2 2 21-Jan-20 22-Jan-20
C-C05-1142 Remove / Salvage Toilet Partitions 2 2 21-Jan-20 22-Jan-20
C-C05-1143 Demo 1 1 23-Jan-20 23-Jan-20
C-C05-1144 Abatement 1 1 24-Jan-20 24-Jan-20
C-C05-1145 Post Abatement Demo 1 1 27-Jan-20 27-Jan-20
C-C05-1146 Rough-In In-Wall MEP 3 3 28-Jan-20 30-Jan-20
C-C05-1147 Rough-In OVHD Mechanical Duct 2 2 29-Jan-20 30-Jan-20
C-C05-1148 Install In-Wall Block ing 1 1 31-Jan-20 31-Jan-20
C-C05-1149 Insulate 1 1 31-Jan-20 31-Jan-20
C-C05-1150 In-Wall Inspections 1 1 03-Feb-20 03-Feb-20
C-C05-1151 Rough-In OVHD Electrical 2 2 03-Feb-20 04-Feb-20
C-C05-1152 Rough-In OVHD Fire Suppression 1 1 05-Feb-20 05-Feb-20
C-C05-1153 OVHD Inspection 1 1 06-Feb-20 06-Feb-20
C-C05-1154 Hang Sheetrock 1 1 07-Feb-20 07-Feb-20
C-C05-1155 Tape / Bed / Paint 3 3 10-Feb-20 12-Feb-20
C-C05-1156 Trim Out MEPF 1 1 13-Feb-20 13-Feb-20
C-C05-1157 Install Crown 1 1 13-Feb-20 13-Feb-20
C-C05-1158 Refinish Existing Base / Floors 3 3 13-Feb-20 17-Feb-20
C-C05-1159 Install Wet Wall Marble 1 1 18-Feb-20 18-Feb-20
C-C05-1160 Install Doors and Hardware 1 1 18-Feb-20 18-Feb-20
C-C05-1161 Install Toilet Partitions 2 2 18-Feb-20 19-Feb-20
C-C05-1162 Install Vanities 1 1 19-Feb-20 19-Feb-20
C-C05-1163 Install Plumbing Fixtures 3 3 19-Feb-20 21-Feb-20
C-C05-1164 Install Restroom Accessories 1 1 20-Feb-20 20-Feb-20
C-C05-1165 Install Mirrors 1 1 20-Feb-20 20-Feb-20
C-C05-1166 Final Paint 2 2 21-Feb-20 24-Feb-20
C-C05-1167 Final Clean 1 1 24-Feb-20 24-Feb-20
C-C05-1171 100% Fire Marshal Inspections (All Public Restrooms) 3 3 24-Feb-20 26-Feb-20
C-C05-1168 Complete MCC / FSB Punch List 1 1 25-Feb-20 25-Feb-20
C-C05-1169 Complete AE1 / Owner Punch List 1 1 26-Feb-20 26-Feb-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Final Paint
Final Clean
Complete MCC / FSB Punch List
Complete AE1 / Owner Punch List
Owner Move In
Build Temp Wall
Protect Marble Floors
Pre-Demo Conference
Make Safe
Remove / Salvage Toilet Partitions
Demo
Abatement
Post Abatement Demo
Rough-In In-Wall MEP
Rough-In OVHD Mechanical Duct
Install In-Wall Block ing
Insulate
In-Wall Inspections
Rough-In OVHD Electrical
Rough-In OVHD Fire Suppression
OVHD Inspection
Hang Sheetrock
Tape / Bed / Paint
Trim Out MEPF
Install Crown
Refinish Existing Base / Floors
Install Wet Wall Marble
Install Doors and Hardware
Install Toilet Partitions
Install Vanities
Install Plumbing Fixtures
Install Restroom Accessories
Install Mirrors
Final Paint
Final Clean
100% Fire Marshal Inspections (All Public Restrooms)
Complete MCC / FSB Punch List
Complete AE1 / Owner Punch List
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 13 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C05-1170 Owner Move In 1 1 27-Feb-20 27-Feb-20
RotundaRotunda761 583 21-May-19 A 05-Oct-21
ConstructionConstruction761 583 21-May-19 A 05-Oct-21
Schedule Driven MilestonesSchedule Driven Milestones0 0 05-Oct-21 05-Oct-21
M-C06-1000 Interim Substantial Completion - Rotunda 0 0 05-Oct-21
Construction Phase SummariesConstruction Phase Summaries1095 839 21-May-19 A 05-Oct-21
S-C06-1000 Construction - Rotunda 1095 839 21-May-19 A 05-Oct-21
Supreme Court & Gov Conference Room - 2nd FloorSupreme Court & Gov Conference Room - 2nd Floor42 21 21-May-19 A 19-Jul-19
C-C06-1030 Decorative Paint 42 21 21-May-19 A 19-Jul-19
Rotunda & House Hallways - 2nd FloorRotunda & House Hallways - 2nd Floor148 148 20-Jun-19 21-Jan-20
C-C06-1038 Scaffold Erection 15 15 20-Jun-19 11-Jul-19
C-C06-1037 Base Restoration 45 45 20-Jun-19* 22-Aug-19
C-C06-1039 Base Paint / Plaster Repair 64 64 12-Jul-19 10-Oct-19
C-C06-1040 Decorative Paint 69 69 11-Oct-19 21-Jan-20
Governor Hallway - 2nd FloorGovernor Hallway - 2nd Floor50 50 08-Jul-19 16-Sep-19
C-C06-1033 Marble Floor Restoration 18 18 08-Jul-19* 31-Jul-19
C-C06-1031 Base Paint 22 22 01-Aug-19 30-Aug-19
C-C06-1032 Decorative Paint 10 10 03-Sep-19 16-Sep-19
Blue Room - 2nd FloorBlue Room - 2nd Floor53 53 23-Sep-19 06-Dec-19
C-C06-1034 Marble Base & Perimeter Restoration 26 26 23-Sep-19 28-Oct-19
C-C06-1035 Base Paint 13 13 01-Nov-19 19-Nov-19
C-C06-1036 Decorative Paint 11 11 20-Nov-19 06-Dec-19
Public Hallways - 3rd FloorPublic Hallways - 3rd Floor57 57 01-Nov-19 24-Jan-20
C-C06-1046 Base Restoration 39 39 01-Nov-19* 30-Dec-19
C-C06-1047 Base Paint / Plaster Repair 24 24 25-Nov-19 31-Dec-19
C-C06-1048 Marble Floor Restoration 17 17 02-Jan-20 24-Jan-20
House Hallways - 5th FloorHouse Hallways - 5th Floor5 5 19-Dec-19 26-Dec-19
C-C06-1055 Decorative Paint 5 5 19-Dec-19* 26-Dec-19
House Hallways - 4th FloorHouse Hallways - 4th Floor5 5 27-Dec-19 03-Jan-20
C-C06-1049 Decorative Paint 5 5 27-Dec-19* 03-Jan-20
House Hallways - 3rd FloorHouse Hallways - 3rd Floor5 5 06-Jan-20 10-Jan-20
C-C06-1043 Decorative Paint 5 5 06-Jan-20* 10-Jan-20
Rotunda - 4th FloorRotunda - 4th Floor222 222 06-Jan-20 13-Nov-20
C-C06-1051 Scaffold Erection 25 25 06-Jan-20* 07-Feb-20
C-C06-1050 Base Restoration 45 45 27-Jan-20 27-Mar-20
C-C06-1052 Base Paint / Plaster Repair 66 66 07-Feb-20 08-May-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Owner Move In
Interim Substantial Completion - Rotunda
Construction - Rotunda
Decorative Paint
Scaffold Erection
Base Restoration
Base Paint / Plaster Repair
Decorative Paint
Marble Floor Restoration
Base Paint
Decorative Paint
Marble Base & Perimeter Restoration
Base Paint
Decorative Paint
Base Restoration
Base Paint / Plaster Repair
Marble Floor Restoration
Decorative Paint
Decorative Paint
Decorative Paint
Scaffold Erection
Base Restoration
Base Paint / Plaster Repair
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 14 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C06-1053 Decorative Paint 113 113 05-Mar-20 12-Aug-20
C-C06-1054 Marble Floor Restoration 66 66 13-Aug-20 13-Nov-20
Treasurer Hallways - 2nd FloorTreasurer Hallways - 2nd Floor15 15 10-Feb-20 28-Feb-20
C-C06-1041 Decorative Paint 15 15 10-Feb-20* 28-Feb-20
Hall of GovHall of Gov80 80 10-Feb-20 01-Jun-20
C-C06-1042 Decorative Paint 80 80 10-Feb-20* 01-Jun-20
Rotunda / Mezzanine Hallways - 5th FloorRotunda / Mezzanine Hallways - 5th Floor128 128 01-Jun-20 01-Dec-20
C-C06-1058 Base Restoration 45 45 01-Jun-20* 03-Aug-20
C-C06-1060 Base Paint / Plaster Repair 43 43 03-Aug-20 01-Oct-20
C-C06-1061 Decorative Paint 43 43 12-Aug-20 12-Oct-20
C-C06-1059 Marble Floor Restoration 35 35 12-Oct-20 01-Dec-20
Public Hallways - 1st FloorPublic Hallways - 1st Floor154 154 01-Jun-20 08-Jan-21
C-C06-1025 Base Restoration 43 43 01-Jun-20* 30-Jul-20
C-C06-1026 Plaster Patch / Repair 20 20 06-Jul-20 31-Jul-20
C-C06-1027 Base Paint 15 15 27-Jul-20 14-Aug-20
C-C06-1028 Decorative Paint 94 94 17-Aug-20 30-Dec-20
C-C06-1029 Marble Floor Restoration 59 59 14-Oct-20 08-Jan-21
Senate Hallways - 3rd FloorSenate Hallways - 3rd Floor14 14 15-Jul-20 03-Aug-20
C-C06-1044 Decorative Paint 14 14 15-Jul-20* 03-Aug-20
House Chambers / Lounge - 5th FloorHouse Chambers / Lounge - 5th Floor88 88 02-Jun-21 05-Oct-21
C-C06-1056 Decorative Paint 88 88 02-Jun-21* 05-Oct-21
Senate Chambers / Lounge - 5th FloorSenate Chambers / Lounge - 5th Floor88 88 02-Jun-21 05-Oct-21
C-C06-1057 Decorative Paint 88 88 02-Jun-21* 05-Oct-21
TenantsTenants619 409 31-Aug-18 A 31-Jan-21
1st Floor OMES North1st Floor OMES North260 56 31-Aug-18 A 09-Sep-19
ConstructionConstruction260 56 31-Aug-18 A 09-Sep-19
Schedule Driven MilestonesSchedule Driven Milestones0 0 05-Sep-19 05-Sep-19
M-T08-1000 Interim Substantial Completion - 1st Floor OMES North 0 0 05-Sep-19
Construction Phase SummariesConstruction Phase Summaries214 78 31-Aug-18 A 05-Sep-19
S-T08-1000 Construction - 1st Floor OMES North 214 78 31-Aug-18 A 05-Sep-19
1st Floor OMES North1st Floor OMES North56 56 20-Jun-19 09-Sep-19
C-T08-1397 Awaiting Owner Direction on Redesign 5 5 20-Jun-19 26-Jun-19
C-T08-1398 FSB Redesign 1st Floor OMES North 10 10 27-Jun-19 11-Jul-19
C-T08-1275 Layout and Frame Walls 1 1 12-Jul-19 12-Jul-19
C-T08-1070 Existing Ceiling Restoration 15 15 12-Jul-19 01-Aug-19
C-T08-1295 In-Wall Inspections 2 2 15-Jul-19 16-Jul-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Decorative Paint
Marble Floor Restoration
Decorative Paint
Decorative Paint
Base Restoration
Base Paint / Plaster Repair
Decorative Paint
Marble Floor Restoration
Base Restoration
Plaster Patch / Repair
Base Paint
Decorative Paint
Marble Floor Restoration
Decorative Paint
Decorative Paint
Decorative Paint
Interim Substantial Completion - 1st Floor OMES North
Construction - 1st Floor OMES North
Awaiting Owner Direction on Redesign
FSB Redesign 1st Floor OMES North
Layout and Frame Walls
Existing Ceiling Restoration
In-Wall Inspections
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 15 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T08-1285 Rough-In Overhead Mechanical 4 4 15-Jul-19 18-Jul-19
C-T08-1290 Rough In Overhead Electric 4 4 15-Jul-19 18-Jul-19
C-T08-1330 Install OMES LV Cabling 2 2 19-Jul-19 22-Jul-19
C-T08-1300 Insulate Mechanical 3 3 19-Jul-19 23-Jul-19
C-T08-1320 Install Controls for Heat Pumps 2 2 24-Jul-19 25-Jul-19
C-T08-1305 Rough-In Fire Suppression 2 2 31-Jul-19 01-Aug-19
C-T08-1315 50% Fire Marshal Inspection 0 0 01-Aug-19
C-T08-1310 Hang Sheetrock 2 2 02-Aug-19 05-Aug-19
C-T08-1325 Tape/Bed/Paint 4 4 06-Aug-19 09-Aug-19
C-T08-1335 Install Ceiling Grid 2 2 12-Aug-19 13-Aug-19
C-T08-1340 Overhead Device Out 3 3 14-Aug-19 16-Aug-19
C-T08-1345 Above Ceiling Inspections 2 2 19-Aug-19 20-Aug-19
C-T08-1350 80% Fire Marshal Inspection 0 0 20-Aug-19
C-T08-1355 Drop Ceiling Tiles 2 2 21-Aug-19 22-Aug-19
C-T08-1360 Install Flooring 5 5 23-Aug-19 29-Aug-19
C-T08-1365 Hang Door and Hardware 1 1 30-Aug-19 30-Aug-19
C-T08-1370 Test and Balance 1 1 03-Sep-19 03-Sep-19
C-T08-1375 OMES Activate Security and Card Access 1 1 03-Sep-19 03-Sep-19
C-T08-1380 Complete MCC/FSB Punch List 2 2 04-Sep-19 05-Sep-19
C-T08-1385 100% Fire Marshal Inspection 0 0 05-Sep-19
C-T08-1390 Complete AE1/Owner Punch List 2 2 06-Sep-19 09-Sep-19
C-T08-1395 Owner Move In 0 0 09-Sep-19
2nd Floor Governor2nd Floor Governor294 197 01-Feb-19 A 30-Mar-20
Material ProcurementMaterial Procurement261 184 19-Feb-19 A 11-Mar-20
OAU & Heat PumpsOAU & Heat Pumps40 32 10-Jun-19 A 05-Aug-19
P-T11-1254 Fab & Deliver - Heat Pumps per ASI 27 40 32 10-Jun-19 A 05-Aug-19
Light FixturesLight Fixtures249 184 10-Apr-19 A 11-Mar-20
P-T11-1240 Light Fixture Refinishing - Offices 130 80 10-Apr-19 A 11-Oct-19
P-T11-1252 Light Fixture Refinishing - Blue Room 130 130 06-Sep-19 11-Mar-20
Floor CoveringFloor Covering60 14 14-May-19 A 10-Jul-19
P-T11-1180 Fab & Deliver - Specialty Rugs 60 14 14-May-19 A 10-Jul-19
P-T11-1170 Fab & Deliver Flooring - Carpet 60 14 14-May-19 A 10-Jul-19
Doors / HardwareDoors / Hardware45 7 06-Mar-19 A 28-Jun-19
P-T11-1220 Fab & Deliver - Doors & Hardware 45 7 06-Mar-19 A 28-Jun-19
ElevatorsElevators60 21 19-Feb-19 A 19-Jul-19
P-T11-1230 Fab & Deliver Elevator 60 21 19-Feb-19 A 19-Jul-19
ConstructionConstruction294 197 01-Feb-19 A 30-Mar-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Rough-In Overhead Mechanical
Rough In Overhead Electric
Install OMES LV Cabling
Insulate Mechanical
Install Controls for Heat Pumps
Rough-In Fire Suppression
50% Fire Marshal Inspection
Hang Sheetrock
Tape/Bed/Paint
Install Ceiling Grid
Overhead Device Out
Above Ceiling Inspections
80% Fire Marshal Inspection
Drop Ceiling Tiles
Install Flooring
Hang Door and Hardware
Test and Balance
OMES Activate Security and Card Access
Complete MCC/FSB Punch List
100% Fire Marshal Inspection
Complete AE1/Owner Punch List
Owner Move In
Fab & Deliver - Heat Pumps per ASI 27
Light Fixture Refinishing - Offices
Light Fixture Refinishing - Blue Room
Fab & Deliver - Specialty Rugs
Fab & Deliver Flooring - Carpet
Fab & Deliver - Doors & Hardware
Fab & Deliver Elevator
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 16 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
Schedule Driven MilestonesSchedule Driven Milestones0 0 30-Mar-20 30-Mar-20
M-T11-1000 Interim Substantial Completion - 2nd Floor Governor 0 0 30-Mar-20
Construction Phase SummariesConstruction Phase Summaries359 285 01-Feb-19 A 30-Mar-20
S-T11-1000 Construction - 2nd Floor Governor 359 285 01-Feb-19 A 30-Mar-20
Conference / FoyerConference / Foyer84 84 19-Jun-19 A 17-Oct-19
C-T11-1420 Final Paint - Conf/Foyer 5 4 19-Jun-19 A 25-Jun-19
C-T11-1280 Patch Plaster 1st Floor Ceiling 10 10 20-Jun-19 03-Jul-19
C-T11-1450 Trim Out MEPF Devices - Conf/Foyer 4 4 26-Jun-19 01-Jul-19
C-T11-1470 Restore Marble - Foyer 10 10 02-Jul-19 16-Jul-19
C-T11-1340 Final Paint 1st Floor Corridor 5 5 05-Jul-19 11-Jul-19
C-T11-1530 Install Carpet/Rug - Conference 2 2 17-Jul-19 18-Jul-19
C-T11-1550 Decorative Paint - Conf/Foyer 5 10 17-Jul-19 30-Jul-19
C-T11-1570 TCO - Fire Marshal Inspection 0 0 18-Jul-19
C-T11-1590 Complete MCC/ FSB Punchlist - Conf/Foyer 4 4 31-Jul-19 05-Aug-19
C-T11-1610 Complete AE1/Owner Punch - Conf/Foyer 3 3 06-Aug-19 08-Aug-19
C-T11-1630 Turnover - Conf/Foyer 0 0 08-Aug-19
C-T11-2164 Install Refinished Light Fixtures 4 4 14-Oct-19 17-Oct-19
OfficesOffices124 100 23-Apr-19 A 08-Nov-19
C-T11-1500 Frame Hard Lids 10 1 23-Apr-19 A 20-Jun-19
C-T11-1490 Rough Fire-Suppression @ Hard Lids 5 1 25-Apr-19 A 20-Jun-19
C-T11-1560 Rough-In Electrical @ Hard Lids 7 1 25-Apr-19 A 20-Jun-19
C-T11-1760 Plaster in Historic Corridors 40 2 01-May-19 A 21-Jun-19
C-T11-1620 Hang Sheetrock at Hardlids 5 1 15-May-19 A 20-Jun-19
C-T11-1850 Install Sub Floor 8 1 03-Jun-19 A 20-Jun-19
C-T11-1840 Overhead Device Out 5 2 11-Jun-19 A 21-Jun-19
C-T11-1740 Install SDT in IT Closets 2 2 20-Jun-19 21-Jun-19
C-T11-1950 Install Marble Tile 10 10 21-Jun-19 05-Jul-19
C-T11-1790 Install Base / Case / Crown 20 20 21-Jun-19 19-Jul-19
C-T11-1880 Above Ceiling Inspections 2 2 24-Jun-19 25-Jun-19
C-T11-1780 OMES Install LV Cabling 10 10 27-Jun-19 11-Jul-19
C-T11-1970 Install Plumbing Fixtures 4 4 03-Jul-19 09-Jul-19
C-T11-1860 Install Millwork 5 5 08-Jul-19 12-Jul-19
C-T11-2060 Restore Marble in Corridors 20 20 08-Jul-19 02-Aug-19
C-T11-2010 Install Bathroom Accessories 2 2 10-Jul-19 11-Jul-19
C-T11-1940 Drop Ceiling Tile 3 3 12-Jul-19 16-Jul-19
C-T11-1890 Install Countertops 2 2 15-Jul-19 16-Jul-19
C-T11-1920 Install Wood Flooring 15 15 15-Jul-19 02-Aug-19
C-T11-1960 Install Carpet 15 15 17-Jul-19 06-Aug-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Interim Substantial Completion - 2nd Floor Governor
Construction - 2nd Floor Governor
Final Paint - Conf/Foyer
Patch Plaster 1st Floor Ceiling
Trim Out MEPF Devices - Conf/Foyer
Restore Marble - Foyer
Final Paint 1st Floor Corridor
Install Carpet/Rug - Conference
Decorative Paint - Conf/Foyer
TCO - Fire Marshal Inspection
Complete MCC/ FSB Punchlist - Conf/Foyer
Complete AE1/Owner Punch - Conf/Foyer
Turnover - Conf/Foyer
Install Refinished Light Fixtures
Frame Hard Lids
Rough Fire-Suppression @ Hard Lids
Rough-In Electrical @ Hard Lids
Plaster in Historic Corridors
Hang Sheetrock at Hardlids
Install Sub Floor
Overhead Device Out
Install SDT in IT Closets
Install Marble Tile
Install Base / Case / Crown
Above Ceiling Inspections
OMES Install LV Cabling
Install Plumbing Fixtures
Install Millwork
Restore Marble in Corridors
Install Bathroom Accessories
Drop Ceiling Tile
Install Countertops
Install Wood Flooring
Install Carpet
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 17 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T11-1810 Install Elevator 25 25 22-Jul-19 23-Aug-19
C-T11-2020 Hang Doors & Install Hardware 10 10 05-Aug-19 16-Aug-19
C-T11-2155 Install Wainscot 10 10 05-Aug-19 16-Aug-19
C-T11-2165 Hang Heat Pumps per ASI 27 1 1 06-Aug-19 06-Aug-19
C-T11-2166 RI and Insulate Heat Pumps MEP per ASI 27 4 4 07-Aug-19 12-Aug-19
C-T11-2050 OMES Activate Security & Card Access 5 5 12-Aug-19 16-Aug-19
C-T11-2167 Install Controls for Heat Pumps per ASI 27 1 1 13-Aug-19 13-Aug-19
C-T11-2168 Finish Ceiling at Heat Pumps per ASI 27 2 2 14-Aug-19 15-Aug-19
C-T11-1930 80% Fire Marshal Inspection 0 0 15-Aug-19
C-T11-2070 Install Glazing 6 6 16-Aug-19 23-Aug-19
C-T11-2100 Final Paint 10 10 19-Aug-19 30-Aug-19
C-T11-2090 Test & Balance 15 15 19-Aug-19 09-Sep-19
C-T11-1990 Install Elevator Machine Room equipment 1 1 26-Aug-19 26-Aug-19
C-T11-2080 Elevator Inspection 0 0 26-Aug-19
C-T11-2101 Decorative Paint 10 10 03-Sep-19 16-Sep-19
C-T11-2110 Install Refinished Light Fixtures 5 5 14-Oct-19 18-Oct-19
C-T11-2120 Complete MCC / FSB Punch List 10 10 21-Oct-19 01-Nov-19
C-T11-2130 100% Fire Marshal Inspection (Final) 0 0 01-Nov-19
C-T11-2140 Complete AE1 / Owner Punch List 5 5 04-Nov-19 08-Nov-19
C-T11-2150 Owner Move In 0 0 08-Nov-19
Blue RoomBlue Room162 162 09-Aug-19 30-Mar-20
C-T11-2152 Owner Move Out 2 2 09-Aug-19 12-Aug-19
C-T11-2151 Make Safe 2 2 13-Aug-19 14-Aug-19
C-T11-1910 Restore Marble 10 10 15-Aug-19 28-Aug-19
C-T11-2158 Protect Marble 1 1 29-Aug-19 29-Aug-19
C-T11-2156 Install Scaffold 2 2 30-Aug-19 03-Sep-19
C-T11-2154 Remove & Store Salvaged Components 2 2 04-Sep-19 05-Sep-19
C-T11-2153 Demo Misc MEP 7 7 06-Sep-19 16-Sep-19
C-T11-1640 Demo Select Plaster for MEPF 2 2 17-Sep-19 18-Sep-19
C-T11-1660 Rough-In Elec in Conf/Foyer 5 5 19-Sep-19 25-Sep-19
C-T11-1670 Rough-In Fire Suppression 5 5 19-Sep-19 25-Sep-19
C-T11-1710 Patch and Repair Plaster 20 20 26-Sep-19 23-Oct-19
C-T11-1830 Final Paint 5 5 24-Oct-19 30-Oct-19
C-T11-1870 Trim Out MEPF Devices 4 4 31-Oct-19 05-Nov-19
C-T11-1900 Decorative Paint 5 40 06-Nov-19 06-Jan-20
C-T11-2159 Install Refinished Light Fixtures 2 2 12-Mar-20 13-Mar-20
C-T11-2157 Remove Scaffold 2 2 16-Mar-20 17-Mar-20
C-T11-1980 Install Carpet/Rug 2 2 18-Mar-20 19-Mar-20
C-T11-2000 Complete MCC Punch - Blue Room 4 4 20-Mar-20 25-Mar-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Install Elevator
Hang Doors & Install Hardware
Install Wainscot
Hang Heat Pumps per ASI 27
RI and Insulate Heat Pumps MEP per ASI 27
OMES Activate Security & Card Access
Install Controls for Heat Pumps per ASI 27
Finish Ceiling at Heat Pumps per ASI 27
80% Fire Marshal Inspection
Install Glazing
Final Paint
Test & Balance
Install Elevator Machine Room equipment
Elevator Inspection
Decorative Paint
Install Refinished Light Fixtures
Complete MCC / FSB Punch List
100% Fire Marshal Inspection (Final)
Complete AE1 / Owner Punch List
Owner Move In
Owner Move Out
Make Safe
Restore Marble
Protect Marble
Install Scaffold
Remove & Store Salvaged Components
Demo Misc MEP
Demo Select Plaster for MEPF
Rough-In Elec in Conf/Foyer
Rough-In Fire Suppression
Patch and Repair Plaster
Final Paint
Trim Out MEPF Devices
Decorative Paint
Install Refinished Light Fixtures
Remove Scaffold
Install Carpet/Rug
Complete MCC Punch - Blue Room
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 18 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T11-2030 Complete AE1/Owner Punch - Blue Room 3 3 26-Mar-20 30-Mar-20
C-T11-2040 Turnover - Blue Room 0 0 30-Mar-20
2nd Floor Court of Criminal Appeals2nd Floor Court of Criminal Appeals250 107 19-Feb-19 A 19-Nov-19
Material ProcurementMaterial Procurement99 99 16-May-19 A 07-Nov-19
OAU & Heat PumpsOAU & Heat Pumps30 6 16-May-19 A 27-Jun-19
P-T12-1080 Fab & Deliver - Grilles 30 6 16-May-19 A 27-Jun-19
Light FixturesLight Fixtures40 40 15-Aug-19 10-Oct-19
P-T12-1252 Fab & Deliver - Lighting 40 40 15-Aug-19 10-Oct-19
Floor CoveringFloor Covering60 60 15-Aug-19 07-Nov-19
P-T12-1253 Fab & Deliver Flooring - Carpet 60 60 15-Aug-19 07-Nov-19
MillworkMillwork20 20 15-Aug-19 12-Sep-19
P-T12-1254 Fab & Deliver - Millwork 20 20 15-Aug-19 12-Sep-19
ConstructionConstruction250 107 19-Feb-19 A 19-Nov-19
Schedule Driven MilestonesSchedule Driven Milestones0 0 19-Nov-19 19-Nov-19
M-T12-1000 Interim Substantial Completion - 2nd Floor Court of Criminal Appeals 0 0 19-Nov-19
Construction Phase SummariesConstruction Phase Summaries359 153 19-Feb-19 A 19-Nov-19
S-T12-1000 Construction - 2nd Floor Court of Criminal Appeals 359 153 19-Feb-19 A 19-Nov-19
Conference Room / MezzanineConference Room / Mezzanine131 107 30-May-19 A 19-Nov-19
C-T12-1402 FSB Redesign Court of Criminal Appeals 45 29 30-May-19 A 31-Jul-19
C-T12-1403 Owner Review Redesign Court of Criminal Appeals 10 10 01-Aug-19 14-Aug-19
C-T12-1160 Install Temp Mechanical Piping 3 3 15-Aug-19 19-Aug-19
C-T12-1170 Install Mechanical Duct 5 5 20-Aug-19 26-Aug-19
C-T12-1180 Insulate Mech 5 5 27-Aug-19 03-Sep-19
C-T12-1210 Frame Hardlid Ceiling 2 2 04-Sep-19 05-Sep-19
C-T12-1220 Rough In MEPF 5 5 06-Sep-19 12-Sep-19
C-T12-1260 80% Fire Marshal Inspection 0 0 12-Sep-19
C-T12-1270 Overhead Inspection 0 0 12-Sep-19
C-T12-1280 Hang / Tape / Prime 5 5 13-Sep-19 19-Sep-19
C-T12-1290 Start Up Heat Pumps 1 1 20-Sep-19 20-Sep-19
C-T12-1291 Millwork 2 2 20-Sep-19 23-Sep-19
C-T12-1310 Trim Out MEPF 5 5 20-Sep-19 26-Sep-19
C-T12-1320 Final Paint 2 2 27-Sep-19 30-Sep-19
C-T12-1330 Test & Balance 2 2 27-Sep-19 30-Sep-19
C-T12-1340 Hang Stained Glass Fixture 1 1 01-Oct-19 01-Oct-19
C-T12-1350 Install Border Carpet 2 2 08-Nov-19 11-Nov-19
C-T12-1360 Complete MCC / FSB Punchlist 2 2 12-Nov-19 13-Nov-19
C-T12-1370 Final Clean 2 2 14-Nov-19 15-Nov-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Complete AE1/Owner Punch - Blue Room
Turnover - Blue Room
Fab & Deliver - Grilles
Fab & Deliver - Lighting
Fab & Deliver Flooring - Carpet
Fab & Deliver - Millwork
Interim Substantial Completion - 2nd Floor Court of Criminal Appeals
Construction - 2nd Floor Court of Criminal Appeals
FSB Redesign Court of Criminal Appeals
Owner Review Redesign Court of Criminal Appeals
Install Temp Mechanical Piping
Install Mechanical Duct
Insulate Mech
Frame Hardlid Ceiling
Rough In MEPF
80% Fire Marshal Inspection
Overhead Inspection
Hang / Tape / Prime
Start Up Heat Pumps
Millwork
Trim Out MEPF
Final Paint
Test & Balance
Hang Stained Glass Fixture
Install Border Carpet
Complete MCC / FSB Punchlist
Final Clean
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 19 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T12-1380 Complete AE1 / Owner Punchlist 2 2 18-Nov-19 19-Nov-19
C-T12-1390 100% Fire Marshal Inspections 0 0 19-Nov-19
C-T12-1400 Owner Move In 0 0 19-Nov-19
CourtroomCourtroom49 49 04-Sep-19 11-Nov-19
C-T12-1190 Remove Existing Fixtures & Grilles 5 5 04-Sep-19 10-Sep-19
C-T12-1200 Patch Plaster and Paint 5 5 04-Sep-19 10-Sep-19
C-T12-1240 Re-Install Gates 2 2 11-Sep-19 12-Sep-19
C-T12-1250 Install New Grilles 2 2 11-Sep-19 12-Sep-19
C-T12-1230 Install New Light Fixtures 2 2 11-Oct-19 14-Oct-19
C-T12-1300 Install Border Carpet 2 2 08-Nov-19 11-Nov-19
2nd Floor Judicial / Supreme Court2nd Floor Judicial / Supreme Court296 119 04-Feb-19 A 09-Dec-19
Material ProcurementMaterial Procurement270 114 22-Feb-19 A 02-Dec-19
OAU & Heat PumpsOAU & Heat Pumps101 18 15-Apr-19 A 16-Jul-19
P-T13-1080 Fab & Deliver - Grilles 20 18 15-Apr-19 A 16-Jul-19
P-T13-1487 Scan & Fabricate Historic Grilles 60 18 04-Jun-19 A 16-Jul-19
Light FixturesLight Fixtures270 114 15-Mar-19 A 02-Dec-19
P-T13-1100 Fab & Deliver - Regular Lighting 270 30 15-Mar-19 A 01-Aug-19
P-T13-1498 Fab & Deliver - Historic Lighting 182 114 15-Mar-19 A 02-Dec-19
Casework & Wood TrimCasework & Wood Trim100 35 22-Feb-19 A 08-Aug-19
P-T13-1030 MCC Receive/Review Submittal - Millwork 3 3 22-Feb-19 A 24-Jun-19
P-T13-1070 AE2(FSB) Receive/Review Submittal - Millwork 10 6 24-Jun-19 01-Jul-19
P-T13-1489 Fab & Deliver - Base / Case / Crown 15 15 24-Jun-19 15-Jul-19
P-T13-1120 Fab & Deliver - Millwork 20 20 02-Jul-19 30-Jul-19
P-T13-1490 MCC Contract - Wood Refinishing 15 15 20-Jun-19 11-Jul-19
P-T13-1485 Refinish Wood Pews 20 20 12-Jul-19 08-Aug-19
Floor CoveringFloor Covering60 47 16-Apr-19 A 26-Aug-19
P-T13-1110 Fab & Deliver Flooring - Carpet 60 47 16-Apr-19 A 26-Aug-19
Doors / HardwareDoors / Hardware35 3 26-Feb-19 A 24-Jun-19
P-T13-1496 Fab & Deliver - Doors & Hardware 35 3 26-Feb-19 A 24-Jun-19
ConstructionConstruction220 119 04-Feb-19 A 09-Dec-19
Schedule Driven MilestonesSchedule Driven Milestones0 0 23-Oct-19 23-Oct-19
M-T13-1000 Interim Substantial Completion - 2nd Floor Judicial 0 0 23-Oct-19
Construction Phase SummariesConstruction Phase Summaries302 126 04-Feb-19 A 23-Oct-19
S-T13-1000 Construction - 2nd Floor Judicial 302 126 04-Feb-19 A 23-Oct-19
Supreme CourtSupreme Court123 119 21-May-19 A 09-Dec-19
C-T13-1427 Decorative Paint 60 39 21-May-19 A 14-Aug-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Complete AE1 / Owner Punchlist
100% Fire Marshal Inspections
Owner Move In
Remove Existing Fixtures & Grilles
Patch Plaster and Paint
Re-Install Gates
Install New Grilles
Install New Light Fixtures
Install Border Carpet
Fab & Deliver - Grilles
Scan & Fabricate Historic Grilles
Fab & Deliver - Regular Lighting
Fab & Deliver - Historic Lighting
MCC Receive/Review Submittal - Millwork
AE2(FSB) Receive/Review Submittal - Millwork
Fab & Deliver - Base / Case / Crown
Fab & Deliver - Millwork
MCC Contract - Wood Refinishing
Refinish Wood Pews
Fab & Deliver Flooring - Carpet
Fab & Deliver - Doors & Hardware
Interim Substantial Completion - 2nd Floor Judicial
Construction - 2nd Floor Judicial
Decorative Paint
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 20 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T13-1424 Install New Grilles 3 3 17-Jul-19 19-Jul-19
C-T13-1504 Install New Historic Replica Grilles 3 3 17-Jul-19 19-Jul-19
C-T13-1474 80% Fire Marshal Inspection 0 0 02-Aug-19
C-T13-1481 Install Light Fixtures 5 5 15-Aug-19 21-Aug-19
C-T13-1503 Trim Out MEPF / Device Out 5 5 15-Aug-19 21-Aug-19
C-T13-1491 Test and Balance 5 5 21-Aug-19 27-Aug-19
C-T13-1502 Remove Scaffold 5 5 22-Aug-19 28-Aug-19
C-T13-1431 Reinstall Wood Railing and Marble Base 4 4 29-Aug-19 04-Sep-19
C-T13-1419 Install New Ramp and Stairs 5 5 29-Aug-19 05-Sep-19
C-T13-1428 Install New Carpet 7 7 05-Sep-19 13-Sep-19
C-T13-1429 Refinish Wood Dais & Wood Railing 20 20 05-Sep-19 02-Oct-19
C-T13-1501 Rough In Electrical at Ramp and Stairs 5 5 06-Sep-19 12-Sep-19
C-T13-1486 Reinstall Wood Pews 2 2 16-Sep-19 17-Sep-19
C-T13-1432 Final Clean 5 5 03-Oct-19 09-Oct-19
C-T13-1475 Complete MCC / FSB Punchlist 5 5 10-Oct-19 16-Oct-19
C-T13-1476 Complete AE1 / Owner Punchlist 5 5 17-Oct-19 23-Oct-19
C-T13-1477 100% Fire Marshal Inspections 0 0 23-Oct-19
C-T13-1478 Owner Move In 0 0 23-Oct-19
C-T13-1505 Install Historic Light Fixtures 5 5 03-Dec-19 09-Dec-19
Mechanical and Storage RoomsMechanical and Storage Rooms51 47 14-Jun-19 A 26-Aug-19
C-T13-1433 Insulate Mech - Level 3 5 1 14-Jun-19 A 20-Jun-19
C-T13-1487 Remove Scaffold 1 1 21-Jun-19 21-Jun-19
C-T13-1488 Install Heat Pumps - Level 2 5 5 24-Jun-19 28-Jun-19
C-T13-1489 Rough In Fire Suppression - Level 2 6 6 01-Jul-19 09-Jul-19
C-T13-1490 Rough In Electrical - Level 2 10 10 01-Jul-19 15-Jul-19
C-T13-1492 Install Mechanical Duct - Level 2 5 5 16-Jul-19 22-Jul-19
C-T13-1493 Install Mechanical Piping - Level 2 5 5 23-Jul-19 29-Jul-19
C-T13-1494 Insulate Mech - Level 2 5 5 30-Jul-19 05-Aug-19
C-T13-1435 Seal Concrete 1 1 06-Aug-19 06-Aug-19
C-T13-1436 Install Base 1 1 07-Aug-19 07-Aug-19
C-T13-1437 Trim Out MEPF 3 3 08-Aug-19 12-Aug-19
C-T13-1438 Final Paint 5 5 13-Aug-19 19-Aug-19
C-T13-1439 Final Clean 5 5 20-Aug-19 26-Aug-19
RestroomsRestrooms48 47 19-Jun-19 A 26-Aug-19
C-T13-1440 Rough In Fire Suppression 5 1 19-Jun-19 A 20-Jun-19
C-T13-1441 Insulate Mechanical OH 5 4 19-Jun-19 A 25-Jun-19
C-T13-1442 Build Up Restroom Floor 3 3 21-Jun-19 25-Jun-19
C-T13-1443 Install Plumbing Below Floor 2 2 26-Jun-19 27-Jun-19
C-T13-1444 Install Sub Floor 1 1 28-Jun-19 28-Jun-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Install New Grilles
Install New Historic Replica Grilles
80% Fire Marshal Inspection
Install Light Fixtures
Trim Out MEPF / Device Out
Test and Balance
Remove Scaffold
Reinstall Wood Railing and Marble Base
Install New Ramp and Stairs
Install New Carpet
Refinish Wood Dais & Wood Railing
Rough In Electrical at Ramp and Stairs
Reinstall Wood Pews
Final Clean
Complete MCC / FSB Punchlist
Complete AE1 / Owner Punchlist
100% Fire Marshal Inspections
Owner Move In
Install Historic Light Fixtures
Insulate Mech - Level 3
Remove Scaffold
Install Heat Pumps - Level 2
Rough In Fire Suppression - Level 2
Rough In Electrical - Level 2
Install Mechanical Duct - Level 2
Install Mechanical Piping - Level 2
Insulate Mech - Level 2
Seal Concrete
Install Base
Trim Out MEPF
Final Paint
Final Clean
Rough In Fire Suppression
Insulate Mechanical OH
Build Up Restroom Floor
Install Plumbing Below Floor
Install Sub Floor
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 21 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T13-1445 Frame Walls 2 2 01-Jul-19 02-Jul-19
C-T13-1446 Rough In MEP in Wall 2 2 03-Jul-19 05-Jul-19
C-T13-1496 Insulate Plumbing In Wall 1 1 08-Jul-19 08-Jul-19
C-T13-1479 50% Fire Marshal Inspection 0 0 11-Jul-19
C-T13-1447 In Wall Inspec tion 1 1 12-Jul-19 12-Jul-19
C-T13-1448 Hang / Tape / Prime Sheetrock 3 3 15-Jul-19 17-Jul-19
C-T13-1449 Install Ceiling Access Grid 1 1 18-Jul-19 18-Jul-19
C-T13-1450 Rough In MEP in Ceiling 3 3 19-Jul-19 23-Jul-19
C-T13-1480 80% Fire Marshal Inspection 0 0 02-Aug-19
C-T13-1499 Overhead Inspection 1 1 05-Aug-19 05-Aug-19
C-T13-1451 Set Ceiling Tile 1 1 06-Aug-19 06-Aug-19
C-T13-1461 Trim Out MEPF / Ceiling Devices 2 2 07-Aug-19 08-Aug-19
C-T13-1462 Install Marble Tile 3 3 09-Aug-19 13-Aug-19
C-T13-1463 Install Plumbing Fixtures 3 3 14-Aug-19 16-Aug-19
C-T13-1470 Install Doors & Hardware 1 1 19-Aug-19 19-Aug-19
C-T13-1464 Install Bath Accessories / Mirror 2 2 20-Aug-19 21-Aug-19
C-T13-1465 Final Paint 2 2 22-Aug-19 23-Aug-19
C-T13-1466 Final Clean 1 1 26-Aug-19 26-Aug-19
Conference RoomConference Room48 48 20-Jun-19 27-Aug-19
C-T13-1404 Install Heat Pump 5 5 20-Jun-19 26-Jun-19
C-T13-1405 Rough In OH MEPF 7 7 27-Jun-19 08-Jul-19
C-T13-1403 Rough In MEP in Wall 3 3 08-Jul-19 10-Jul-19
C-T13-1406 Insulate Mech 5 5 09-Jul-19 15-Jul-19
C-T13-1452 In Wall Inspec tion 1 1 11-Jul-19 11-Jul-19
C-T13-1453 Hang / Tape / Prime Sheetrock 5 5 12-Jul-19 18-Jul-19
C-T13-1454 Frame Ceiling 4 4 19-Jul-19 24-Jul-19
C-T13-1455 Rough In MEPF in Ceiling 5 5 25-Jul-19 31-Jul-19
C-T13-1456 Overhead Inspection 2 2 01-Aug-19 02-Aug-19
C-T13-1457 Hang / Tape / Prime Sheetrock Ceilings 7 7 05-Aug-19 13-Aug-19
C-T13-1472 Install Millwork 2 2 14-Aug-19 15-Aug-19
C-T13-1458 Trim Out MEPF 3 3 14-Aug-19 16-Aug-19
C-T13-1460 Install Wood Base / Case / Crown 4 4 14-Aug-19 19-Aug-19
C-T13-1473 Install Plumbing Fixtures 1 1 16-Aug-19 16-Aug-19
C-T13-1459 Install Carpet 2 2 16-Aug-19 19-Aug-19
C-T13-1469 Install Doors & Hardware 1 1 20-Aug-19 20-Aug-19
C-T13-1467 Final Paint 3 3 21-Aug-19 23-Aug-19
C-T13-1468 Final Clean 2 2 26-Aug-19 27-Aug-19
2nd Floor House West2nd Floor House West219 139 09-Apr-19 A 08-Jan-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Frame Walls
Rough In MEP in Wall
Insulate Plumbing In Wall
50% Fire Marshal Inspection
In Wall Inspec tion
Hang / Tape / Prime Sheetrock
Install Ceiling Access Grid
Rough In MEP in Ceiling
80% Fire Marshal Inspection
Overhead Inspection
Set Ceiling Tile
Trim Out MEPF / Ceiling Devices
Install Marble Tile
Install Plumbing Fixtures
Install Doors & Hardware
Install Bath Accessories / Mirror
Final Paint
Final Clean
Install Heat Pump
Rough In OH MEPF
Rough In MEP in Wall
Insulate Mech
In Wall Inspec tion
Hang / Tape / Prime Sheetrock
Frame Ceiling
Rough In MEPF in Ceiling
Overhead Inspection
Hang / Tape / Prime Sheetrock Ceilings
Install Millwork
Trim Out MEPF
Install Wood Base / Case / Crown
Install Plumbing Fixtures
Install Carpet
Install Doors & Hardware
Final Paint
Final Clean
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 22 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
Material ProcurementMaterial Procurement76 43 09-Apr-19 A 20-Aug-19
OAU & Heat PumpsOAU & Heat Pumps20 16 13-Jun-19 A 12-Jul-19
P-T14-1016 Fab & Deliver - OAU & Heat Pumps 20 16 13-Jun-19 A 12-Jul-19
Light FixturesLight Fixtures30 31 09-Apr-19 A 02-Aug-19
P-T14-1015 Fab & Deliver - Lighting 30 31 09-Apr-19 A 02-Aug-19
Casework & Wood TrimCasework & Wood Trim32 8 23-Apr-19 A 01-Jul-19
P-T14-1010 AE2(FSB) Receive / Review Submittal - Base / Case / Crown 10 8 23-Apr-19 A 01-Jul-19
P-T14-1017 Fab & Deliver - Base / Case / Crown 20 8 23-Apr-19 A 01-Jul-19
Floor CoveringFloor Covering40 22 16-Apr-19 A 22-Jul-19
P-T14-1014 Fab & Deliver Flooring - Carpet 40 22 16-Apr-19 A 22-Jul-19
Doors / HardwareDoors / Hardware35 43 28-May-19 A 20-Aug-19
P-T14-1013 Fab & Deliver - Doors & Hardware 35 43 28-May-19 A 20-Aug-19
P-T14-1405 Fab & Deliver - Door Frames 15 23 28-May-19 A 23-Jul-19
MillworkMillwork30 8 23-Apr-19 A 01-Jul-19
P-T14-1012 Fab & Deliver - Millwork 30 8 23-Apr-19 A 01-Jul-19
ConstructionConstruction167 139 20-Jun-19 08-Jan-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 08-Jan-20 08-Jan-20
M-T14-1000 Interim Substantial Completion - 2nd Floor House West 0 0 08-Jan-20
Construction Phase SummariesConstruction Phase Summaries243 203 20-Jun-19 08-Jan-20
S-T14-1000 Construction - 2nd Floor House West 243 203 20-Jun-19 08-Jan-20
2nd Floor House West2nd Floor House West139 139 20-Jun-19 08-Jan-20
C-T14-1000 Owner Move Out 5 5 20-Jun-19 26-Jun-19
C-T14-1001 Pre Demo Conference 1 1 27-Jun-19 27-Jun-19
C-T14-1005 Remove Misc Millwork 2 2 27-Jun-19 28-Jun-19
C-T14-1002 Make Safe 3 3 27-Jun-19 01-Jul-19
C-T14-1006 Demo Ceiling Grid/Lights 8 8 01-Jul-19 11-Jul-19
C-T14-1007 Demo Doors and Frames 5 5 02-Jul-19 09-Jul-19
C-T14-1004 Demo Flooring and Base 5 5 02-Jul-19 09-Jul-19
C-T14-1008 Demo Misc Heat Pumps and Misc Ductwork 4 4 08-Jul-19 11-Jul-19
C-T14-1009 Abatement 3 3 12-Jul-19 16-Jul-19
C-T14-1010 Cut Openings for New Doors 3 3 17-Jul-19 19-Jul-19
C-T14-1011 Rough-In Overhead Ductwork 10 10 17-Jul-19 30-Jul-19
C-T14-1012 Hang Heat Pumps 5 5 19-Jul-19 25-Jul-19
C-T14-1013 Post Demo Conference 1 1 22-Jul-19 22-Jul-19
C-T14-1014 Infill Existing Openings 3 3 23-Jul-19 25-Jul-19
C-T14-1015 Frame Walls 3 3 23-Jul-19 25-Jul-19
C-T14-1016 Rough-In In wall 3 3 26-Jul-19 30-Jul-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Fab & Deliver - OAU & Heat Pumps
Fab & Deliver - Lighting
AE2(FSB) Receive / Review Submittal - Base / Case / Crown
Fab & Deliver - Base / Case / Crown
Fab & Deliver Flooring - Carpet
Fab & Deliver - Doors & Hardware
Fab & Deliver - Door Frames
Fab & Deliver - Millwork
Interim Substantial Completion - 2nd Floor House West
Construction - 2nd Floor House West
Owner Move Out
Pre Demo Conference
Remove Misc Millwork
Make Safe
Demo Ceiling Grid/Lights
Demo Doors and Frames
Demo Flooring and Base
Demo Misc Heat Pumps and Misc Ductwork
Abatement
Cut Openings for New Doors
Rough-In Overhead Ductwork
Hang Heat Pumps
Post Demo Conference
Infill Existing Openings
Frame Walls
Rough-In In wall
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 23 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T14-1017 Rough-In Overhead Electrical 10 10 26-Jul-19 08-Aug-19
C-T14-1020 Cut and Frame in New MEPF Openings in Corridors 4 4 07-Aug-19 12-Aug-19
C-T14-1019 Install Mechanical Controls 5 5 09-Aug-19 15-Aug-19
C-T14-1021 Relocate Fire Supression Branch Lines as necessary 5 5 09-Aug-19 15-Aug-19
C-T14-1022 Rough-In Plumbing 2 2 12-Aug-19 13-Aug-19
C-T14-1018 Insulate Mech/Plumbing 3 3 13-Aug-19 15-Aug-19
C-T14-1023 Patch Plaster 8 8 13-Aug-19 22-Aug-19
C-T14-1025 50% Fire Marshal Inspeciton 0 0 15-Aug-19
C-T14-1024 In Wall Inpsec tions 1 1 16-Aug-19 16-Aug-19
C-T14-1026 Install Sheetrock 8 8 19-Aug-19 28-Aug-19
C-T14-1027 Restore Marble Base 20 20 23-Aug-19 20-Sep-19
C-T14-1029 Install Door Frames 5 5 29-Aug-19 05-Sep-19
C-T14-1028 Frame Hard Lids 5 5 29-Aug-19 05-Sep-19
C-T14-1030 Rough-In MEPF in Hardlids 5 5 06-Sep-19 12-Sep-19
C-T14-1031 Tape/Bed/Paint 10 10 06-Sep-19 19-Sep-19
C-T14-1032 Install SDT/Base 2 2 12-Sep-19 13-Sep-19
C-T14-1033 Overhead Inspection at Hardlids 1 1 13-Sep-19 13-Sep-19
C-T14-1034 Set Electrical Panels 4 4 13-Sep-19 18-Sep-19
C-T14-1035 Install Sheetrock at Hardlids 5 5 16-Sep-19 20-Sep-19
C-T14-1036 Make Up Electrical Panels 6 6 19-Sep-19 26-Sep-19
C-T14-1037 Install Ceiling Grid 10 10 20-Sep-19 03-Oct-19
C-T14-1038 Restore Marble in Corridors 10 10 23-Sep-19 04-Oct-19
C-T14-1041 Conditioned Air Available 0 0 26-Sep-19
C-T14-1039 Permanent Power Available 0 0 26-Sep-19
C-T14-1040 Install Base/Case/Crown 20 20 27-Sep-19 24-Oct-19
C-T14-1043 Trim Out MEPF 10 10 04-Oct-19 17-Oct-19
C-T14-1042 Install New Lighting 10 10 04-Oct-19 17-Oct-19
C-T14-1044 Install Millwork 20 20 11-Oct-19 07-Nov-19
C-T14-1046 80% Fire Marshal Inspection 0 0 17-Oct-19
C-T14-1047 Overhead Inspection - Accessible Ceiling 3 3 18-Oct-19 22-Oct-19
C-T14-1045 Update LV Devices 5 5 18-Oct-19 24-Oct-19
C-T14-1048 Drop Ceiling Tiles 10 10 23-Oct-19 05-Nov-19
C-T14-1049 Install Carpet 15 15 01-Nov-19 21-Nov-19
C-T14-1050 Final Paint 10 10 08-Nov-19 21-Nov-19
C-T14-1051 Decorative Paint 10 10 22-Nov-19 09-Dec-19
C-T14-1052 Install Doors and Hardware 10 10 22-Nov-19 09-Dec-19
C-T14-1054 Security and Card Access 1 1 10-Dec-19 10-Dec-19
C-T14-1053 Install Shoe Molding 10 10 10-Dec-19 23-Dec-19
C-T14-1055 Test and Balance 15 15 10-Dec-19 31-Dec-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Rough-In Overhead Electrical
Cut and Frame in New MEPF Openings in Corridors
Install Mechanical Controls
Relocate Fire Supression Branch Lines as necessary
Rough-In Plumbing
Insulate Mech/Plumbing
Patch Plaster
50% Fire Marshal Inspeciton
In Wall Inpsec tions
Install Sheetrock
Restore Marble Base
Install Door Frames
Frame Hard Lids
Rough-In MEPF in Hardlids
Tape/Bed/Paint
Install SDT/Base
Overhead Inspection at Hardlids
Set Electrical Panels
Install Sheetrock at Hardlids
Make Up Electrical Panels
Install Ceiling Grid
Restore Marble in Corridors
Conditioned Air Available
Permanent Power Available
Install Base/Case/Crown
Trim Out MEPF
Install New Lighting
Install Millwork
80% Fire Marshal Inspection
Overhead Inspection - Accessible Ceiling
Update LV Devices
Drop Ceiling Tiles
Install Carpet
Final Paint
Decorative Paint
Install Doors and Hardware
Security and Card Access
Install Shoe Molding
Test and Balance
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 24 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T14-1056 MCC Punchlist 5 5 24-Dec-19 31-Dec-19
C-T14-1057 100% Fire Marshal Inspection 0 0 31-Dec-19
C-T14-1058 Complete Owner/AE1 Punchlist 5 5 02-Jan-20 08-Jan-20
C-T14-1059 Owner Move In 0 0 08-Jan-20
2nd Floor Senate North2nd Floor Senate North235 108 09-Apr-19 A 20-Nov-19
Material ProcurementMaterial Procurement64 72 09-Apr-19 A 01-Oct-19
Light FixturesLight Fixtures30 72 09-Apr-19 A 01-Oct-19
P-T15-1111 Fab & Deliver - Lighting 30 72 09-Apr-19 A 01-Oct-19
Doors / HardwareDoors / Hardware35 19 23-Apr-19 A 17-Jul-19
P-T15-1107 Fab & Deliver - Doors & Hardware 35 19 23-Apr-19 A 17-Jul-19
MillworkMillwork22 22 20-Jun-19 22-Jul-19
P-T15-1100 Price & Field Measure - Countertops 5 7 20-Jun-19 28-Jun-19
P-T15-1106 Fab & Deliver - Countertops 15 15 01-Jul-19 22-Jul-19
ConstructionConstruction168 83 26-Jul-19 20-Nov-19
Schedule Driven MilestonesSchedule Driven Milestones0 0 20-Nov-19 20-Nov-19
M-T15-1000 Interim Substantial Completion - 2nd Floor Senate North 0 0 20-Nov-19
Construction Phase SummariesConstruction Phase Summaries243 118 26-Jul-19 20-Nov-19
S-T15-1000 Construction - 2nd Floor Senate North 243 118 26-Jul-19 20-Nov-19
2nd Floor Senate North2nd Floor Senate North83 83 26-Jul-19 20-Nov-19
C-T15-1000 Owner Move Out 5 5 26-Jul-19 01-Aug-19
C-T15-1001 Pre Demo Conference 1 1 02-Aug-19 02-Aug-19
C-T15-1002 Make Safe 4 4 05-Aug-19 08-Aug-19
C-T15-1003 Demo Select Tile Flooring / Walls / Mechanical 4 4 09-Aug-19 14-Aug-19
C-T15-1004 Demo Ceiling Grid 3 3 15-Aug-19 19-Aug-19
C-T15-1005 Demo Select Plaster in Rotunda 3 3 20-Aug-19 22-Aug-19
C-T15-1006 Skim Coat Walls 5 5 23-Aug-19 29-Aug-19
C-T15-1007 Install Misc Mechanical / Plumbing Risers 5 5 23-Aug-19 29-Aug-19
C-T15-1019 OMES Install LV Cabling 5 5 23-Aug-19 29-Aug-19
C-T15-1012 Install Fire Suppression / FA 8 8 23-Aug-19 04-Sep-19
C-T15-1026 50% Fire Marshal Inspection 0 0 26-Aug-19
C-T15-1029 Install New Countertops 2 2 30-Aug-19 03-Sep-19
C-T15-1018 Install Base / Case / Crown 7 7 30-Aug-19 10-Sep-19
C-T15-1013 Install Ceiling Grid 5 5 05-Sep-19 11-Sep-19
C-T15-1024 Patch Plaster in Rotunda 10 10 05-Sep-19 18-Sep-19
C-T15-1016 Final Paint 5 5 11-Sep-19 17-Sep-19
C-T15-1027 80% Fire Marshal Inspection 0 0 11-Sep-19
C-T15-1017 Install Coat Hooks 2 2 18-Sep-19 19-Sep-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
MCC Punchlist
100% Fire Marshal Inspection
Complete Owner/AE1 Punchlist
Owner Move In
Fab & Deliver - Lighting
Fab & Deliver - Doors & Hardware
Price & Field Measure - Countertops
Fab & Deliver - Countertops
Interim Substantial Completion - 2nd Floor Senate North
Construction - 2nd Floor Senate North
Owner Move Out
Pre Demo Conference
Make Safe
Demo Select Tile Flooring / Walls / Mechanical
Demo Ceiling Grid
Demo Select Plaster in Rotunda
Skim Coat Walls
Install Misc Mechanical / Plumbing Risers
OMES Install LV Cabling
Install Fire Suppression / FA
50% Fire Marshal Inspection
Install New Countertops
Install Base / Case / Crown
Install Ceiling Grid
Patch Plaster in Rotunda
Final Paint
80% Fire Marshal Inspection
Install Coat Hooks
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 25 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T15-1025 Paint in Rotunda 5 5 19-Sep-19 25-Sep-19
C-T15-1011 Install Lights 5 5 02-Oct-19 08-Oct-19
C-T15-1014 OH Inspection 2 2 09-Oct-19 10-Oct-19
C-T15-1015 Drop Ceiling Tile 4 4 11-Oct-19 16-Oct-19
C-T15-1020 Test & Balance 5 5 17-Oct-19 23-Oct-19
C-T15-1010 Install Cabinet Doors and Drawer Fronts 10 10 17-Oct-19 30-Oct-19
C-T15-1008 Install Carpet 5 5 31-Oct-19 06-Nov-19
C-T15-1009 Install Doors & Hardware 5 5 07-Nov-19 13-Nov-19
C-T15-1021 Complete MCC / FSB Punch List 5 5 07-Nov-19 13-Nov-19
C-T15-1028 100% Fire Marshal Inspection 0 0 13-Nov-19
C-T15-1022 Complete AE1 / Owner Punch List 5 5 14-Nov-19 20-Nov-19
C-T15-1023 Owner Move In 0 0 20-Nov-19
2nd Floor Treasurer2nd Floor Treasurer244 205 25-Apr-19 A 09-Apr-20
Material ProcurementMaterial Procurement89 75 25-Apr-19 A 04-Oct-19
Light FixturesLight Fixtures30 11 25-Apr-19 A 05-Jul-19
P-T16-1015 Fab & Deliver - Lighting 30 11 25-Apr-19 A 05-Jul-19
Casework & Wood TrimCasework & Wood Trim63 59 06-Jun-19 A 12-Sep-19
P-T16-1004 MCC Receive / Review Submittal - Base / Case / Crown 5 7 06-Jun-19 A 28-Jun-19
P-T16-1010 AE2(FSB) Receive / Review Submittal - Base / Case / Crown 10 10 01-Jul-19 15-Jul-19
P-T16-1017 Fab & Deliver - Base / Case / Crown 20 40 18-Jul-19 12-Sep-19
Floor CoveringFloor Covering40 14 14-May-19 A 10-Jul-19
P-T16-1014 Fab & Deliver Flooring - Carpet 40 14 14-May-19 A 10-Jul-19
Doors / HardwareDoors / Hardware50 75 20-Jun-19 04-Oct-19
P-T16-1001 MCC Receive / Review Submittal - Doors & Hardware 5 5 20-Jun-19 26-Jun-19
P-T16-1007 AE2(FSB) Receive/Review Submittal - Doors & Hardware 10 10 27-Jun-19 11-Jul-19
P-T16-1013 Fab & Deliver - Doors & Hardware 35 60 12-Jul-19 04-Oct-19
P-T16-1406 Fab & Deliver - Door Frames 15 15 12-Jul-19 01-Aug-19
MillworkMillwork71 57 06-Jun-19 A 10-Sep-19
P-T16-1000 MCC Receive / Review Submittal - Millwork 5 7 06-Jun-19 A 28-Jun-19
P-T16-1006 AE2(FSB) Receive/Review Submittal - Millwork 10 10 01-Jul-19 15-Jul-19
P-T16-1012 Fab & Deliver - Millwork 30 40 16-Jul-19 10-Sep-19
ConstructionConstruction187 187 17-Jul-19 09-Apr-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 09-Apr-20 09-Apr-20
M-T16-1000 Interim Substantial Completion - 2nd Floor Treasurer 0 0 09-Apr-20
Construction Phase SummariesConstruction Phase Summaries180 268 17-Jul-19 09-Apr-20
S-T16-1000 Construction - 2nd Floor Treasurer 180 268 17-Jul-19 09-Apr-20
2nd Floor Treasurer2nd Floor Treasurer187 187 17-Jul-19 09-Apr-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Paint in Rotunda
Install Lights
OH Inspection
Drop Ceiling Tile
Test & Balance
Install Cabinet Doors and Drawer Fronts
Install Carpet
Install Doors & Hardware
Complete MCC / FSB Punch List
100% Fire Marshal Inspection
Complete AE1 / Owner Punch List
Owner Move In
Fab & Deliver - Lighting
MCC Receive / Review Submittal - Base / Case / Crown
AE2(FSB) Receive / Review Submittal - Base / Case / Crown
Fab & Deliver - Base / Case / Crown
Fab & Deliver Flooring - Carpet
MCC Receive / Review Submittal - Doors & Hardware
AE2(FSB) Receive/Review Submittal - Doors & Hardware
Fab & Deliver - Doors & Hardware
Fab & Deliver - Door Frames
MCC Receive / Review Submittal - Millwork
AE2(FSB) Receive/Review Submittal - Millwork
Fab & Deliver - Millwork
Interim Substantial Completion - 2nd Floor Treasurer
Construction - 2nd Floor Treasurer
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 26 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T16-1060 Owner Move Out 10 10 17-Jul-19* 30-Jul-19
C-T16-1061 Pre Demo Conference 1 1 31-Jul-19 31-Jul-19
C-T16-1064 Save/Salvage Misc Components 1 1 31-Jul-19 31-Jul-19
C-T16-1063 Remove and Store Storm Windows 3 3 31-Jul-19 02-Aug-19
C-T16-1062 Make Safe 5 5 31-Jul-19 06-Aug-19
C-T16-1065 Demo Doors/Frames 2 2 05-Aug-19 06-Aug-19
C-T16-1066 Demo Existing Store Front Components 2 2 05-Aug-19 06-Aug-19
C-T16-1067 Demo Flooring/Base 3 3 07-Aug-19 09-Aug-19
C-T16-1068 Demo Ceilings 4 4 07-Aug-19 12-Aug-19
C-T16-1070 Abatement 5 5 12-Aug-19 16-Aug-19
C-T16-1071 Demo All Mechanical 7 7 13-Aug-19 21-Aug-19
C-T16-1072 Post Demo Conference 1 1 22-Aug-19 22-Aug-19
C-T16-1073 Frame Walls 8 8 23-Aug-19 04-Sep-19
C-T16-1074 One Side Sheetrock - Room Side 9' 2 2 03-Sep-19 04-Sep-19
C-T16-1075 Tape Joints 1 1 05-Sep-19 05-Sep-19
C-T16-1076 R/I In Wall Electr ical - 12' or higher 5 5 06-Sep-19 12-Sep-19
C-T16-1077 R/I Remaining In Wall MEPF 6 6 10-Sep-19 17-Sep-19
C-T16-1078 2nd Side Sheetrock 2 2 13-Sep-19 16-Sep-19
C-T16-1079 Tape Joints 1 1 17-Sep-19 17-Sep-19
C-T16-1083 In Wall Inspec itions 1 1 18-Sep-19 18-Sep-19
C-T16-1081 Install Mechanical - Ducts 6 6 18-Sep-19 25-Sep-19
C-T16-1080 Hang Heat Pumps 8 8 18-Sep-19 27-Sep-19
C-T16-1082 R/I OVHD Elec 8 8 18-Sep-19 27-Sep-19
C-T16-1084 Insulate Mech 5 5 26-Sep-19 02-Oct-19
C-T16-1086 Install Heat Pump Controls 5 5 30-Sep-19 04-Oct-19
C-T16-1085 R/I Mechanical Piping 8 8 30-Sep-19 09-Oct-19
C-T16-1087 Insulate 4 4 10-Oct-19 15-Oct-19
C-T16-1088 R/I Fire Suppression 5 5 15-Oct-19 21-Oct-19
C-T16-1089 Install Cable Tray 3 3 16-Oct-19 18-Oct-19
C-T16-1090 50% Fire Marshal Inspeciton 0 0 21-Oct-19
C-T16-1091 Hang Sheetrock 8 8 22-Oct-19 31-Oct-19
C-T16-1092 Tape/Bed/Paint 15 15 29-Oct-19 18-Nov-19
C-T16-1094 Install Door Frames 5 5 01-Nov-19 07-Nov-19
C-T16-1095 Hang Electrical Panels 2 2 04-Nov-19 05-Nov-19
C-T16-1097 Make Up Elec Panels 4 4 06-Nov-19 11-Nov-19
C-T16-1098 Install Marble Thresholds 2 2 08-Nov-19 11-Nov-19
C-T16-1101 Permanent Power 0 0 11-Nov-19
C-T16-1104 Conditioned Air 0 0 14-Nov-19
C-T16-1093 Frame Hardlids 8 8 19-Nov-19 02-Dec-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Owner Move Out
Pre Demo Conference
Save/Salvage Misc Components
Remove and Store Storm Windows
Make Safe
Demo Doors/Frames
Demo Existing Store Front Components
Demo Flooring/Base
Demo Ceilings
Abatement
Demo All Mechanical
Post Demo Conference
Frame Walls
One Side Sheetrock - Room Side 9'
Tape Joints
R/I In Wall Electr ical - 12' or higher
R/I Remaining In Wall MEPF
2nd Side Sheetrock
Tape Joints
In Wall Inspec itions
Install Mechanical - Ducts
Hang Heat Pumps
R/I OVHD Elec
Insulate Mech
Install Heat Pump Controls
R/I Mechanical Piping
Insulate
R/I Fire Suppression
Install Cable Tray
50% Fire Marshal Inspeciton
Hang Sheetrock
Tape/Bed/Paint
Install Door Frames
Hang Electrical Panels
Make Up Elec Panels
Install Marble Thresholds
Permanent Power
Conditioned Air
Frame Hardlids
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 27 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T16-1100 Install LV Cabling 8 8 19-Nov-19 02-Dec-19
C-T16-1096 R/I in Hardlids 4 4 03-Dec-19 06-Dec-19
C-T16-1099 Overhead Inspection - Hardlids 1 1 09-Dec-19 09-Dec-19
C-T16-1102 Install Sheetrock - Hardlids 2 2 10-Dec-19 11-Dec-19
C-T16-1103 Tape/Bed/Paint Ceilings 10 10 12-Dec-19 26-Dec-19
C-T16-1107 Install Marble Tile/Base 4 4 27-Dec-19 02-Jan-20
C-T16-1105 Install Ceiling Grid 8 8 27-Dec-19 08-Jan-20
C-T16-1106 Install Millwork 20 20 27-Dec-19 24-Jan-20
C-T16-1108 Trim Out MEPF in Ceilings 12 12 03-Jan-20 20-Jan-20
C-T16-1110 80% Fire Marshal Inspection 1 1 21-Jan-20 21-Jan-20
C-T16-1111 Overhead Inspection - Accessible Ceiling 1 1 21-Jan-20 21-Jan-20
C-T16-1112 Drop Ceiling Tiles 10 10 22-Jan-20 04-Feb-20
C-T16-1109 Install Base/Case/Crown 20 20 27-Jan-20 21-Feb-20
C-T16-1113 Install Carpet 15 15 21-Feb-20 12-Mar-20
C-T16-1114 Install Doors and Hardware 10 10 13-Mar-20 26-Mar-20
C-T16-1115 Final Paint 10 10 13-Mar-20 26-Mar-20
C-T16-1117 Security/Card Access Install 3 3 27-Mar-20 31-Mar-20
C-T16-1116 Test & Balance 5 5 27-Mar-20 02-Apr-20
C-T16-1118 MCC Punch List 10 10 27-Mar-20 09-Apr-20
C-T16-1119 Owner/AE1 Punch List 5 5 03-Apr-20 09-Apr-20
C-T16-1120 100% Fire Marshal Inspection 0 0 09-Apr-20
C-T16-1121 Owner Move In 0 0 09-Apr-20
1st Floor Lt. Governor1st Floor Lt. Governor364 111 03-Jun-19 A 25-Nov-19
Material ProcurementMaterial Procurement75 75 24-Jun-19 08-Oct-19
OAU & Heat PumpsOAU & Heat Pumps35 35 24-Jun-19 12-Aug-19
P-T17-1000 MCC Receive / Review Submittal - OAU & Heat Pumps 5 5 24-Jun-19 28-Jun-19
P-T17-1001 AE2(FSB) Receive / Review Submittal - OAU & Heat Pumps 10 10 01-Jul-19 15-Jul-19
P-T17-1002 Fab & Deliver - OAU & Heat Pumps 20 20 16-Jul-19 12-Aug-19
Casework & Wood TrimCasework & Wood Trim57 57 24-Jun-19 12-Sep-19
P-T17-1003 MCC Receive / Review Submittal - Base / Case / Crown 5 5 24-Jun-19 28-Jun-19
P-T17-1004 AE2(FSB) Receive / Review Submittal - Base / Case / Crown 10 10 01-Jul-19 15-Jul-19
P-T17-1005 Fab & Deliver - Base / Case / Crown 40 40 18-Jul-19 12-Sep-19
Floor CoveringFloor Covering55 55 24-Jun-19 10-Sep-19
P-T17-1006 MCC Receive / Review Submittal - Carpet 5 5 24-Jun-19 28-Jun-19
P-T17-1007 AE2(FSB) Receive/Review Submittal - Carpet 10 10 01-Jul-19 15-Jul-19
P-T17-1008 Fab & Deliver Flooring - Carpet 40 40 16-Jul-19 10-Sep-19
Doors / HardwareDoors / Hardware75 75 24-Jun-19 08-Oct-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Install LV Cabling
R/I in Hardlids
Overhead Inspection - Hardlids
Install Sheetrock - Hardlids
Tape/Bed/Paint Ceilings
Install Marble Tile/Base
Install Ceiling Grid
Install Millwork
Trim Out MEPF in Ceilings
80% Fire Marshal Inspection
Overhead Inspection - Accessible Ceiling
Drop Ceiling Tiles
Install Base/Case/Crown
Install Carpet
Install Doors and Hardware
Final Paint
Security/Card Access Install
Test & Balance
MCC Punch List
Owner/AE1 Punch List
100% Fire Marshal Inspection
Owner Move In
MCC Receive / Review Submittal - OAU & Heat Pumps
AE2(FSB) Receive / Review Submittal - OAU & Heat Pumps
Fab & Deliver - OAU & Heat Pumps
MCC Receive / Review Submittal - Base / Case / Crown
AE2(FSB) Receive / Review Submittal - Base / Case / Crown
Fab & Deliver - Base / Case / Crown
MCC Receive / Review Submittal - Carpet
AE2(FSB) Receive/Review Submittal - Carpet
Fab & Deliver Flooring - Carpet
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 28 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-T17-1009 MCC Receive / Review Submittal - Doors & Hardware 5 5 24-Jun-19 28-Jun-19
P-T17-1010 AE2(FSB) Receive/Review Submittal - Doors & Hardware 10 10 01-Jul-19 15-Jul-19
P-T17-1011 Fab & Deliver - Doors & Hardware 60 60 16-Jul-19 08-Oct-19
P-T17-1012 Fab & Deliver - Door Frames 15 15 16-Jul-19 05-Aug-19
MillworkMillwork55 55 24-Jun-19 10-Sep-19
P-T17-1013 MCC Receive / Review Submittal - Millwork 5 5 24-Jun-19 28-Jun-19
P-T17-1014 AE2(FSB) Receive/Review Submittal - Millwork 10 10 01-Jul-19 15-Jul-19
P-T17-1015 Fab & Deliver - Millwork 40 40 16-Jul-19 10-Sep-19
ConstructionConstruction364 111 03-Jun-19 A 25-Nov-19
Schedule Driven MilestonesSchedule Driven Milestones0 0 22-Nov-19 22-Nov-19
M-T17-1000 Interim Substantial Completion - 1st Floor Lt. Governor 0 0 22-Nov-19
Construction Phase SummariesConstruction Phase Summaries180 156 03-Jun-19 A 22-Nov-19
S-T17-1000 Construction - 1st Floor Lt. Governor 180 156 03-Jun-19 A 22-Nov-19
1st Floor Lt. Governor1st Floor Lt. Governor244 111 03-Jun-19 A 25-Nov-19
C-T17-1050 Owner Move Out 5 2 03-Jun-19 A 21-Jun-19
C-T17-1003 Pre Demo Conference 1 1 24-Jun-19 24-Jun-19
C-T17-1000 Make Safe 5 5 24-Jun-19 28-Jun-19
C-T17-1001 Demo Ceilings 4 4 01-Jul-19 05-Jul-19
C-T17-1004 Demo Mechanical and Heat Pumps 3 3 08-Jul-19 10-Jul-19
C-T17-1002 Demo Flooring/Base 4 4 08-Jul-19 11-Jul-19
C-T17-1005 Abatement 5 5 12-Jul-19 18-Jul-19
C-T17-1006 Demo Remaining Items 5 5 19-Jul-19 25-Jul-19
C-T17-1007 Post Demo Conference 1 1 26-Jul-19 26-Jul-19
C-T17-1013 Saw Cut Opening for Door 1 1 26-Jul-19 26-Jul-19
C-T17-1008 Frame Walls 6 6 29-Jul-19 05-Aug-19
C-T17-1026 Install Marble Thresholds 3 3 01-Aug-19 05-Aug-19
C-T17-1011 Rough In Overhead Electrical 12 12 06-Aug-19 21-Aug-19
C-T17-1012 Rough In Walls 14 14 06-Aug-19 23-Aug-19
C-T17-1009 Install Heat Pumps and Ductwork 14 14 13-Aug-19 30-Aug-19
C-T17-1015 In Wall Inspec tion 1 1 26-Aug-19 26-Aug-19
C-T17-1052 Heat Pump Controls 1 1 26-Aug-19 26-Aug-19
C-T17-1010 Install Fire Suppression 3 3 03-Sep-19 05-Sep-19
C-T17-1051 OH Mech Piping 4 4 03-Sep-19 06-Sep-19
C-T17-1016 50% Fire Marshal Inspection 0 0 05-Sep-19
C-T17-1014 Insulate 5 5 09-Sep-19 13-Sep-19
C-T17-1017 Hang Sheetrock 5 5 16-Sep-19 20-Sep-19
C-T17-1037 Set Electrical Panels 1 1 23-Sep-19 23-Sep-19
C-T17-1024 Install Door Frames 3 3 23-Sep-19 25-Sep-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
MCC Receive / Review Submittal - Doors & Hardware
AE2(FSB) Receive/Review Submittal - Doors & Hardware
Fab & Deliver - Doors & Hardware
Fab & Deliver - Door Frames
MCC Receive / Review Submittal - Millwork
AE2(FSB) Receive/Review Submittal - Millwork
Fab & Deliver - Millwork
Interim Substantial Completion - 1st Floor Lt. Governor
Construction - 1st Floor Lt. Governor
Owner Move Out
Pre Demo Conference
Make Safe
Demo Ceilings
Demo Mechanical and Heat Pumps
Demo Flooring/Base
Abatement
Demo Remaining Items
Post Demo Conference
Saw Cut Opening for Door
Frame Walls
Install Marble Thresholds
Rough In Overhead Electrical
Rough In Walls
Install Heat Pumps and Ductwork
In Wall Inspec tion
Heat Pump Controls
Install Fire Suppression
OH Mech Piping
50% Fire Marshal Inspection
Insulate
Hang Sheetrock
Set Electrical Panels
Install Door Frames
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 29 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T17-1018 Tape/Bed/Paint 10 10 23-Sep-19 04-Oct-19
C-T17-1038 Make Up Electrical Panels 3 3 24-Sep-19 26-Sep-19
C-T17-1019 Frame Hardlids 2 2 25-Sep-19 26-Sep-19
C-T17-1040 Permanent Power 1 1 27-Sep-19 27-Sep-19
C-T17-1020 Rough In at Hardlids 2 2 27-Sep-19 30-Sep-19
C-T17-1039 Conditioned Air 1 1 30-Sep-19 30-Sep-19
C-T17-1021 Inspect Hard Lids 1 1 01-Oct-19 01-Oct-19
C-T17-1034 Install Millwork 20 20 01-Oct-19 28-Oct-19
C-T17-1022 Install Sheetrock Hard Lids 2 2 02-Oct-19 03-Oct-19
C-T17-1023 Tape/Bed/Paint Hardlids 3 3 04-Oct-19 08-Oct-19
C-T17-1031 Install SDT at IT Room 1 1 07-Oct-19 07-Oct-19
C-T17-1030 OMES Install LV Cabling 5 5 08-Oct-19 14-Oct-19
C-T17-1025 Install Base/Case/Crown 14 14 11-Oct-19 30-Oct-19
C-T17-1028 Install Ceiling Grid 2 2 15-Oct-19 16-Oct-19
C-T17-1029 Trim Out MEPF in Ceiling Grid 3 3 17-Oct-19 21-Oct-19
C-T17-1027 Install Marble Tile 4 4 17-Oct-19 22-Oct-19
C-T17-1041 Overhead Inspection 1 1 22-Oct-19 22-Oct-19
C-T17-1033 80% Fire Marshal Inspection 0 0 22-Oct-19
C-T17-1044 Install Ceiling Tiles 3 3 23-Oct-19 25-Oct-19
C-T17-1035 Install Countertops 2 2 29-Oct-19 30-Oct-19
C-T17-1032 Install Flooring 4 4 29-Oct-19 01-Nov-19
C-T17-1036 Set Fixtures 2 2 31-Oct-19 01-Nov-19
C-T17-1042 Final Paint 7 7 31-Oct-19 08-Nov-19
C-T17-1049 Install Doors & Hardware 3 3 04-Nov-19 06-Nov-19
C-T17-1043 Test and Balance 4 4 07-Nov-19 12-Nov-19
C-T17-1046 100% Fire Marshal Inspection 0 0 08-Nov-19
C-T17-1045 Complete MCC/FSB Punch List 5 5 11-Nov-19 15-Nov-19
C-T17-1047 Complete AE1/Owner Punch List 5 5 18-Nov-19 22-Nov-19
C-T17-1048 Owner Move In 1 1 25-Nov-19 25-Nov-19
3rd Floor House West3rd Floor House West233 138 09-Apr-19 A 07-Jan-20
Material ProcurementMaterial Procurement82 52 09-Apr-19 A 03-Sep-19
OAU & Heat PumpsOAU & Heat Pumps20 16 13-Jun-19 A 12-Jul-19
P-T18-1003 Fab & Deliver - OAU & Heat Pumps 20 16 13-Jun-19 A 12-Jul-19
Electrical Panel Boards @ Electrical RoomsElectrical Panel Boards @ Electrical Rooms35 27 20-Jun-19 29-Jul-19
P-T18-1004 MCC Receive / Review Submittal - Panel Boards 5 5 20-Jun-19 26-Jun-19
P-T18-1006 AE2(FSB) Receive / Review Submittal - Panel Boards 10 10 27-Jun-19 11-Jul-19
P-T18-1008 Release / Fab & Deliver Cans 8 8 02-Jul-19 12-Jul-19
P-T18-1026 Fab & Deliver - Panel Boards 20 12 12-Jul-19 29-Jul-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Tape/Bed/Paint
Make Up Electrical Panels
Frame Hardlids
Permanent Power
Rough In at Hardlids
Conditioned Air
Inspect Hard Lids
Install Millwork
Install Sheetrock Hard Lids
Tape/Bed/Paint Hardlids
Install SDT at IT Room
OMES Install LV Cabling
Install Base/Case/Crown
Install Ceiling Grid
Trim Out MEPF in Ceiling Grid
Install Marble Tile
Overhead Inspection
80% Fire Marshal Inspection
Install Ceiling Tiles
Install Countertops
Install Flooring
Set Fixtures
Final Paint
Install Doors & Hardware
Test and Balance
100% Fire Marshal Inspection
Complete MCC/FSB Punch List
Complete AE1/Owner Punch List
Owner Move In
Fab & Deliver - OAU & Heat Pumps
MCC Receive / Review Submittal - Panel Boards
AE2(FSB) Receive / Review Submittal - Panel Boards
Release / Fab & Deliver Cans
Fab & Deliver - Panel Boards
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 30 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
Light FixturesLight Fixtures30 52 09-Apr-19 A 03-Sep-19
P-T18-1028 Fab & Deliver - Lighting 30 52 09-Apr-19 A 03-Sep-19
Casework & Wood TrimCasework & Wood Trim52 17 23-Apr-19 A 15-Jul-19
P-T18-1059 AE2(FSB) Receive / Review Submittal - Base / Case / Crown 10 17 23-Apr-19 A 15-Jul-19
P-T18-1060 Fab & Deliver - Base / Case / Crown 40 17 23-Apr-19 A 15-Jul-19
Floor CoveringFloor Covering50 22 16-Apr-19 A 22-Jul-19
P-T18-1012 Fab & Deliver - Floor Covering 50 22 16-Apr-19 A 22-Jul-19
Doors / HardwareDoors / Hardware35 30 28-May-19 A 01-Aug-19
P-T18-1020 Fab & Deliver - Doors & Hardware 35 30 28-May-19 A 01-Aug-19
MillworkMillwork20 17 13-May-19 A 15-Jul-19
P-T18-1027 Fab & Deliver - Base / Case / Crown 20 17 13-May-19 A 15-Jul-19
ConstructionConstruction186 138 14-Jun-19 A 07-Jan-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 07-Jan-20 07-Jan-20
M-T18-1000 Interim Substantial Completion - 3rd Floor House West 0 0 07-Jan-20
Construction Phase SummariesConstruction Phase Summaries240 202 14-Jun-19 A 07-Jan-20
S-T18-1000 Construction - 3rd Floor House West 240 202 14-Jun-19 A 07-Jan-20
3rd Floor House West3rd Floor House West138 138 20-Jun-19 07-Jan-20
C-T18-1004 Install Temp Power / Lighting 10 10 20-Jun-19 03-Jul-19
C-T18-1006 Demolition 15 15 20-Jun-19 11-Jul-19
C-T18-1007 Asbestos Abatement 10 10 02-Jul-19 16-Jul-19
C-T18-1000 Test For Asbestos 2 2 05-Jul-19 08-Jul-19
C-T18-1001 Submit & File Asbestos Report with DOL 5 5 09-Jul-19 15-Jul-19
C-T18-1008 DOL Asbestos Inspection (Friable Material) 1 1 16-Jul-19 16-Jul-19
C-T18-1012 Frame Walls 10 10 17-Jul-19 30-Jul-19
C-T18-1013 O/H Electrical R.I.'s 10 10 17-Jul-19 30-Jul-19
C-T18-1015 O/H Mechanical R.I.'s 20 20 17-Jul-19 13-Aug-19
C-T18-1014 O/H Ductwork R.I.'s 23 23 17-Jul-19 16-Aug-19
C-T18-1016 O/H Plumbing R.I.'s 15 15 25-Jul-19 14-Aug-19
C-T18-1017 O/H Sprinkler Rough In 25 25 01-Aug-19 05-Sep-19
C-T18-1021 Plumbing In-Wall Rough In's 3 3 31-Jul-19 02-Aug-19
C-T18-1022 Frame Ceilings & Soffits 20 20 26-Jul-19 22-Aug-19
C-T18-1024 Electrical In-Wall Rough In's 15 15 30-Jul-19 19-Aug-19
C-T18-1019 Insulate Mechanical 10 10 19-Aug-19 30-Aug-19
C-T18-1025 50% Fire Marshal Inspection 0 0 20-Aug-19
C-T18-1026 MEP In-Wall Inspection 2 2 03-Sep-19 04-Sep-19
C-T18-1023 Frame & Plaster Ceilings @ Corridors 20 20 06-Sep-19 03-Oct-19
C-T18-1029 Sheetrock Walls & Soffits 10 10 18-Sep-19 01-Oct-19
C-T18-1030 Tape / Bed / Prime & 1st Coat Paint Walls-Ceilings-Soffits 15 15 24-Sep-19 14-Oct-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Fab & Deliver - Lighting
AE2(FSB) Receive / Review Submittal - Base / Case / Crown
Fab & Deliver - Base / Case / Crown
Fab & Deliver - Floor Covering
Fab & Deliver - Doors & Hardware
Fab & Deliver - Base / Case / Crown
Interim Substantial Completion - 3rd Floor House West
Construction - 3rd Floor House West
Install Temp Power / Lighting
Demolition
Asbestos Abatement
Test For Asbestos
Submit & File Asbestos Report with DOL
DOL Asbestos Inspection (Friable Material)
Frame Walls
O/H Electrical R.I.'s
O/H Mechanical R.I.'s
O/H Ductwork R.I.'s
O/H Plumbing R.I.'s
O/H Sprinkler Rough In
Plumbing In-Wall Rough In's
Frame Ceilings & Soffits
Electrical In-Wall Rough In's
Insulate Mechanical
50% Fire Marshal Inspection
MEP In-Wall Inspection
Frame & Plaster Ceilings @ Corridors
Sheetrock Walls & Soffits
Tape / Bed / Prime & 1st Coat Paint Walls-Ceilings-Soffits
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 31 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T18-1034 Marble Restoration 20 20 01-Oct-19 28-Oct-19
C-T18-1041 LV Cabling Complete (By Owner) 0 0 01-Oct-19
C-T18-1032 Door Frames 6 6 09-Oct-19 16-Oct-19
C-T18-1031 Install Ceiling Grid w/ Borders 11 11 15-Oct-19 29-Oct-19
C-T18-1036 Install Wood Trim 14 14 17-Oct-19 05-Nov-19
C-T18-1042 Install Casework 15 15 25-Oct-19 14-Nov-19
C-T18-1033 Grills / Diffusers 6 6 28-Oct-19 04-Nov-19
C-T18-1040 MEP Trimout 15 15 01-Nov-19 21-Nov-19
C-T18-1043 Install Carpet 20 20 15-Nov-19 16-Dec-19
C-T18-1048 Install Granite Tops 5 5 18-Nov-19 22-Nov-19
C-T18-1039 80% Fire Marshal Inspection 0 0 21-Nov-19
C-T18-1038 O/H MEP & Sprinkler Inspections 4 4 22-Nov-19 27-Nov-19
C-T18-1047 Drop Ceiling Tile 5 5 02-Dec-19 06-Dec-19
C-T18-1046 Install Doors & Hardware 9 9 09-Dec-19 19-Dec-19
C-T18-1052 Touchup Paint 3 3 13-Dec-19 17-Dec-19
C-T18-1044 Install Side Light Glass 1 1 17-Dec-19 17-Dec-19
C-T18-1049 Final Paint 9 9 17-Dec-19 30-Dec-19
C-T18-1050 Test & Balance 8 8 18-Dec-19 30-Dec-19
C-T18-1053 100% Fire Marshal Inspection 0 0 20-Dec-19
C-T18-1045 Complete MCC / FSB Punch List 5 5 23-Dec-19 30-Dec-19
C-T18-1054 Complete AE1 / Owner Punch List 5 5 31-Dec-19 07-Jan-20
3rd Floor Senate North3rd Floor Senate North240 240 20-Jun-19 14-Feb-20
ConstructionConstruction240 240 20-Jun-19 14-Feb-20
Construction Phase SummariesConstruction Phase Summaries240 240 20-Jun-19 14-Feb-20
S-T19-1000 Construction - 3rd Floor Senate North 240 240 20-Jun-19 14-Feb-20
4th Floor Senate North4th Floor Senate North124 25 25-Mar-19 A 25-Jul-19
Material ProcurementMaterial Procurement35 7 26-Apr-19 A 28-Jun-19
Doors / HardwareDoors / Hardware35 7 26-Apr-19 A 28-Jun-19
P-T20-1007 Fab & Deliver - Doors & Hardware 35 7 26-Apr-19 A 28-Jun-19
ConstructionConstruction124 25 25-Mar-19 A 25-Jul-19
Schedule Driven MilestonesSchedule Driven Milestones0 0 25-Jul-19 25-Jul-19
M-T20-1000 Interim Substantial Completion - 4th Floor Senate North 0 0 25-Jul-19
Construction Phase SummariesConstruction Phase Summaries177 36 25-Mar-19 A 25-Jul-19
S-T20-1000 Construction - 4th Floor Senate North 177 36 25-Mar-19 A 25-Jul-19
Senator OfficesSenator Offices41 25 10-Jun-19 A 25-Jul-19
C-T20-1038 Install Millwork / Countertops 5 1 10-Jun-19 A 20-Jun-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Marble Restoration
LV Cabling Complete (By Owner)
Door Frames
Install Ceiling Grid w/ Borders
Install Wood Trim
Install Casework
Grills / Diffusers
MEP Trimout
Install Carpet
Install Granite Tops
80% Fire Marshal Inspection
O/H MEP & Sprinkler Inspections
Drop Ceiling Tile
Install Doors & Hardware
Touchup Paint
Install Side Light Glass
Final Paint
Test & Balance
100% Fire Marshal Inspection
Complete MCC / FSB Punch List
Complete AE1 / Owner Punch List
Construction - 3rd Floor Senate North
Fab & Deliver - Doors & Hardware
Interim Substantial Completion - 4th Floor Senate North
Construction - 4th Floor Senate North
Install Millwork / Countertops
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 32 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T20-1035 Install Base / Case / Crown 5 2 17-Jun-19 A 21-Jun-19
C-T20-1025 50% Fire Marshal Inspection 0 0 20-Jun-19
C-T20-1040 80% Fire Marshal Inspection 0 0 20-Jun-19
C-T20-1032 Install Door Frames 2 2 20-Jun-19 21-Jun-19
C-T20-1026 Install Replica-Historic Door Frames 3 3 20-Jun-19 24-Jun-19
C-T20-1039 Install Plumbing Fixture 3 3 20-Jun-19 24-Jun-19
C-T20-1034 OMES Install LV Cabling 5 5 20-Jun-19 26-Jun-19
C-T20-1042 Install Carpet / LVT 5 5 24-Jun-19 28-Jun-19
C-T20-1028 Overhead Inspection 1 1 27-Jun-19 27-Jun-19
C-T20-1041 Drop Ceiling Tile 3 3 28-Jun-19 02-Jul-19
C-T20-1043 Re-Hang Storm Windows 2 2 01-Jul-19 02-Jul-19
C-T20-1044 Install Doors and Hardware 3 3 01-Jul-19 03-Jul-19
C-T20-1049 Final Paint 4 4 01-Jul-19 05-Jul-19
C-T20-1059 Paint in Corridor 4N.5 4 4 01-Jul-19 05-Jul-19
C-T20-1046 Install Wood Blinds 2 2 03-Jul-19 05-Jul-19
C-T20-1048 Activate Security & Card Access 5 5 05-Jul-19 11-Jul-19
C-T20-1050 Test & Balance 5 5 05-Jul-19 11-Jul-19
C-T20-1045 Install Accessories 1 1 08-Jul-19 08-Jul-19
C-T20-1047 Install Signage 1 1 08-Jul-19 08-Jul-19
C-T20-1052 100% Fire Marshal Inspection 0 0 12-Jul-19
C-T20-1051 Complete MCC / FSB Punchlist 5 5 12-Jul-19 18-Jul-19
C-T20-1053 Complete AE1 / Owner Punch List 5 5 19-Jul-19 25-Jul-19
C-T20-1054 Owner Move In 0 0 25-Jul-19
4th Floor House West4th Floor House West208 152 09-Apr-19 A 27-Jan-20
Material ProcurementMaterial Procurement101 53 09-Apr-19 A 04-Sep-19
OAU & Heat PumpsOAU & Heat Pumps30 16 13-Jun-19 A 12-Jul-19
P-T30-1005 Fab & Deliver - Heat Pumps 30 16 13-Jun-19 A 12-Jul-19
Light FixturesLight Fixtures30 37 09-Apr-19 A 12-Aug-19
P-T30-1008 Fab & Deliver - Lighting 30 37 09-Apr-19 A 12-Aug-19
Floor CoveringFloor Covering40 22 16-Apr-19 A 22-Jul-19
P-T30-1021 Fab & Deliver Flooring - Carpet 40 22 16-Apr-19 A 22-Jul-19
Doors / HardwareDoors / Hardware70 53 28-May-19 A 04-Sep-19
P-T30-1012 Fab & Deliver - Door Frames 15 24 28-May-19 A 24-Jul-19
P-T30-1014 Fab & Deliver - Doors & Hardware 35 43 28-May-19 A 20-Aug-19
P-T30-1013 Fab & Deliver - Historic Door Frames 70 53 28-May-19 A 04-Sep-19
MillworkMillwork40 26 06-Jun-19 A 26-Jul-19
P-T30-1018 Fab & Deliver - MIllwork 40 26 06-Jun-19 A 26-Jul-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Install Base / Case / Crown
50% Fire Marshal Inspection
80% Fire Marshal Inspection
Install Door Frames
Install Replica-Historic Door Frames
Install Plumbing Fixture
OMES Install LV Cabling
Install Carpet / LVT
Overhead Inspection
Drop Ceiling Tile
Re-Hang Storm Windows
Install Doors and Hardware
Final Paint
Paint in Corridor 4N.5
Install Wood Blinds
Activate Security & Card Access
Test & Balance
Install Accessories
Install Signage
100% Fire Marshal Inspection
Complete MCC / FSB Punchlist
Complete AE1 / Owner Punch List
Owner Move In
Fab & Deliver - Heat Pumps
Fab & Deliver - Lighting
Fab & Deliver Flooring - Carpet
Fab & Deliver - Door Frames
Fab & Deliver - Doors & Hardware
Fab & Deliver - Historic Door Frames
Fab & Deliver - MIllwork
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 33 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-T30-1019 Fab & Deliver - Base / Case / Crown 20 26 06-Jun-19 A 26-Jul-19
ConstructionConstruction169 152 04-Jun-19 A 27-Jan-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 20-Jan-20 20-Jan-20
M-T30-1000 Interim Substantial Completion - 4th Floor House West 0 0 20-Jan-20
Construction Phase SummariesConstruction Phase Summaries245 215 04-Jun-19 A 20-Jan-20
S-T30-1000 Construction - 4th Floor House West 245 215 04-Jun-19 A 20-Jan-20
4th Floor House West4th Floor House West152 152 20-Jun-19 27-Jan-20
C-T30-1012 Install Temp Water 2 2 20-Jun-19 21-Jun-19
C-T30-1008 Install Temp Power 5 5 20-Jun-19 26-Jun-19
C-T30-1005 Demo Ceilings 15 15 20-Jun-19 11-Jul-19
C-T30-1013 Make Safe - Life Safety 3 3 27-Jun-19 01-Jul-19
C-T30-1011 Demo Masonry Walls 10 10 27-Jun-19 11-Jul-19
C-T30-1014 Asbestos Abatement 2 2 12-Jul-19 15-Jul-19
C-T30-1010 Demo Low Voltage IT 10 10 12-Jul-19 25-Jul-19
C-T30-1018 Abatement of Overhead and Floor Mastics 10 10 12-Jul-19 25-Jul-19
C-T30-1007 Protect and Identify Low Voltage Cabling to Remain 15 15 12-Jul-19 01-Aug-19
C-T30-1015 Demo Plumbing Risers 4 4 16-Jul-19 19-Jul-19
C-T30-1017 Demo Topping Slabs as Req'd 5 5 16-Jul-19 22-Jul-19
C-T30-1020 Infill Existing Trenches 5 5 26-Jul-19 01-Aug-19
C-T30-1019 Abatement Door Frames 5 5 26-Jul-19 01-Aug-19
C-T30-1016 Demo Overhead MEP 5 5 02-Aug-19 08-Aug-19
C-T30-1022 Layout & Frame Walls 10 10 02-Aug-19 15-Aug-19
C-T30-1025 Hang Heat Pumps 5 5 07-Aug-19 13-Aug-19
C-T30-1021 Rough-In Overhead Electric 15 15 07-Aug-19 27-Aug-19
C-T30-1029 Rough Fire-Suppression @ Hard Lids 10 10 09-Aug-19 22-Aug-19
C-T30-1023 Rough-In In Wall 12 12 09-Aug-19 26-Aug-19
C-T30-1030 Rough-In Fire Suppression 15 15 14-Aug-19 04-Sep-19
C-T30-1024 Frame Hard Lids 5 5 16-Aug-19 22-Aug-19
C-T30-1027 Rough-In Mechanical Piping & Duct 8 8 16-Aug-19 27-Aug-19
C-T30-1026 Rough-In Electrical @ Hard Lids 8 8 16-Aug-19 27-Aug-19
C-T30-1031 Plaster in Historic Corridors 35 35 16-Aug-19 04-Oct-19
C-T30-1028 Insulate Mechanical 25 25 23-Aug-19 27-Sep-19
C-T30-1033 In-Wall Inspections 2 2 27-Aug-19 28-Aug-19
C-T30-1035 Hard Lid Overhead Inspection 1 1 28-Aug-19 28-Aug-19
C-T30-1036 Hang Sheetrock at Hardlids 5 5 29-Aug-19 05-Sep-19
C-T30-1032 50% Fire Marshal Inspection 0 0 04-Sep-19
C-T30-1034 Hang Sheetrock Walls 10 10 05-Sep-19 18-Sep-19
C-T30-1045 Install Door Frames 5 5 12-Sep-19 18-Sep-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Fab & Deliver - Base / Case / Crown
Interim Substantial Completion - 4th Floor House West
Construction - 4th Floor House West
Install Temp Water
Install Temp Power
Demo Ceilings
Make Safe - Life Safety
Demo Masonry Walls
Asbestos Abatement
Demo Low Voltage IT
Abatement of Overhead and Floor Mastics
Protect and Identify Low Voltage Cabling to Remain
Demo Plumbing Risers
Demo Topping Slabs as Req'd
Infill Existing Trenches
Abatement Door Frames
Demo Overhead MEP
Layout & Frame Walls
Hang Heat Pumps
Rough-In Overhead Electric
Rough Fire-Suppression @ Hard Lids
Rough-In In Wall
Rough-In Fire Suppression
Frame Hard Lids
Rough-In Mechanical Piping & Duct
Rough-In Electrical @ Hard Lids
Plaster in Historic Corridors
Insulate Mechanical
In-Wall Inspections
Hard Lid Overhead Inspection
Hang Sheetrock at Hardlids
50% Fire Marshal Inspection
Hang Sheetrock Walls
Install Door Frames
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 34 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T30-1038 Tape / Bed / Paint Sheetrock 15 15 12-Sep-19 02-Oct-19
C-T30-1040 OMES Install LV Cabling 5 5 19-Sep-19 25-Sep-19
C-T30-1046 Install Ceiling Grid with Borders 8 8 24-Sep-19 03-Oct-19
C-T30-1039 Install Controls for Heat Pumps 6 6 30-Sep-19 07-Oct-19
C-T30-1047 Overhead Device Out 5 5 01-Oct-19 07-Oct-19
C-T30-1052 Install Plumbing Fixtures 4 4 03-Oct-19 08-Oct-19
C-T30-1048 Install Marble Tile 5 5 03-Oct-19 09-Oct-19
C-T30-1041 80% Fire Marshal Inspection 0 0 03-Oct-19
C-T30-1037 Install Marble Thresholds and Base 5 5 07-Oct-19 11-Oct-19
C-T30-1042 Start Up of Heat Pumps 2 2 08-Oct-19 09-Oct-19
C-T30-1051 Above Ceiling Inspections 2 2 08-Oct-19 09-Oct-19
C-T30-1056 Install Bathroom Accessories 1 1 09-Oct-19 09-Oct-19
C-T30-1057 Drop Ceiling Tile 3 3 10-Oct-19 14-Oct-19
C-T30-1043 Install Base / Case / Crown 50 50 10-Oct-19 20-Dec-19
C-T30-1049 Restore Marble in Corridors 10 10 14-Oct-19 25-Oct-19
C-T30-1059 Hang Doors & Install Hardware 10 10 24-Oct-19 06-Nov-19
C-T30-1053 Install Glazing 20 20 24-Oct-19 20-Nov-19
C-T30-1044 Install Millwork 50 50 24-Oct-19 07-Jan-20
C-T30-1055 Test & Balance 14 14 25-Oct-19 13-Nov-19
C-T30-1058 OMES Activate Security & Card Access 10 10 31-Oct-19 13-Nov-19
C-T30-1050 Install Countertops 20 20 04-Nov-19 03-Dec-19
C-T30-1054 Final Paint 10 10 04-Dec-19 17-Dec-19
C-T30-1061 Install Carpet / LVT / SDT 15 15 30-Dec-19 20-Jan-20
C-T30-1060 Complete MCC / FSB Punch List 5 5 14-Jan-20 20-Jan-20
C-T30-1063 100% Fire Marshal Inspection (Final) 0 0 20-Jan-20
C-T30-1062 Complete AE1 / Owner Punch List 5 5 21-Jan-20 27-Jan-20
C-T30-1064 Owner Move In 0 0 27-Jan-20
5th Floor House West5th Floor House West208 149 09-Apr-19 A 22-Jan-20
Material ProcurementMaterial Procurement101 72 09-Apr-19 A 01-Oct-19
OAU & Heat PumpsOAU & Heat Pumps30 16 13-Jun-19 A 12-Jul-19
P-T31-1006 Fab & Deliver - Heat Pumps 30 16 13-Jun-19 A 12-Jul-19
Light FixturesLight Fixtures30 72 09-Apr-19 A 01-Oct-19
P-T31-1009 Fab & Deliver - Lighting 30 72 09-Apr-19 A 01-Oct-19
Floor CoveringFloor Covering40 22 16-Apr-19 A 22-Jul-19
P-T31-1021 Fab & Deliver Flooring - Carpet 40 22 16-Apr-19 A 22-Jul-19
Doors / HardwareDoors / Hardware70 53 28-May-19 A 04-Sep-19
P-T31-1014 Fab & Deliver - Door Frames 15 24 28-May-19 A 24-Jul-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Tape / Bed / Paint Sheetrock
OMES Install LV Cabling
Install Ceiling Grid with Borders
Install Controls for Heat Pumps
Overhead Device Out
Install Plumbing Fixtures
Install Marble Tile
80% Fire Marshal Inspection
Install Marble Thresholds and Base
Start Up of Heat Pumps
Above Ceiling Inspections
Install Bathroom Accessories
Drop Ceiling Tile
Install Base / Case / Crown
Restore Marble in Corridors
Hang Doors & Install Hardware
Install Glazing
Install Millwork
Test & Balance
OMES Activate Security & Card Access
Install Countertops
Final Paint
Install Carpet / LVT / SDT
Complete MCC / FSB Punch List
100% Fire Marshal Inspection (Final)
Complete AE1 / Owner Punch List
Owner Move In
Fab & Deliver - Heat Pumps
Fab & Deliver - Lighting
Fab & Deliver Flooring - Carpet
Fab & Deliver - Door Frames
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 35 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-T31-1013 Fab & Deliver - Doors & Hardware 35 43 28-May-19 A 20-Aug-19
P-T31-1012 Fab & Deliver - Historic Door Frames 70 53 28-May-19 A 04-Sep-19
MillworkMillwork71 40 09-Jun-19 A 15-Aug-19
P-T31-1000 MCC Receive / Review Submittal - Millwork 5 8 09-Jun-19 A 01-Jul-19
P-T31-1016 AE2(FSB) Receive / Review Submittal - Millwork 10 10 01-Jul-19 15-Jul-19
P-T31-1018 Fab & Deliver - Base / Case / Crown 20 33 01-Jul-19 15-Aug-19
P-T31-1019 Fab & Deliver - MIllwork 40 33 01-Jul-19 15-Aug-19
ConstructionConstruction169 149 03-Jun-19 A 22-Jan-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 15-Jan-20 15-Jan-20
M-T31-1000 Interim Substantial Completion - 5th Floor House West 0 0 15-Jan-20
Construction Phase SummariesConstruction Phase Summaries245 210 03-Jun-19 A 15-Jan-20
S-T31-1000 Construction - 5th Floor House West 245 210 03-Jun-19 A 15-Jan-20
5th Floor House West5th Floor House West149 149 20-Jun-19 22-Jan-20
C-T31-1007 Install Temp Power 2 2 20-Jun-19 21-Jun-19
C-T31-1012 Install Temp Water 2 2 20-Jun-19 21-Jun-19
C-T31-1010 Demo Low Voltage IT 10 10 20-Jun-19 03-Jul-19
C-T31-1011 Demo Masonry Walls 10 10 20-Jun-19 03-Jul-19
C-T31-1008 Protect and Identify Low Voltage Cabling to Remain 15 15 20-Jun-19 11-Jul-19
C-T31-1013 Make Safe - Life Safety 3 3 24-Jun-19 26-Jun-19
C-T31-1015 Abatement Door Frames 5 5 05-Jul-19 11-Jul-19
C-T31-1016 Asbestos Abatement 5 5 05-Jul-19 11-Jul-19
C-T31-1014 Abatement of Overhead and Floor Mastics 10 10 05-Jul-19 18-Jul-19
C-T31-1019 Demo Plumbing Risers 4 4 12-Jul-19 17-Jul-19
C-T31-1018 Demo Overhead MEP 7 7 12-Jul-19 22-Jul-19
C-T31-1017 Demo Topping Slabs as Req'd 5 5 19-Jul-19 25-Jul-19
C-T31-1020 Infill Existing Trenches 5 5 22-Jul-19 26-Jul-19
C-T31-1021 Layout & Frame Walls 15 15 22-Jul-19 09-Aug-19
C-T31-1026 Hang Heat Pumps 7 7 25-Jul-19 02-Aug-19
C-T31-1022 Rough-In Overhead Electric 15 15 25-Jul-19 14-Aug-19
C-T31-1025 Rough-In In Wall 18 18 29-Jul-19 21-Aug-19
C-T31-1029 Rough-In Fire Suppression 5 5 01-Aug-19 07-Aug-19
C-T31-1033 50% Fire Marshal Inspection 0 0 07-Aug-19
C-T31-1038 Install Marble Thresholds and Base 5 5 12-Aug-19 16-Aug-19
C-T31-1024 Frame Hard Lids 10 10 12-Aug-19 23-Aug-19
C-T31-1028 Rough-In Mechanical Piping & Duct 10 10 12-Aug-19 23-Aug-19
C-T31-1031 Rough Fire-Suppression @ Hard Lids 30 30 12-Aug-19 23-Sep-19
C-T31-1023 Plaster in Historic Corridors 80 80 12-Aug-19 04-Dec-19
C-T31-1048 Restore Marble in Corridors 10 10 19-Aug-19 30-Aug-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Fab & Deliver - Doors & Hardware
Fab & Deliver - Historic Door Frames
MCC Receive / Review Submittal - Millwork
AE2(FSB) Receive / Review Submittal - Millwork
Fab & Deliver - Base / Case / Crown
Fab & Deliver - MIllwork
Interim Substantial Completion - 5th Floor House West
Construction - 5th Floor House West
Install Temp Power
Install Temp Water
Demo Low Voltage IT
Demo Masonry Walls
Protect and Identify Low Voltage Cabling to Remain
Make Safe - Life Safety
Abatement Door Frames
Asbestos Abatement
Abatement of Overhead and Floor Mastics
Demo Plumbing Risers
Demo Overhead MEP
Demo Topping Slabs as Req'd
Infill Existing Trenches
Layout & Frame Walls
Hang Heat Pumps
Rough-In Overhead Electric
Rough-In In Wall
Rough-In Fire Suppression
50% Fire Marshal Inspection
Install Marble Thresholds and Base
Frame Hard Lids
Rough-In Mechanical Piping & Duct
Rough Fire-Suppression @ Hard Lids
Plaster in Historic Corridors
Restore Marble in Corridors
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 36 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T31-1027 Rough-In Electrical @ Hard Lids 10 10 19-Aug-19 30-Aug-19
C-T31-1030 Insulate Mechanical 25 25 19-Aug-19 23-Sep-19
C-T31-1046 Install Historic Door Frames 4 4 05-Sep-19 10-Sep-19
C-T31-1035 Hard Lid Overhead Inspection 1 1 24-Sep-19 24-Sep-19
C-T31-1032 In-Wall Inspections 2 2 24-Sep-19 25-Sep-19
C-T31-1041 Install Controls for Heat Pumps 6 6 24-Sep-19 01-Oct-19
C-T31-1036 Hang Sheetrock at Hardlids 5 5 25-Sep-19 01-Oct-19
C-T31-1034 Hang Sheetrock Walls 10 10 26-Sep-19 09-Oct-19
C-T31-1040 Start Up of Heat Pumps 2 2 02-Oct-19 03-Oct-19
C-T31-1044 Install Door Frames 5 5 03-Oct-19 09-Oct-19
C-T31-1037 Tape / Bed / Paint Sheetrock 20 20 03-Oct-19 30-Oct-19
C-T31-1039 OMES Install LV Cabling 10 10 10-Oct-19 23-Oct-19
C-T31-1054 Install Glazing 20 20 10-Oct-19 06-Nov-19
C-T31-1043 Install Base / Case / Crown 25 25 17-Oct-19 20-Nov-19
C-T31-1047 Install Ceiling Grid with Borders 8 5 22-Oct-19 28-Oct-19
C-T31-1049 Overhead Device Out 5 5 24-Oct-19 30-Oct-19
C-T31-1045 80% Fire Marshal Inspection 0 0 28-Oct-19
C-T31-1051 Above Ceiling Inspections 2 2 31-Oct-19 01-Nov-19
C-T31-1057 Hang Doors & Install Hardware 20 20 31-Oct-19 27-Nov-19
C-T31-1042 Install Millwork 25 25 31-Oct-19 06-Dec-19
C-T31-1053 Drop Ceiling Tile 3 3 04-Nov-19 06-Nov-19
C-T31-1058 OMES Activate Security & Card Access 5 5 07-Nov-19 13-Nov-19
C-T31-1052 Test & Balance 15 15 07-Nov-19 27-Nov-19
C-T31-1050 Install Countertops 5 5 03-Dec-19 09-Dec-19
C-T31-1059 Install Carpet / LVT / SDT 15 15 04-Dec-19 24-Dec-19
C-T31-1055 Final Paint 10 10 10-Dec-19 23-Dec-19
C-T31-1063 Historic Paint 10 10 24-Dec-19 08-Jan-20
C-T31-1056 Complete MCC / FSB Punch List 5 5 09-Jan-20 15-Jan-20
C-T31-1061 100% Fire Marshal Inspection (Final) 0 0 15-Jan-20
C-T31-1060 Complete AE1 / Owner Punch List 5 5 16-Jan-20 22-Jan-20
C-T31-1062 Owner Move In 0 0 22-Jan-20
6th Floor House West6th Floor House West212 176 16-Apr-19 A 28-Feb-20
Material ProcurementMaterial Procurement78 69 16-Apr-19 A 26-Sep-19
OAU & Heat PumpsOAU & Heat Pumps30 16 13-Jun-19 A 12-Jul-19
P-T32-1006 Fab & Deliver - Heat Pumps 30 16 13-Jun-19 A 12-Jul-19
Floor CoveringFloor Covering40 22 16-Apr-19 A 22-Jul-19
P-T32-1022 Fab & Deliver - Carpet 40 22 16-Apr-19 A 22-Jul-19
Doors / HardwareDoors / Hardware35 43 28-May-19 A 20-Aug-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Rough-In Electrical @ Hard Lids
Insulate Mechanical
Install Historic Door Frames
Hard Lid Overhead Inspection
In-Wall Inspections
Install Controls for Heat Pumps
Hang Sheetrock at Hardlids
Hang Sheetrock Walls
Start Up of Heat Pumps
Install Door Frames
Tape / Bed / Paint Sheetrock
OMES Install LV Cabling
Install Glazing
Install Base / Case / Crown
Install Ceiling Grid with Borders
Overhead Device Out
80% Fire Marshal Inspection
Above Ceiling Inspections
Hang Doors & Install Hardware
Install Millwork
Drop Ceiling Tile
OMES Activate Security & Card Access
Test & Balance
Install Countertops
Install Carpet / LVT / SDT
Final Paint
Historic Paint
Complete MCC / FSB Punch List
100% Fire Marshal Inspection (Final)
Complete AE1 / Owner Punch List
Owner Move In
Fab & Deliver - Heat Pumps
Fab & Deliver - Carpet
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 37 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-T32-1013 Fab & Deliver - Door Frames 15 24 28-May-19 A 24-Jul-19
P-T32-1021 Fab & Deliver - Doors & Hardware 35 43 28-May-19 A 20-Aug-19
MillworkMillwork55 52 20-Jun-19 03-Sep-19
P-T32-1015 Millwork Pricing & Submittal Prep 10 10 20-Jun-19 03-Jul-19
P-T32-1016 MCC Receive / Review Submittal - Millwork 5 5 05-Jul-19 11-Jul-19
P-T32-1019 Fab & Deliver - MIllwork 40 37 12-Jul-19 03-Sep-19
P-T32-1018 Fab & Deliver - Base / Case / Crown 20 37 12-Jul-19 03-Sep-19
ChairliftChairlift69 69 20-Jun-19 26-Sep-19
P-T32-1010 Pricing Chairlift 19 19 20-Jun-19 17-Jul-19
P-T32-1011 Chairlift Contracting & Submittal Prep 10 10 03-Jul-19 17-Jul-19
P-T32-1012 MCC Receive / Review Submittal - Chairlift 5 5 18-Jul-19 24-Jul-19
P-T32-1020 AE2(FSB) Receive / Review Submittal -Chairlift 10 10 25-Jul-19 07-Aug-19
P-T32-1023 Fab & Deliver - Chairlift 35 35 08-Aug-19 26-Sep-19
ConstructionConstruction203 176 20-Jun-19 28-Feb-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 21-Feb-20 21-Feb-20
M-T32-1000 Interim Substantial Completion - 6th Floor House West 0 0 21-Feb-20
Construction Phase SummariesConstruction Phase Summaries245 199 07-Aug-19 21-Feb-20
S-T32-1000 Construction - 6th Floor House West 245 199 07-Aug-19 21-Feb-20
6th Floor House West6th Floor House West176 176 20-Jun-19 28-Feb-20
C-T32-1000 Demo Overhead Abandoned MEP 10 10 07-Aug-19 20-Aug-19
C-T32-1001 Remove Scaffold 5 5 21-Aug-19 27-Aug-19
C-T32-1004 Install Spray Foam on Roof Decking 5 5 21-Aug-19 27-Aug-19
C-T32-1002 Post-Demo Conference 1 1 28-Aug-19 28-Aug-19
C-T32-1006 Layout, Frame Walls & Top Out High Walls 20 20 29-Aug-19 26-Sep-19
C-T32-1005 Frame Vaulted Ceiling 5 5 06-Sep-19 12-Sep-19
C-T32-1007 Rough-In Overhead Electric 5 5 11-Sep-19 17-Sep-19
C-T32-1039 Installation of Chairlift 5 5 27-Sep-19 03-Oct-19
C-T32-1013 Rough-In Overhead Mechanical 20 20 27-Sep-19 24-Oct-19
C-T32-1015 Rough-In Mechanical Piping 20 20 27-Sep-19 24-Oct-19
C-T32-1017 Insulate Mechanical 20 20 27-Sep-19 24-Oct-19
C-T32-1009 Complete Wall Framing 5 5 30-Sep-19 04-Oct-19
C-T32-1010 Frame Hard Lids 2 2 15-Oct-19 16-Oct-19
C-T32-1014 Rough-In Fire Suppression 8 8 15-Oct-19 24-Oct-19
C-T32-1012 Rough-In @ Hard Lids 4 4 17-Oct-19 22-Oct-19
C-T32-1011 Rough-In In Wall 10 10 25-Oct-19 07-Nov-19
C-T32-1008 50% Fire Marshal Inspection 0 0 07-Nov-19
C-T32-1016 Hardlids & In-Wall Inspections 1 1 08-Nov-19 08-Nov-19
C-T32-1069 Suspend Work Until Completion of House 2 - 5 0 0 11-Nov-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Fab & Deliver - Door Frames
Fab & Deliver - Doors & Hardware
Millwork Pricing & Submittal Prep
MCC Receive / Review Submittal - Millwork
Fab & Deliver - MIllwork
Fab & Deliver - Base / Case / Crown
Pricing Chairlift
Chairlift Contracting & Submittal Prep
MCC Receive / Review Submittal - Chairlift
AE2(FSB) Receive / Review Submittal -Chairlift
Fab & Deliver - Chairlift
Interim Substantial Completion - 6th Floor House West
Construction - 6th Floor House West
Demo Overhead Abandoned MEP
Remove Scaffold
Install Spray Foam on Roof Decking
Post-Demo Conference
Layout, Frame Walls & Top Out High Walls
Frame Vaulted Ceiling
Rough-In Overhead Electric
Installation of Chairlift
Rough-In Overhead Mechanical
Rough-In Mechanical Piping
Insulate Mechanical
Complete Wall Framing
Frame Hard Lids
Rough-In Fire Suppression
Rough-In @ Hard Lids
Rough-In In Wall
50% Fire Marshal Inspection
Hardlids & In-Wall Inspections
Suspend Work Until Completion of House 2 - 5
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 38 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T32-1070 Resume Work After Completion of House 2 - 5 0 0 20-Jan-20
C-T32-1018 Hang Sheetrock 4 4 21-Jan-20 24-Jan-20
C-T32-1019 Tape / Bed / Paint Sheetrock 5 5 23-Jan-20 29-Jan-20
C-T32-1030 Install Base / Case / Crown 10 10 27-Jan-20 07-Feb-20
C-T32-1024 Install Door Frames 10 10 27-Jan-20 07-Feb-20
C-T32-1022 Overhead Device Out 5 5 28-Jan-20 03-Feb-20
C-T32-1020 Install Ceiling Grid with Borders 1 1 30-Jan-20 30-Jan-20
C-T32-1021 Install Marble Tile @ Restroom 5 5 30-Jan-20 05-Feb-20
C-T32-1027 80% Fire Marshal Inspection 0 0 03-Feb-20
C-T32-1023 Above Ceiling Inspections 2 2 04-Feb-20 05-Feb-20
C-T32-1031 Drop Ceiling Tile 2 2 06-Feb-20 07-Feb-20
C-T32-1029 Install Bathroom Fixtures @ Restroom 2 2 06-Feb-20 07-Feb-20
C-T32-1026 Install Millwork 5 5 06-Feb-20 12-Feb-20
C-T32-1032 Hang Doors & Install Hardware 2 2 10-Feb-20 11-Feb-20
C-T32-1035 Install Carpet / LVT / SDT 10 10 10-Feb-20 21-Feb-20
C-T32-1033 Final Paint 10 10 10-Feb-20 21-Feb-20
C-T32-1037 Test & Balance 7 7 12-Feb-20 20-Feb-20
C-T32-1025 Install Countertops 3 3 13-Feb-20 17-Feb-20
C-T32-1034 Complete MCC / FSB Punch List 5 5 17-Feb-20 21-Feb-20
C-T32-1028 Install Breakroom Sinks & Fixtures 2 2 18-Feb-20 19-Feb-20
C-T32-1036 100% Fire Marshal Inspection (Final) 0 0 21-Feb-20
C-T32-1038 Complete AE1 / Owner Punch List 5 5 24-Feb-20 28-Feb-20
C-T32-1040 OMES Owner Move In 0 0 28-Feb-20
C-T32-1058 Pre-Demo Conference 1 1 20-Jun-19 20-Jun-19
C-T32-1059 Make Safe for Demo 5 5 21-Jun-19 27-Jun-19
C-T32-1060 Demo / Remove Ceiling 5 5 25-Jun-19 01-Jul-19
C-T32-1061 Install Temp Lighting 5 5 02-Jul-19 09-Jul-19
C-T32-1062 Install Temp Power 5 5 02-Jul-19 09-Jul-19
C-T32-1063 Demo / Remove Interior Walls 15 15 02-Jul-19 23-Jul-19
C-T32-1064 Demo / Remove Floor Finishes 5 5 17-Jul-19 23-Jul-19
C-T32-1065 File DOL Asbestos Removal Forms 10 10 24-Jul-19 06-Aug-19
C-T32-1068 Install Scaffold for Demo 10 10 24-Jul-19 06-Aug-19
C-T32-1067 Complete Overhead / Pipe Riser Abatement 10 10 07-Aug-19 20-Aug-19
C-T32-1066 Final DOL Abatement 0 0 20-Aug-19
419 A & B419 A & B177 177 02-Jan-20 26-Jun-20
ConstructionConstruction177 177 02-Jan-20 26-Jun-20
Construction Phase SummariesConstruction Phase Summaries177 177 02-Jan-20 26-Jun-20
S-T21-1000 Construction - 419 A & B 177 177 02-Jan-20* 26-Jun-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Resume Work After Completion of House 2 - 5
Hang Sheetrock
Tape / Bed / Paint Sheetrock
Install Base / Case / Crown
Install Door Frames
Overhead Device Out
Install Ceiling Grid with Borders
Install Marble Tile @ Restroom
80% Fire Marshal Inspection
Above Ceiling Inspections
Drop Ceiling Tile
Install Bathroom Fixtures @ Restroom
Install Millwork
Hang Doors & Install Hardware
Install Carpet / LVT / SDT
Final Paint
Test & Balance
Install Countertops
Complete MCC / FSB Punch List
Install Breakroom Sinks & Fixtures
100% Fire Marshal Inspection (Final)
Complete AE1 / Owner Punch List
OMES Owner Move In
Pre-Demo Conference
Make Safe for Demo
Demo / Remove Ceiling
Install Temp Lighting
Install Temp Power
Demo / Remove Interior Walls
Demo / Remove Floor Finishes
File DOL Asbestos Removal Forms
Install Scaffold for Demo
Complete Overhead / Pipe Riser Abatement
Final DOL Abatement
Construction - 419 A & B
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 39 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
511 A511 A177 177 02-Jan-20 26-Jun-20
ConstructionConstruction177 177 02-Jan-20 26-Jun-20
Construction Phase SummariesConstruction Phase Summaries177 177 02-Jan-20 26-Jun-20
S-T22-1000 Construction - 511 A 177 177 02-Jan-20 26-Jun-20
1st Floor Art Gallery1st Floor Art Gallery177 177 02-Jan-20 26-Jun-20
ConstructionConstruction177 177 02-Jan-20 26-Jun-20
Construction Phase SummariesConstruction Phase Summaries177 177 02-Jan-20 26-Jun-20
S-T23-1000 Construction - 1st Floor Art Gallery 177 177 02-Jan-20 26-Jun-20
1st Floor Multipurpose1st Floor Multipurpose177 177 02-Jan-20 26-Jun-20
ConstructionConstruction177 177 02-Jan-20 26-Jun-20
Construction Phase SummariesConstruction Phase Summaries177 177 02-Jan-20 26-Jun-20
S-T24-1000 Construction - 1st Floor Multipurpose 177 177 02-Jan-20 26-Jun-20
5th Floor Senate North5th Floor Senate North245 245 01-Jun-20 31-Jan-21
ConstructionConstruction245 245 01-Jun-20 31-Jan-21
Construction Phase SummariesConstruction Phase Summaries245 245 01-Jun-20 31-Jan-21
S-T25-1000 Construction - 5th Floor Senate North 245 245 01-Jun-20* 31-Jan-21
5th Floor Conference Rooms South5th Floor Conference Rooms South245 245 01-Jun-20 31-Jan-21
ConstructionConstruction245 245 01-Jun-20 31-Jan-21
Construction Phase SummariesConstruction Phase Summaries245 245 01-Jun-20 31-Jan-21
S-T26-1000 Construction - 5th Floor Conference Rooms South 245 245 01-Jun-20 31-Jan-21
4th Floor House Committee North4th Floor House Committee North453 372 16-Apr-19 A 07-Dec-20
Material ProcurementMaterial Procurement251 203 16-Apr-19 A 07-Apr-20
OAU & Heat PumpsOAU & Heat Pumps20 11 07-Jun-19 A 05-Jul-19
P-T27-1002 Fab & Deliver - OAU & Heat Pumps 20 11 07-Jun-19 A 05-Jul-19
Casework & Wood TrimCasework & Wood Trim37 37 05-Feb-20 26-Mar-20
P-T27-1003 MCC Receive / Review Submittal - Base / Case / Crown 5 5 05-Feb-20 11-Feb-20
P-T27-1004 AE2(FSB) Receive / Review Submittal - Base / Case / Crown 10 10 12-Feb-20 25-Feb-20
P-T27-1005 Fab & Deliver - Base / Case / Crown 20 20 28-Feb-20 26-Mar-20
Floor CoveringFloor Covering40 22 16-Apr-19 A 22-Jul-19
P-T27-1008 Fab & Deliver Flooring - Carpet 40 22 16-Apr-19 A 22-Jul-19
Doors / HardwareDoors / Hardware246 26 26-Apr-19 A 26-Jul-19
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Construction - 511 A
Construction - 1st Floor Art Gallery
Construction - 1st Floor Multipurpose
Construction - 5th Floor Senate North
Construction - 5th Floor Conference Rooms South
Fab & Deliver - OAU & Heat Pumps
MCC Receive / Review Submittal - Base / Case / Crown
AE2(FSB) Receive / Review Submittal - Base / Case / Crown
Fab & Deliver - Base / Case / Crown
Fab & Deliver Flooring - Carpet
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 40 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-T27-1011 Fab & Deliver - Doors & Hardware 35 26 26-Apr-19 A 26-Jul-19
P-T27-1012 Fab & Deliver - Door Frames 15 26 26-Apr-19 A 26-Jul-19
MillworkMillwork45 45 05-Feb-20 07-Apr-20
P-T27-1013 MCC Receive / Review Submittal - Millwork 5 5 05-Feb-20 11-Feb-20
P-T27-1014 AE2(FSB) Receive/Review Submittal - Millwork 10 10 12-Feb-20 25-Feb-20
P-T27-1015 Fab & Deliver - Millwork 30 30 26-Feb-20 07-Apr-20
ConstructionConstruction174 131 02-Jun-20 07-Dec-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 04-Dec-20 04-Dec-20
M-T27-1000 Interim Substantial Completion - 4th Floor House Committee North 0 0 04-Dec-20
Construction Phase SummariesConstruction Phase Summaries245 179 09-Jun-20 04-Dec-20
S-T27-1000 Construction - 4th Floor House Committee North 245 179 09-Jun-20 04-Dec-20
4th Floor Committee North4th Floor Committee North131 131 02-Jun-20 07-Dec-20
C-T27-1000 Owner Move Out 5 5 02-Jun-20 08-Jun-20
C-T27-1002 Pre Demo Conference 1 1 09-Jun-20 09-Jun-20
C-T27-1003 Make Safe 5 5 09-Jun-20 15-Jun-20
C-T27-1004 Demo Doors and Frames 3 3 16-Jun-20 18-Jun-20
C-T27-1005 Demo Walls and Ceilings 5 5 16-Jun-20 22-Jun-20
C-T27-1006 Abatement 10 10 23-Jun-20 07-Jul-20
C-T27-1007 Saw Cut New Door Opening 1 1 08-Jul-20 08-Jul-20
C-T27-1008 Remaining Demo 5 5 08-Jul-20 14-Jul-20
C-T27-1038 Install Marble Thresholds 1 1 09-Jul-20 09-Jul-20
C-T27-1010 Post Demo Conference 1 1 15-Jul-20 15-Jul-20
C-T27-1009 Saw Cut and Infill Trenches 3 3 15-Jul-20 17-Jul-20
C-T27-1012 Frame Walls 2 2 20-Jul-20 21-Jul-20
C-T27-1020 Rough In Electrical 8 8 20-Jul-20 29-Jul-20
C-T27-1016 Rough In Walls 5 5 22-Jul-20 28-Jul-20
C-T27-1015 Insulate In Wall 3 3 29-Jul-20 31-Jul-20
C-T27-1025 Install LV Cabling 4 4 30-Jul-20 04-Aug-20
C-T27-1017 In Wall Inspec tion 1 1 03-Aug-20 03-Aug-20
C-T27-1018 50% Fire Marshal Inspection 0 0 03-Aug-20
C-T27-1049 Hang Sheetrock 2 2 04-Aug-20 05-Aug-20
C-T27-1011 Install Mechanical Pads 1 1 06-Aug-20 06-Aug-20
C-T27-1021 Install Door Frames 2 2 06-Aug-20 07-Aug-20
C-T27-1022 Tape / Bed / Paint 4 4 06-Aug-20 11-Aug-20
C-T27-1013 Install Heat Pumps 4 4 12-Aug-20 17-Aug-20
C-T27-1024 Heat Pump Controls 2 2 18-Aug-20 19-Aug-20
C-T27-1014 Rough In Mechanical 4 4 18-Aug-20 21-Aug-20
C-T27-1026 Install Ceiling Grid 1 1 24-Aug-20 24-Aug-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Fab & Deliver - Doors & Hardware
Fab & Deliver - Door Frames
MCC Receive / Review Submittal - Millwork
AE2(FSB) Receive/Review Submittal - Millwork
Fab & Deliver - Millwork
Interim Substantial Completion - 4th Floor House Committee North
Construction - 4th Floor House Committee North
Owner Move Out
Pre Demo Conference
Make Safe
Demo Doors and Frames
Demo Walls and Ceilings
Abatement
Saw Cut New Door Opening
Remaining Demo
Install Marble Thresholds
Post Demo Conference
Saw Cut and Infill Trenches
Frame Walls
Rough In Electrical
Rough In Walls
Insulate In Wall
Install LV Cabling
In Wall Inspec tion
50% Fire Marshal Inspection
Hang Sheetrock
Install Mechanical Pads
Install Door Frames
Tape / Bed / Paint
Install Heat Pumps
Heat Pump Controls
Rough In Mechanical
Install Ceiling Grid
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 41 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T27-1050 Insulate Mechanical 3 3 24-Aug-20 26-Aug-20
C-T27-1019 Plaster Repair / Refinish 20 20 24-Aug-20 21-Sep-20
C-T27-1029 Trim Out MEPF in Ceiling 3 3 25-Aug-20 27-Aug-20
C-T27-1027 OH Inspections 1 1 28-Aug-20 28-Aug-20
C-T27-1028 80% Fire Marshal Inspection 0 0 28-Aug-20
C-T27-1044 Drop Ceiling Tile 2 2 31-Aug-20 01-Sep-20
C-T27-1023 Frame Raised Floor 4 4 22-Sep-20 25-Sep-20
C-T27-1030 Install Electrical at Raised Floor 3 3 28-Sep-20 30-Sep-20
C-T27-1031 Close Up Inspection at Raised Floor 1 1 01-Oct-20 01-Oct-20
C-T27-1032 Close Up Raised Floor 2 2 02-Oct-20 05-Oct-20
C-T27-1040 Install Millwork 15 15 06-Oct-20 26-Oct-20
C-T27-1043 Install Base / Case / Crown 4 4 23-Oct-20 28-Oct-20
C-T27-1041 Install Countertops 1 1 27-Oct-20 27-Oct-20
C-T27-1033 Install Flooring 10 10 27-Oct-20 09-Nov-20
C-T27-1042 Install Fixtures 1 1 28-Oct-20 28-Oct-20
C-T27-1037 Final Paint 5 5 29-Oct-20 04-Nov-20
C-T27-1036 Decorative Paint 10 10 05-Nov-20 18-Nov-20
C-T27-1035 Install Doors and Hardware 2 2 10-Nov-20 11-Nov-20
C-T27-1039 Install Security and Access Control 3 3 12-Nov-20 16-Nov-20
C-T27-1034 Test and Balance 5 5 12-Nov-20 18-Nov-20
C-T27-1048 100% Fire Marshal Inspection 0 0 18-Nov-20
C-T27-1045 Complete MCC / FSB Punch List 5 5 19-Nov-20 25-Nov-20
C-T27-1046 Complete AE1 / Owner Punch List 5 5 30-Nov-20 04-Dec-20
C-T27-1047 Owner Move In 1 1 07-Dec-20 07-Dec-20
4th Floor Press North4th Floor Press North410 321 26-Apr-19 A 23-Sep-20
Material ProcurementMaterial Procurement326 296 26-Apr-19 A 18-Aug-20
OAU & Heat PumpsOAU & Heat Pumps20 8 20-Jun-19 01-Jul-19
P-T28-1002 Fab & Deliver - Historic Grilles 20 8 20-Jun-19 01-Jul-19
Light FixturesLight Fixtures40 31 26-Apr-19 A 02-Aug-19
P-T28-1005 AE2(FSB) Receive/Review Submittal - Lighting 10 2 26-Apr-19 A 21-Jun-19
P-T28-1006 Fab & Deliver - Lighting 30 31 02-May-19 A 02-Aug-19
Doors / HardwareDoors / Hardware70 26 26-Apr-19 A 26-Jul-19
P-T28-1009 Fab & Deliver - Doors & Hardware 35 26 26-Apr-19 A 26-Jul-19
P-T28-1010 Fab & Deliver - Door Frames 15 26 26-Apr-19 A 26-Jul-19
P-T28-1011 Fab & Deliver - Historic Door Frames 70 26 26-Apr-19 A 26-Jul-19
MillworkMillwork55 55 02-Jun-20 18-Aug-20
P-T28-1012 MCC Receive / Review Submittal - MIllwork 5 5 02-Jun-20 08-Jun-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Insulate Mechanical
Plaster Repair / Refinish
Trim Out MEPF in Ceiling
OH Inspections
80% Fire Marshal Inspection
Drop Ceiling Tile
Frame Raised Floor
Install Electrical at Raised Floor
Close Up Inspection at Raised Floor
Close Up Raised Floor
Install Millwork
Install Base / Case / Crown
Install Countertops
Install Flooring
Install Fixtures
Final Paint
Decorative Paint
Install Doors and Hardware
Install Security and Access Control
Test and Balance
100% Fire Marshal Inspection
Complete MCC / FSB Punch List
Complete AE1 / Owner Punch List
Owner Move In
Fab & Deliver - Historic Grilles
AE2(FSB) Receive/Review Submittal - Lighting
Fab & Deliver - Lighting
Fab & Deliver - Doors & Hardware
Fab & Deliver - Door Frames
Fab & Deliver - Historic Door Frames
MCC Receive / Review Submittal - MIllwork
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 42 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-T28-1013 AE2(FSB) Receive/Review Submittal - MIllwork 10 10 09-Jun-20 22-Jun-20
P-T28-1016 Fab & Deliver - Base / Case / Crown 20 20 23-Jun-20 21-Jul-20
P-T28-1014 Fab & Deliver - MIllwork 40 40 23-Jun-20 18-Aug-20
ConstructionConstruction169 80 02-Jun-20 23-Sep-20
Schedule Driven MilestonesSchedule Driven Milestones0 0 23-Sep-20 23-Sep-20
M-T28-1000 Interim Substantial Completion - 4th Floor Press North 0 0 23-Sep-20
Construction Phase SummariesConstruction Phase Summaries245 114 02-Jun-20 23-Sep-20
S-T28-1000 Construction - 4th Floor Press North 245 114 02-Jun-20 23-Sep-20
4th Floor Press North4th Floor Press North80 80 02-Jun-20 23-Sep-20
C-T28-1000 Install Temp Walls/Doors at Construction Entrance 1 1 02-Jun-20 02-Jun-20
C-T28-1001 Install Demising Wall at Northside of 447 1 1 03-Jun-20 03-Jun-20
C-T28-1002 Make Safe 1 1 04-Jun-20 04-Jun-20
C-T28-1003 Install Temp Power 1 1 05-Jun-20 05-Jun-20
C-T28-1004 Install Temp Water 1 1 05-Jun-20 05-Jun-20
C-T28-1005 Label, Remove, Store Storm Windows 1 1 05-Jun-20 05-Jun-20
C-T28-1006 Demo Ceilings 3 3 08-Jun-20 10-Jun-20
C-T28-1007 Protect & Identify Low Voltage Cabling to Remain 4 4 09-Jun-20 12-Jun-20
C-T28-1008 Demo Walls 4 4 11-Jun-20 16-Jun-20
C-T28-1009 Demo OH MEP 5 5 11-Jun-20 17-Jun-20
C-T28-1010 Demo Low Voltage IT 4 4 15-Jun-20 18-Jun-20
C-T28-1011 Abatement Door Frames 2 2 19-Jun-20 22-Jun-20
C-T28-1012 Asbestos Abatement 7 7 19-Jun-20 29-Jun-20
C-T28-1013 Demo Plumbing Risers 2 2 30-Jun-20 01-Jul-20
C-T28-1014 Demo Topping Slabs 3 3 30-Jun-20 02-Jul-20
C-T28-1015 Infill Existing Trenches 3 3 30-Jun-20 02-Jul-20
C-T28-1016 Identify & Cut Areas of Plaster Removal 5 5 30-Jun-20 07-Jul-20
C-T28-1018 Install Marble Thresholds 2 2 06-Jul-20 07-Jul-20
C-T28-1017 Layout and Frame Walls / Furdowns 4 4 06-Jul-20 09-Jul-20
C-T28-1019 Install Lintels 2 2 08-Jul-20 09-Jul-20
C-T28-1022 Hang Heat Pumps 3 3 10-Jul-20 14-Jul-20
C-T28-1020 Rough In In Wall 3 3 10-Jul-20 14-Jul-20
C-T28-1021 Frame & Patch Plaster 10 10 10-Jul-20 23-Jul-20
C-T28-1051 Install Replica-Historic Door Frames 3 3 14-Jul-20 16-Jul-20
C-T28-1023 Rough in Overhead Electric 5 5 15-Jul-20 21-Jul-20
C-T28-1024 Rough In Overhead Mechanical 5 5 15-Jul-20 21-Jul-20
C-T28-1025 Rough In Fire Suppression 3 3 22-Jul-20 24-Jul-20
C-T28-1026 Insulate Mechanical 4 4 22-Jul-20 27-Jul-20
C-T28-1027 OMES Install LV Cabling 5 5 22-Jul-20 28-Jul-20
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
AE2(FSB) Receive/Review Submittal - MIllwork
Fab & Deliver - Base / Case / Crown
Fab & Deliver - MIllwork
Interim Substantial Completion - 4th Floor Press North
Construction - 4th Floor Press North
Install Temp Walls/Doors at Construction Entrance
Install Demising Wall at Northside of 447
Make Safe
Install Temp Power
Install Temp Water
Label, Remove, Store Storm Windows
Demo Ceilings
Protect & Identify Low Voltage Cabling to Remain
Demo Walls
Demo OH MEP
Demo Low Voltage IT
Abatement Door Frames
Asbestos Abatement
Demo Plumbing Risers
Demo Topping Slabs
Infill Existing Trenches
Identify & Cut Areas of Plaster Removal
Install Marble Thresholds
Layout and Frame Walls / Furdowns
Install Lintels
Hang Heat Pumps
Rough In In Wall
Frame & Patch Plaster
Install Replica-Historic Door Frames
Rough in Overhead Electric
Rough In Overhead Mechanical
Rough In Fire Suppression
Insulate Mechanical
OMES Install LV Cabling
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 43 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T28-1028 Install Controls for Heat Pumps 5 5 22-Jul-20 28-Jul-20
C-T28-1029 50% Fire Marshal Inspection 0 0 24-Jul-20
C-T28-1030 In Wall / Hard Lid Inspections 1 1 28-Jul-20 28-Jul-20
C-T28-1032 Startup Heat Pumps 1 1 29-Jul-20 29-Jul-20
C-T28-1031 Hang Sheetrock 3 3 29-Jul-20 31-Jul-20
C-T28-1033 Tape / Bed / Paint Sheetrock 5 5 03-Aug-20 07-Aug-20
C-T28-1034 Install Door Frames 2 2 10-Aug-20 11-Aug-20
C-T28-1035 Install Ceiling Grid 2 2 10-Aug-20 11-Aug-20
C-T28-1040 Install Historic Grills in Corridor 4N.5 2 2 12-Aug-20 13-Aug-20
C-T28-1037 Install Base / Case / Crown 5 5 12-Aug-20 18-Aug-20
C-T28-1038 Install OH Devices 5 5 12-Aug-20 18-Aug-20
C-T28-1041 80% Fire Marshal Inspection 0 0 18-Aug-20
C-T28-1042 Overhead Inspection 1 1 19-Aug-20 19-Aug-20
C-T28-1043 Install Carpet / LVT 5 5 19-Aug-20 25-Aug-20
C-T28-1036 Install Millwork / Countertops / Electrical Connections 15 15 19-Aug-20 09-Sep-20
C-T28-1044 Drop Ceiling Tile 3 3 20-Aug-20 24-Aug-20
C-T28-1045 Re-Hang Storm Windows 2 2 26-Aug-20 27-Aug-20
C-T28-1052 Install Doors and Hardware 3 3 26-Aug-20 28-Aug-20
C-T28-1046 Final Paint 4 4 26-Aug-20 31-Aug-20
C-T28-1047 Paint in Corridor 4N.5 4 4 26-Aug-20 31-Aug-20
C-T28-1048 Install Wood Blinds 2 2 28-Aug-20 31-Aug-20
C-T28-1053 Activate Security & Card Access 5 5 31-Aug-20 04-Sep-20
C-T28-1054 Test & Balance 5 5 31-Aug-20 04-Sep-20
C-T28-1049 Install Accessories 1 1 01-Sep-20 01-Sep-20
C-T28-1050 Install Signage 1 1 01-Sep-20 01-Sep-20
C-T28-1039 Install Plumbing Fixture 3 3 04-Sep-20 09-Sep-20
C-T28-1056 100% Fire Marshal Inspection 0 0 10-Sep-20
C-T28-1055 Complete MCC / FSB Punchlist 5 5 10-Sep-20 16-Sep-20
C-T28-1057 Complete AE1 / Owner Punch List 5 5 17-Sep-20 23-Sep-20
C-T28-1058 Owner Move In 0 0 23-Sep-20
4th & 5th Large Conference South4th & 5th Large Conference South245 245 01-Jun-20 31-Jan-21
ConstructionConstruction245 245 01-Jun-20 31-Jan-21
Construction Phase SummariesConstruction Phase Summaries245 245 01-Jun-20 31-Jan-21
S-T29-1000 Construction - 4 & 5th Large Conference South 245 245 01-Jun-20 31-Jan-21
Senate ChambersSenate Chambers245 245 01-Jun-20 31-Jan-21
ConstructionConstruction245 245 01-Jun-20 31-Jan-21
Construction Phase SummariesConstruction Phase Summaries245 245 01-Jun-20 31-Jan-21
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Install Controls for Heat Pumps
50% Fire Marshal Inspection
In Wall / Hard Lid Inspections
Startup Heat Pumps
Hang Sheetrock
Tape / Bed / Paint Sheetrock
Install Door Frames
Install Ceiling Grid
Install Historic Grills in Corridor 4N.5
Install Base / Case / Crown
Install OH Devices
80% Fire Marshal Inspection
Overhead Inspection
Install Carpet / LVT
Install Millwork / Countertops / Electrical Connections
Drop Ceiling Tile
Re-Hang Storm Windows
Install Doors and Hardware
Final Paint
Paint in Corridor 4N.5
Install Wood Blinds
Activate Security & Card Access
Test & Balance
Install Accessories
Install Signage
Install Plumbing Fixture
100% Fire Marshal Inspection
Complete MCC / FSB Punchlist
Complete AE1 / Owner Punch List
Owner Move In
Construction - 4 & 5th Large Conference South
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 44 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
S-T33-1000 Construction - Senate Chambers 245 245 01-Jun-20 31-Jan-21
House ChambersHouse Chambers245 245 01-Jun-20 31-Jan-21
ConstructionConstruction245 245 01-Jun-20 31-Jan-21
Construction Phase SummariesConstruction Phase Summaries245 245 01-Jun-20 31-Jan-21
S-T34-1000 Construction - House Chambers 245 245 01-Jun-20 31-Jan-21
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2019 2020 2021 2022
Construction - Senate Chambers
Construction - House Chambers
Start Date 23-Feb-15
Finish Date 02-Feb-22
Data Date 20-Jun-19
Run Date 26-Jun-19
Page 45 of 45
3707-CR51
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration
June 2019
4-1
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
4-2
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
4-3
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
4-4
RFI’s
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
4-5
RFI’s
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
4-6
RFI’s
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
4-7
RFI’s
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
4-8
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
4-9
OUTSTANDING SUBMITTAL LOG
SECTION 5
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
5-1
Submittals
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
6-1
Rotunda State Seal Removal
Pictured Right: First floor slab removed and open to ground floor.
Pictured Above: The Oklahoma State Seal prior to removal. Pictured Below: 1st floor slab being cut for removal to connect the sightlines from the 5th floor to the renovated ground floor rotunda.
Pictured Above: The Oklahoma State Seal removal; stars being cored out and removed for preservation.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
6-2
Rotunda Historic Preservation
Pictured Above: New paint scheme mock up on the right side of the picture. Pictured Left: Continued restoration of thousands of square feet of marble.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
6-3
2nd Floor Governor’s Suite
Pictured Left: Ceiling grid being installed in the Governor’s Suite.
Pictured Above: Historic plaster repairs in the Governor’s Waiting Area. Pictured Left: Historic plaster repairs in the Governor’s Conference Room.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
6-4
4th & 5th Floor House of Representatives Demolition
Pictured Right and Below: Demolition of the 4th and 5th floor continues into the House of Representatives offices.
Pictured Right: Trash chutes constructed for debris removal from the 3rd, 4th and 5th floors. Crews sorted debris and filled approximately 220 dump trucks in June.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
6-5
Visitor’s Entrance
Pictured Right: The footings for the new visitor entry where it will connect to the Capitol. Pictured Below: Walls of the new tunnel where it connects to the existing tunnel.
Pictured Right: Overview of the new visitor entry where the existing tunnel ties into the new visitor building.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration June 2019
6-6
Other Capitol Areas
Pictured Right: 4th Floor Senate Offices receiving final touches. Pictured Below: Restoration of historic plaster continues in the Supreme Court.
Pictured Right: Overhead work nearing completion in the new loading dock shop area.