Sentinel-2 Payload Data Ground Segment
Olivier Colin - S2 PDGS Project Manager
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012
We care for a safer world
Contents
• PDGS System Overview
• Data Access Concepts
• PDGS Procurement and Schedule
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 2
We care for a safer world
The Sentinel-2 PDGS
• An element of the Sentinel-2 system responsible for: – Sentinel-2 payload and downlink planning
– Sentinel-2 data acquisition, processing and dissemination
– MSI calibration and performance monitoring
– Product quality verification, calibration and validation
– Mission performance monitoring and control, while contributing to the monitoring of the payload and platform in coordination with the Flight Operation Segment (FOS at ESA/ESOC)
• A component of the GSC ground infrastructure responsible for: – feeding Sentinel-2 products to the GMES Services through the GSCDA similarly to
any GMES Contributing Mission (GCM)
– providing direct access to Sentinel-2 products through GMES operational services and according to the Sentinel-2 Data Policy
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 3
We care for a safer world
PDGS Context in S2 System
• The S2 PDGS interfaces with:
– The Sentinel-2 FOS for mission planning,
– The Sentinel-2 Satellites, for X-Band data reception
– The Coordinated Data access Services for providing integrated services to GMES users
– GMES users for direct access to S2 data
– The EDRS satellites for Ka-Band data reception and the EDRS Ground Segment for coordination activities
– Local Ground Stations and other Collaborative Ground Segment entities
– CNES/CST and ESA/ESTEC during the Commissioning Phase
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 4
We care for a safer world
PDGS Technical Challenges
• Very large volumes of data to
be managed on ground
• Complex and innovative data
processing (L1C)
• System end-to-end
reliability/performance and
long-term sustainability
Large Volumes
Processing Complexity
Operational Reliability/Sustainability
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 5
We care for a safer world
High-Level Design Drivers
Reliability,
Performance,
Sustainability
High Volumes
Data Handling
scalable design,
parallelisation,
distributed
archives
Simplify for
robustness Embedded
redundancy
on critical
components
high system
automation
assessment &
control of
system/mission
performance
Data-driven
design
Minimise /
optimise I/O
within and
across sites
Adapt product
to user needs
Flexible
design to
support
evolutions
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 6
We care for a safer world
Data Volume Challenge
• Systematic Observation Scenario – MSI pixel supply rate (490 Mbps) is ~ 50x that of
ENVISAT MERIS/FR
– In average ~17 minutes of MSI operation/orbit 0.8 TBytes daily of compressed raw data for one satellite (1000 CDs!)
– Equivalent continuous raw data supply rate of ~170 Mbps (compressed) to be sustained with two satellites
– One 100km x 100km MSI image weights ~500MBytes (J2K compressed)
• Systematic Processing scenario – Sustain this flow down to the availability of high-level and quality proof
products in the archives ready for downstream usage
– Product archive of 27 Petabytes after 12 years, and over 1 Terabyte / day expected polling from the users
High-level products
at the user’s sites PDGS 170 Mbps
ingestion, calibration, radio/geo correction, ortho-
rectification, QC, archiving…
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 7
We care for a safer world
Physical Layout (1)
• The S2 PDGS is made of:
– 4 Core Ground Stations (CGSs) for data acquisition, processing and data access
– 2 redunded Processing & Archiving Centres (PACs) for long-term data archiving and data access, as well as reprocessing
– One Mission Performance Centre (MPC) for Image quality control and Cal/Val
– One control centre for mission and system control (PDMC)
– An interconnecting wide area network for internal data circulation
– Network points of presence at CGSs and PACs for user data access over the global archive
Data Access Index
DAX
Collaboration Support Service
Reference Platform
Mission Planning
Mission Config. & Control
MPL
MCC CSSRP
Monitoring & Control
M&C
DataCirculation
DC
PD
GS
Da
ta M
an
ag
em
en
t
Ce
ntr
e (
PD
MC
)
DataAccess
Gateway DAG
Mission Ref. Files
DAX metadata updates
DAX
server I/F
DAIL
front-end
Front-End Services
FES
Mission-Plan|Acquisition-Schedule,
POD products,
MRF/Configuration
GSCDA/MPA reports
System-
configuration &
maintenance
Operator
Interfaces
MMUS
transactions
MSI
Decomp.
SW
MMUS
Archive &Inventory
DataProcessing
Control
DataCirculation
DataAccess
Gateway
On-LineQualityControl
Instr. Data
Processing
DAG AI
DPC
IDP
OLQC
DC
Monitoring & Control
M&C
PAC (Processing /
Archiving Centre)
PDIs
DAG server
Configuration data
Queries to
DAX
PDIs
& all other data
Long-Term ArchivingService
LTA
Data-Access Index
(backup)
DAX
Processing Option LTA Option DAX Mirror Option
DataReception
Archive &Inventory
DataProcessing
Control
DataCirculation
DataAccess
Gateway
On-LineQualityControl
Instr. Data
Processing
DAG
AI
DRX
DPC
IDP
OLQC
DC
Monitoring & Control
M&C
DAG
server
Acquisition-Schedule-Plan
MRF/Configuration
RF signal
MSI & HKTM PDIs
MRF/Operation-Reports
Queries to
DAX
CGS
MPC
PDMC
PACs
CGSs
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 8
We care for a safer world
Physical Layout (2)
• CGS (Core Ground Station) x4
– Matera
– Maspalomas
– Svalbard
– Alaska
• PAC (Processing/Archiving Centre) x2
– Farnborough (UK)
– Madrid (Spain)
• MPC (Mission Performance Centre)
– Still to be selected
• PDMC (Payload Data Management Centre)
– ESRIN, Frascati
Maspalomas
Matera
Svalbard
Alaska
Farnborough Frascati
Madrid
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 9
We care for a safer world
< 100 minutes
Level-1B and -1C
products
Processing of all data up to Level-1C within 100 minutes after satellite downlink
PDGS Processing Concept
Sentinel-2 products
CGSs
PACs
Archive &Inventory
DataProcessing
Control
DataCirculation
DataAccess
Gateway
On-LineQualityControl
Instr. Data
Processing
DAG AI
DPC
IDP
OLQC
DC
Monitoring & Control
M&C
PAC (Processing /
Archiving Centre)
PDIs
DAG server
Configuration data
Queries to
DAX
PDIs
& all other data
Long-Term ArchivingService
LTA
Data-Access Index
(backup)
DAX
Processing Option LTA Option DAX Mirror Option
DataReception
Archive &Inventory
DataProcessing
Control
DataCirculation
DataAccess
Gateway
On-LineQualityControl
Instr. Data
Processing
DAG
AI
DRX
DPC
IDP
OLQC
DC
Monitoring & Control
M&C
DAG
server
Acquisition-Schedule-Plan
MRF/Configuration
RF signal
MSI & HKTM PDIs
MRF/Operation-Reports
Queries to
DAX
CGS
Centralised
& transparent
access
Long-Term availability from PACs
Short term rolling availability from stations
internal circulation
< 100 minutes after station acquisition
within typically a week
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 10
We care for a safer world
Timeliness
The timeliness pattern is cascading from the observation pattern relative to the core station network, it will range typically from:
- 100mins from sensing in direct station visibility
- between 3h and 24h otherwise
0-1
1-2
2-3
3-4
4-5
5-6
>6
Average download ageing (hours)
Age of the data (in hours) accumulated on board
at the time it is received at the PDGS ground station
Example of the timeliness pattern at summer solstice with the network of ground stations (Matera, Svalbard, Maspalomas, Alaska)
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 11
We care for a safer world
User Product Concept
• Product contents are defined by the user at query/download time – Area of interest
– Selected product components (level, bands, metadata, etc)
– Formatting/Packaging options
• Data Handling – Product data is archived as elementary
product “granules” (slices for L1B or tiles for L1C) following a geographical split
– Product granules are assembled during download into the final “User-Products” transparently to the user
Data-driven processing/archiving User-driven data-access
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 12
We care for a safer world
S2 PDGS System Highlights
• Systematic operation concept
• Challenging performance - All processing systematic within an orbit
• Huge data volumes and petabyte scale mission lifetime archive
• Innovative Level-1C and product concept
• On-line data access from a Federated System of Stations and PACs
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 13
We care for a safer world
Sentinel-2 Specific Procurements
• PDGS Core Procurement – Most sub-systems procurements
– Instrument Processors and Mission Performance Assessment sub-systems via Best Practices ITTs
– Integration Verification & Validation activities
• Sentinel-2 Mission Planning
• Sentinel-2 Atmospheric Correction prototype processor – To be integrated in the Sentinels User Toolbox
Procurement Approach (1)
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 14
We care for a safer world
Procurement Approach (2)
Sentinels Common Procurements
• Demodulator and Front-End Processor (DFEP) – Common procurement for S1/S2/S3
• Next Generation User Services for Earth Observation (ngEO) – Common procurement for Sentinels, Explorers and TPM
• GSC Infrastructure Procurement & Operations – CGS Procurement including operation SLAs (in negotiation)
– PAC Procurement including operation SLAs (in negotiation)
– Network WAN infrastructure procurement and operations, ITT planned mid 2012
• Sentinel User Handbook and Exploitation Tools – Common procurement for S1/S2/S3
• Precise Orbit Determination (POD) – Common procurement for S1/S2/S3, ITT planned end 2012
• Station Resource Allocation (SRA) – PDGS Sentinel-1/2/3 Coordination facility for mission planning, design in preparation
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 15
We care for a safer world
Delta-hardware deployment for S2B
PDGS Deployment for GSC Operations (Ramp-up phase)
S2 PDGS Schedule
System Requirements Review: Passed Preliminary Design Review: Passed Critical Design Review: Q4 2012
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 16
PDGS Development
Initial PDGS deployment for satellite Commissioning
S2A Commissioning
LS2A End 2013
Full S2A
mission capacity
(2014)
Jan 2013 LS2B 2015
LS2A + 3 months
Product availability
S2B Commissioning
Full S2
mission
capacity
S2A S2B
We care for a safer world
Thank you!
Olivier Colin, Barbara Angelucci, Olivier Barois, Gioacchino Buscemi, Enrico Cadau, Maurizio Cao, Andrea Cavallini, Steven Delwart, Eric Doyle, Steffen Dransfeld, Pierre Femenias, Antonio de la
Fuente, Ferran Gascon, Javier Gorrono Vinegla, Bianca Hoersch, Nigel Houghton, Gian Piero Izzo, Cristiano Lopes, Borja López Fernández, Fabio Lozito, Davide Moretti, Francesco Nisi, Mats
Onnestam, Alessandro Piro, Cristiano Silvagni, Andrea Simonini, Nityaporn Sirikan
Sentinel-2 Preparatory Symposium, ESRIN 23.04.2012, O.Colin 17