sines lng terminal - ntnu conferences/2005/sds...aclose link to lng operators through tbl group. 4...

Post on 22-May-2018

215 Views

Category:

Documents

2 Downloads

Preview:

Click to see full reader

TRANSCRIPT

1

Sines LNG terminal

GASTECH 2005

2

Location of SINES LNG RECEIVING TERMINAL (Portugal)

3

Contract award

Contract awarded on 13/11/00As result of international competitionTRACTEBEL consortium selected for:

Price levelClose link to LNG operators through TBL group

4

Project challenges

Tight schedule: 37 months

Integration in an existing harbour, still under development

Congested area

between public roads, railways and coal terminal

5

Plant view of SINES LNG RECEIVING TERMINAL

Process areaJetty with bearthingand unloading facilities

Seawaterintake

Service area with main service building

6

Sea water intake

7

SINES Aerial view

8

Aerial view (general facilities)

9

Terminal performances

Unloading:Ship from 35 000 thru 165 000 m³Unloading rate: 10 000 m³/hr

Storage:2 tanks of 120 000 m³ net capacity

Sendout:300 000 Nm³/hr as average900 000 Nm³/hr in peak84 barg

Truck loading3000 trucks per year

10

SINES Unloading

11

Terminal installation overview – on plot area

Open rack vaporizers

High pressure booster pumps

Truck loadingStorage tanks

2 x 120,000 m3

Boil-off compressors & unloading blowers

Space for future Phase 2

Gas metering & trunk line station

Ship unloadingline

12

Process area: compressor and pumps shelters

13

SINES Storage and vaporisation

14

New technologies and HSE approach

In the design

During construction

For operators

15

New approaches in the design

Intensive use of electronic mailing to allow « real time » coordination betweenpartners and with fieldEDMS for document circulationFull ISO 9000 complianceDynamic simulation for earthquakecalculationElectronic 3D model

16

New approaches in the design (foll’d)

Dampeners to absorb dynamic loads from waterhammer in unloading linesIntegrated control & command systemFiber optic cablesErgonomic study of the control room andoperators offices interfaces

Better communicationFaster response in case of alarm or emergencyCorrect lighting to avoid useless constrains

Wireless telephonic system

17

HSE policy during construction

Spent manhours: 3 950 000 hrsNb of accident:

Without lost time: 29With lost time: 8

Nb of near-misses: 48Nb of lost days: 168Lost-time index = 2.04 (<21, Portuguese standard)Nb of safety induction training: 3730Nb of toolbox meetings: 346Nb of attendees to toolbox meetings: 10 370

18

Foreseen for operation

PMSInterfaces between DCS and PMS to download information needed for preventive and condition basedmaintenancesAsset management systemWalk-inside 3D model allowing operatorto simulate the field interventions

19

Approach towards EN 1473

Hazard definition and management

earthquake

20

Hazard Definition and Management

Quantitive Risk AssessmentHazard : identificationConsequence ModellingProbability

Risk matrix & level of risks as per annexes K/L

Appropriate prevention & investigation

IIIIIIIII> 10-21

IIIIIIIII10-4 – 10-22

IIIIIIIIIII10-6 – 10-43

IIIIIIIIIIIII10-8 – 10-64

IIIIIIIIIIIIIII< 10-85

IIIIIIIVV

ConsequenceProbability

Not acceptableI

To be improvedII

AcceptableIII

21

TGE seismic approachearthquake levels

As per EN 1473 definitionsOBE = operation basic earthquake

Plant must remain operational after earthquakeNon-essential components could be damaged provided it will not affect the plant safe operation

SSE = safe shutdown earthquakeDesign as per classificationOperation resume could require important repairsNeed to keep monitoring of important tank and process data

22

Seismicity

Area in seismic area0.15 g acceleration for OBE0.5 g acceleration for SSE

Acceleration value at the ground levelNeed to develop a global approach to

guarantee integrity and stability of systems and structure but without over-design

23

TGE seismic approach as per EN 1473classification

4 classes on a safety point of view:Class A: vital for safetyClass B: failure could bring an additional hazardClass C: could not collapse as collapse could affect A or B classified itemsClass D: other items for which no specific requirements

Other considerations (operating costs or capital losses): to be discussed with client

24

TGE seismic approachclassification matrix table

XClass C

XClass B

XClass A

stabilityintegrityoperationCriteriaclass

25

TGE seismic approachbasic principle

Plant will be shutdown after any earthquake

Operator decision or seismic detectorEquipment would trip from vibration

Plant will be fully inspected prior to resume operation:

OperabilityIntegritystability

26

Thank you for your attention

top related