Marshall Marik Project Manager South Sacramento Streams Group Sacramento District May 17, 2012. SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE. Morrison Creek Construction Along Union Pacific Railroad. Construction started May 1 st . - PowerPoint PPT Presentation

TRANSCRIPT

US Army Corps of EngineersSacramento District

BUILDING STRONG®

SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

Marshall Marik

Project Manager

South Sacramento Streams Group

Sacramento District

May 17, 2012

BUILDING STRONG®

Morrison Creek Construction Along Union Pacific Railroad

Construction started May 1st.

Coordinated with Union House Elementary School for placement of crossing guards.

Construction scheduled for completion in October 2012.

BUILDING STRONG®

Post Authorization Change Report (PACR)

Preliminary FEMA floodplain information provided by the City of Sacramento contract indicates that a PACR will not be required.

Corps will complete verification of FEMA floodplain model by December 2012.

BUILDING STRONG®

Marshall Marik

US Army Corps of Engineers

1325 J Street

Sacramento, CA 95814-2922

(916) 557-7698