ONLINE PUBLIC ENGAGEMENT
South West Mississauga Water System Improvements
Watermain Construction on South Sheridan Way and Indian Grove
Project background
What are we doing?
Watermain construction to ensure the Region maintains the water system in south west Mississauga by:
• Replacing aging critical watermain infrastructure (circa 1960)
• Adding new support watermains to the system to support customer demand and optimize pressure zones, with some areas experiencing an increase in water pressure
Watermain construction overview
Map Data © 2020 Google
South Sheridan Way
CONTRACT 1Indian Grove
February 2021 – Spring 2022
CONTRACT 2South Sheridan Way
Spring 2021 – Fall 2022
QEW
Contract 1 - Construction on Indian Grove
Ind
ian
Ro
ad
Contract 1 Includes:
600mm (24 inch) diameter transmission watermain
300mm (12 inch) diameter residential supply watermain
Schedule:
February 2021 to Spring 2022
Map Data © 2020 Google
Contract 1 - Construction sequence on Indian Grove
Construct 300mm
distribution watermain from South Sheridan Way
to Indian Road
Transfer all water services
from old transmission watermain to new
distribution watermain
Construct 600mm sub-
transmission watermain from South Sheridan Way
to Indian Road
Map Data © 2020 Google
Indian Grove
Indian Grove is a crowded utility corridor. Due to space constraints the two watermains must be constructed on opposite sides of the road. Construction sequence ensures water supply, and vehicle and pedestrian traffic flow is maintained.
Contract 1 - Construction impacts
Indian GroveLocal Traffic Only
Feb 2021 to Dec 2021
Access to paths from Indian Grove to
Tecumseh Public School and Wateska
Boulevard will be maintained
Indian GroveTemporary Sidewalk
South Sheridan Way Road Closure
Approximately 6 WeeksSummer 2021
Indian RoadTemporary Lane
ClosuresIntermittent
Driveway access will be maintained, and
any temporary interruptions will be
coordinated with homeowners
Map Data © 2020 Google
Contract 1 - Road closure and detour
South Sheridan Way Road ClosureApproximately 6 Weeks
Summer 2021
Map Data © 2020 Google
Detour Route
Road Closure
South Sheridan Way
Contract 1 - Indian Grove temporary sidewalk
• A temporary sidewalk will be constructed on east side of Indian Grove during watermain construction on the west side of Indian Grove
• The temporary sidewalk will be removed for 600mm watermain construction in same location
• Area will be restored to original condition at end of construction
Map Data © 2020 Google
Contract 1 - Driveway and landscaping restoration
• Watermains will be constructed within the municipal right-of-way but will disrupt driveways
• All efforts will be made to reinstate driveways to match existing conditions• Interlocking brick will be removed, stored
onsite and replaced• Region will contact residents with concrete
driveways to arrange restoration
• All efforts will be made to minimize tree removals/transplants
• New curb, sidewalk and asphalt on Indian Grove
Map Data © 2020 Google
Ind
ian
Gro
ve
Contract 2 - Construction on South Sheridan Way
• Sub-transmission and local distribution watermains on South Sheridan Way from Southdown Road to Indian Grove, and on Pierre Place, Indian Road and Cottonwood Court
• Pressure zone increase to residents on South Sheridan Way and Indian Road
• Construction from Spring 2021 to Fall 2022
South Sheridan Way
Map Data © 2020 Google
Contract 2 - Traffic impacts
South Sheridan Way
Map Data © 2020 Google
• Lane closures expected on South Sheridan Way during the day (9 a.m. to 4 p.m.)
• Flag persons onsite to maintain traffic flow in both directions
• Spring 2021 to Fall 2022
Contract 2 - Road closures and detours
South Sheridan Way Road Closure between Clarkson Road North and Indian RoadApproximately 6 Weeks, Summer/Fall 2021Access will be maintained to all properties
Detour Route
Road Closure
Map Data © 2020 Google
South Sheridan Way
Contract 2 - Road closures and detours
Detour Route
Road Closure
Map Data © 2020 Google
South Sheridan Way
South Sheridan Way Road Closure at Indian Road IntersectionApproximately 1 Week
Fall 2021
Contract 2 - Pedestrian detour
Pedestrian Detour Route
Sidewalk Closed
South Sheridan Way
Crestdale Road
South Sheridan Way Sidewalk Closed between Calgary Court and Vanier DriveApproximately 1 Month
Map Data © 2020 Google
Contract 2 - Pressure zone increase
• A water pressure increase is planned as part of Contract 2
• You will receive a notice with specific dates prior to the work
• Residents in this area will see an increase in the water pressure flowing from their taps
Old pressure zone boundary New pressure zone boundary Increased pressure
Map Data © 2020 Google
South Sheridan Way
Kira
n
Ct.
Contacts
Ben Percy, P.Eng.
ben.percy@gmblueplan.ca
(519) 824-8150 ext. 1281
Nicole Sartor, P.Eng.
nicole.sartor@peelregion.ca
(905) 791-7800 ext. 7832
Your comments are important to us. Please provide any comments or questions to the Region of Peel or GM BluePlan Engineering by November 30, 2020.