spectrometer solenoid report and coupling coil update

Post on 20-Jan-2016

50 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

DESCRIPTION

Spectrometer Solenoid Report and Coupling Coil Update. Michael S. Zisman M ICE O perations M anager C enter for B eam P hysics Lawrence Berkeley National Laboratory MICO Meeting March 16, 2009. Status (1). Making slow but steady progress on first Spectrometer Solenoid (“Magnet 2”) - PowerPoint PPT Presentation

TRANSCRIPT

Spectrometer Solenoid Reportand

Coupling Coil Update

Michael S. ZismanMICE Operations ManagerCenter for Beam Physics

Lawrence Berkeley National Laboratory

MICO MeetingMarch 16, 2009

March 16, 2009 Solenoid Report-Zisman 2

Status (1)•Making slow but steady progress on first Spectrometer Solenoid (“Magnet 2”)— fabrication work on turret completed

o welding radiation shield and LN2 reservoir connections doneo wrapping in MLIo welding outer vacuum covers

— already doneo cold mass leak checkedo condenser sleeves and magnet leads completed

— to doo complete instrumentation feedthroughso complete fill/vent connectionso add weld preps to end plates (under way; weld rings already in place in vacuum vessel)

March 16, 2009 Solenoid Report-Zisman 3

Status (2)

•Expect final assembly of radiation shield and vacuum vessel completed this week— leak check next week (week of March 23)— first cool-down expected week of March 30

o keep your fingers crossed!

•Other news— tried tracker go-no-go gauge in Magnet 1 (the earlier one)

o bore was out of magnet but still welded to patch panel and plate– fit fine! (see photo later)

— test will be repeated in Magnet 2 this week after warm bore installed

Magnet turret inner components wrapped in MLI

Magnet power leads at top of turret

Weld ring in place for vacuum vessel end plate (patch panel end)

Welding of radiation shield and LN2 reservoir connections

Tracker ‘go-no go’ gage in warm bore of Magnet #1

March 16, 2009 Solenoid Report-Zisman 9

Coupling Coil Update

•Visited likely vendor for magnet fabrication— Qihuan Mechanical and Electronic Engineering Corporation (QMEEC)

o located in Beijing— Derun Li, Steve Virostek, MZ, Li Wang and ShiXian Zheng were

there

•Company statistics— 29 employees; 2200 m2 floor space— 20 years experience with superconducting magnets

o MRI magnetso BEPC-II detector magnet (3 m diameter, 4 m long)o completing MRI magnet of their own design now (see photos)

•Impressions— quite favorable; they are interested and knowledgeable

o but, we still want Li Wang to manage the work!

Coil winding form parts at QMEEC ready for welding

High bay at QMEEC showing magnet assembly area

Coil array for 1.5T MRI magnet nearing completion at QMEEC

Iron vacuum vessel for 1.5T MRI

Coil winding facility at QMEEC

Aluminum weld samples for coupling coil cooling lines and cold mass cover plates

March 16, 2009 Solenoid Report-Zisman 16

Test Coil at ICST

•Close to being able to test the “long coil” in Harbin