Arlington CountyDepartment of

Environmental Services

October 18, 2011

Ballston Pond Improvement

Project

In Association With:

Stakeholder Meeting

Presentation Agenda

Key Findings from last meeting

Preferred Concept

Phasing Plan

Interpretive Opportunity Areas

Precedents: Real Life Examples

Break-Out Group Discussion Questions

Presentation of Discussion Points

Next Steps – Project Schedule

Next Meeting – Public Session on October 27, 2011

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 2

Wetland design•Preapproval of plantings•Increased habitat and wildlife

Trash Control •Check that structures do not impede flow;•Low maintenance; •Maintenance plan in place immediately

Overlooks•Concern of bike path traffic and speed•East side overlook more preferred location

Key Findings from last meeting

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 3

Preferred Concept

Wetland Design• Plantings approved by Arlington County

• Wildlife Diversity Components – Bat Boxes and Turtle Basking Stations

Trash Control Plan modified• Upstream and Downstream Capture

• Maintenance and Accessibility

Overlooks Phase 1 – East Side Overlook included

Wide transition from east to south for bikers/pedestrians

Future Phases – 2 Additional Boardwalks; Bridge in front of weir.

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 4

Preferred Concept

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 5

Preferred Concept(enlarged)

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 6

Typical Cross-section of Pond

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 7

Phasing Plan

Phase 1 – (Shown in exhibits)• One boardwalk (east side)

• All the trails – realignment and new

• Wetland Pond design in its entirety

• Trash Control

Other Phases – TBD • Budget Constraints will determine

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 8

Phasing Plan

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 9

Interpretive Opportunity Areas

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 10

Precedents: Real Life Examples

Wetland Plantings Trash Control

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 11

Precedents: Real Life Examples

• Turtle Basking

• Bat Boxes

• Wildlife Habitats

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 12

Precedents: Real Life Examples

• Interpretive kiosk with context map

• Interpretive signage integrated with guardrail

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 13

Interpretive Opportunity Areas

• Interpretative elements as a component of public art

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 14

Discussion / Questions on Presentation

(prior to break out session)

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 15

Break-Out Discussion Questions

What kinds of information/stories should be featured on: • Larger “Gateway Kiosks”

• Smaller Interpretive Areas

Interpretive Information• Primarily Informational OR Public Art

Component?

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 16

Presentation of Discussion Points

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 17

Design Development Phase

Present Plans to Public

o 3rd Stakeholder Meeting – Tonight; October 18th

o 3rd Public Meeting – October 27, 2011

Finalize Plans - December 2011/January 2012

Prepare Permit Application - April 2012

Submit 100% Construction Documents - April 2012

Pretreatment begins mid-November 2012

Construction begins May 2013

Next Steps - Project Schedule

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 18

Next Meeting!

Public Meeting • October 27, 2011, 7:00-9:00 p.m.

Please Tell Everyone!!

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 19

Construction Schedule

• Site Preparation November 2012 through May 2013

Remove Invasive Plants November 2012 – May 2013

Wildlife Rescue/RemovalMay 1- May 31, 2013

Tree RemovalMay 1-31, 2013

• Earthwork and Grading June 1 –September 30, 2013

• Seeding (in-pond) October 1-31, 2013

• Planting (in-pond and upland) March –April 2014

Ballston Pond Stakeholder Meeting October 18, 2011 Slide 20