t-76.5613 test documentation and reporting 2006
Post on 13-May-2022
6 Views
Preview:
TRANSCRIPT
Juha ItkonenSoberIT
HELSINKI UNIVERSITY OF TECHNOLOGY
T-76.5613 Software Testing and Quality Assurance
23.10.2006
Test documentation and Reporting
2Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
IEEE 829 Standard for Software Test Documentation
Test PlanningTest plan
Project levelPhase level
Test SpecificationTest design SpecificationTest case specificationTest procedure specification
Test ReportingTransmittal reportTest logIncident reportTest summary report
Number of needed test documents, their format, thoroughness and level of detail depends on context.
3Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
IEEE 829 Standard for Software Test Documentation
Test PlanningTest plan
Project levelPhase level
Test SpecificationTest design SpecificationTest case specificationTest procedure specification
Test ReportingTransmittal reportTest logIncident reportTest summary report
4Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test plan – a project plan for testing
A document describing the scope, approach, resources, and schedule of intended testing activities.It identifies test items, the features to be tested, the testing tasks, responsibilities, schedules, and risksTest plan can be either product or tool
Test plan as a product: structure, format and level of detail are determined not only what’s best for the effectiveness of the testing effort but also by what customer or regulating agency requires.Test plan as a tool: Creating long, impressive, or detailed test planning documents is not the best use of your limited time. A test plan is a valuable tool to the extent that it helps you manage your testing project and achieve your testing goals.
5Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test Plan (IEEE Std 829) 1/5
1 Test plan identifier2 Introduction
Product to be tested, objectives, scope of the test planSoftware items and features to be testedReferences to project authorization, project plan, QA plan, CM plan, relevant policies & standards
3 Test itemsTest items including version/revision level
Items include end-user documentationBug fixes
How transmitted to testingReferences to software documentation
6Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test Plan (IEEE Std 829) 2/5
4 Features to be testedIdentify test design / specification techniquesReference requirements or other specs
5 Features not to be testedDeferred features, environment combinations, …Reasons for exclusion
6 ApproachHow you are going to test this system
Activities, techniques and tools
Detailed enough to estimateCompletion criteria
Specify degree of comprehensiveness (e.g. coverage) and other criteria (e.g faults)
Identify constraints (environment, staff, deadlines)
7Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test Plan (IEEE Std 829) 3/5
7 Item pass/fail criteriaWhat constitutes success of the testingE.g. coverage, bug count, bug rate, number of executed tests, …Is NOT product release criteria
8 Suspension and resumption criteriaFor all or parts of testing activitiesWhich activities must be repeated on resumption
9 Test deliverablesTest planTest design specificationTest case specificationTest procedure specificationTest item transmittal reportTest logsTest incident reportsTest summary reports
8Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test Plan (IEEE Std 829) 4/5
10 Testing tasksIncluding inter-task dependencies & special skillsEstimates
11 EnvironmentPhysical, hardware, software, toolsMode of usage, security, office spaceTest environment set-up
12 ResponsibilitiesTo manage, design, prepare, execute, witness, check, resolve issues, providing environment, providing the software to test
13 Staffing and Training needs
9Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test Plan (IEEE Std 829) 5/5
14 ScheduleTest milestones in project scheduleItem transmittal milestonesAdditional test milestones (environment ready)What resources are needed when
15 Risks and ContingenciesTesting project risksContingency and mitigation plan for each identified risk
16 ApprovalsNames and when approved
10Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Course Test Plan Templatefor the exercise phase 3
1. Introduction
2. Tested items and features
3. Testing Approach
4. Resources
5. Tasks and Schedule
6. Risks and contingencies
7. Approvals
The high level structure for your test planDetails below each chapter give you the idea of the contents of each chapterYou should apply information from your course book, lectures, and IEEE 829-1998 standard to make as good test plan as possible
Remember: Content or nothingGrading is not based on word count
11Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test plan quality criteria
Usefulness: Will the test plan effectively serve its intended functions?Clarity: Is the test plan self-consistent and sufficiently unambiguous?Accuracy: Is the test plan document accurate with respect to any statements of fact?Adaptability: Will it tolerate reasonable change and unpredictability in the project?Efficiency: Does it make efficient use of available resources?Usability: Is the test plan document concise, maintainable, and helpfully organized?Compliance: Does the test plan meet externally imposed requirements?Foundation: Is the test plan the product of an effective test planning process?Feasibility: Is the test plan within the capability of the organization that must use it?
Source: Kaner, Bach, Pettichord. Lessons Learned in Software Testing. 2002
12Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
IEEE 829 Standard for Software Test Documentation
Test PlanningTest plan
Project levelPhase level
Test SpecificationTest design SpecificationTest case specificationTest procedure specification
Test ReportingTransmittal reportTest logIncident reportTest summary report
13Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test Case Specification (IEEE Std 829)1. Test-case-specification identifier: specifies the unique
identifier.2. Test items: detailed feature, code module, etc. to be tested;
references to product specifications or other design docs3. Input specifications: Each input required to execute the test
case (by value with tolerances or by name); identifies all appropriate databases, files, terminal messages, etc.; specifiesall required relationships between inputs (for example, timing)
4. Output specifications: result expected from executing the test case; outputs and features (for example, response time) required of the test items; exact value (with tolerances where appropriate) for each required output or feature
5. Environmental needs: hardware, software, test tools, facilities, staff, etc.
6. Special procedural requirements: special constraints7. Intercase dependencies: lists the identifiers of test cases
which must be executed prior to this test case; the nature of the dependencies
14Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test design specification
Specifies a one set of tests and refines the test plan informationSpecific methods, tools and techniques Groups together tests that test a certain set of featuresReferences to test procedures and test casesPass/fail criteria
15Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test procedure specification
Used if neededTest plan and test design specification are not enough
Specifies the steps for executing a set of test casesSpecial requirements for executing the testsReferences to test casesSteps and any measurements to be made
16Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
IEEE 829 Standard for Software Test Documentation
Test PlanningTest plan
Project levelPhase level
Test SpecificationTest design SpecificationTest case specificationTest procedure specification
Test ReportingTransmittal reportTest logIncident reportTest summary report
17Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Reporting test results
Evaluation of the tested softwareFound defects and issuesTesters’ assessment of the qualityRisk assessment based on test results and gained knowledge
Comparison of planned vs. actualTesting project management report
A post mortem for tests to comeWeak and omitted areasIdeas for new testsRisks
18Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test record (log) contains
Chronological record of relevant details about the tests executionIdentities and versions (unambiguously) of
Software under test (exact build, versions of components, …)Test specifications
Testing environment Identify the attributes of the environments in which the testing is conductedInclude hardware being used (e.g., amount of memory being used, CPU model, mass storage devices)system software usedresources available
Activity entriesDate and time for beginning and end of activitiesIdentity of the testerExecution descriptionResultsAnomalous eventsDefect ID:sReferences to other documents (test case, test design specification, …)
19Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Check the results
Follow the plan and mark off progress on test scriptNote that these records are used to establish that all test activities have been carried out as specified
Document actual outcomes from the testCapture any other ideas you have for new test casesCompare actual outcome with expected outcome.Log discrepancies accordingly
Software faultTest fault (e.g. expected results wrong)Environment or version faultTest run incorrectly
Log coverage and other planned metrics for measures specified as test completion criteria
20Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Defect reporting
Defect reportA technical document written to describe the symptoms of a defect to
Communicate the impact and circumstances of a quality problemPrioritize the defect for repairHelp a programmer to locate and fix the underlying fault
Defect reports are the most frequent and visible results of testing workDefect reports are an important communication channel from testing to developmentDefect reports are challenging to write
Bearing bad newsExplaining complicated behaviourCommunicating to people with different mindset using as few words as possibleGoal is to make people fix their mess instead of creating some new fancy functionality
21Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Reporting the found defects
Report the defects immediatelyDon’t leave it until the end of test session
Make sure the defect has not been previously reportedFind out how to reproduce the defect
Easier to isolate and get fixed
Write specific and clear defect reportsSpend some time to find out what is the actual defect and under which conditions it occursWhat were the specific expected outcome and the actual outcome
Be non-judgmental in reporting bugs. Bug reports need to be non-judgmental and non-personalReports should be written against the product, not the person, and state only the facts.
22Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
An effective bug description
Useful bug reports are ones that get bugs fixed!Minimal
Just the facts and details necessary An exact sequence of steps that shows the problem
SingularOnly one bug per report – only one report per bug
Obvious and generalUse steps that are easily performed and show the bug to be as general as possible and readily seen by usersIf a programmer or tester has to decipher a bug, they may spend more time cursing the submitter than solving the problem
ReproducibleIsolate and reproduce what seems like random software behaviorIf an engineer can't see it or conclusively prove that it exists, the engineer will probably stamp it "WORKSFORME" or "INVALID", and move on to the next bug.
SeverityShow clearly how severe are the consequences if this defect is delivered to operation
23Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
10 steps to great defect reports1. Structure
Testing must be structured, to understand what you are doing.2. Reproduce
Clear steps. Three tries.3. Isolate
Which factors affect the defect and how.4. Generalize
Try to find out the more general case when the defect occurs.5. Compare
Does the same defect exist in other versions, and other parts of the product.6. Summarize
Communicate with a single sentence the essence and significance of the defect.7. Condense
Remove any excess information. Use just the words you need and describe only the necessary steps.
8. DisambiguateRemove confusing or misleading words – be clear.
9. NeutralizeAs a bearer of bad news, express yourself calmly, don’t attack programmer or use unnecessary humour or sarcasm.
10. ReviewE.g. informal check by another tester, or pair testing.
Rex Black, 2004. Critical Testing Processes.
24Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Motivate fixing the defect
Make the defect look more seriousFind a credible scenario that demonstrates the impact of the defectE.g., a realistic story that describes how a user can lose data when this defect occurs
Make the defect look more generalYou discovered the defect in some specific caseWhat is the most general case the defect occursE.g., if you first found out that the system cannot cope with ‘~’ and ’\’
you might be able to generalize the defect into “the system only accepts characters ‘a-z’, ‘A-Z’ and ‘0-9’ and not any special characters including ‘-’,’ä’, and ‘ö’.”
25Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Defect report
1. Defect-report identifier2. Title: A short description of the defect3. Bug description: A detailed description of the
defectDate, time and finderTest item and environment including version and build numbersExpected resultsActual resultsRepeatability (whether repeated; whether occurring always, occasionally or just once)Additional information that may help to isolate and correct the cause of the incident
4. Severity of the bug
26Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Reporting a bug – an exercise
Suppose that you are running tests on the Windows Calculator and find following results:
1+1=22+2=53+3=64+4=95+5=106+6=134+6=104+5=9
Write a bug title and bug description that effectively describes the problem.
27Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Reporting a bug – one solution
Title: Adding a pair of equal even numbers gives too big result (by one)Description:
Setup: start Version 1.0 of CalculatorRepro steps: Try adding pairs of equal even number such as 2+2, 4+4, and 10+10. Also try adding pairs of equal odd numbers such as 3+3, 5+5, and 13+13 and pairs of unequal numbers such as 1+2, 4+6, and 15+13. Expected result: Correct answer for all pairs 2+2=4, 4+4=8…Actual result: For pairs of equal even numbers, the answer is one too big: 2+2=5, 4+4=9, 10+10=21 and so on. Other info: This wasn’t tried exhaustively, but the bug occurred on many instances from 2+2 to 65536+65536. The bug doesn’t seem to occur with odd numbers or unequal pairs.Environment: Windows 2000, 5.00.2195, Service Pack 4Reporter: Jack Debugger
28Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test Summary Report (IEEE Std 829) 1/2
1. Test-summary-report identifier2. Summary
summarizes the evaluation of the test itemsidentifies the items tested (including their version/revision level)indicates the environments in which the testing took placesupplies references to the documentation over the testing process
3. Variancesindicates any variances of the actual testing process from the test plan or test proceduresspecifies the reason for each variance
4. Comprehensiveness assessmentevaluates the comprehensiveness of the actual testing processagainst the criteria specified in the test planidentifies features or feature combinations which were not sufficiently tested and explains the reasons for omission
29Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Test Summary Report (IEEE Std 829) 2/2
5. Summary of resultssummarizes the success of testing (such as coverage, numbers of defects, severities, etc.), identifies all resolved and unresolved incidents
6. Evaluationprovides an overall evaluation of each test item including its limitationsbased upon the test results and the item-level pass/fail criteria
7. Summary of activitiesthe major testing activities and eventsresource consumption (total staffing level, total person-hours, total machine time, total elapsed time used for each of the major testing activities, …)
8. Approvalsspecifies the persons who must approve this report (and the whole testing phase)
30Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Meetings, reports and project control issues
Test manager should collect and track the metrics regularly (weekly) and direct the testing groups efforts by status meetingsTest results must be reported regularly to the whole project group (or development team)
Depending on the used sw development model, the required pace of feedback (test results) varies from 1 day to over a month
The mission of a testing team is to produce, for the rest of the organisation, relevant information about the quality status of the system promptly and in a useful formSummary reports are provided to upper management at least in every milestone
31Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Status reports to management
Reports should be brief and contain (J. Rakos)
Activities and accomplishments during the reporting periodProblems encountered since the last meeting/reportProblems solvedOutstanding problemsCurrent state versus planExpenses versus budgetPlans for the next time period
What is the most important information for upper management from a testing project?
32Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
The most important information (my answer)
1. Evaluation of quality and status of the software development (project)
BriefEasy and quick to understandBrings clearly forth the relevant informationRisks
2. Problems that require management actions3. Status of testing versus plans
Accomplishments, coverage, defect counts and ratesExpensesRequired changes to plans
33Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Testing Dashboard
6.6.2003 Build 1.34.52
Functional Area Activity Coverage Quality Comments ☺ PerfectFile management low 2 ☺ HmmMain hierarchy high 2 Some weird behavior, still testing Aargghhh!Formatting high 2 Some critical bugs foundDrag and drop pause 1 Don't work with other applications 3 Its testedImports Ready 3 ☺ 2 Features checkedExports blocked 0 Can't test: no specs for exprt formats 1 We tried it (once)Overall GUI blocked 3 A lot of small bugs 0 NothingEditing area pause 2 ☺ Looks goodClipboard 0 Not deliveredProperty tables 0 Not implementedPreferences high 1 Nothing serious yet…Help pause 2 Mainly spelling and grammatic issues
Kaner et al. 2002. Lessons Learned in Software testing.
34Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Risk-based reporting
Res
idua
l Ris
ks
P r o g r e s s t h r o u g h t h e P l a n n e d T e s t i n g
T o d a y P l a n n e dE n d
S t a r t
A l l i d e n t i f i e d r i s k s o p e n a tt h e b e g i n n i n g
R e s i d u a l r i s k s o f r e l e a s i n gt o d a y
Gerrard, P. & Thompson, N. 2002. Risk-based E-business Testing.
35Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Risk based testing
Risk based test case design techniquesGoal is to analyse product risks and use that information to design good tests (test-cases)How this system could fail?
Error guessingFailure modelsExperience
Risk based test management Estimating risks for each function or featureUsing risk analysis to prioritise testing
Choosing what to test firstChoosing what to test most
36Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Qualitative vs. quantitative
Technical IncompatibilityVery likelyCould affect many usersSystem facilities not fully available or usable
Funding withdrawnUnlikelySevere impact
Technical Incompatibility70% likelihoodmay affect 80 % of users7 facilities could be unusable, 3 difficult to use
Funding withdrawn5 % probability95 % chance of project cancellation (5 % find other sponsors)
37Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Qualitative risk analysis
Low impact, likely
Low impact, mid-likely
Low impact, unlikely
Some impact, likely
Some impact, mid-likely
Some impact, unlikely
Severeimpact, likely
Severeimpact, mid-likely
Severeimpact, unlikely
Mostbenefits in addressingthese risks
NuisancesInsignificant
Nightmares
unlikely mid-likely likely
Severeimpact
Someimpact
Lowimpact
38Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Example – Statistical Risk Analysis Matrix
InterestCalculation
Close Account
CreateAccount
Dev Cust Avrg.NewFunc.
DesignQual. Size
Com-plexity
Weigh.Sum
RiskExposure
5 5 1 3
3 3 3
1 3 2
2 1 1,5
2 3 3 3 37
2 2 2 3 31
3 3 2 3 41
111
62
61,5
Cost * Probability = Re
Modified slide, originally from Ståle Amland
Weight
Idea is to get the features into priority order - somehow
39Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Collectionsan empty collection exactly one element (this is somewhat low-yield) more than one element
the maximum number of elements (if that's not reasonable, try it at least once with more than just a few elemenduplicate elements
Searching Collectionsmatch not found. (If searching a limited subset of a collection, arrange for there to be a match outside that subset. Example below.) one match (The best possible place to put it is probably just before the end bounds, if such a thing makes sense. Example below.) more than one match
Finding subsets (filtering out elements)Filtering out no elements (subset is the same as the original) Filtering out one element Filtering out all but one element Filtering out all elements (subset is empty)
Special collection elementsthe collection contains itself (redundant with next one, but the first one to try). indirect containment: the collection contains a collection that contains the original collection
Pairs of collectionsBoth collections empty First collection has one element, second has none. First collection has no elements, second has one. Both collections have more than one elements.
Test catalogs can be helpful
40Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
ContainersAppending to a container's contentsContainer initially empty. Container initially not empty. Adding just enough elements to fill it. A full container, adding one element. A partially full container, add one too many elements Add zero new elements
Overwriting a container's contentsNew contents have one more element than will fit New contents just fit. Zero elements used. Is the container correctly emptied? Some elements added, but fewer than in original (are old contents correctly cleared?)
Deleting elementsThe container has one element (low yield) The container is already empty.
FilesAbility to operate on the filethe file exists
it's readable it's not readable it's writeable it's not writeable
the file does not exist it doesn't exist, but it can be created it doesn't exist, and it can't be created
File typesAn ordinary file A directory/folder An alias or symbolic link (note that both exist on Mac OS X) A special file (Unix)
41Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
NamesWhatever the name names does not exist Two different names name the same thing.
PathnamesPOSIX / M ac OS XEmpty. (For example, in a Unix shell, give it the argument "", which is equivalent to ".".) Absolute Example: /tmp/foo Relative Example: tmp/foo
If the program is likely to take the pathname apart (to use one of its parts, or to build a new pathname): Containing the component "..", as in ../../dir/X Slash at end: foo/ No slash: foo Slash in the middle: foo/bar More than one slash: foo/bar/baz Duplicate slashes: foo//bar (should be equivalent to foo/bar)
Pathname as argument to command-line command: Pathname begins with dash. (How do you get the command to work on -file?)
PercentageIf the percentage is calculated from some Count, try to make the count be zero.
42Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Textual Input/QuotedUnpaired Quotes
Quote mark as first character in text. Example: \abcd Quote mark somewhere in the middle of the text. Example: ab\cd Quote mark as the last character (quoting nothing). Example: abcd\
Paired QuotesLik e double quotes (") around strings, or /* */ around Java comments. I'll use /* and */ for start-of-quote and end-of-quote. Quote everything - no unquoted text. A quote in the middle - with "real" text before and after it. Example: ab/*de*/fg No closing quote mark. Example: ab/*de Opening quote as last character in the text. Example: /* Nested quotes. Example: /*/*hi*/*/ Nothing inside the quote. (low yield) Example: /**/ Open quote without close quote. Example: /*no end Close quote without open quote. Example: no beginning */
CombinationsSingle-quoted double-quote mark. Example: \"some text without closing quote Double quote, where close-quote immediately follows a single-quote mark. Example: \/*Not quoted.
Lik e Unix's use of \ to quote many special characters, or comments that apply from comment character lik e # or // to the end of the line. In the
43Juha ItkonenSoberIT/HUTHELSINKI UNIVERSITY OF TECHNOLOGY
Textual inputNothingEmpty (clear default)0LB-1 LB = Lower boundaryLB UB = Upper boundaryUBUB+1Far below LBFar above UBUB number of charsUB+1 number of charsFar beoynd UB charsNegativeNon-digit (/ ASCII 47)Non-digit (: ASCII 58Upper ASCII (128-254) charactersASCII 255 Wrong data typeExpressionsLeading zerosLeading spacesNon-printing charO/S file nameUpper ASCIIUpper caseLower caseModifiers (ctrl, alt, etc.)Function keysEdited with backspace and deleteInput while processingLanguage reserved characters