tornado licensing basis and mitigation strategy · 2012. 11. 20. · tornado licensing basis and...

Post on 04-Oct-2020

2 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

/|Duake

Tornado Licensing Basisand Mitigation Strategy

Kick-off Meeting

9f 9-TTT 99 999 9 -TTTTTg Oconee Nuclear StationMarch 17, 2005

1

Duker Agenda

L IntroductionsLi ObjectivesL Oconee Licensing Basis InsightsLiJ\Safety ReviewLi Design Basis Upgrade Initiative

SummaryL Potential ModificationsCl Closing Remarks

2

^ Dukebl~e~rig Goals & Objectives

I c 7 7 * , - -

EJ Engage with NRC to find and implement aneffective solution to the Oconee Tornado licensingbasis and mitigation issues

L Provide anan Oconee

overview of licensing basis insights fromperspective

l Communicate results of the Safety Reviewperformed relative to the list of NRC concerns

E Move beyond differences in interpretation of theOconee current licensing basis

3

DuEke Goals & Objectives

LI Establish a framework of cooperative issue resolution withNRC/ What changes will bring our two views of the Current Licensing

Basis (CLB) closer together?/ Craft a LB both Duke and NRC agree on, and most

importantly, stands the test of time.

LI Provide an overview of modifications under consideration toeliminate or decrease tornado vulnerabilities

Li Provide periodic status to NRC of Duke activities tostrengthen the licensing basis both in the short-term andlong-term. Establish a schedule to support these discussions

4

Duke Oconee Licensing Basis Insights

Cl Original LB (1973 - Unit 1; 1974- Units 2 and 3)

Oconee's initial operating license pre-dates the GDCs, SRPs and theNRC (AEC).

/ several diverse and physically separated power sourcesV abundant supply of water (up to 37 days)/ protected station ASW pump and power supplyv/ no single failure requirementsv/ tornado does not occur with nor can not cause a LOCA

El Issues not addressed with respect to tornadoes in original FSAR/SER:V Primary make-up capabilitiesX RCP seal LOCAsV PORV/PRV failuresIv SG tube stresses

5

lukewnergy Oconee Licensing Basis Insights

1 .

EJ LB: 1974-1994

/ NUREG 0737, ll.E.1. 1, "Short-term Auxiliary FeedwaterSystem Evaluation"

a/ SSF begins operationLI LB: 1995

/ Primary make-up capabilities added to UFSAR due to industryRCP seal LOCA concerns.

* SSF RCMU* HPI pump fed from BWST or SFP

LI LB: 1998 - present/ Added clarification to UFSAR 3.2.2 based on IPEEE risk

results.6

Dukee Results of Safety Review

INAMIMants MINIM-111 0- ;47! I Mly?-`�M;Vz Mi -rM! i. 7-7-2,�,.,7-.-?:!� 1 �--

El A Safety Review was performed for each"Licensing Basis Discrepancy" document

issue identified in thereceived from NRC.

El The Oconee position is thatan operability determination

we are in compliance with CLB. Therefore,in accordance with GL 91-18 did not apply.

Li The CLB is based on diversity and defense in depth, not deterministic.

/ Concerns articulated by NRC are tornado vulnerabilities, not licensingbasis conformance deviationsGL 88-20 drove non-SRP plants to perform IPEEE evaluationsThe IPEEE Technical Evaluation Report (TER) for Oconee acceptedthe IPEEE's conclusion that Oconee had no severe accidentvulnerabilities that needed to be addressed via the 10CFR 50.109backfit process

/ GL 95-04, System Evaluation Process (SEP), contains a table thatsupports the Oconee position regarding IPEEE tornado strategy

Dukemnergy Results of Safety Review

U NRC concerns list evaluatedv Results:

* Safety evaluation performed. Based primarily on low-riskimpact of the items from the list, Oconee is safe.

* UFSAR needs to be clarified.Action:

* Submit an LAR to clarify/strengthen UFSAR Section 3.2.2U LAR Details

V Traditional LAR submittal w/risk insights (but not a classic riskinformed LAR per RG 1.1 74)Clarify actual mitigation strategy

* Limitations are described/quantified using risk* Overall tornado risk discussed

8

ZDuke Design Basis Upgrade Initiativeer Modifications

L Presentation addresses phase I of the modprocessv Investigate design conceptsv' Evaluate feasibility and constructability/ Develop order of magnitude cost estimates

1L Mod proposals outlined in this presentationv/ Developed as an aid for the vendorsv/ The optimum design concept resulting from phase I

of the mod process may differ significantly from themodification proposals outlined in this presentation

9

Duke Design Basis Upgrade Initiativee Modifications

1 ScopeEnhance natural phenomena barriersImproved alternate safe shutdown path* Using Station ASW and HPI* Upgraded power supplies* Control from the main control room* Significantly reduces tornado damage frequency

10

ZDuke Design Basis Upgrade Initiativee Modifications

IN -,/, I it.. , _. .

Li Scope (cont'd)Enhance natural phenomena barriers* Upgrade north Unit 3 Control Room Wall

> Missiles addressed via TORMIS submittal> Wind/DP to be addressed with additional shielding

* Upgrade elevated SSF trench to withstand missiles* Upgrade west pen and cask decon room walls for

missiles, wind, and DP

11

DukeCEnergy

Design Basis Upgrade InitiativeModifications

--- --.-

IJSensitive Information (withheld per SECY 04-01 91)

12

Dukee

Design Basis Upgrade InitiativeModifications

LJSensitive Information (withheld per SECY 04-0191)

13

Dukeenergy

Design Basis Upgrade InitiativeModifications

LIS'ensitive Information (withheld per SECY 04-0191)

14

Duke Design Basis Upgrade InitiativeEnergy Modifications

D Scope (cont'd)v/ Alternate safe shutdown path

Station ASW> Upgrade Station ASW to high pressure system

Eliminates need to manually operate atmosphericdumpsImproves tube to shell differential temperatures

> Provide start and flow control and indication in control roomResponse time reduced from 40 minutes to less than 15minutesEliminates PORV, PSV challengeImproves three unit control capability

15

Legend \/ Cm )3ASW-11 3ASW-12Existing Piping to Remain b . ,

- New or Replaced Piping .C Pr - I

l51°U3 HPIP's SStF-ASVI

Return to U2 CCW Inlt

Proposed Station ASW Upgrade 16

ergyDesign Basis Upgrade Initiative

Modificationsi. '- --. , 2

I Sensitive Information (withheld per SECY 04-0191)

17

Dueke Design Basis Upgrade Initiativeer Modifications

Cl Scope (cont'd)v New Station ASW switchgear loads

* High pressure ASW pump & system> Isolation Valves> Flow control valves> Flow instrumentation

* One HPI pump per unit & system> Provide remote transfer to new ASW switchgear for one HPI

pump/unit> Provide sufficient power and cubicles for future equipment

(next slide)

18

DuIke Design Basis Upgrade Initiativeer Modifications

WHIM - _ = 7777e r r . .+

Ii Scope (cont'd)v' Alternate safe shutdown path (cont'd)

HPI (to follow Station ASW and electrical upgrades)> Provide hardened power supply and remote control for

BWST suction valvesRCP seal flow control valvesReactor head and high point vent valves for letdownPressurizer heaters

19

ZDuke Design Basis Upgrade Initiativeer Modifications

Li Proposed Schedulev' Duke completes phase I of the mod process

* Natural phenomena barriers> Complete design concepts- May 2005> Test of concepts if necessary- End of 2005

* Station ASW and electrical enhancement- End of 2005* HPI upgrade- to follow Station ASWand Electrical

UpgradesDuke initiates final design package- early 2006

20

Duke Design Basis Upgrade InitiativeEnergy Modifications

O Statusv Natural phenomena barriers

* Contracted Fluor to develop design concept@ Past experience at Hanford* Design concept, feasibility, order of magnitude cost on

target for completion by May 2005* Testing targeted for completion by end of 2005 if

necessary

21

Duke Design Basis Upgrade InitiativeEnergy Modifications

El Status (cont'd)v Station ASW

* ONS mod teams in place (PM, lead design eng, riskreduction eng, system eng)

* Technical Scope Requirement document completed* Request for quotes sent to vendors this week

/ Upgrade power suppliese ONS mod teams in place* Draft Technical Scope Requirement document

completed* Request for quotes to vendors to be sent out by the end

of March22

XDuke Design Basis Upgrade Initiative1119TV Modifications

Li Challenges/ Accelerated schedule

e Feasibility/design for SG Replacement took several yearsa Large, complex project* Scarce resources for oversight* Working with new vendors

/ Technical Challenges* Providing alternate or upgraded power supply to new ASW

SWGR* New cable runs to cable spread room* Avoiding adverse impact on existing SSCs* Implementation- CT5, Standby Bus and Station ASW are 3

unit systems23

/ Graded approach to a technical review./Could be eng li supv or couMd he/

' / ~MRPT t 'phase review./

anl E /-/Preliminary scope.ine Ible Yes describing 'what is anageme

_ soluti .s obtains Yess the s teen\ nierim cion No dosired and _ od Actvate MRPT Discrelion Io Noat onInput. and ap rnt Required? relative priority Is yImplement asa

makes produced and sent enieharecommendrlion. _ to Mod Eng. Mod

N Engineering Yes

Bac to; PIP and Documr.n1 InterirnmPlant Eng for other Dsign . ion' l action in the l

/souions to be tad tiHeatth Report and l mo Mod Eng createsY/ pnoblem /implement action cope proposa procurement spec,

be deveoped request forhenu proposat

Plant Eng n I *Yes Mod Eng sends4 performs rfo >,package to

evaluallon I Mod Eng creates vendors forscope and proposal

associated cost developmentI PIP id.lifies a | Yestimate

IMod En ere Mod Eng reviewsMod ng erfrms rojct e &proposals and

14 evaluation lea rthe Mod Eng creates selects best'.aluanion. Evaluate Impact of scope. associated

Plus Senior Emergent Mod on cost estimate.Management s= Scheduled Work priorty. and |

Discroion Nschedule. SendsDiscreion I|to Plant Eng. forreview.

Plant Eng.ERRT develops Reviews and

appropriate approvesEngineering

Change R No MRPT performs

/Acknowlde \ review forScheduln Ipacs > prioritizaton |\ nd Aclivale / | budgeting, slotting|

MOO and final decision.|

Back to PIP andv od egi r Ye s No Plant Eng for other

Phase I of the Mod Process vn bpginhase ss p solutionseto

24

Duke Design Basis Upgrade Initiativee Modifications

~ nv.. - -. .....:- ,..- .

El NRC concerns being addressedNatural Phenomena Barriers* New power supply from Station ASW Switchgear to

battery chargers in Auxiliary Building* Upgraded west penetration and cask decon rooms* Upgraded unit 3 north control room wall* Upgraded SSF trench* Eliminating manual actions in turbine building to open

atmospheric dumps

25

Design Basis Upgrade Initiativenergy Modifications

J NRC concerns being addressed (cont'd)Mitigation system functionality@ Reduces PORV and PSV challenge* Significantly reduces steam generator tube to shell

differential temperatures* Remote and reliable flow control of station ASW to all

three units* Provides for hot shutdown capability using HPI and

alternate letdown paths (to follow Station ASW andelectrical upgrades)

26

Duker Closing Remarks-5 .- - :

Oconee is safe today relative to tornado riskOconee will add clarity and detail to the existing LBcontained in UFSAR.Modifications are being aggressively pursued toaddress vulnerabilities and improve overall tornadomitigation strategy for the future.Oconee has a strong desire to proactively engagewith NRC to resolve these issues and implementsatisfactory solutions.QuestionsNext meeting

27

top related