u04 cost accumulation system
Post on 28-Apr-2015
266 Views
Preview:
TRANSCRIPT
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 1
PART 1
Financial Planning,
Performance and
Control C. Cost Management (25% - Levels A, B, and C)
Job costing (Cost accumulation method) with Actual costing (Cost measurement method)
Job costing (Cost accumulation method) with Normal Costing (Cost measurement method) & End-of-
Accounting- Year Adjustments
ACTUAL/NORMAL/STANDARD COSTS
TRADITIONAL COSTING SYSTEMS (single& departmental) Vs. ABC
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 2
INTRODUCTION
Product costing is the process of accumulating, classifying, and assigning direct materials, direct labor, and
factory overhead costs to products or services.
Product costing provides useful cost information for both manufacturing and nonmanufacturing firms for
(1) product and service cost determination and inventory measurement,
(2) management planning, cost control, and performance evaluation, and
(3) strategic and operational decision making.
Several different types of product costing systems are available; these include :
(1) Cost accumulation method-job or process costing systems,
(2) Cost measurement method-actual, normal, or standard costing systems, and
(3) Overhead assignment method-traditional or activity-based costing systems.
The choice of a particular system depends on
(1) the nature of the industry and the product or service,
(2) the firm's strategy and management information needs, and
(3) the costs and benefits of acquiring, designing, modifying, and operating a particular system.
Cost accumulation systems represent the manner in which the accounting system develops costs. The system
is modified by the cost object involved. Most commonly tested cost accumulation systems are job order costing
and process costing,
if the cost object is a custom order, job costing may be used, and
if the cost object is a mass produced homogeneous product (e. g., steel), process costing using
average costs would be used.
Further, there are many variations of cost accumulation systems-those that use components of both job
order costing and process costing (e. g., operations costing), and
those that account for certain costs at the end of the process (e. g., back flush costing) because there is
little need for in- process inventory valuation.
Other systems (e. g., life cycle costing) seek to monitor costs throughout the product's life cycle and
expand on the traditional costing systems that focus only on the manufacturing phase of a product's life.
Finally, the assignment of costs to cost objects may occur using a variety of cost drivers (or allocation
bases). Activity- based costing is an approach that assists in the assignment of costs, regardless of the
cost accumulation system used.
STUDY UNIT FOUR COST ACCUMULATION SYSTEMS
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 3
JOB ORDER COSTING
(COST ACCUMULATION
SYSTEM)
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 4
III. JOB ORDER COSTING (COST ACCUMULATION SYSTEM)
Job-order costing is the method of product costing that identifies the job (or individual units or batches) as the
cost objective and is used when there are relatively few units produced and when each unit is unique or easily
identifiable.
A. COST OBJECTIVE IS THE JOB (OR UNIT)
Under job order costing, cost is allocated to a specific job as it moves through the manufacturing process.
Record keeping for job-costing emphasizes the job as the cost objective.
Job-cost systems are best suited for customized production environments such as construction, aircraft
assembly, printing, etc. A new job-cost record would be started every time a new job (building project, airplane
or print job) is started.
B. JOB COST RECORDS
Job-cost records are maintained for each product, service, or batch of products, and they serve as the primary
records used to accumulate all costs for the job. Job-cost records are also referred to as job-cost sheets or job
orders. Job-cost records accumulate data from the following internal documents:
1. Materials Requisitions
Materials requisitions are documents that show the materials requested for use on the job.
2. Labor Time Tickets (Time Cards)
Labor time tickets (time cards) are documents that show the labor hours and labor rate associated with the time
applied to the job.
3. Overview of Job Order Costing
Job-costing systems require a limited number of work-in-process accounts.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 5
Pictorial Overview
Job Order Costing
PASS KEY
Application of overhead is accomplished in two steps:
Step #1: Calculate Overhead Rate = Budgeted Overhead Costs ÷ Estimated Cost Driver
Step #2: Apply Overhead = Actual Cost Driver x Overhead Rate (from Step #1)
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 6
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 7
TRADITIONAL COSTING SYSTEMS (single& departmental) Vs. ABC
LIMITATIONS OF TRADITIONAL COSTING SYSTEMS
For example, Dole Company has two factories Alpha and Beta. Alpha is a highly automated factory; Beta is a
labor-intensive factory. The company has budgeted the following information for the year:
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 8
To obtain more accurate product-costing information, assume that Dole Company decides to use two cost
drivers, i.e., two separate departmental overhead rates for overhead costs, with a machine-hour-based rate for
Alpha and a labor-hour-based rate for Beta. The departmental predetermined overhead cost driver rates are
calculated as follows:
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 9
Using departmental overhead rates, the factory overhead cost assigned to the two products follows:
The preceding calculations show that the applied overhead costs with the single plantwide overhead cost driver
rate are $13,000 ($45,000 - $32,000) higher for Widget and $13,000 ($15,000 - $28,000) lower for Gidget than
had the firm used the two departmental overhead rates. Gidget requires considerably more machine-hours than
Widget, but the overhead cost allocation to products with the single plantwide overhead cost driver rate does
not consider these differences. Use of departmental rates causes product cost to more accurately reflect the
different amount of labor and the different types of machinery and labor involved in producing the two products.
Departmental rates, however, do not consider the varying overhead costs of different processes or activities;
within a department because some factory overhead costs are not volume based. For example, machine setup
cost, product design cost, purchase ordering cost, and materials handling cost are not directly related to either
direct labor-hours or machine-hours. The traditional volume-based plantwide and departmental cost driver rate
overhead allocation methods can lead to inaccurate product costing.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 10
ACTIVITY-BASED COSTING
(Transaction-based costing)
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 11
ACTIVITY-BASED COSTING (transaction-based costing)
Definition
Activity- base d costing (ABC) is define d as a cost accounting system that is based on activity level as
the fundament al cost object. Activity- base d costing is also referred to as transaction-based costing.
The cost driver is typically the number of transactions involve d in a particular activity.
Characteristics of ABC
ABC applies a more focused and detailed approach than using a department or plant as the level for
gathering costs.
ABC can be part of a job order system or a process cost system.
ABC can be use d for manufacturing or service businesses.
ABC takes a long-term viewpoint and treats production costs as variable.
The cost driver is often a non-financial variable.
ABC may be used for internal and external purposes (as can job order costing and process costing).
ABC is a refinement of an existing costing system (job-order or process)
Under a traditional (volume-based) costing system, overhead is simply dumped into a single cost pool
and spread evenly across all end products.
Under ABC, indirect costs are attached to activities that are then rationally allocated to end products.
ABC may be used by manufacturing, service, or retailing entities.
ABC focuses management on the cost/benefit of activities. Value-added activities increase the product
value or service.
a. Value Chain (Value-added Activities)
A value chain is a series of activities in which customer usefulness is added to the product. Support
activities directly support value- added activities.
b. Non -value Added Activities
Non-value added activities do not increase product value or service and are targeted for elimination. These
types of activities (e. g. warehousing)should be eliminated.
ABC Vs. Peanut-butter costing.
The inaccurate averaging or spreading of indirect costs over products or service units that use different
amounts of resources is called peanut-butter costing.
Peanut-butter costing results in product-cost cross-subsidization, the condition in which the miscosting
of one product causes the miscosting of other products.
The peanut-butter effect of using a traditional (i.e., volume-based) costing system can be summarized
as follows:
Direct labor and direct materials are traced to products or service units.
A single pool of indirect costs (overhead) is accumulated for a given organizational unit.
Indirect costs from the pool are assigned using an allocative (rather than a tracing) procedure, such
as using a single overhead rate for an entire department, e.g., $3 of overhead for every direct labor hour.
o The effect is an averaging of costs that may result in significant inaccuracy when products
or service units do not use similar amounts of resources.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 12
Volume-based systems, as illustrated above, involve:
Accumulating costs in general ledger accounts (utilities, taxes, etc.).
Using a single cost pool to combine the costs in all the related accounts.
Selecting a single driver to use for the entire indirect cost pool.
Allocating the indirect cost pool to final cost objects.
Activity-based systems, by contrast, involve(4 main steps):
Identifying organization activities that constitute overhead.
o In this step ABC team will define activities , activity cost pools and activity measures (resource
cost drivers)
o Activity cost pools will group activities according to five categories of activities (unit-level
activity, batch-level activity, product-sustaining activity, facility-sustaining activity, customer-
level activity)
Assigning the costs of resources consumed by the activities to activity cost pools using resource cost
drivers, In this step first-stage allocation will be applied ,
o Stage one: resource cost assignment of overhead costs to activity cost pools or groups of
activities called activity centers using appropriate resource cost drivers (here functionally
organized overhead costs derived from a company’s general ledger will be assigned to the
activity cost pools.)
Calculate activity rates (by dividing total cost for each activity by its total activity (activity cost driver) (ex:
the cost of product design cost pool will be divided by no. of designs (activity cost driver).
Assign overhead costs to cost objects , in this step second-stage allocation will be applied,
o Stage two: activity cost assignment of activity costs to cost objects (Product or service) using
appropriate activity cost drivers.
A traditional cost system assigns overhead with a single plant-wide overhead application rate or rates for operating departments. These rates are volume-based using an application basis such as direct labor hours or machine hours. All overhead costs, however, do not fluctuate with volume. Assigning these costs with a volume basis will distort the amount of costs assigned to various product lines. Activity-based costing attempts to correct this by emphasizing long-term product analysis.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 13
ABC TERMS
Activity
An activity is work performed within an organization. It is also an aggregation of actions performed within an
organization useful for purposes of activity-based costing.
Activities are composed of actions, movements, or work sequences.
For example, moving inventory is a warehousing activity
Resource
A resource is an economic element applied or used to perform activities.
Salaries and materials, for example, are resources used in performing activities.
Two types of cost drivers
As defined in Chapter 3, a cost driver is any factor that causes a change in the cost of an activity. It is also a
measurable factor used to assign costs to activities and from activities to other activities, products, or services.
Note; In respect to ABC, two more terms with which you need to be familiar are resource drivers and activity
drivers. These are details in the allocation process and you are not expected to know this for a numerical
question, but perhaps for a CMA word question.
The two types of cost drivers are
resource cost drivers and
activity cost drivers.
A resource cost driver is a measure of the amount of resources consumed by an activity. It is the cost driver
used to assign a resource cost consumed by an activity to a particular cost pool.
An example of a resource cost driver is the percentage of total square feet required to perform an activity.
An activity cost driver measures how much of an activity a cost object uses. It is used to assign cost pool costs
to cost objects.
An example is machine hours required for the activity of running machines to produce product X.
Categories of Activities
There are five categories of activities, based upon where the activity occurs In relation to the final product and
the facility as a whole. These four categories are;
Activity-based costing (ABC) is a costing approach that assigns costs to products, services, or customers based on the consumption of resources caused by activities. Resources are assigned to activities, and activities are assigned to cost objects based on the activities' use.
ABC recognizes the causal relationships of cost drivers to activities
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 14
1. A unit-level activity : These activities are performed for each unit that is produced.
Examples of unit-level (volume-based or unit-based) activities include using direct materials, using direct labor-
hours, inserting a component, inspecting every item, and running machines.
2. A batch-level activity: These activities occur each time a batch is produced rather than for each unit of
production.
Examples of batch-level activities are setting up machines, placing purchase orders, scheduling production,
inspecting every batch, and handling materials.
3. A product-sustaining activity is performed to support the production of a specific product.
Examples of product-sustaining activities include designing products, administering parts, issuing engineering
change orders, and expediting.
4. A facility-sustaining activity is performed to support the production of products in general. Examples of
facility-sustaining activities include providing security, safety, maintenance, and plant management, calculating
plant depreciation, and paying property taxes.
5. A customer-level activity includes activities that are performed to support customer needs such as customer
service, phone banks, or custom orders.
Benefits and Limitations of an Activity Based Costing System
Benefits
Activity-based costing helps reduce distortions caused by traditional cost allocations.
It provides a clear view of how the mix of a firm's diverse products, services, and activities contributes to the
bottom line in the long run.
Major benefits of the activity-based costing are the following:
1. ABC provides more accurate and informative product costs, which lead to more accurate product profitability
measurements and to better-informed strategic decisions about pricing, product line, customer market, and
capital expenditure.
2. ABC provides more accurate measurements of activity-driving costs, which helps managers improve product
and process value by making better product design decisions, controlling costs better, and fostering various
value-enhancement projects.
3. ABC provides managers easier access to relevant costs for making business decisions, enabling them to
take a more competitive position
Note; Fortunately, on the CMA Exam you will generally not need to Identify the cost drivers or cost pools in a
large question because they will be provided for you. You will simply need to use the provided Information to
determine the amount of overhead that will need to be allocated to any product. In a smaller question It is
possible that you will need to determine the appropriate driver, but these are usually fairly direct, and If you
simply think about what would cause costs to be Incurred, you will see the correct answer.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 15
Limitations
Although activity-based costing provides better tracing of costs to individual products than traditional systems,
managers should be aware of its limitations before using it to calculate product costs:
1. Allocations. Even if activity data are available, some costs probably require allocations to departments and
products based on arbitrary volume measures because finding a specific activity that causes the incurrence of
the costs might not be practical. Examples are some of the facility-sustaining costs, such as cleaning the factory
and managing the production process
2. ABC reports do not conform to GAAP, so restating financial data adds an expense and causes confusion
(unsure whether to rely on the ABC or external data).
3. Expense and time. An ABC system is very expensive to develop a~t and is very time consuming. Like most
innovative management or accounting systems,
4. ABC usually requires more than a year for successful development and implementation.
5. ABC generates vast amounts of information. Too much information can mislead managers into concentrating
on the wrong data.
Comprehensive Example to compute product costs under a traditional costing system and an activity based
costing system.
The following example contrasts steps 2 and 3 of the traditional costing system, using direct labor-hours as the
cost driver, with the activity-based costing system, using both volume-based and non-volume-based cost
drivers.
Northern High-Tech, Inc., successfully produces and sells two types of quality printers, the deluxe and the
regular. Assume that the company has the following financial and cost data for the two products:
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 16
The company's management accountant has identified the following activities, budgeted cost pools, and activity
drivers:
These are the actual activity units or transactions for each product:
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 17
Traditional Costing Analysis In the traditional costing approach, the factory overhead (OH) is allocated on the
basis of direct labor-hours (DLH) as the cost driver:
Activity-Based Costing Analysis In the activity-based costing approach, the cost driver rate for each activity cost
driver-that is, the activity rate-is calculated as follows:
Factory overhead costs are assigned to both products, as shown by these calculations
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 18
Exhibit 4-6 presents a product profitability analysis under the activity-based costing system and Exhibit 4-7 compares
product costs and profit margins under the two costing systems.
EFFECTS OF ABC An ABC system will apply high amounts of overhead to a product that places high demands on expensive resources. If a product places few demands on expensive resources, the system will assign little of that cost to the product. This will remove much of the cost distortion caused by traditional, volume- based overhead systems.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 19
Remember that one major limitation of the traditional costing system is that it generally undercosts complex
low-volume products and overcasts high-volume products.
The activity-based costing system presents a more accurate measurement pattern of overhead consumption.
The preceding comparison shows that the traditional product costing system can significantly undercost the
deluxe printer (a low-volume product) and overcast the regular printer (a high-volume product) compared with
the actual overhead consumption. Consequently, traditional product costing can cause distorted inventory
measurement, incorrect product-line decisions, unrealistic pricing, ineffective resource allocations, misplaced
strategic focus, misidentified critical success factors, and lost competitive advantage.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 20
LIFE-CYCLE COSTING (basis for cost planning and product pricing NOT GAAP)
A life-cycle approach to budgeting estimates a product's revenues and expenses over its entire sales life cycle
beginning with research and development, proceeding through the introduction and growth stages into the
maturity stage, and finally into the harvest or decline stage.
Accordingly, life-cycle costing fakes a long-term view of the entire cost life cycle, also known as the value chain.
Value Chain for a Manufacturer
Upstream costs Downstream costs
The total costs for a product's life cycle have three phases, thus Costs are determined for all value-chain
categories:
1. Upstream (R&D, design),
a. Upstream costs: costs that are prior to the manufacturing of the product or sale of the service, such
as R&D or design (prototypes, tests, and engineering)
2. Manufacturing,
a. Manufacturing costs: costs involved in producing a product or service, such as purchasing and
direct and indirect manufacturing costs and
3. Downstream (marketing, distribution, and customer service).
a. Downstream costs: costs subsequent to (or coincident with) manufacturing costs, such as
marketing, distribution (packaging, shipping and handling, promotions, and advertising), service
costs, and warranty costs (defect recalls, returns, and liability).
LIFE CYCLE COSTING VS. TRADITIONAL COSTING
In contrast, traditional approaches focus on cost control (as opposed to cost reduction) during production and
treat pre- and postproduction (upstream and downstream) costs as period costs that are largely ignored in
determining the profitability of specific products.
a. Other costs that traditional methods ignore are the after-purchase costs (operating, .support, repair; and
disposal) incurred by customers.
CMA Sample Q (Whole-life cost equals the Life-cycle cost plus after-purchase costs.)
Claremont Company has been asked to evaluate the profitability of a product that it manufactured and sold from
Year 7 through Year 10. The product had a one-year warranty from date of sale. The following information
appears in the financial records.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 21
Research,
development, and Manufacturing and
design cost distribution costs Warranty costs Warranty cost
Yr 5 & Yr 6 Yr 7 - Yr 10 Yr 7 - Yr 10 Yr 11
$5,000,000 $7,000,000 $200,000 $100,000
The life-cycle cost for this product is…………………..
Life-cycle costing takes into account costs incurred at all stages of the value-chain, not just manufacturing. The life-cycle
cost for this product is thus $12,300,000 ($5,000,000 + $7,000,000 + $200,000 + $100,000).
Life-cycle and whole-life cost concepts are associated with target costing and target pricing
A firm may determine that market conditions require that a product sell at a given target price. Hence, a target cost
can be determined by subtracting the desired unit profit margin from the target price. The cost reduction objectives of
life-cycle and whole-life cost management can therefore be determined using target costing.
LIFE-CYCLE COSTING (NOT GAAP)
For financial statement purposes, costs during the upstream phase must be expensed in the period incurred. For
management accounting purposes, the costs (such as R&D) that result in marketable products represent a life-cycle
investment and must therefore be capitalized.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 22
Backflush costing in just-in-time production systems
A just-in-time (JIT) system produces materials just as they are needed for the next step in production. The
trigger for manufacturing at a particular work area is the demand from the next station down the line, thus JIT
production systems are a "demand-pull" manufacturing system. Customer demand triggers initial production
need, working backward all the way to raw material purchases at the beginning of the cycle. JIT also reduces
manufacturing lead time by organizing manufacturing into cells that are closely coordinated. HT ensures timely
material deliveries and meets customer demands while simultaneously ensuring high-quality products at the
lowest possible cost. Therefore, organizations using HT production have very little inventory, making the choice
of inventory valuation methods (e.g., FIFO, weighted-average) and inventory costing methods (e.g., absorption
costing, variable costing) irrelevant because the costs flow directly to cost of goods sold during an accounting
period.
Backflush costing Vs. Traditional costing systems (sequential tracking)
Backflush costing. Costing system that omits recording some or all of the journal entries relating to the cycle
from purchase of direct material to the sale of finished goods.
Traditional costing systems use sequential tracking, which is any process that records purchases and
movements of costs between inventories and accounts in the order in which they occur.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 23
Process cost accounting
Process cost accounting is used to assign costs to inventoriable goods or services. It is applicable to relatively
homogeneous products that are mass produced on a continuous basis (e.g., petroleum products, thread,
computer monitors, Oil refining, Textiles, Paints, Flour, Canneries, Rubber, Steel, Food processing).
Characteristics of Process Costing
Due to mass production direct labor costs are usually small in comparison to other costing system , thus DL
cost combined with Manufacturing overhead to constitutes conversion costs.
Comparing Job-Order and Process Costing
Where job-order costing uses subsidiary ledgers to keep track of specific jobs, process costing typically has a
work-in-process account for each department through which the production of output passes.
Process costing is an averaging process that calculates the average cost of all units:
1) Costs are accumulated for a cost object that consists of a large number of similar units of goods or services;
2) Work-in-process is stated in terms of equivalent units;
3) Unit costs are established.
The accumulation of costs under a process costing system is by department rather than by project. This reflects
the continuous, homogeneous nature of the manufacturing process.
Because manufacturing overhead is assigned to work-in-process as part of conversion costs, there is rarely an
overhead control or overhead applied account under process costing, and the issue of over- or underapplied
overhead does not arise. The exception is when a standard costing system is used. Under standard costing, a
predetermined overhead rate (as in job-order costing) is used to assign overhead costs.(See flow of cost
accumulation in a process costing system in your book).
Steps in process costing
1. Account for all units (physical flow of quantities).
2. Compute the equivalent units of production (EUP).
3. Compute unit cost per EUP.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 24
Step 2: compute Equivalent Units of Production
a. One equivalent unit is the amount of direct materials or conversion costs (direct labor and manufacturing
overhead) required to produce one unit of finished goods.
b. The objective is to allocate direct materials and conversion costs incurred during the period to finished goods,
ending work-in-process (EWIP) and spoilage.
c. EUP is separately computed for direct materials and conversion (DL & MOH) costs.
Step 1: Account for All Units : step 1 important to determine any missing information in questions
(normally spoilage), same in both FIFO and Weighted average methods, ignores the %
percentage of completion for beginning and ending WIP).
.
Beginning WIP XX
Started Units this period XX
________
Total Units to Account for xxxxxx
Finished or
transferred-
out goods
Ending WIP
Spoilage
(lost)
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 25
Example: For the current period, Jones started 15,000 units and completed 10,000 units, leaving 5,000 units
in process 30 percent complete. How many equivalent units of production did Jones have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
Answer: 10,000 units + (5,000 units × 0.30)
= 11,500 equivalent units
Two cost-flow assumptions in Process costing: First In First Out (FIFO).Vs. Weighted Average.
First In First Out (FIFO) Assumptions:
Only costs incurred this period are allocated between finished goods and EWIP. Manufacturing costs in
beginning work in process (BWIP) are excluded from the current –period unit cost calculations.
The beginning work in process
(BWIP) inventory is to be
completed and transferred first.
The ending work-in-process
(EWIP) inventory results from
goods processed this period.
EUP is separately computed for
direct materials and conversion
(DL & MOH) costs.
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 26
EUP Computation under FIFO (If materials are added as work in process (continually):
Material Conversion
Total units Completed XX XX
- Beginning WIP (regardless of % of completion) (XX) (XX)
______________________
Units Started and Completed this Period XX XX
+ Amount needed to complete Beginning WIP XX XX
+ Amount Completed on Ending WIP XX XX
_______________________
EUP under FIFO XX XX
_______________________
If materials are added at the beginning of a process :
Total Units Completed XX
+ Amount of materials Needed to Complete BWIP zero
+ Amount of materials Added to Date on EWIP 100%
_____
EUP for Materials XXX
____
If materials are added at the end of a process
Total Units Completed XX
+ Amount of materials Needed to Complete BWIP 100%
+ Amount of materials Added to Date on EWIP zero
_____
EUP for Materials XXX
____
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 27
EUP : Weighted Average
Assumptions
No differentiation is made between goods started in the preceding and the current periods.
The beginning WIP inventory costs are merged with the costs of the units started during the period and
new average cost is obtained.
EUP under weighted average differs from EUP under FIFO by the amount of EUP in beginning WIP.
Total EUP completed from beginning WIP is not deducted in determining current EUP.
Comparing Weighted Average to FIFO
The difference between weighted average and FIFO is the handling of beginning WIP.
If there is no beginning WIP inventory, both assumptions will have the same EUP.
EUP :Example 1 The following data relate to the activities of department A during the month of
January :
assume that all materials are added at the beginning of the process .
Units Beginning WIP (66.67% Completed as to Conversion) 1,500 Units started this period 5,000 Units Completed and Transferred to the following process 5,500 EWIP (60% Completed as to conversion) 1,000
Required Compute EUP using FIFO and Weighted Average. EUP :Example 1 Solution Accounting for all units (Physical Quantities)
Units
BWIP 1500 Units Started this period 5000 Total Units to Account for 6500
Units completed and transferred 5500 EWIP 1000 Total Units to Accounted for 6500
EUP under weighted average costing may be computed as follows:
Total Units Completed this period XX
+ Work to date on Ending WIP XX
_____
EUP under weighted average XXXX
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 28
EUP : Examples 1 solution (EUP-FIFO) Materials Conversion Units Completed and transferred 5500 5500
- Beginning WIP (1500) (1500)
Units Started and Completed this period 4000 4000 Amount needed to complete BWIP 0% materials zero 33.33% Conversion (1500 units X 33.33%) 500 Amount to date on Ending WIP 100% Materials (1000 units x 100%) 1000 60% Conversion (1000 x60%) 600
EUP Under FIFO 5000 5100
EUP :Example 1 solution (EUP-Weighted average ) Materials Conversion Units Completed and Transferred 5500 5500 Amount to Date on EWIP 100%materials ( 1000 x 100%) 1000 60% Conversion ( 1000 x 60%) 600 EUP Under Weighted Average 6500 6100
EUP : Example 2 The same facts as in example 1 except that all materials are added at the end of
the process.
Required
Compute EUP using FIFO and Weighted average
EUP :Example solution (EUP-FIFO ) Materials Conversion Units Completed and transferred 5500 5500
- Beginning WIP (1500) (1500)
Units started and Completed this period 4000 4000 Amount needed to Complete 100% Materials 1500 33.33% Conversion (1500 x33.33%) 500 Amount to Date on Ending WIP 0% materials (1000 x 0%) 0 60% Conversion (1000 x 60%) 600
EUP Under FIFO 5500 5100
EUP :Example solution (EUP-Weighted average ) Materials Conversion Units Completed and Transferred 5500 5500 Amount to Date on EWIP 0% Materials (1000 x 100%) 0 60%Conversion (1000 x 60%) 600 EUP Under Weighted Average 5500 6100
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 29
Step 3 : Compute Unit Cost Unit Cost Under FIFO
Current Manufacturing Cost EUP (FIFO) Manufacturing Cost Current MC ÷ EUP (FIFO) = Unit Cost DM $xx ÷ xx = $xx Conversion (DL&MOH) $xx ÷ xx = xx Total Unit Cost –FIFO $XXX
Unit cost under Weighted Average (WA)
Cost of BWIP + Current manufacturing Cost EUP (WA) Manufacturing Cost BWIP Cost + Current MC ÷ EUP (WA) = Unit Cost DM $xx + $xx ÷ xx = $xx Conversion (DL&MOH) $xx + $xx ÷ xx = xx Total Unit Cost –Weighted Average $XXX
Accounting for spoilage
Southwood Industries uses a process costing system and inspects its goods at the end of
manufacturing. The inspection as of June 30 revealed the following information for the month of June.
Good units completed 16,000
Normal spoilage (units) 300
Abnormal spoilage (units) 100
Unit costs were: materials, $3.50; and conversion costs, $6.00.
What is the number of units that Southwood would transfer to its finished goods inventory and the
related cost of these units are?
Step 1: calculating the total cost of the completed units = 16,000 X ($3.5+$6) = $ 152,000
Step 2: adding only the cost of normal spoilage as it represents the additional product cost for the completed
units totaled 16,000 {Cost of Normal spoilage = 300 X ($3.5+$6) = $2,850}
Thus, for sure the number of units that Southwood would transfer to its finished goods inventory sould
based on the 16,000 “Good units completed” but with total cost =$ 152,000 + $2,850= $154,850
Prepared by: Sameh.Y.El-lithy. CMA,CIA. 30
Operation costing
Many companies have costing systems that are neither pure job costing nor pure process costing but have
elements of both. so it use a hybrid system called Operation costing, in a hybrid system direct materials costs
are charged to specific products (as in job-order systems) but conversion costs are accumulated and a unit
conversion cost for each operation is derived (as in process costing).
Example : Fashion Inc. manufactures women’s dresses using cotton and polyester. Since the same style
dresses are made out of both fabrics, Fashions uses operation costing.
During June, 1,000 cotton dresses were completely produced.
Also during June, 1,500 polyester dresses were started by adding all materials at the beginning of the process.
Of these 1,500 dresses, 700 were completely finished and the remainder were 25 percent complete by the end
of the month. There was no work-in-process inventory at the beginning of June.
Costs incurred during June were as follows.
Cotton $10,000
Polyester 22,500
Conversion costs 13,300
The cost per unit to manufacture one polyester dress during June was
M C
$22,500 $13,300.0
units
1500 1900 per unit
$15 $7 $22