Slinger School DiStrictPROJECT PROGRESS REPORT > > > April 2017

Phase 02: Addison Elementary / Allenton Elementary School

Questions? Contact:

Daren Sievers, Superintendent, at d.sievers@slingerschools.org or 262.644.9615Jim Curler, Assistant Superintendent, at j.curler@slingerschools.org or 262.644.9615

What’s New?April showers could not dampen spirits at the April 27th groundbreaking event at Slinger High School! The past month has brought referendum progress across the district, with construction teams continuing to collaborate with staff and administration. Addison Elementary has reached a major milestone with second floor precast structure in place and exterior walls growing taller! Progress at Allenton Elementary includes classroom casework and installation of plumbing fixtures, as well as interior finishes. Construction teams are mobilized at Slinger High School and excavation of the Auditorium Addition and Concession Building will begin shortly. See below and the following pages for construction progress photos and groundbreaking images.

Addison - addition overview from parking lot

Addison - second floor walls almost complete Addison - west elevation before roof installation

Slinger School DiStrictPROJECT PROGRESS REPORT > > > April 2017

Phase 02: Addison Elementary / Allenton Elementary School

Questions? Contact:

Daren Sievers, Superintendent, at d.sievers@slingerschools.org or 262.644.9615Jim Curler, Assistant Superintendent, at j.curler@slingerschools.org or 262.644.9615

Allenton - cabinets installed in classrooms; carpet is up next Allenton - view of gym windows from Inside

Allenton - view of gym windows from outside Allenton - insulation and brick has begun on gym exterior

Slinger School DiStrictPROJECT PROGRESS REPORT > > > April 2017

Questions? Contact:

Daren Sievers, Superintendent, at d.sievers@slingerschools.org or 262.644.9615Jim Curler, Assistant Superintendent, at j.curler@slingerschools.org or 262.644.9615

Phase 03: Slinger High School / Auditorium

STATUS: Construction is Underway! OVERVIEW: • Groundbreaking event for the high school was a huge success! Congratulations to all who devoted time and comments to the design.• Miron and JH Hassinger are mobilized and construction has begun.

◦ Excavation and site utilities will be the first priority on-site.

Auditorium Rendering

Concession Rendering

Slinger School DiStrictPROJECT PROGRESS REPORT > > > April 2017

Questions? Contact:

Daren Sievers, Superintendent, at d.sievers@slingerschools.org or 262.644.9615Jim Curler, Assistant Superintendent, at j.curler@slingerschools.org or 262.644.9615

Phase 03: Slinger High School / Auditorium

School board members at groundbreaking event