wise update and south metro’s progress to sustainable ... · • smwsa –renewable supply for...

Post on 22-Jul-2020

0 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Lisa Darling, Executive DirectorRick Marsicek, Director of EngineeringSouth Metro Water Supply Authority

October 5, 2017

WISE Update and South Metro’s Progress to Sustainable Water Supplies

Water Resources Review Committee

Who We Are

2

• 13 Members

• Serve 300,000 people

• Projected to serve 550,000 people by 2050– 80% of Douglas

County– 10% of Arapahoe

County

• Goal: Shift away from nonrenewable sources of water

• Plan based on three pillars1. Partnerships – Leverage relationships with each other, local

governments in the region, and other water providers

2. Investment – In supply and storage projects, individually and

collectively

3. Efficiency – Become a leader in conservation and the efficient

use of water

3

2004: South Metro Water Supply Authority

4

2016 Master Plan Update1999

Metropolitan Study

2003

South Metro Water

Supply Study

2007

Master Plan

2011

Master Plan Update

Shift to Renewable Supply• Early 2000’s: 60% nonrenewable; Many of the region’s

largest water providers were 100% nonrenewable

• By 2020: 22% nonrenewable

• By buildout (2065) it will be down to 15%

• Some entities are already almost

completely renewable on average

5

Tremendous Progress

Conservation and Efficiency

• Reduced per capita water demands across the region by 30%

• The region currently averages about 120 GPCD.

• The region is set up to reuse all of the supplies that are legally able to be reused.

6

0

50

100

150

200

250

2000 2010 2014

Gal

lon

s p

er c

apit

a p

er d

ay (

gpcd

)

Regional Per Capita Water Use (gpcd)

Tremendous Progress

ACWWA/ Cottonwood Joint Water

Purification Facility

WISE Project: Smoky Hill Tank

ECCV Northern Project

Chatfield Reallocation Project

Plum Creek Water

Purification Facility Rueter-Hess Reservoir

WISE Project: Quebec St.

Water Purification Facility

WISE Project: Aurora

Temporary Connection

Progress: Projects

8

WISE:Regional Collaboration

• Centennial Water and Sanitation

• Cottonwood Water and Sanitation

• Dominion Water and Sanitation

• Inverness Water and Sanitation

• Meridian Metropolitan District

• Parker Water and Sanitation District

• Pinery Water and Wastewater

• Rangeview Metropolitan District

• Stonegate Village Metropolitan

• Town of Castle Rock

South Metro WISE Authority

Aurora Water

Denver Water

Denver & Aurora Water

Supplies

Aurora’s PWP Infrastructure

Delivery to Aurora, Denver,

& SMWA

Uses $800 million in existing infrastructure• Cost Recovery for Aurora’s

Investments• Purchase of existing “Western

Pipeline”

Construction of ~$120M of new infrastructure

What is WISE?

• Aurora Water– Offset PWP costs (annual revenue of $10M)

– Continued use of PWP for drought supply

• SMWSA– Renewable supply for SMWSA (100KAF/10yr)

– Allows use of Denver Basin aquifer for drought supply

• Denver Water– Drought and emergency supplies for Denver

Opens the door to regional cooperationTotal Affected Population = 2 million 10

WISE:

Water Supply Benefits

WISE Timeline

12

2007 Began Planning

2013 WISE Water Delivery Agreement Executed

2014 WISE/DW Purchase of ECCV Pipeline

2015-2016 WISE infrastructure construction

June 2017 -- Final Completion of WISE Pipeline Modifications

Summer 2017 -- WISE Water Deliveries began to some WISE Members

Early 2018 – WISE Deliveries will begin to remaining members

WISE AGREEMENTS

13

WISE Infrastructure

WISE PIPELINE

- $34M Purchase

Aurora Water Connection

March 29, 2016

March 29, 2016

August 21, 2016

Smoky Hill Tank

April 1, 2015

August 6, 2015 September 10, 2015

Smoky Hill TankSeptember 28, 2015

October 28, 2015

April 20, 2016July 13, 2016

BEFORE

AFTER

Quebec Street Water Treatment Plant

March 17, 2015

March 15, 2016April 20, 2016

Quebec Street Water Treatment PlantMay 31, 2016

September 22, 2016

May 31, 2016 DW Bypass

February 2016

Pipeline Connections

ECCV Connection

January 18, 2017

Cottonwood Connection

February 1, 2017

Ridgegate Connection

January 31, 2017

Managing 10 Connections

22Partner Ordering Portal

Orders Entered into SCADA System

Summary of WISE Phase I Construction Costs

23

*Does not include investment by each WISE

Member for individual connections

2014 BudgetTotal $ 11.90

Denver Water $ 3.45 ECCV $ 3.45

WISE $ 5.00*

WSRA Grants $ 1.57

Summary of WISE Phase I Construction Costs

24

*Does not include investment by each WISE

Member for individual connections

2014 Budget Final CostTotal $ 11.90 $ 16.06

Denver Water $ 3.45 $ 3.45 ECCV $ 3.45 $ 3.45

WISE $ 5.00* $ 9.16*

WSRA Grants $ 1.57

Summary of WISE Phase I Construction Costs

25

*Does not include investment by each WISE

Member for individual connections

2014 Budget Final CostTotal $ 11.90 $ 16.06

Denver Water $ 3.45 $ 3.45 ECCV $ 3.45 $ 3.45

WISE $ 5.00* $ 9.16*

WSRA Grants $ 1.57 $ 2.49

WISE - SRF Loans

26

• 4 WISE Members received State Revolving Fund Loans totaling $35M to help pay for:

• Pipeline purchase

• Phase I infrastructure

• Future Infrastructure

Thank You !

Future WISE Infrastructure

1. Additional increment of

supply: ~30KAF of additional renewable supplies by 2065

2. Storage (surface and ASR) to

firm existing and new supplies

3. TDS management for new supplies and WISE supplies: Blend water or RO

4. Conservation: Individual member’s efforts and regional

28

Non-Renewable16,900 AF

14%

Renewable72,240 AF

60%

Planned Renewable20,000 AF

17%

Renewable Goal11,307 AF

9%

SMWSA Projected Supplies at Buildout (2065)

Non-Renewable Renewable Planned Renewable Renewable Goal

The Path Forward:

Our 4-Point Plan for the Future

Despite ongoing needs, our region is well on

its way to a secure water future.

29

The Bottom Line

Questions?

30

top related