an-najah national university

31
AN-NAJAH NATIONAL UNIVERSITY Faculty of Engineering Civil Engineering Department Graduation Project Local Productivity Rates For Formwork , Concrete and Waterproofing in structure elements Prepared By : Mohammad Rabay’a Mohammad Ghidan Omar Shaheen Supervisor : Eng.Lu’ay Dawikat

Upload: gratia

Post on 24-Feb-2016

22 views

Category:

Documents


0 download

DESCRIPTION

Faculty of Engineering Civil Engineering Department Graduation Project Local Productivity Rates For Formwork , Concrete and Waterproofing in structure elements Prepared By : Mohammad Rabay ’ a Mohammad Ghidan Omar Shaheen Supervisor : Eng.Lu’ay Dawikat. AN-NAJAH NATIONAL UNIVERSITY. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: AN-NAJAH NATIONAL UNIVERSITY

AN-NAJAH NATIONAL UNIVERSITY

Faculty of EngineeringCivil Engineering Department

Graduation Project

Local Productivity Rates For Formwork , Concrete and Waterproofing in structure elements

Prepared By :Mohammad Rabay’aMohammad Ghidan

Omar Shaheen

Supervisor : Eng.Lu’ay Dawikat

Page 2: AN-NAJAH NATIONAL UNIVERSITY

Contents Productivity definition and importance. Factors affecting productivity unsafe working conditions Ways of productivity improvement Productivity measurement. Implementation work . Data collection and analysis Conclusion and recommendations

Page 3: AN-NAJAH NATIONAL UNIVERSITY

“Productivity isn’t everythingbut in the long run it is almosteverything” Paul Krugman

Page 4: AN-NAJAH NATIONAL UNIVERSITY

Productivity Definition "Productivity is the quantitative relationship

between what we produce and the resources we use” (Currie (1972)).

In engineering it can be defined as the average direct labor hours to install a unit of material or Output per unit of time.

For construction managers, the output can be construction tasks such as cubic meters of concrete, square meters of some surface, tons of steel or linear meters of weld.

Page 5: AN-NAJAH NATIONAL UNIVERSITY

Why Is Productivity Important ?

Productivity is a critical matter for managers especially in the big projects, to estimate :

1) The duration required to perform the work.2) Size of human recourses that the project

requires .3) Labor cost also indirect cost such as

Insurance.

Page 6: AN-NAJAH NATIONAL UNIVERSITY

General factors affecting productivity: Skilled Labor Availability. Lack of proper tools and equipment. Overstaffing

Page 7: AN-NAJAH NATIONAL UNIVERSITY

General factors affecting productivity(cont.): Weather

Page 8: AN-NAJAH NATIONAL UNIVERSITY

General factors affecting productivity(cont.): Life-Cycle Construction Process. Material shortage at project site . Change order by consultants. Availability of good communication. Using new method of construction and

available alternatives that improve productivity

Page 9: AN-NAJAH NATIONAL UNIVERSITY

Unsafe Work Conditions Impact on Productivity rates.

When using safety strategies ,there was a 66% increase in productivity.

halving safety risk is associated with a 12% improvement in productivity.

Page 10: AN-NAJAH NATIONAL UNIVERSITY

Improvement of productivity productivity improvement is needed and set

as an ultimate goal; because the money is wasted every day as a result of lack of knowledge in productivity improvement.

Two points should be taken in consideration :

1) determining the best way to perform the job.2) measuring the time to achieve this job

using the best way.

Page 11: AN-NAJAH NATIONAL UNIVERSITY

Ways of Productivity Improvement : Job site planning. Labor managements, conditions and relation. Increase effectiveness and productivity of

employees by Training and Motivation.

Motivation : the motivation can be defined increase the thing satisfy workers about a job

Page 12: AN-NAJAH NATIONAL UNIVERSITY

Factors affecting motivation :

Method of payment to the workers. Planning. Reward. Desire of work. Ownerships.

Page 13: AN-NAJAH NATIONAL UNIVERSITY

Productivity Measurement

Measurement cannot be achieved without site information. Our approach in this project is to collect daily outputs for 3 months .

Two approaches of productivity measurement:1) Total factor productivity (TFP): where all inputs and

outputs are considered.2) Partial factor productivity : where a single

production factor is taken into consideration.

The data to be observed and registered will be used to calculate the Partial Productivity rate .

Page 14: AN-NAJAH NATIONAL UNIVERSITY

Total factor productivity (TFP)

where Q = quantity of all output tangible and intangible.L = quantity of labor input.K = value of invested assets.E = use of construction equipment.a, b & c are weighting factors.

Page 15: AN-NAJAH NATIONAL UNIVERSITY

Partial productivity

Labor productivity has consequently been widely used by contractors.

Page 16: AN-NAJAH NATIONAL UNIVERSITY

Work Methodology

Page 17: AN-NAJAH NATIONAL UNIVERSITY

Implemented Methodology :

Figure 14.3

Collect random samples for each item(30 samples for each item)

Convert crew size for each item into the ideal crew size

Perform analysis procedure on data collected using Minitab and SPSS programs

Conclusion and recommendations

Get analysis result and tabulate it

Page 18: AN-NAJAH NATIONAL UNIVERSITY

Method of construction: The calculation of the productivity rates was based

on the Traditional timber formwork method.

The formwork is built on site out of timber and it is:1- easy to produce but time-consuming for larger structures .

2-It is still used extensively where the labor costs are lower than the costs for procuring re-usable formwork .

3-It is also the most flexible type of formwork .

Page 19: AN-NAJAH NATIONAL UNIVERSITY

Concrete: The data collected conclude pump, ready mix Lorries and labor productivity rates.

Waterproofing: The data collected conclude surface preparation, cleaning, and water proofing application.

Page 20: AN-NAJAH NATIONAL UNIVERSITY

Data collection:

Our measuring have been based on statistical sampling theory, observation, collect a samples by field observations and questioner , analyze it and build a confidence limit around it.

in order to examine the effect of the factor affecting productivity ,the high temperatures and over crowding situation have been avoided .

Page 21: AN-NAJAH NATIONAL UNIVERSITY

There was 30 observation collected on each item.

To have representative results, the data collected gathered from 6 different cities of west bank (Ramallah. Tulkarm, Jenin, Qalqilya, Jerico, and Nablus).

Collection sheet including data about:1-quantity performed for each reading .2-corresponding duration (in hours).

Page 22: AN-NAJAH NATIONAL UNIVERSITY

The following table shows an example of data collected for isolating footing formwork:

Page 23: AN-NAJAH NATIONAL UNIVERSITY

Data collection constrains : Collection process requires staying at the site from start to end of the working day.

crew changing for the same item from day to another or in the same day.

convincing site managers and the responsible people at the site about the importance of this data after analyzing it .

The output of some of the activities couldn't be daily collected(e.g. slaps formwork), and others ends in a few hours of the work day(e.g. some concrete works some times)

Page 24: AN-NAJAH NATIONAL UNIVERSITY

Data analysis: The analysis process has been done on Minitab and SPSS

programs in order evaluate the statistical mean of each structural element(e.g. concrete works for footings ) .

Page 25: AN-NAJAH NATIONAL UNIVERSITY

To get more accurate value of the mean, the outlier values will be eliminated .As in the following picture

Page 26: AN-NAJAH NATIONAL UNIVERSITY

Results :Activity ID Activity Name Crew Size Daily Output Unit

Formwork :-1.1 Isolated Footing 1 Carp. ; 1 helper

13 m²

1.2 Combined Footing 1 Carp. ; 1 helper13 m²

1.3 Strip Footing 1 Carp. ; 1 helper19 m²

1.4 Raft Footing 1 Carp. ; 1 helper39 m²

1.5 Column Neck 1 Carp. ; 1 helper7 m²

1.6 Tie Beams 1 Carp. ; 1 helper24 m²

1.7 Slab on grade 1 Carp. ; 1 helper22 m²

1.8 Rectangular Column 1 Carp. ; 1 helper25 m²

1.9 Circular Column 1 Carp. ; 1 helper22 m²

1.10 Stairs 1 Carp. ; 1 helper8 m²

1.11 Slab 1 Carp. ; 1 helper51 m²

1.12 Shear Walls 1 Carp. ; 1 helper25 m²

Page 27: AN-NAJAH NATIONAL UNIVERSITY

Activity ID Activity Name Crew Size Daily Output Unit

Concrete works :-

2.1 All Footing 4 workers 132 m³

2.2Raft Footing 4 workers 112 m³

2.3Column Neck 4 workers 9 m³

2.4Tie Beams 4 workers 67 m³

2.5Slab on grade 4 workers 47 m³

2.6Columns 4 workers 46 m³

2.7Stairs 4 workers 52 m³

2.8Slab 4 workers 119 m³

2.9Shear Walls 4 workers 135 m³

Page 28: AN-NAJAH NATIONAL UNIVERSITY

Activity ID Activity Name Crew Size Daily Output Unit

Water Proofing works :-

3.1 Footing liquid applied waterproofing system 2 workers 54 m²

3.2 Tie Beams liquid applied waterproofing system 2 workers 64 m²

3.3 Shear Walls liquid applied waterproofing system 2 workers 76 m²

3.4 Wet Area liquid applied waterproofing system 2 workers 10 m²

3.5 Roofing liquid applied waterproofing 2 workers 81 m²

3.5Roofing Bituminous sheet membrance water proofing system

2 workers 47 m²

Page 29: AN-NAJAH NATIONAL UNIVERSITY

Conclusion : Productivity rate is very important in

estimating cost and duration for construction projects, and any labor productivity loss would affect the whole project in time and cost .

To prevent productivity loss ,factors that affect productivity mentioned earlier rates should be examine as possible.

Page 30: AN-NAJAH NATIONAL UNIVERSITY

Recommendation: Keep on training and motivating the workers.

Do not move the worker between work items unless the item is finished.

Don't work in hot and cold temperatures , the best temperature to do the works is 21°c .

Always hire labor with experiences .

Workers who are in safe and comfort conditions can feel more secure when they do their duties .

Page 31: AN-NAJAH NATIONAL UNIVERSITY

Thank You