an overview of the garpur project.€¦ · pscc, genoa, italy, june 2016. i w. bukhsh, g. hawker,...

22
An overview of the GARPUR project. Waqquas Bukhsh 1 , Keith Bell 1 , Tim Bedford 2 1 Institute of Energy & Environment, University of Strathclyde. 2 Department of Management Sciences, University of Strathclyde. 29th January, 2016.

Upload: others

Post on 13-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

An overview of the GARPUR project.

Waqquas Bukhsh 1, Keith Bell 1,Tim Bedford 2

1Institute of Energy & Environment, University of Strathclyde.

2Department of Management Sciences, University of Strathclyde.

29th January, 2016.

Page 2: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Outline

1. Introduction to GARPUR

2. Present situation and challenges

3. A glimpse of ongoing work

4. Key messages

Page 3: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Introduction to GARPUR

GARPUR stands for:Generally Accepted Reliability Principle with Uncertainty modellingand through probabilistic Risk assessment

Purpose of GARPUR:I to design and evaluate new power system reliability criteria;I need for probabilistic reliability criteria to supplement and

enhance the N≠1 criterion;I if successful, these criteria could be progressively implemented

at the pan-European level, optimally balancing reliability andcosts.

Page 4: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Ambitions of GARPURDesign, develop, and assess new probabilistic reliability criteria.GARPUR aims to:

I Define new classes of reliability criteria able to quantify thepan-European electric power system reliability in coherencewith its evolution towards and beyond 2030

I Evaluate the relevance of the criteria and compare di�erentreliability management strategies through impact comparisonon the resulting global social welfare, thus pinpointing themost favourable evolutions away from the N-1 criterion in thedecades to come

GARPUR covers the three time horizons:I Power system operationI Asset management andI System development

Page 5: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

A coherent reliability management approach acrossall time scales of TSO activitiesA coherent reliability management approach

across all time scales of TSO activities

Page 6: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

GARPUR in figures

I Start date: 01/09/2013I Duration: 4 yearsI Estimated budget: 10.9 MeI Requested EC grant: 7.8 MeI 20 partners

I 7 TSOsI 12 research organizationI 1 innovation management expert

Page 7: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

The GARPUR consortium

Page 8: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Structure of the GARPUR

SINTEF Energy Research 11

GARPUR project structure

WP1 Revisiting reliability management methodologies (SINTEF)

WP10

D

issemin

ation

(TECH

NO

FI) WP7 Development of a quantification platform for

reliability criteria (KUL)

WP4 System development

(ELIA)

WP5 Asset management

(RTE)

WP6 Power system operation

(Landsnet)

WP8 Pilot scale validation

(STATNETT)

WP9 Recommendations and roadmap for

migration (STATNETT)

WP1

1 C

oo

rdin

atio

n a

nd

man

agem

ent

(SIN

TEF)

WP3 Socio-economic assessment of

reliability criteria (RU)

WP2 Development of new reliability criteria for the pan-European electric power

system (ULG)

Page 9: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

1. Introduction to GARPUR

2. Present situation and challenges

3. A glimpse of ongoing work

4. Key messages

Page 10: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Present situation

I The N≠1 criterion is usedI (N≠1)-Criterion means the rule according to which elements

remaining in operation after a contingency must be capable ofaccommodating the new operational situation withoutviolating operational security limits.

Secure Region

Adequate Region

Infeasible Region

Inadequate Region

Page 11: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Present situation

I The N≠1 criterion is usedI (N≠1)-Criterion means the rule according to which elements

remaining in operation after a contingency must be capable ofaccommodating the new operational situation withoutviolating operational security limits.

I Concept- adequate level of reliability (ALR)I Each TSO has its own way of implementing ALR

I What are ”acceptable limits” of the di�erent power systemoperating states?

I What are the ”credible contingencies”?I How to use corrective control, when the sole preventive

approach leads to the inability to satisfy the N-1 criterion?

Page 12: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Why GARPUR?

I The N≠1 criterion has limitations:I N≠1 does not distinguish situations that are not N≠1 secure

(N≠0, N≠ 12 ...)

I No guidelines for relaxations relying on post-contingencycorrective control

I Advent of markets and smart-grid technology integrating newgeneration and demand patterns:

I Growing uncertainties in the context of power system operationI Growing complexity of the pan-European power systemI Growing power volatility and uncertainty in the system

development and asset management contextsI Growing deployment of new devices that enable fast corrective

actions

Page 13: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Why GARPUR?

I The N≠1 criterion has limitations:I N≠1 does not distinguish situations that are not N≠1 secure

(N≠0, N≠ 12 ...)

I No guidelines for relaxations relying on post-contingencycorrective control

I Advent of markets and smart-grid technology integrating newgeneration and demand patterns:

I Growing uncertainties in the context of power system operationI Growing complexity of the pan-European power systemI Growing power volatility and uncertainty in the system

development and asset management contextsI Growing deployment of new devices that enable fast corrective

actions

No evidence that N-1 will continue to provide the right signals.

Page 14: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Drivers for a new reliability criteria

Drivers (from the questionnaire)

11

Q50 If the reliability criterion is changed from N − 1 to one that in some way considers the probability and consequences of contingencies would you achieve one or more of the following benefits?

0 2 4 6 8

More efficient grid use

More transmission capacity given to themarket

Less capacity given to the reserves and morecapacity to power transmission

Probabilistic methods would enable anestimate of the reliability

Increase in wind or other variable production

Other

Number of responses

Page 15: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Barriers for a new reliability criteriaBarriers (from the questionnaire)

12

0 1 2 3 4 5 6 7

Applying the method/tools would be too laborious

Applying the method/tools would take too muchtime

There would not be sufficient and reliable statisticalor other data available for the evaluation

It would be difficult to understand and justify tosociety

Regulation requirements

The uncertainty of the acceptable and non-acceptable consequences would increase

Other

Number of responses

Q51 Which factors will prevent or act as barriers to introducing a reliability criterion that in some way considers the probability and consequences of contingencies instead of the strict N − 1?

Page 16: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

1. Introduction to GARPUR

2. Present situation and challenges

3. A glimpse of ongoing work

4. Key messages

Page 17: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

WP2: Reliability Management Approach and Criteria(RMAC)

The proposed RMAC acknowledges the fact that:I 100% reliability is not possible (chance constraint)I Both probabilities and criticalities matter (objective function)I Normally only a relatively small subset of contingencies will be

binding, but this subset should be determined dynamicallygiven the spatio-temporal variation of threats and criticalities

I Relaxation principle is part of the RMAC

Page 18: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

WP4: System Development

System development is about finding network reinforcements thatfacilitate future system maintenance and operation.Goal: answer the following three questions:

I identify the need for investmentI when and where to investI how much to invest

HorizonI several years to decades

UncertaintiesI Huge, and extremely di�cult to ”probabilize”

Page 19: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

WP4: System DevelopmentSystem development is about finding network reinforcements thatfacilitate future system maintenance and operation.Goal: answer the following three questions:

I identify the need for investmentI when and where to investI how much to invest

HorizonI several years to decades

UncertaintiesI Huge, and extremely di�cult to ”probabilize”

Proxies could be used to reduce the complexity of the systemdevelopment problems.

Page 20: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

1. Introduction to GARPUR

2. Present situation and challenges

3. A glimpse of ongoing work

4. Key messages

Page 21: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Key messages

I Probabilistic criteria can bring in better balance of cost andreliability.

I Overall reduction in costs (grid costsú + outage costs)I short term: using existing grid closer to limit. This means e.g.

higher ATC values between zones and less balancing actionswithin zones

I Long term: less grid infrastructure† needed and/or businesscase of expanding grid will improve

úGrid costs include OPEX, CAPEX and balancing costs.†Small is profitable, RMI, 2007.

Page 22: An overview of the GARPUR project.€¦ · PSCC, Genoa, Italy, June 2016. I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future electricity networks, submitted

Web: http://www.garpur-project.eu/

Deliverables: http://www.garpur-project.eu/deliverables

Publications:I E. Karangelos and L. Wehenkel, Probabilistic reliability management approach

and criteria for power system real-time operation, submitted for presentation atPSCC, Genoa, Italy, June 2016.

I W. Bukhsh, G. Hawker, K. Bell, T. Bedford, Adequacy assessment of future

electricity networks, submitted for presentation at PSCC, Genoa, Italy, June2016.

N-1 limitations¾ Does not consider probability of outages¾ Does not distinguish situations that are

− Not N-1 secure (N-0, N-½ …) or,− N-1 secure (but still many options)

¾ Difficult/impossible to handle the comprehensive uncertainties in a large interconnected system

¾ Complexity of the pan-European system, increasing probability of multiple outages

¾ Volatility caused by RES increasingly necessitates probabilistic approaches

¾ Hard to handle new devices that enable fast corrective actions

5

Waqquas Bukhsh

Institute of Energy and Environment,

University of Strathclyde, Glasgow.

email: [email protected]

web: http://personal.strath.ac.uk/waqquas.bukhsh/