analysis of a hybrid renewable wind - solar power system for a rural gsmumts site
TRANSCRIPT
1
National Conference on Communications Analysis of a Hybrid Renewable Wind - Solar Power System for a Rural GSM/UMTS
Site. Case Study - Uganda
Paul Asiimwe Kyoma
Department of Electrical and Computer Engineering
Makerere University
Kampala, Uganda
Edwin Mugume
School of Electrical and Electronic Engineering
University of Manchester
Manchester, United Kingdom
Abstract — The mobile cellular communications industry
in Uganda is one of the fastest growing sectors of the
economy. However, mobile operators are faced with high
costs of operation which hamper service provision and
reduce profit and further investment in the industry. One
of the major contributors to the total operating costs is the
electricity needed to run the base station sites and other
system components. This problem is more prominent in
rural areas, most of which are not connected to the
national electricity grid and have to run on diesel
generators all the time. For such sites, service providers
incur high operating costs due to the high cost of diesel and
associated generator maintenance costs. Operators are
always looking for solutions to reduce their operational
expenses. This paper proposes low cost and economical
configuration of a stand-alone PV/wind hybrid energy
system for a typical GSM/UMTS site in rural Uganda. The
meteorological data of solar insolation and wind speed for
a typical rural area in Uganda, and the energy
consumption of a typical rural site are studied and
simulated using the HOMER energy modeling software.
The simulations show that such a power system can
reliably run a typical rural site. The proposed system is not
only more environmentally friendly than a diesel generator
system but also more cost effective in the long run
considering the ever increasing fuel prices. This hybrid
system also reduces maintenance costs and makes it
cheaper for operators to roll out sites in rural areas.
Key words – rural, mobile communication, hybrid, operation
I. INTRODUCTION
Operators of Global System for Mobile Communications
(GSM) and Universal Mobile Telecommunications Systems
(UMTS) in many rural areas in Africa incur high operational
expenses (OPEX) due to limited extent of the national
electricity grid in such areas. In Uganda‘s case, most rural
areas are not connected to the national electricity grid and
operators are forced to run diesel generators in a 1+1
configuration. Due to high costs of diesel and the fact that two
generators are always required (one for redundancy), power
costs account for over 60% of the total OPEX per site [1].
This makes it very expensive for the network operators to
install GSM/UMTS sites. For rural areas where there is less
potential for acquiring new mobile subscribers, the average
revenue per user (RPU) is low which makes the operators to
shun such areas. Operators must therefore reduce their OPEX
in order to recoup their initial investment faster. Since power
related costs make up most of the OPEX, operators are always
looking for cheaper alternatives to run their sites.
With the stiff competition that characterises Uganda‘s mobile
communications sector, operators are seeking ways of
providing very quality service with minimal OPEX so as to
maximise their profits. Another issue is the need for operators
to become more environmentally friendly and reduce their
carbon footprint. According to Bell labs research, it is
estimated that base stations in the whole world produce
roughly 18 million metric tons of carbon dioxide annually [2].
The manufacture and use of information and communication
technology (ICT) contributes 2% of the total global carbon
emissions and it is estimated that this value will reach 3% by
the year 2020 [3], [4].
Due to the above reasons, operators, vendors, researchers and
other industry players are exploring cheaper, renewable and
energy efficient equipment not only to reduce OPEX but also
to enhance the effort towards greener communications. Studies
have shown that the radio access network (RAN) contributes
up to 57% of the total energy consumed by the network and
therefore, the biggest priority for operators is to find solutions
that can reduce the consumption of the RAN [5].
Fig. 1 shows the contributions of the different components of
the telecommunication network. A typical base station in a
rural area has a number of microwave transmission links for
backhaul to connect 900MHz and/or 1800MHz transceivers
that provide GSM coverage. In addition, some sites have a
NodeB for 3G coverage. In the radio base station (RBS), the
power amplifier consumes the highest amount of power.
2
Figure 1. Electricity usage in a mobile network [3]
Uganda lies in the solar belt and therefore, it receives 2500-
3200 hours of sunshine per year and a mean solar radiation or
insolation of 5.1kWh/m2 per day on a horizontal surface [6].
Solar insolation is essentially a measure of the radiation or
solar energy received over a given area on the surface of the
earth per unit time.
According to Rodolfo and Sebbit in [7], Uganda has an average
wind speed of 3 m/s. This is higher in some areas such as the
Karamoja region, high altitude areas and on the shores of Lake
Victoria. Most base stations in rural areas are located on high
hills so as to provide a wide coverage footprint. Most of them
use tall masts to gain a high elevation over the surrounding
reflectors, scatterers and other obstacles which would
otherwise hamper the signal propagation. Thus, in general,
rural base stations are located in areas with a high wind speed.
This means that wind and solar have potential to provide
alternative energy sources that can ultimately contribute to the
total energy requirements of the network. Diesel generators can
then be used as back up especially during major maintenance
works.
The purpose of this paper is to analyze the potential of a hybrid
solar and wind generation system as a solution to provide extra
energy that can be used to run some of these components. It
will provide a mathematical analysis of a typical rural base
station and discuss qualitatively the potential energy savings,
pay back period and provide an optimum system design
suitable for rural deployment.
II. CASE STUDY
A site in Kalangala District (coordinates S0.3084, E32.2250)
has been chosen for the subsequent analysis in this paper.
Kalangala is a typical rural area in Uganda but its tourism,
palm oil and fishing industries are booming. Thus, such a place
would easily pass the initial marketing feasibility study because
of the high traffic potential it possesses. Different operators in
Uganda have stepped up their coverage in Lake Victoria and
the fishing villages in and around it so as to provide sufficient
coverage to the fishermen and tourists.
In the analysis, typical Alcatel-Lucent equipment was used for
the system design. This included a 900MHz GSM base station,
a UMTS NodeB and one microwave link. An outdoor site was
considered so that more energy efficient fans can be considered
as opposed to indoor base station sites which require air
conditioners. Using specifications given by Alcatel-Lucent, the
electrical load of the site was calculated. Using NASA data for
this region, the wind speed and solar insolation was obtained
[8]. A battery bank was considered for storing the excess
power from the solar and wind system. This was obtained from
the simulation using HOMER. Fig. 2 shows a schematic of the
hybrid power system that was designed to run the site. Each of
the power sources will be dimensioned in the next section.
Table 1 shows data was obtained from NASA for the
Kalangala area that includes the solar insolation and wind
speeds. It can be seen that the average solar insolation on a
horizontal surface is 5.1kWh/m2 per day and the average wind
speed at a height of 50m above the surface of the earth is
4.6m/s.
Figure 2: Schematic diagram of hybrid solar-wind for GSM/UMTS site with a
possible diesel generator backup.
TABLE 1: METEOROLOGICAL DATA FOR THE SITE [6]
Month Insolation (kWh/m2) Wind velocity (m/s)
Jan 5.2 4.1
Feb 5.7 4.4
Mar 5.6 4.6
Apr 5.0 4.7
May 4.7 4.9
Jun 4.8 5.2
Jul 5.0 5.0
Aug 5.2 4.8
Sept 5.4 4.8
Oct 5.0 4.5
Nov 4.7 4.2
Dec 4.9 3.8
Average 5.1 4.6
3
Most of the base station equipment uses direct current but there
is equipment that uses alternating current. For example, a
socket may be provided for charging laptops which are used
during installation, commissioning and maintenance of the base
station. Thus, an inverter is normally used to supply power for
such equipment.
Table 2 shows the average hourly energy/power consumption
by each component of the site obtained from the specifications
of the equipment. Thus, the total power required to run a base
station site with this equipment is 1783 Watts.
In the following analysis, two scenarios have been identified.
In the first scenario, the required power is provided by either
solar or wind system independently. In the second scenario, a
solar-wind hybrid system is used to provide the required
power to run the site. Observations and conclusions are drawn
based on results of the analysis.
Scenario A: Stand-alone system
Average Energy requirement per day = 178324 = 42,792Wh
Wind Turbine dimensioning
The power generated by a wind system can be expressed as:
3
2
1ACP p (1)
P is the generated power available, pC is the efficiency of
the turbine, A is the area of the turbine (2rA where r is
the rotor radius), is the wind velocity and is the density
of air. According to the International Standard Atmosphere,
air has a density of 1.22 kg/m3 at sea level and a temperature
of 15oC. Assuming an efficiency of 25%, the rotor radius
required to generate power of 1783W for an average wind
velocity of 4.6m/s is obtained from equation (1) as:
mC
Pr
p
8.6*2
3
(2)
TABLE 1. AVERAGE POWER REQUIRMENTS
Equipment Power (W) Number Total (W)
Compact BTS
900 Outdoor
1283 1 1283
UMTS NodeB 300 1 300
1 Socket (for
laptop)
100 1 100
Microwave
(IDU+ODU)
100 1 100
Total 1783
Solar Photovoltaic Array dimensioning
In the case of a solar system, it will be dimensioned to produce
130% of the power which will cover about 25% of the losses.
Therefore, the required solar panel power rating can be
expressed as: )(*3.1
Wattsinsolationsolar
LoadP
(3)
This design considers the worst case scenario to deliver a
power system with the highest reliability. Therefore, the
lowest solar insolation value of 4.7kWh/m2 (corresponding to
May and November) was used in equation (3). For a load of
42,792Wh, the required solar panel power rating is:
P = 11836Wp
Scenario B: Hybrid System
An independent solar system would have the weakness that
solar power can only be harvested during the day. A hybrid
system combines both the solar and wind systems to make one
power source that optimizes the cost of powering the base
station. Dimensioning such a hybrid system can be based on
any of four criteria:
a) Splitting the cost of the hybrid system 50-50.
b) Splitting the power generated by both systems 50-50.
c) Optimizing the total cost for the combined hybrid system.
d) Fixing power of one system and dimensioning the other.
Since the major reason why operators would consider a hybrid
renewable power system is to reduce their OPEX, then the
third criteria is preferred and has been chosen for this analysis.
However, there are other constraints that must be considered
during the design of such a system. These include:
The space available for the site might dictate the size of
the solar array and the size of the wind turbine.
The turbine can be accommodated on the same tower as
the radio antennas. However, this has to be taken into
account during the civil design of the tower as the turbine
can add significant weight. Otherwise, a separate tower
may be built for the turbine although this increases the
total cost of the site including site lease costs.
A number of cost optimization methods exist. These are
probabilistic, iterative or graphical [9]. For this paper
however, HOMER (Hybrid Optimization Model for Electrical
Renewables) simulation tool was used to optimize the cost of
the system for a typical rural site.
According to European Wind Energy Association (EWEA),
the average cost per kW of wind power ranges between $1,000
to $1,265 while the average cost per kW of solar energy
ranges between $3,300-$4,400 [10], [11].
From the simulation results, the cheapest system will consist
of a 5kW solar array, two generic 10kW wind turbines at a
hub height of 40m and 48 160Ah Narada batteries. Such a
4
system would cost $49,000 (1 USD = 2,600 Uganda Shillings
at the time of writing this paper).
Fig. 3 shows the possible combinations of the PV photovoltaic
and wind systems that can be used for optimal system
operation. The highlighted one in the figure shows the most
optimal configuration considering the excess power that will
be produced. The system summary is shown in Tables 3 and 4.
Fig. 4 shows the percentage contribution of the different
power sources towards the total power output of the system. It
can be seen that most of the power contributed by the wind
sub-system. This is the preferred scenario because the cost per
kWh of wind is cheaper than that of a solar photovoltaic
system.
III. OBSERVATIONS
From the calculations and simulations, it was observable that:
For enough wind power to be harnessed to supplement the
power generated from solar, big wind turbines have to be
used. This will significantly increase the initial investment
cost of the project because of the huge turbine and a tower
on which it has to be installed. It will also increase the
amount of space that the operator needs for the site which
increases cost of site lease. For this reason, two small wind
turbines are proposed instead of one.
Figure 3. Most optimal hybrid system combinations
TABLE 3. SYSTEM COMPONENTS
PV Array 5 kWp
Wind turbines 2 Generic 10kW at a hub height of 40m
Battery 48 Narada (each rated 160Ah).
TABLE 4. ELECTRICAL POWER DISTRIBUTION
Component Production (kWh/yr) Fraction
PV array 7,427 19%
Wind turbines 31,369 81%
Total 38,795 100%
Figure 4. Monthly average electric production
If only solar energy is to be used, the total size of the solar
array needed to generate significant solar power becomes
very large. Thus, the solar array will require a very large
area for its deployment. In addition to the high cost per
kWh of a solar system, the costs associated with site lease
will also increase.
The wind and solar hybrid system can produce more
power than is necessary to run the system. However, there
are also periods when the generated power may be less
than the load. This problem is countered by having bigger
battery storage to store any extra energy and feed it back
into the system later. This problem can also be countered
by having a standby generator that provides any power
shortfalls when required. Such a generator should be able
to supply the 1783W required by the site. A 2kW
generator should be sufficient for such a purpose. It is
recommended that such a generator be a mobile diesel
generator as it might be redundant of the time.
A mobile standby diesel generator may be required in
cases where major maintenance work on the hybrid system
is due to take place or when the system breaks down. This
will reduce the downtime of the site and enhance network
availability further.
Such a hybrid system also has significant advantages over
current sources of power. Once installed, it reduces the fuel
costs and CO2 emissions by 100%. This system also does not
require a high maintenance effort and maintenance costs can be
reduced significantly by over 80%. Considering that such a
system has a life span of over 10 years, it leaves ample time for
operators to regain their initial investment and then enjoy
significant profits. It therefore makes good business sense for
operators to consider it for most of their rural sites which are
very difficult to connect to the national grid and for which they
incur high OPEX with little return on investment (ROI).
IV. CONCLUSION
The analysis presented in this paper shows that there is enough
potential to exploit solar and wind energy to provide power in
rural areas in Uganda. In the context of cellular communication
systems, an entire stand-alone base station can be supported on
power generated by a solar-wind hybrid system at all times.
However, a battery bank would be needed for redundancy
purposes and will be charged by excess power generated by the
hybrid system. Such a power source would significantly reduce
the OPEX of operators, increase their desire to invest in rural
5
areas and hence enhance penetration of telecommunication
services in rural areas.
As governments start implementing climate change policies
and as operators continue to seek more energy efficient power
solutions, Uganda should not be left behind. The world is
facing an energy crisis and Uganda is not immune. Fuel prices
are very unstable but the general trend is that the prices are
increasing. This reduces the profit margins of operators in
Uganda‘s competitive mobile telecommunications market.
Implementing a hybrid solar and wind system to run their base
stations in rural areas would go a long away in reducing their
costs, improving the potential for further investment in the
sector and crucially, it would reduce their carbon footprint.
REFERENCES
[1] Global Huawei Success Story [online]. Available at
http://www.huawei.com/ilink/en/success-
story/HW_078294?KeyTemps=D.G.%20battery,%20M
TN%20Uganda,%20fuel%20consumption,%20OPEX
[Accessed on 27th
June, 2011].
[2] Alcatel-Lucent Launches LightRadio Base Station
Rival, February 2011 [online]. Available at
http://www.zdnet.co.uk/news/networking/2011/02/07/al
catel-lucent-launches-lightradio-base-station-rival-
40091699/ , [Accessed on 20th
June, 2011].
[3] Global Action Plan, Green ICT Handbook: A Guide to
Green ICT, 2009.
[4] Parliamentary Office of Science and Technology,
United Kingdom, ICT and CO2 Emissions, Number
319, December 2008.
[5] J. He, P. Loskot, T. O‘Frarrell, V. Friderikos, S.
Armour and J. Thomson, ‗Energy Efficient
Architectures and Techniques fro access Networks‖,
IEEE International Conference on Communications and
Netwrking in China, 2010, pp. 1-6.
[6] Uganda Investment Authority, Investing in Uganda -
Investment Potentials in Solar Sector: Assembly and
Marketing of Solar Units in Uganda, October 2009.
[7] Rodolfo Pallabazzer and Adam M. Sebbit, ―The Wind
Resources in Uganda‘ Renewable Energy‖, An
international Journal, Elsevier, 13(1), January 1998.
[8] NASA Langley Atmospheric Science Data Center
(Distributed Active Archive Center) [Online]. Available
at http://eosweb.larc.nasa.gov/, Accessed on 15th
June,
2011.
[9] H. Yang, W. Zhou, L. Lu, Z. Fang, ―Optimal sizing
method for stand-alone hybrid-solar system with LPSP
technology using genetic algorithm‖, Solar Energy (82)
Elsevier,2008, pg. 354-367.
[10] Poul Erik Morthorst, Wind Energy – The Facts, Vol 2:
Costs and Prices, pp. 93-110.
[11] Severin Borenstein, The Market Value and Cost of
Solar Photovoltaic Electricity Production, Center for
the Study of Energy Markets, January 2008.