Norris Energy Consulting Co.
Analysis of the NAS Battery and Multi-TechnologyDemonstration at AEP
Benjamin L. NorrisNorris Energy Consulting Co.
Georgianne H. PeekSandia National Laboratories
David K. NicholsAmerican Electric Power
DOE Energy Storage Systems ResearchAnnual Peer Review, October, 2005
Sandia is a multi-program laboratory operated by Sandia Corporation, a Lockheed Martin Company, for the United States Department of Energy’s National Nuclear Security Administration under contract DE-AC04-94AL85000.
Norris Energy Consulting Co.
ACKNOWLEDGMENTS
Funded in part by the Energy Storage Systems Program of the U.S.Department Of Energy (DOE/ESS) through Sandia National Laboratories (SNL).
Norris Energy Consulting Co.
PartnersDOE / Sandia National LaboratoriesAEP EmTech, LLC.Tokyo Electric Power Co.NGK Insulators Ltd.ABB Inc.EPRI
Norris Energy Consulting Co.
Project Scope
Performance assessment of NAS demonstration systemEconomic analysis of NASMulti-technology comparison
Norris Energy Consulting Co.
Instrumentation13.8kV / 480V
Heater and auxiliary powerfor the battery modules A&B
kWkWhVdcIdct
kWkWhVloadIload
t
kWkWh
VsourceIsource
t
kWkWhVdcIdc
VblocksTbaseTsideAh
DODt
From NGK's DataAcquisition System
CB1
CB3
CB2
StaticSwitch
BuildingLoad
480V / 200V
NAS Battery Modules A&B
BAT-A
INV-A
kWkWhVPCSIPCS
t480V / 200V
BAT-B
INV-BBi-DirectionalInverter
MIS (SW)BIB (CB)
CB-MBP (N.O.)
480V / 208V
Auxiliary power for PCS A&B
kV2
VA400/5 1/1
kWkWh
IV
THD
kV2
VA400/5 1/1
kWkWh
IV
THD
kV2
kWkWh
IV
THD
CT accuracyis ±0.3%
KV2 meteraccuracy is
±0.5%
V A 800/11/1HOBRUY C10.5
V A 800/11/1
HOBRUY C10.5Shorted Shorted
V
1/1
ILVcap
V1/1
NGK measurements
AEP measurements
ABB measurements
ILVcap
NGK Current and Voltage MeasurementAccuracy
1. Current Measurement:
Typically ±0.5%, max. ±1.0% at 1000A
* LT 1005-S: ±0.4% (catalogue value) * Others: max. ±0.6% (for secondary measurement circuit plus A/Dconversion)
2. Voltage Measurement:
Typically ±0.1%, max. ±0.3% at 990V
CT accuracyis ±0.3%
Voltage is directly measuredKV2 meter
accuracy is ±0.5%
KV2 meteraccuracy is
±0.5%
This KV2 directly measuresvoltage and current
Voltage is directly measured
Norris Energy Consulting Co.
Regime 6 Profile (2/5/2004)
Storage Power Flows
-150
-100
-50
0
50
100
150
3:00 AM 6:00 AM 9:00 AM 12:00 PM 3:00 PM 6:00 PM 9:00 PM 12:00 AM 3:00 AM 6:00 AM 9:00 AM
Time
Pow
er (k
W)
Storage Input Storage Output Auxiliary Input Auxiliary Output
Norris Energy Consulting Co.
Regime 7 Profile (5/19/2004)
Storage Power Flows
-150
-100
-50
0
50
100
6:00 AM 9:00 AM 12:00 PM 3:00 PM 6:00 PM 9:00 PM 12:00 AM 3:00 AM 6:00 AM 9:00 AM
Time
Pow
er (k
W)
Storage Input Storage Output Auxiliary Input Auxiliary Output
Norris Energy Consulting Co.
Sample Cycle Storage Energy
Regime Storage Charge
Storage Discharge
Auxiliary Load
Charging Cost
Total Cost
Aux. Portion
6 1050 kWh 699 kWh 66 kWh 351 kWh 417 kWh 16% 7 1100 kWh 726 kWh 68 kWh 373 kWh 441 kWh 15%
Norris Energy Consulting Co.
System Performance
Charging efficiency includes PCS, static switch, and batterySystem efficiency includes PCS, battery, and auxiliariesAuxiliary load includes: battery heaters; PCS cabinet heaters (x2); control cabinet heater; PCS fans (x2); microcontrollers; instrumentation.
Regime Charging Efficiency System Efficiency 6 64-68% 57-63% 7 65-69% 57-63%
Norris Energy Consulting Co.
Power Quality Impacts
Grid
Load
0
100
200
300
400
500
600
0.0001 0.001 0.01 0.1 1 10 100
Duration (s)
Volta
ge
0
100
200
300
400
500
600
0.0001 0.001 0.01 0.1 1 10 100
Duration (s)
Volta
ge
Norris Energy Consulting Co.
Regime 6 Peak Shaving
0
50
100
150
200
250
3:00 AM 6:00 AM 9:00 AM 12:00 PM 3:00 PM 6:00 PM 9:00 PM 12:00 AM 3:00 AM 6:00 AM 9:00 AM
Time
Pow
er (k
W)
Grid Net Load
Norris Energy Consulting Co.
Regime 7 Peak Shaving
0
50
100
150
200
250
6:00 AM 9:00 AM 12:00 PM 3:00 PM 6:00 PM 9:00 PM 12:00 AM 3:00 AM 6:00 AM 9:00 AM
Time
Pow
er (k
W)
Grid Net Load
Norris Energy Consulting Co.
Lessons Learned
Battery system overall efficiency needs to be addressed in the specificationFor PQ+PS systems, efficiency should be pegged at the nominal PS power levelPerformance monitoring and measurement sensitivities need to be addressed in the specificationControl system should optimize peak loads
Norris Energy Consulting Co.
Multi-technology Comparison
NAS
MGE UPS / ActivePower
PureWave
Norris Energy Consulting Co.
2 Recorded Concurrent Events
6 months data collected (Oct’03 – Apr’04)14 extended periods of concurrent data collection2 events propagate through all three systems during concurrent data collection:
68-cycle interruptionVoltage sag sequence (8 sags)
Norris Energy Consulting Co.
Interruption Protection
Grid ALoad ALoad B
Load C 1.133s (68 cycle) Interruption
Norris Energy Consulting Co.
Sag Protection
200
220
240
260
280
300
320
0 50 100 150 200
msec
Vrm
s
34ms (2 cycle) A-phase Sag
11/27/03 14:03:11
301V (9%) overvoltage
Norris Energy Consulting Co.
Conclusions - 3 Technologies
InterruptionTwo systems fully protected loadsOne system protected load against outage, but introduced a voltage sag on one phase
Voltage SagAll three systems fully protected load
Norris Energy Consulting Co.
NAS Economic Analysis
Customer combined PQ/PS applicationNational tariff reviewCost / performance data based upon commercial products and existing manufacturing capacity
Norris Energy Consulting Co.
System Specifications
Installed cost (TI/NGK) includes modules, PCS ($202/kW), BOP ($100/kW), land, and installation.PQ rating - pulse factor of 3.Based on mature price projections.
Module System (5 Modules)PS/PQ Power Rating 50 kW / 150 kW 250 kW / 750 kWPQ duration 30 seconds 30 secondsPS Energy 360 kWh 1800 kWhPrice $75k (module price) $605,000 (installed)
Norris Energy Consulting Co.
Technical Assumptions
O&M includes maintenance, standby heat losses, property taxes, and insurance.Efficiency includes DC/DC battery efficiency and power conversion efficiency (double pass).
PS Discharge Duration 7.2 hoursRecharge Duration 8.64 hoursCalendar Life 15 yearsCycle Life 2500 cycles
O&M $26/kW-yrAC/AC Roundtrip Efficiency 77%
Norris Energy Consulting Co.
Other AssumptionsTariff Data On Peak Demand Charge ($/kW-mo) 10 Facilities Charge ($/mo) 25 On Peak Energy Charge ($/kWh) 0.08 Off Peak Energy Charge ($/kWh) 0.06Customer Billing Data - Without NAS Peak (operating) Days in Billing Cycle 20 On Peak Consumption (kWh) 400000 Off Peak Consumption (kWh) 100000 Peak Demand (kW) 1000Financial Escalation Rate 2.50% Discount Rate 7% State Marginal Tax Rate 5% Federal Marginal Tax Rate 35% Study Period (yr) 15Reduced losses from PQ protection Value ($/kW-event) 5 Events per year 20
Norris Energy Consulting Co.
Bill Comparison
Original New Benefit
On Peak Consumption (kWh) 400,000 364,000Off Peak Consumption (kWh) 100,000 146,753On Peak Demand (kW) 1,000 750Power factor 1 1Billed On-Peak Demand (kW) 1,000 750Total consumption (kWh) 500,000 510,753Load factor 0.694 0.946
Utility Bill ($) On-peak Demand Charge 10,000 7,500 2,500 Facilities Charge 25 25 0 On-peak Energy Charge 32,000 29,120 2,880 Off-Peak Energy Charge 6,000 8,805 -2,805Total Bill ($/mo) 48,025 45,450 2,575
PS Operating months/yr 8Annual Utility Bill Savings ($/yr) 20,598
Norris Energy Consulting Co.
Proforma (15 yr)YEAR YEAR YEAR YEAR
NPV 0 1 2 3 …NAS Ownership NAS Capital Cost -604,500 -604,500 NAS Depreciation -30,225 -57,428 -51,685 NAS O&M -68,621 -6,500 -6,663 -6,829
Power Quality PQ Loss Savings 791,783 75,000 76,875 78,797
Peak Shaving Utility Bill Savings 217,460 20,598 21,113 21,641Net Profit/(Loss) Before Tax 58,873 33,898 41,924LESS: Tax -219,787 -22,519 -12,966 -16,036Net Profit/(Loss) After Tax 36,354 20,932 25,888ADDBACK: Depreciation 30,225 57,428 51,685Net Present Value (NPV) 116,335 -604,500 66,579 78,360 77,573
Internal Rate of Return (IRR) 9.801%
MACRS Depr Rate (15 year) 5.000% 9.500% 8.550%
Norris Energy Consulting Co.
Conclusions - NAS Economic Analysis
Reasonable IRR (9.8%) for typical PS/PQ combined applicationBenefits dominated by PQ loss savings, rather than utility bill savingsCustomer-specific analysis should include impact of tariff switching (penalties for increased demand charge, BESS oversizing)
Norris Energy Consulting Co.
Project Wrap Up
Economic analysis reportMulti-technology comparison report