ANALYST’S BRIEFING : No.1/2014
March 5, 2014
1
This presentation was made from the analysis of reliable information in order to assist
investment community to better understand the company's financial status and operation. It also
supports the "Good Corporate Governance Project" of the Securities and Exchange Commission
(SEC).
However, the information within this presentation has been derived from the existing factors in
the present time. Therefore, the forward-looking information on this presentation may not occur
in the future if the aforementioned factors or situations are changed. Investors are, nevertheless,
required to use their own discretion regarding the use of information contained in this
presentation for any purpose.
For further information, please contact Investor Relations Section of the Electricity Generating
Public Company Limited (EGCO) at Tel: (662) 998-5145-8 or Email: [email protected]
2
3
► 2013 Highlights
► 2013 Financial Results
► EGCO Group’s Overview
2013 Highlights 2013 Financial Results EGCO Group’s Overview
4
► 2013 Highlights
♦ COD Achievements
♦ Significant Events
♦ Under Construction Projects
♦ Divestments of EGCO’s investment in JV
2013 Highlights 2013 Financial Results EGCO Group’s Overview
5
COD
February 1, 2013
May 2, 2013
July 18, 2013
November 18, 2013
December 16, 2013
Bueng Sam Phan Solar Project (GPS Phase 4)
NED Expansion Project
Theppana Wind Farm Power Project (TWF)
Solarco Power Project (Solarco)
2013 Highlights 2013 Financial Results EGCO Group’s Overview
6
Bueng Sam Phan Solar Project (GPS Phase 4)
Project Description
Type: Solar Power Plant
Location: Bueng Sam Phan, Petchabun Province
Shareholders: EGCO 60%, Gunkul 40%
PPA with PEA (VSPP Program)
Contracted Capacity: 6.5 MW
Adder: 8 baht/unit for 10 years
Project Progress
- COD on February 1, 2013.
Operating Performance Ending 2013
- Total net electricity generating was 10.79 GWh.
- Plant Availability Factor was 98.34%.
- Capacity Factor was 20.70%.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
7
NED Expansion Project
Project Description
Type: Solar Power Plant
Location: Wang Ploeng, Lopburi Province
Shareholders: EGCO 33.33%, CLP 33.33%, DGA 33.33%
PPA with PEA (VSPP Program)
Contracted Capacity: 8 MW
Adder: 8 baht/unit for 10 years
Project Progress
- COD on May 2, 2013
Operating Performance Ending 2013
- Total net electricity generating was 10.70 GWh.
- Plant Availability Factor was 97.39%.
- Capacity Factor was 22.72%.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
8
Theppana Wind Farm Power Project (TWF)
Project Description
Type: Wind Power Plant
Location: Watabak, Chaiyaphum Province
Shareholders: EGCO 90%, PVI Group 10%
PPA with PEA (VSPP Program)
Contracted Capacity: 6.9 MW
Adder: 3.5 baht/unit for 10 years
Project Progress
- COD on July 18, 2013.
Operating Performance Ending 2013
- Total net electricity generating was 5.33 GWh.
- Plant Availability Factor was 93.50%.
- Capacity Factor was 19.25%.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
9
Solarco Power Project (Solarco)
Project Description
Type: Solar Power Plants
Location: Sai Kyo - Suphan Buri Province
Sai Yai 1-2&Sai Phet 1-3 - Nakhon Pathom Province
Shareholders: EGCO 49%, Yanhee Solar Power 51%
PPA with PEA (VSPP Program)
Contracted Capacity: 6x9.5 MW
Adder: 8 baht/unit for 10 years
Project Progress
- Sai Yai 1-2 and Sai Phet 3, COD: November 18, 2013
- Sai Phet 1-2 and Sai Kyo, COD: December 16, 2013
Operating Performance Ending 2013
- Total Electricity Generating was 9.56 GWh.
- Plant Availability Factor was 99.78%.
- Capacity Factor was 22.49%.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
10
► 2013 Highlights
♦ COD Achievements
♦ Significant Events
♦ Under Construction Projects
♦ Divestments of EGCO’s investment in JV
2013 Highlights 2013 Financial Results EGCO Group’s Overview
New Project Acquisition
June 27, 2013
Signing Power Purchase
Agreement
July 25, 2013
December 17, 2013
Boco Rock Wind Farm (BRWF)
Khanom Power Plant Project Unit 4 (KN4)
Chaiyaphum Wind Farm Project (CWF)
2013 Highlights 2013 Financial Results EGCO Group’s Overview
11
12
Boco Rock Wind Farm (BRWF)
BRWF Stage-1
Project Description
Type: Wind Power Plant (Green field)
Turbine: Totaling 67 GE Wind Turbine Generators (WTG)
- 58 WTG x 1.7 MW
- 9 WTG x 1.6 MW
Location: New South Wales, Australia
Shareholders: EGCO 100%
PPA: 15 years with Energy Australia Pty Ltd.
(100% of output purchased by Energy Australia)
SCOD: February 2015
Installed Capacity: 113 MW
Acquisition Date
- June 27, 2013
2013 Highlights 2013 Financial Results EGCO Group’s Overview
13
Khanom Power Plant Project Unit 4 (KN4)
Project Description
Type: Combined Cycle Power Plant
Location: Khanom, Nakhon Si Thammarat Province
Shareholder: EGCO 99.99%
SCOD: June 2016
PPA: 25 years with EGAT
Contracted Capacity: 930 MW
Signing Date
- July 25, 2013
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Project Description
Type: Wind Power Plant
Location: Subyai, Chaiyaphum province
Shareholders: EGCO 90%, PVI Group 10%
SCOD: December 2016
PPA with EGAT (SPP Non-Firm Program)
Contracted Capacity: 90 MW
Adder: 3.5 baht/unit for 10 years
Signing Date
- December 17, 2013
14
Chaiyaphum Wind Farm Project (CWF)
2013 Highlights 2013 Financial Results EGCO Group’s Overview
15
► 2013 Highlights
♦ COD Achievements
♦ Significant Events
♦ Under Construction Projects
♦ Divestments of EGCO’s investment in JV
2013 Highlights 2013 Financial Results EGCO Group’s Overview
16
SCOD
April 2014
February 2015
June 2016
October 2019
GiDEC Waste Power Plant Project (GIDEC)
Boco Rock Wind Farm (BRWF)
Khanom Power Plant Project Unit 4 (KN 4)
Xayaburi Power Company Limited (XPCL)
2013 Highlights 2013 Financial Results EGCO Group’s Overview
17
GIDEC Waste Power Plant Project (GIDEC)
Project Description
Type: Municipal Solid Waste Plant
Location: Hat Yai, Songkhla Province
Shareholders: EGCO 50%, IEC Green Energy 50%
Expected COD: April 2014
PPA with PEA (VSPP Program)
Contracted Capacity: 6.5 MW
Adder: 3.5 baht/unit for 7 years
Project Progress
- Ending 2013, the progress of work was 95%.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
18
Boco Rock Wind Farm (BRWF)
Project Description
Type: Wind Power Plant (Green Field)
Location: New South Wales, Australia
Shareholder: EGCO 100%
SCOD: February 2015
PPA: 15 years with Energy Australia Pty Ltd.
Installed Capacity: 113 MW
(100% of output purchased by Energy Australia)
Project Progress
- Ending 2013, the progress of work was 18.15%.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
19
Khanom Power Plant Project Unit 4 (KN 4)
Project Description
Type: Combined Cycle Power Plant
Location: Khanom, Nakhon Si Thammarat Province
Shareholder: EGCO 99.99%
SCOD: June 2016
PPA: 25 years with EGAT
Contracted Capacity: 930 MW
Project Progress
- Ending 2013, the overall project progress was 22.80%.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Xayaburi Power Company Limited (XPCL)
Project Description
Type: Hydro Power Plant Project, Run off River
Location: Xayaburi District, Laos PDR
Shareholders: EGCO 12.5%, CK 30%, EDL 20%, BECL 7.5%,
Natee Synergy 25%, PT Construction and
Irrigation Co., Ltd. 5%
SCOD: October 2019
PPA: 29 years with EGAT and EDL
Contracted Capacity with EGAT: 1,220 MW
Contracted Capacity with EDL: 60 MW
Project Progress
- Ending 2013, the progress of work was 20.02%.
20
2013 Highlights 2013 Financial Results EGCO Group’s Overview
21
► 2013 Highlights
♦ COD Achievements
♦ Significant Events
♦ Under Construction Projects
♦ Divestments of EGCO’s investment in JV
2013 Highlights 2013 Financial Results EGCO Group’s Overview
22
Divestments of EGCO's
investment in JV
July 2, 2013
October 21, 2013
Conal Holding Corporation (Conal)
Absolute Power P Company Limited (APPC)
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Conal Holding Corporation (Conal)
Details of Divestment
- Sale of all existing EGCO’s share in Conal (40% of shares in Conal)
- Conal holds the share in:
1) Alto Power Management Corporation, a management company
2) Southern Philippines Power Corporation, a 55 MW diesel power plant
3) Western Mindanao Power Plant Corporation, a 110 MW diesel power plant
Divestment Date
- July 2, 2013
23
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Detail of Divestment
- Sale of all existing EGCO’s share in APPC (50% of share in APPC)
Divestment Date
- October 21, 2013
24
Absolute Power P Company Limited (APPC)
2013 Highlights 2013 Financial Results EGCO Group’s Overview
25
► 2013 Highlights
► 2013 Financial Results
► EGCO Group’s Overview
2013 Highlights 2013 Financial Results EGCO Group’s Overview
-
2,000
4,000
6,000
8,000
10,000
12,000
2012 2012(Restated)
2013
Net Profit Before FX Gain from Combination Deferred Tax
Million Baht
+ 1,545
or
25.50%
10,242 10,686
26
4,182 4,182
7,605
6,060 6,060
- 128 444
MD&A
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Amortised QPL
27
55 1,562
(72)
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
Million Baht
Increase in AP
KEGCO 276
Rayong 82
GPG (124)
BLCP (179)
Operating Performances
GEC-SPP 446 SPP2 42
QPL 382 SPP4 20
NTPC 290 KEGCO 19
EGCO Cogen 269 ESCO 11
BLCP 222 EGCOM Tara 9
Rayong 128 TWF 8
GPS 96 APPC (8)
NED 83 YEH (11)
GPG 73 Roi ET green (36)
SPP5 48 MME (44)
SPP3 43 EGCO (528)
6,115
7,677
6,060
7,605
2013 2012
Under Construction Projects
Bangpong 3 GIDEC (23)
Klonglaung 3 BRWF (55)
7,605
2013 Highlights 2013 Financial Results EGCO Group’s Overview
22%
22%
19%
11%
8%
7%
5%
3%
28
BLCP 2,084 MB
Quezon 2,042 MB
(QPL,QMS,PEPOI)
NTPC 1,033 MB
Note: Excluding EGCO GPG(KK2) 1,835 MB
Conal 34 MB, 0%
SPP 712 MB
(GEC, EGCO Cogen,
Roiet Green)
RYPP 517 MB
SOLAR 676 MB
(GPS,SPP2-5,NED,YEH)
ESCO 175 MB, 2%
KEGCO 254 MB
ET 131 MB, 1% Unit: Million Baht
2013 Highlights 2013 Financial Results EGCO Group’s Overview
USD 761 M
THB 12,814 M
JPY 367 M
Total Outstanding
(Baht Equivalent) THB 36,287 M
Total Outstanding
As of 31 Dec 2013
USD 910 M
THB 17,095 M
JPY 262 M
THB 49,982 M
Total Outstanding
As of 31 Dec 2012
29
AUD 0 M AUD 99 M
2013 Highlights 2013 Financial Results EGCO Group’s Overview
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Unit: Million Baht 2013
Beginning Cash 1,217
Net Cash Receipts from Operating Activities 1,027
Dividend Receipts from Subsidiaries JVs & Others 5,425
Net Cash Payments in Investing Activities (2,866)
Investments in subsidiaries & JVs (1,848)
Shareholder Loans (net) (1,011)
Others (7)
Net Cash Receipts (Payments) in Financing Activities (3,003)
Loan receipts 14,051
Loan repayments (13,263)
Interest Payments (633)
Dividend Payments (3,158)
Ending Cash 1,800 30
0.28 0.23 0.21
0.25
0.70
0.87
0.18 0.18 0.17
0.23
0.41
0.44
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
2008 2009 2010 2011 2012 2013
EGCO+Subsidiaries EGCO
Debt 24,809
Equity 55,820
Debt Equity
Debt 60,793 Equity
70,144
Debt Equity
EGCO + Subsidiaries
Unit: MB
EGCO
Unit: MB
Times (X)
31
2013 Highlights 2013 Financial Results EGCO Group’s Overview
1.00 1.25 1.25 1.50 1.50 2.00 2.25 2.50 2.50 2.50 2.50 2.75 2.75
1.25 1.25 1.50
1.50 1.75
2.00
2.50 2.50 2.75 2.75 2.75
3.25
-
1.00
2.00
3.00
4.00
5.00
6.00
7.00
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Second Payment
Interim Payment 6.00
5.25 5.00
5.25 5.25
4.75
4.00
3.25 3.00
2.75 2.50
2.25
Baht/Share
6.00
3.25
*EGCO’s Board of Directors on February 24, 2014 proposed to Shareholder’s 2014 Annual General Meeting to
approve the 2013 final dividend payment at 6 baht per share.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
33
► 2013 Highlights
► 2013 Financial Results
► EGCO Group’s Overview
2013 Highlights 2013 Financial Results EGCO Group’s Overview
34
► EGCO Group’s Overview
♦ EGCO Shareholders
♦ Progress of Work
♦ Portfolio and Corporate Strategies
2013 Highlights 2013 Financial Results EGCO Group’s Overview
EGAT
25.41%
TEPDIA
23.94%
Thai Investors
17.94%
Foreign Investors
20.88%
NVDR 10.43% NVDR
11.83%
35
TEPCO 50%
Mitsubishi 50%
As of September 10, 2013
* Nuclear Damage Liability Facilitation Fund
NDF* 50.11%
Others 49.89%
2013 Highlights 2013 Financial Results EGCO Group’s Overview
36
► EGCO Group’s Overview
♦ EGCO Shareholders
♦ Progress of Work
♦ Portfolio and Corporate Strategies
2013 Highlights 2013 Financial Results EGCO Group’s Overview
37
SCOD
2016
2016
2017
TP Cogeneration Project (TP Cogen)
SK Cogeneration Project (SK Cogen)
Chaiyaphum Wind Farm (CWF)
TJ Cogeneration Project (TJ Cogen)
2013 Highlights 2013 Financial Results EGCO Group’s Overview
38
TP Cogeneration Project (TP Cogen)
Project Description
Type: Cogeneration Power Plant
Location: Ban Pong, Ratchaburi Province
Shareholder: EGCO 100%
SCOD: June 2016
Installed Capacity: 125 MW
Contracted Capacity with EGAT: 90 MW
Contracted Capacity with IUs: 23 MW with 40 T/hr of steam
Project Progress
- Project development activities are ongoing.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
39
SK Cogeneration Project (SK Cogen)
Project Description
Type: Cogeneration Power Plant
Location: Ban Pong, Ratchaburi Province
Shareholder: EGCO 100%
SCOD: June 2016
Installed Capacity: 125 MW
Contracted Capacity with EGAT: 90 MW
Contracted Capacity with IUs: 17 MW with 60 T/hr of steam
Project Progress
- Project development activities are ongoing.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Chaiyaphum Wind Farm (CWF)
Project Description
Type: Wind Power Plant
Location: Subyai, Chaiyaphum
Shareholders: EGCO 90%, PVI Group 10%
SCOD: December 2016
PPA with EGAT (SPP Non-Firm)
Contracted Capacity: 90 MW
Adder: 3.50 baht/unit for 10 years
Project Progress
- Project development activities are ongoing.
40
2013 Highlights 2013 Financial Results EGCO Group’s Overview
41
TJ Cogeneration Project (TJ Cogen)
Project Description
Type: Cogeneration Power Plant
Location: Klongluang, Pathum Thani Province
Shareholder: EGCO 100%
SCOD: June 2017
Installed Capacity: 110 MW
Contracted Capacity with EGAT: 90 MW
Contracted Capacity with IUs: 16 MW with 10 T/hr of steam
Project Progress
- Project development activities are ongoing.
2013 Highlights 2013 Financial Results EGCO Group’s Overview
42
► EGCO Group’s Overview
♦ EGCO Shareholders
♦ Progress of Work
♦ Portfolio and Corporate Strategies
2013 Highlights 2013 Financial Results EGCO Group’s Overview
43
Currently, EGCO Group’s portfolio comprises of 20 operating power plants, totaling contracted capacity 4,518.02 MWe.
IPPs SPPs Renewable Overseas
277.99 MWe
6.2%
3,330.44 MWe
73.7%
808.85 MWe
17.9%
100.74 MWe
2.2%
Total 4,518.02 MWe
IPPs Renewable
Rayong 1,174.99 1,174.99 NED 63.00 21.00
KEGCO 748.20 748.20 SPP2 8.00 8.00
GPG (KK 2) 1,468.00 734.00 SPP3 8.00 8.00
BLCP 1,346.50 673.25 SPP4 6.00 6.00
3,330.44 SPP5 8.00 8.00
SPPs GPS 26.00 15.60
EGCO COGEN 111.88 89.50 TWF 6.90 6.21
ROI-ET GREEN 8.80 6.19 Solarco 57.00 27.93
GEC-GCC 108.63 54.32 100.74
GEC-NKCC 121.30 60.65 Overseas
GEC-SCC 114.45 57.23 NTPC 1,023.00 358.05
GEC-GYG 20.20 10.10 QUEZON 460.00 450.80
277.99 808.85
Power Plant MW EquityContracted
Cap. (MW)Power Plant MW Equity
Contracted
Cap. (MW)
IPPs Renewable
Rayong 1,174.99 1,174.99 NED 63.00 21.00
KEGCO 748.20 748.20 SPP2 8.00 8.00
GPG (KK 2) 1,468.00 734.00 SPP3 8.00 8.00
BLCP 1,346.50 673.25 SPP4 6.00 6.00
3,330.44 SPP5 8.00 8.00
SPPs GPS 26.00 15.60
EGCO COGEN 111.88 89.50 TWF 6.90 6.21
ROI-ET GREEN 8.80 6.19 Solarco 57.00 27.93
GEC-GCC 108.63 54.32 100.74
GEC-NKCC 121.30 60.65 Overseas
GEC-SCC 114.45 57.23 NTPC 1,023.00 358.05
GEC-GYG 20.20 10.10 QUEZON 460.00 450.80
277.99 808.85
Power Plant MW EquityContracted
Cap. (MW)Power Plant MW Equity
Contracted
Cap. (MW)
IPPs Renewable
Rayong 1,174.99 1,174.99 NED 63.00 21.00
KEGCO 748.20 748.20 SPP2 8.00 8.00
GPG (KK 2) 1,468.00 734.00 SPP3 8.00 8.00
BLCP 1,346.50 673.25 SPP4 6.00 6.00
3,330.44 SPP5 8.00 8.00
SPPs GPS 26.00 15.60
EGCO COGEN 111.88 89.50 TWF 6.90 6.21
ROI-ET GREEN 8.80 6.19 Solarco 57.00 27.93
GEC-GCC 108.63 54.32 100.74
GEC-NKCC 121.30 60.65 Overseas
GEC-SCC 114.45 57.23 NTPC 1,023.00 358.05
GEC-GYG 20.20 10.10 QUEZON 460.00 450.80
277.99 808.85
Power Plant MW EquityContracted
Cap. (MW)Power Plant MW Equity
Contracted
Cap. (MW)
Renewable
NED 63.00 21.00
SPP2 8.00 8.00
SPP3 8.00 8.00
SPP4 6.00 6.00
SPP5 8.00 8.00
GPS 26.00 15.60
TWF 6.90 6.21
Solarco 57.00 27.93
100.74
Power Plant MW EquityContracted
Cap. (MW)
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Under Construction Under Development
Currently, EGCO Group’s portfolio consists of 4 under construction projects and 4 under development projects,
totaling contracted capacity 1,613.25 MWe.
Total 1,613.25 MWe
407 MWe
25.2%
1,206.25 MWe
74.8%
44
Under Development
TP Cogen 113.00 113.00
SK Cogen 107.00 107.00
CWF 90.00 81.00
TJ Cogen 106.00 106.00
407.00
Power Plant MW EquityContracted
Cap. (MW)
Under Construction
GIDEC 6.50 3.25
BRWF 113.00 113.00
KN4 930.00 930.00
XPCL 1,280.00 160.00
1,206.25
Contracted
Cap. (MW)Power Plant MW Equity
2013 Highlights 2013 Financial Results EGCO Group’s Overview
Currently, EGCO Group’s other business portfolio comprises of 6 companies:
45
Company Business Type
EGCO Engineering and Service Co., Ltd. (ESCO)
Pearl Energy Philippines Operating Inc. (PEPOI)
Quezon Management Services Inc. (QMS)
Eastern Water Resources Development and Management Plc. (EASTW)
Egcom Tara Co., Ltd. (Egcom Tara)
Manambang Muara Enim Co., Ltd. (MME)
O&M
O&M
Management Service
Water
Water
Coal Mining
2013 Highlights 2013 Financial Results EGCO Group’s Overview
XPCL
(Hydro)
KN4
(Gas)
TJ Cogen
(Gas)
BRWF
(Wind)
GIDEC
(Waste)
Under Development Projects
Under Construction Projects
2014 2015 2016 2017 2018 2019 2020
Under Construction Projects
Under Development Projects
SK Cogen
(Gas)
TP Cogen
(Gas)
CWF
(Wind)
46
47
Operate power plant portfolio to achieve optimum efficiency and
manage projects under construction to achieve on time and within
budget completion
Focus on seeking opportunities to acquire operating assets to
realize quick earning
Focus on the opportunities in greenfield projects to boost its earning
prospects in long term by utilizing existing projects to expand its
investments
2013 Highlights 2013 Financial Results EGCO Group’s Overview
THANK YOU
48
49
50
Classified by Producer Classified by Fuel type
As of December 2013, Thailand’s Power Installed Capacity was 33,681.02 MW.
EGAT : 15,010 MW SPP : 3,525 MW
IPP : 12,742 MW Import : 2,404 MW
Natural Gas : 22,642 MW Coal : 4,556 MW
Hydro : 5,541 MW Others* : 942 MW
*OTHERS = Fuel Oil, Diesel, Renewable
67.2%
16.5%
13.5%
2.8%
NATURAL GAS HYDRO COAL OTHERS*
44.6%
37.8%
10.5%
7.1%
EGAT IPP SPP IMPORT
51
15,000
20,000
25,000
30,000
January Februaary March April May June July August September October November December
2008 2009 2010 2011 2012 2013
23,900.21 MW (May 24, 2011)
26,121.10 MW (April 26, 2012)
+ 1.8%
26,598.14 MW (May 16, 2013)
MW
Key Financial Data:
FX Variance MD&A
52
2012 2013 +/-
EGCO 472.74 (754.67) (1,227.41)
Rayong Power Plant 0.00 (0.02) (0.02)
KEGCO 0.28 (100.16) (100.44)
EGCO Cogen 8.68 (6.26) (14.94)
Roi-Et Green 16.80 11.38 (5.42)
ESCO (4.27) 14.06 18.33
ET - - -
PEPOI (0.75) 2.75 3.50
Quezon 105.43 (38.74) (144.17)
QMS (1.36) 0.59 1.95
SPP2 (0.69) (2.28) (1.59)
SPP3 0.60 - (0.60)
SPP4 0.87 - (0.87)
SPP5 (7.43) 0.22 7.65
TWF - (15.38) (15.38)
YEH - (90.11) (90.11)
Banpong - - -
Klonglaung - - -
BRWF - (0.04) (0.04)
Total Subs FX 590.90 (978.66) (1,569.56)
BLCP (29.55) 580.93 610.48
GPG 85.53 (123.10) (208.63)
GEC(GCC, NKCC, SCC, GYG) 32.95 (38.16) (71.11)
CONAL (1.65) 1.22 2.87
NTPC (124.15) 375.20 499.35
NED (0.03) (0.02) 0.01
GPS - - -
APPC - - -
GIDEC 0.01 - (0.01)
MME 0.04 0.14 0.10
Total JVEs FX (36.85) 796.21 833.06
Grand Total 554.05 (182.45) (736.50)
* FX gains/losses from Income Statements including financial cost from foreign currency loans (EGCO & Subs) and JVs 53
2012 2013
Debt to Equity (Time) 0.70 0.87
Net Debt to Equity (Time) 0.54 0.71
Net Profit before FX* (Million Baht) 10,686 7,096
EPS (Baht) 21.35 13.13
Operating Cash Flow / share (Baht) 8.00 10.55
BV / share (Baht) 121.87 131.57
Financial Ratio Highlights
Key Financial Data:
54
Segmental Operating Results, Ended December 31, 2013
Key Financial Data:
Subsidiaries Joint Ventures Joint Ventures Grand
Power Generation Power Generation Others Others Total
(Million Baht) EGCO
Rayong
power
plant
KEGCOEGCO
Cogen
Roi-Et
GreenSPP4 SPP3 YEH SPP2 SPP5 TWF
QPL
(included
PEPOI&QMS)
Klongluang Bangpong BRWF BLCP GPG
GCC,
NKCC,
SCC,
GYG
NED CONAL NTPC GPS GIDEC ESCO ET MME APPC
Sales of Electricity - 2,201 2,035 2,548 365 140 179 34 187 187 35 9,839 - - - 17,750 - - - 17,750
- Capacity Payment - 2,125 1,972 242 43 - - - - - - - - - - 4,382 - - - 4,382
- Energy Payment - 76 63 2,306 322 140 179 34 187 187 35 9,839 - - - 13,368 - - - 13,368
Sales of Water - - - - - - - - - - - - - - - - - 309 309 309
Service Income - - - - - - - - - - - 401 - - - 401 726 - 727 1,127
Cost of Sales - 1,511 1,429 2,318 189 38 49 31 52 50 14 5,500 - - - 11,182 - 86 86 11,268
Cost of Services - - - - - - - - - - - 315 - - - 315 477 - 479 794
Gross Profit - 690 606 230 176 102 130 3 135 137 21 4,425 - - - - - - - - - - - 6,653 249 223 - - 472 7,125
EBITDA (1,310) 1,638 1,255 300 147 131 168 39 174 173 24 4,505 3 3 (55) 3,646 2,938 879 437 78 1,808 280 (27) 17,236 231 188 (15) (18) 386 17,622
EBIT (1,357) 534 358 160 128 102 130 17 134 135 15 3,815 3 3 (55) 2,637 2,172 602 338 78 1,808 199 (27) 11,929 209 172 (15) (18) 348 12,277
Net Profit before FX (1,602) 431 289 116 106 62 77 (24) 84 87 1 1,939 3 3 (238) 1,789 1,835 457 243 33 1,032 135 (28) 6,833 175 130 (18) (24) 263 7,096
Net Profit (2,356) 431 189 109 117 62 77 (114) 82 87 (14) 1,903 3 3 (238) 2,370 1,712 420 243 33 1,408 135 (28) 6,636 189 130 (18) (24) 277 6,914
2013 Holding
Total Other
businesses
Total Power
generation
Subsidiaries
55
Segmental Operating Results, Ended December 31, 2012
Key Financial Data:
Subsidiaries Joint Ventures Joint Ventures Grand
Power Generation Power Generation Others Others Total
(Million Baht) EGCO
Rayong
power
plant
KEGCOEGCO
Cogen
Roi-Et
GreenSPP4 SPP3 YEH SPP2 SPP5 TWF
QPL
(included
PEPOI&QMS)
Klongluang Bangpong BRWF BLCP GPG
GCC,
NKCC,
SCC,
GYG
NED CONAL NTPC GPS GIDEC ESCO ET MME APPC
Sales of Electricity - 2,166 1,763 1,631 397 127 149 - 105 93 - 8,647 - - - 15,078 - - - 15,078
- Capacity Payment - 2,043 1,696 96 52 - - - - - - - - - - 3,888 - - - 3,888
- Energy Payment - 123 67 1,535 345 127 149 - 105 93 - 8,647 - - - 11,190 - - - 11,190
Sales of Water - - - - - - - - - - - - - - - - - 290 290 290
Service Income - - - - - - - - - - - 343 - - - 343 819 - 819 1,162
Cost of Sales - 1,673 1,529 1,732 168 35 40 - 31 27 - 5,040 - - - 10,275 - 81 81 10,356
Cost of Services - - - - - - - - - - - 225 - - - 225 569 569 794
Gross Profit - 493 234 (101) 229 92 109 - 74 66 - 3,725 - - - - - - - - - - - 4,921 250 209 - - 459 5,380
EBITDA 3,516 1,431 917 44 192 113 131 (1) 97 88 (5) 4,005 - - - 3,707 3,163 462 329 287 2,080 141 (4) 20,693 213 190 26 (11) 418 21,111
EBIT 3,465 323 (12) (103) 173 82 95 (1) 73 64 (5) 3,093 - - - 2,676 2,284 174 250 117 1,646 90 (4) 14,480 195 167 26 (11) 377 14,857
Net Profit before FX 3,146 307 (42) (128) 141 43 37 (1) 44 39 (5) 1,794 - - - 2,041 1,886 71 160 81 742 39 (4) 10,391 164 121 26 (16) 295 10,686
Net Profit 3,747 307 (42) (119) 158 44 38 (1) 43 31 (5) 1,769 - - - 2,011 1,972 104 160 79 618 39 (4) 10,949 160 121 26 (16) 291 11,240
2012 Holding
Total Other
businesses
Total Power
generation
Subsidiaries
Net Generation
GWh
Electricity Sales MM Baht
REGCO and KEGCO receive the capacity payment (Rayong Power Plant) or availability payment (KEGCO) for maintaining the availability of the power plants, regardless of whether the electric power will be supplied to EGAT
or not.
EGAT is the sole offtaker for electricity produced by Rayong Power Plant and KEGCO under long term cost-plus based Power Purchase Agreements (PPAs).
56
Annual Net Generation & Electricity Sales for the Year 2009-2013
Operating Performance (IPPs) : 2
,952
4,7
83
2,1
27
4,0
04
2,6
93 5
,643
5,4
76
5,8
16
5,3
11
5,1
88
10,0
18
10,0
36
10,6
17
10,7
70
10,1
57
9,3
29
9,8
57
8,8
13
10,8
48
9,3
23
-
4,9
76
6,3
61
5,7
70
5,8
97
-
3,000
6,000
9,000
12,000
2009 2010 2011 2012 2013
RYPP KEGCO BLCP KK II NT2
3,7
22
2,5
35
2,2
58
2,1
67
2,2
01
2,3
19
2,7
88
2,1
70
1,7
62
2,0
38
17,9
09
17,7
06
17,8
68
18
,50
5
17,2
55
22,5
06
22,7
50
22,6
55
29,6
49
27
,47
0
-
6,3
17
7,6
72
8,1
07
7,9
37
-
5,000
10,000
15,000
20,000
25,000
30,000
2009 2010 2011 2012 2013
57
Major Maintenance Expenses for the Year 2014
Operating Performance (IPPs) :
Quarter 1 2 3 4 Total
Budget Budget Budget Budget
Spare Parts 4.06 0.00 0.00 0.00 4.06
Service Charge 13.47 8.26 7.21 7.21 36.15
Total 17.53 8.26 7.21 7.21 40.21
Quarter 1 2 3 4 Total
Budget Budget Budget Budget
Spare Parts 11.64 21.45 15.31 5.22 53.62
Service Charge 21.19 61.79 25.05 4.96 112.99
Total 32.83 83.24 40.36 10.18 166.61
Rayong Power Plant
KEGCO
Million Baht
Million Baht
58
Major Maintenance Expenses for the Year 2013
Operating Performance (IPPs) :
Quarter 1 2 3 4 Total
Actual Actual Actual Actual
Spare Parts 10.67 2.12 5.66 0.22 18.67
Service Charge 25.74 23.12 21.44 7.80 78.10
Total 36.41 25.24 27.10 8.02 96.77
Quarter 1 2 3 4 Total
Actual Actual Actual Actual
Spare Parts 19.09 15.93 27.68 51.64 114.34
Service Charge 21.84 33.03 39.57 48.69 143.14
Total 40.93 48.96 67.25 100.33 257.48
Rayong Power Plant
KEGCO
Operating Performance Equivalent Availability Factor
Operating Performance (IPPs) :
59
Rayong Power Plant
Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%)
CCGT #1 99.00 99.95 97.14 98.78 98.91 99.98 88.16 91.57
CCGT #2 98.88 99.95 97.89 98.69 90.76 94.02 97.16 98.10
CCGT #3 98.38 99.35 79.21 90.89 98.91 93.46 97.28 96.51
CCGT #4 99.44 99.87 98.26 98.78 77.72 78.20 69.10 74.91
Rayong Power Plant
Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%)
CCGT #1 81.85 85.83 98.44 99.06 98.80 97.82 95.90 97.12
CCGT #2 99.63 99.66 97.60 98.47 82.25 83.44 96.74 98.00
CCGT #3 90.19 92.95 97.60 98.44 99.64 99.50 95.90 97.43
CCGT #4 99.49 100.00 98.31 99.10 97.87 97.10 96.65 96.59
KEGCO
Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%)
Barge #1 93.00 88.94 89.27 - - - - -
Barge #2 91.00 98.76 91.00 99.75 91.00 89.78 90.39 99.69
CCGT #3 81.82 86.77 88.60 74.60 88.60 94.40 86.60 93.91
KEGCO
Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%)
Barge #1 - - - - - - - -
Barge #2 94.00 99.51 63.01 66.83 78.67 88.18 92.90 87.36
CCGT #3 79.87 87.31 80.53 86.88 91.66 95.10 66.22 79.50
2012
Plant Type1Q12 2Q12 3Q12 4Q12
2013
Plant Type1Q13 2Q13 3Q13 4Q13
2012
Plant Type1Q12 2Q12 3Q12 4Q12
2013
Plant Type1Q13 2Q13 3Q13 4Q13
60
Net Generation and Fuel Consumption
Operating Performance (IPPs) :
Rayong Power Plant
CCGT #1- 4 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13 3Q13 4Q13
Net Generation
- By Natural Gas (GWh) 1,138 1,101 1,044 722 979 1,146 288 280
- By Secondary Fuel (GWh) 0.160 - - - - 0.170 - -
Fuel Consumption
- By Natural Gas (MMBTU) 9,823,707 9,515,501 9,025,465 6,287,046 8,432,352 9,904,901 2,557,558 2,483,331
- By Secondary Fuel (Million Litre) 0.040 - - - - 0.040 - -
KEGCO
Barge # 2 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13 3Q13 4Q13
Net Generation
- By Natural Gas (GWh) 141 145 131 146 142 98 130 124
- By Secondary Fuel (GWh) - - - - - - - -
Fuel Consumption
- By Natural Gas (MMBTU) 1,775,680 1,850,363 1,676,533 1,875,388 1,791,289 1,286,936 1,695,172 1,590,779
- By Secondary Fuel (Million Litre) - - - - - - 0.004 0.002
CCGT # 3 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13 3Q13 4Q13
Net Generation
- By Natural Gas (GWh) 1,192 983 1,284 1,290 1,162 1,181 1,288 1,062
- By Secondary Fuel (GWh) - - - - - - - -
Fuel Consumption
- By Natural Gas (MMBTU) 9,604,779 10,842,732 10,335,010 10,286,267 9,404,137 9,571,503 10,481,570 8,696,415
- By Secondary Fuel (Million Litre) - 0.005 0.017 0.004 0.012 0.01 - -
2013
2013
2012
2012
For further information, Please contact
Investor Relations at Tel. 02-998-5147-8
or E-mail: [email protected]
61