andrew biddle project list

8
Andrew Biddle [email protected] (610) 662-2256 Project List: #1 213 Howarth Road, Media, PA. Pine tree landed on house. Extensive water damage. 16 week project. 4 workers Exterior: Install new shingle roof. 58 square. Replace skylights. Add tubular skylight in hall bath. Replace all fascia and gutters on the front of house. Replace stucco on front of house Interior 1 st floor: New drywall ceilings/walls New insulation Install tubular skylight in hall bath Install 1500 sq ft of raw white oak flooring. Sand and stain. Install new craftmade kitchen cabinets Install new light fixtures in kitchen Install tile backsplash in kitchen Vent oven range hood to back porch Install crown molding Replace all window and door casings Paint Basement: Frame and drywall basement ceilings/walls Replace dividing wall and add pocket doors. Install new barn door Install drop ceiling Replace lighting with new LED fixtures Install 1200 sf of laminate flooring Paint

Upload: andrew-biddle

Post on 17-Jan-2017

11 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Andrew Biddle Project List

Andrew [email protected](610) 662-2256

Project List:#1 213 Howarth Road, Media, PA. Pine tree landed on house. Extensive water damage. 16 week project. 4 workers

Exterior:Install new shingle roof. 58 square. Replace skylights. Add tubular skylight in hall bath.Replace all fascia and gutters on the front of house. Replace stucco on front of house

Interior 1st floor:New drywall ceilings/walls New insulationInstall tubular skylight in hall bathInstall 1500 sq ft of raw white oak flooring. Sand and stain. Install new craftmade kitchen cabinetsInstall new light fixtures in kitchenInstall tile backsplash in kitchenVent oven range hood to back porchInstall crown moldingReplace all window and door casingsPaint

Basement:Frame and drywall basement ceilings/walls Replace dividing wall and add pocket doors.Install new barn door Install drop ceiling Replace lighting with new LED fixturesInstall 1200 sf of laminate flooringPaint

Page 2: Andrew Biddle Project List
Page 3: Andrew Biddle Project List

#2 Condo G2. Fox Valley Condominiums, Glen Mills, PA. Pipe burst between kitchen and hall bathroom. Extensive water damage. 5 week project. 3 workers.

Interior:Remove all laminate flooring and tile floors, kitchen cabinets, counters, bathtub etc…Install new tile floor and new walk in shower (approx 1500 sf). Replace old copper piping with pex.Install new kitchen cabinets and color match paint for old cabinets.Install tile backsplash in kitchenVent dryer and built soffit to conceal the vent. Paint

Page 4: Andrew Biddle Project List
Page 5: Andrew Biddle Project List
Page 6: Andrew Biddle Project List
Page 7: Andrew Biddle Project List

#3 1945 Anthony Wayne Drive, Wayne, PA. New roof, dormer, front patio, fascia, and siding. 6 week project. 3 workers.

Exterior: Frame new dormer and install windows.Frame new covered front patio and pour front porch slab. New roof (38 square) and drip edgeNew fascia. New siding. New exterior light fixtures.

Page 8: Andrew Biddle Project List