PresentationANGRA 3 NPP CONSTRUCTION RESUMING
Contracts Overview
Mr. José Eduardo B. Costa MattosConstruction Superintendent
TOP 15 WORLD ELECTRIC GENERATORS BRAZIL IS ONE OF THE MAIN WORLD ELECTRICITY PRODUCERS
0 500 1.000 1.500 2.000 2.500 3.000 3.500 4.000
Billion kilowatts.hour
USA
China
Japan
Russia
Canada
India
Germany
France
United Kingdom
Brazil
South Korea
Italy
Spain
Australia
South Africa
Hydro Nuclear Renewables Thermal
source: International Energy Annual 2003
Brazil: 10th place
Brazil: 90th place
Total Generation
HYDRO93,50%
GAS2,17%
COAL1,08%
OIL0,07%
BIOMASS0,25%
NUCLEAR2,93%
ELECTRIC CONSUMPTION - kWh/hab.
2340
3052ACTUAL
PREDICTION 2015
BRAZILIAN NUCLEAR INDUSTRY MONOPOLY ESTABLISHED BY CONSTITUTION
MINISTRY OFMINES AND ENERGY
ELETROBRÁS(holding)
ELETRONUCLEAR
CONVENTIONAL UTILITIESFurnas, Chesf, ...
MINISTRY OFSCIENCE & TECHNOLOGY
BRAZILIAN NUCLEAR ENERGYCOMMISSION
CNEN
NUCLEAR FUEL INDUSTRY
INB
NUCLEAR HEAVY EQUIPMENT
NUCLEP
RESEARCH INSTITUTESIPEN, CDTN, IEN, IRD, CRCN
NUCLEAR SAFETYAUTHORITY
MINISTRY OFDEFENSE
RESEARCH INSTITUTESNAVY CTMSPAIR FORCE CTA/IEAvARMY CTEx/IEA
ANGRA 2 PWRPower: 1.350 MWTechnology: Siemens/KWU Operation start: January/2001
ANGRA 1 PWRPower: 640 MWTechnology: Westinghouse Operation start: January/1985
ADMIRAL ÁLVARO ALBERTONUCLEAR POWER STATION
ANGRA 3 PWRPower: 1.405 MWTechnology: Siemens/KWU Released for Operation: 2015/12
YEARLY GENERATION
14.403.775 MWH
The power generated by Angra 1 and 2 corresponds to approximately 50% of the consumption and installed
capacity of the State of Rio de Janeiro.
Illustrative image
SCHEDULE FOR THE BRAZILIAN NUCLEAR PROGRAM
MW e NPP 9 1300 MW e 11.027
NPP 8 1300 MW e 9.727
NPNPP 7 1300 MW e8.427
NPP 6 1300 MW e 7.127
NPP 5 1300 MW e5.827
NPP 4 1300 MW e 4.527
ANGRA 3 1300 MW e3.227
ANGRA 2 1300 MW e1.927
ANGRA 1 627MW e PREPARATIONCONSTRUCTION
7 2 7 3 7 4 7 5 7 6 7 7 7 8 7 9 8 0 8 1 8 2 8 3 8 4 8 5 8 6 8 7 8 8 8 9 9 0
1977
ANGRA 1
19851984
ANGRA 2
2000
......... ANGRA 3 .......
20152011
BNPP1BNPP2
BNPP3BNPP4
203020091986
0,10
0,10
0,18
0,09
0,05
EARTHQUAKE- DESIGN BASIS ACCIDENT
ELECTRIC SYSTEM EVOLUTION IN THE 90´sNEED FOR THERMAL REGULATION
installed hydro capacityincreasing …
… but without aproportional increase in
the water stock
Stor
age
in G
W m
onth
Installed Hydropower
MW
Reservoir capacity
Contracts
SCHEDULE FOR THE BRAZILIAN NUCLEAR PROGRAM
MW e NPP 9 1300 MW e 11.027
NPP 8 1300 MW e 9.727
NPNPP 7 1300 MW e8.427
NPP 6 1300 MW e 7.127
NPP 5 1300 MW e5.827
NPP 4 1300 MW e 4.527
ANGRA 3 1300 MW e3.227
ANGRA 2 1300 MW e1.927
ANGRA 1 627MW e PREPARATIONCONSTRUCTION
7 2 7 3 7 4 7 5 7 6 7 7 7 8 7 9 8 0 8 1 8 2 8 3 8 4 8 5 8 6 8 7 8 8 8 9 9 0
1977
ANGRA 1
19851984
ANGRA 2
2000
......... ANGRA 3 .......
20152011
BNPP1BNPP2
BNPP3BNPP4
203020091986
0,10
0,10
0,18
0,09
0,05
EARTHQUAKE- DESIGN BASIS ACCIDENT
ELECTRIC SYSTEM EVOLUTION IN THE 90´sNEED FOR THERMAL REGULATION
installed hydro capacityincreasing …
… but without aproportional increase in
the water stock
Stor
age
in G
W m
onth
Installed Hydropower
MW
Reservoir capacity
Contracts
CONSTRUCTION
ANGRA 2 NPP EXPERIENCE
BRAZILIAN EXPERIENCE IN CONSTRUCTION AND MAJOR DESIGN MODIFICATIONS
ANGRA 2 NPP EXPERIENCEELECTROMECHANICAL
ERECTION
BRAZILIAN EXPERIENCE IN CONSTRUCTION AND MAJOR DESIGN MODIFICATIONS
SCHEDULE FOR THE BRAZILIAN NUCLEAR PROGRAM
MW e NPP 9 1300 MW e 11.027
NPP 8 1300 MW e 9.727
NPNPP 7 1300 MW e8.427
NPP 6 1300 MW e 7.127
NPP 5 1300 MW e5.827
NPP 4 1300 MW e 4.527
ANGRA 3 1300 MW e3.227
ANGRA 2 1300 MW e1.927
ANGRA 1 627MW e PREPARATIONCONSTRUCTION
7 2 7 3 7 4 7 5 7 6 7 7 7 8 7 9 8 0 8 1 8 2 8 3 8 4 8 5 8 6 8 7 8 8 8 9 9 0
1977
ANGRA 1
19851984
ANGRA 2
2000
......... ANGRA 3 .......
20152011
BNPP1BNPP2
BNPP3BNPP4
203020091986
0,10
0,10
0,18
0,09
0,05
EARTHQUAKE- DESIGN BASIS ACCIDENT
ELECTRIC SYSTEM EVOLUTION IN THE 90´sNEED FOR THERMAL REGULATION
installed hydro capacityincreasing …
… but without aproportional increase in
the water stock
Stor
age
in G
W m
onth
Installed Hydropower
MW
Reservoir capacity
Contracts
SCHEDULE FOR THE BRAZILIAN NUCLEAR PROGRAM
MW e NPP 9 1300 MW e 11.027
NPP 8 1300 MW e 9.727
NPNPP 7 1300 MW e8.427
NPP 6 1300 MW e 7.127
NPP 5 1300 MW e5.827
NPP 4 1300 MW e 4.527
ANGRA 3 1300 MW e3.227
ANGRA 2 1300 MW e1.927
ANGRA 1 627MW e PREPARATIONCONSTRUCTION
7 2 7 3 7 4 7 5 7 6 7 7 7 8 7 9 8 0 8 1 8 2 8 3 8 4 8 5 8 6 8 7 8 8 8 9 9 0
1977
ANGRA 1
19851984
ANGRA 2
2000
......... ANGRA 3 .......
20152011
BNPP1BNPP2
BNPP3BNPP4
203020091986
0,10
0,10
0,18
0,09
0,05
EARTHQUAKE- DESIGN BASIS ACCIDENT
ELECTRIC SYSTEM EVOLUTION IN THE 90´sNEED FOR THERMAL REGULATION
installed hydro capacityincreasing …
… but without aproportional increase in
the water stock
Stor
age
in G
W m
onth
Installed Hydropower
MW
Reservoir capacity
Contracts
Concrete pouring
Lean Concrete
ANGRA 3: Foundation Works
P R A DPlano de Recuperação de Áreas Degradadas
(Depredated Areas Recuperation Plan)
Situationat 2006
ANGRA 3 NPP RESUMPTION
Situationat 2009
ANGRA 3
Power: 1.405 MWe
Reference: Angra 2
Progress: 30%
Energy: US$ 84,4 / MWh
Construction: 5,5 years
Budget:National Currency: 70%Foreign Currency: 30%
ANGRA 3: Conditions for theProject Resumption
- Site already prepared- Design in advanced stage- Imported supply already available - Financing approved- IBAMA environmental license - March/09- Construction license - Jun/10
Released for operating
2015/12
ANGRA 3
CONSTRUCTION TIME SCHEDULE
Criticality First Hot Operation (Hot Functional)
PREPARATORYACTIVITIES CONSTRUCTION TIME SCHEDULE
Start of Construction (06/01/2010) = Reactor Building Concrete Pouring
Start of Steel Containment ErectionStart of Electromechanical Erection
Start of Commissioning
START OFCOMMERCIALOPERATION
12 16 36 56 63 66
Months after Start of Civil ConstructionMonths beforeStart of Construction
Month -6 Month -1
ACTIVITIESAUTHORIZED
BY IBAMAContract
Renegotiations
SitePreparation
6 Months
Month 01 Month 66
ANGRA 3
Activities in Progress – Civil Works
7
A N G R A 3Main Contracts
BiddingContracts
Existing contracts(Renegotiations)
ENGINEERINGSERVICES
ELECTROMECHANICALERECTION
NATIONALSUPPLIES
Renegotiated
CIVIL
WORKS
NATIONALSUPPLIES
Existing Contracts
STRUCTURALDESIGN
Partial Scope
IMPORTED GOODSAND SERVICES
ConfabBardellaNuclep Renegotiations
in course
ANGRA 3
Renegotiation Almost
Concluded
CONTRACTS OVERVIEW
CIVIL CONSTRUCTION CONTRACT
Bidding• Performed in 1982/1983
Type• Price and technical type for unit prices
Scope
• Goods and services for complete civil construction
Participation
• 5 biggest Brazilian Companies
Winner• Contract awarded to Construtora Andrade Gutierrez S.A.
• Contract start date: March-1984
Services Stopped
• April-1986
CONTRACTS OVERVIEW
• Site Preservation
Period from April-1986 to February-2006
December-2001 to September-2002
• CONTRACT FIRST NEGOTIATION• Preparation Activities
Specialized companies were contracted to perform market-orientedstudies of unit price composition and formation;
Assessments of unit prices based on the best Angra 2 productivityindexes;
Complete scope of services and civil works (known today) defined;
Basic work time schedule established;
CIVIL CONSTRUCTION CONTRACTCONTRACTS OVERVIEW
Assessment of the market prices for the services and works;
Specifications were revised, introducing more rationalization ofconstruction procedures;
Higher manpower and resources availability at work site considered;
The situation of the already existing facilities was evaluated;
FUSP contracted to perform a Technical and Economical evaluation ofthe Project.
2003 – New Brazilian Government in Office
• Renegotiated unit prices were verified by International Consultancies of one Spanish Company and one German Company
CIVIL CONSTRUCTION CONTRACTCONTRACTS OVERVIEW
NEW RENEGOTIATION
June 2007- Decision for Resumption of the Angra 3 NPP
Conditioned to a Feasability study (Eletrobras) and Budget review ( International Consultancy)
September 2008
Eletrobras authorized the beginning of the renegotiation process for all Contracts
October-2008 to February-2009
Renegotiation of Civil works Contract
ORGANIZATION Values/(R$ millions)
FUSP 1.291,3
INTERNATIONAL CONSULTANCY 1.202,1
ELETRONUCLEAR 1.311,6
PROPOSED A.G. 1.370
CIVIL CONSTRUCTION CONTRACTCONTRACTS OVERVIEW
March-2009 to November-2009
Discussions with National Accountability Court- reduction of 9%
Original Contract value: MR$ 1.483,5
Negotiation from 2002: MR$ 1.297,8
Initial Proposal of AG in 2008: MR$ 1.578,8
Accepted Value in Feb 2009: MR$ 1.368,6
Reduction proposed by ELETRONUCLEAR: MR$ 81,4
Reduction agreed with National Accountability Court: MR$ 120,0
Value Contracted: MR$ 1.248,5
CIVIL CONSTRUCTION CONTRACTCONTRACTS OVERVIEW
AREVA CONTRACT RENEGOTIATION
Brazil-Germany Agreement of 1975German Company was contrated to supply 2 NPP´s with a pre-order of other 2.( KWU/Siemens)The activities to implement Angra 2 and 3 NPP´s started with a 12-month delayin operation date.Angra 3 NPP was postponed to 24 months and stopped in 1986. (lack of funds)Activities related to design, component supply and construction continued tosupport Angra 2 NPP, with budget difficulties from 1986 to 1992In 1992, Angra 2 NPP activities were resumed with the negotiation of contractsto adjust to the new reality.In 1994 main Contracts were reviewed and implemented up to the start ofAngra 2 NPP operation.Considering the possibility of resuming Angra 3 NPP, the Areva Company, nowsuceeding KWU/Siemens and ELETRONUCLEAR started new intermitentrenegotiations in 2002. In 2009, more objective meetings were held andELETRONUCLEAR almost concluded the renegotiation process by December2010.
CONTRACTS OVERVIEW
From 2009 to 2011, 12 meetings were held.
As a result, the scope of contracts was completely agreed upon, the valuesconverged to a modification of 5% from the initial value, based on a very goodpreparation.
The Main Objectives of the renegotiation were:
- Adjusting the scope;- Renegotiation of prices and commercial conditions;- Adjustment of Contract terms to current legal frame.
AREVA CONTRACT RENEGOTIATIONCONTRACTS OVERVIEW
- Supply of all imported services and goods required for construction and forimplementation of Angra 2 and Angra 3 Operation;
- Were signed in July 22th of 1976, between FURNAS and KWU;
- Several amendments were signed to adjust to institutional and stakeholdersmodifications by both parts (NUCLEBRAS/ FURNAS/NUCLEN/ELETRONUCLEAR andKWU/SIEMENS/FRAMATOME/AREVA);
- Current situation:
contracted: AREVA NP GmbH valid contracts were signed in 1997; Supply Contract 9501-A Service Contract 9504-A Warranty and Guarantee Agreement 9502-A.
Scope and Contract Structure
Contract General Information
AREVA CONTRACT RENEGOTIATIONCONTRACTS OVERVIEW
CONTRACT GENERAL INFOMATION
SUPPLY CONTRACT 9501-A
SERVICES CONTRACT9504-A
WARRANTY AND GUARANTEE AGREEMENT
9502-A
Annex I – Supply Scope Annex IIII– Service ScopeAnnex II – Codes and Standards Applicable
Annex IV – Technical description
Annex V – Executive schedule
Annex VI – Intermediate storage
Annex VII – Special supply list
Annex VIII – Containment special condition
Annex IX – Pressurize conditions
Annex XIV – (SIPO) Supply Invoices
Annex X – Test conditions
Annex XI – Service Management
Annex XII – Tax, Daily fares, conditions for delegation
Annex XIII – HERMES CostContracts Structure
AREVA CONTRACT RENEGOTIATIONCONTRACTS OVERVIEW
- ELETRONUCLEAR contracted a Swiss International Consultancy company tosupport it in providing market prices for services performed in Nuclearbusinesses in Europe;
- Used the same Professional Characteristics of the Contract;- Same contractual conditions to define the values.
ELETRONUCLEAR Preparation for Services Contract Negotiations
AREVA CONTRACT RENEGOTIATIONCONTRACTS OVERVIEW
- Negotiations developed considering the reference contractual scope;
- Price negotiations do not include the estimated value to purchase spare parts tosupport operation and for general inspection of delivered components;
- Price negotiations do not include the supply of turbine and electrical generatorauxiliary systems;
- Areva’s offer was split in groups of components according to the Contractstructure, with the prices defined for selected components;
- International reference prices were assessed through Belgian, Italian and SwissConsultancy Companies contracted by ELETRONUCLEAR, covering more than90% of the negotiated scope (with overlap of scope of main Price BreakdownPositions-PBDs).
ELETRONUCLEAR Preparation for Supply Contract Negotiations
AREVA CONTRACT RENEGOTIATIONCONTRACTS OVERVIEW
Supply Contract – Group of Components(PBDs – Price Breakdown Positions)
GLOBALPRICE
PBD1
PBD2
PBD3
PBD43
PBD44
PBD45
International reference price adjusted tocontractual conditions
AREVA`s price for Angra 3
Contractual price(Angra 2 price updated according to contractformulas)
PBDn
The most representative values were selected asreference
Reactor Pressure Vessel
Core Structure and Core Components
AREVA CONTRACT RENEGOTIATIONCONTRACTS OVERVIEW
SUMMARY OF AGREED CONDITIONS
GENERAL CONTACTUAL STIPULATIONS-introduction of the performance guarantee bond;-replacement of Swiss Law by Brazilian law as basis for dispute resolution;
SUPPLY CONTRACT-scope of supplies revised considering changes in plant configuration, materialavailability at site, technological evolution and possibilities of ordering fromnational manufacturers;-price conditions renegotiated considering contractual commitments andinternational market prices;-payment conditions adjusted according to international practices in view ofneutral cash flow;-price readjustment formula revised with official indexes better reflecting marketprice evolution;-commercial conditions for additional scope and spare and wear parts -renegotiated considering more realistic estimations of procurement and followup costs.
AREVA CONTRACT RENEGOTIATIONCONTRACTS OVERVIEW
SUMMARY OF AGREED CONDITIONS
SERVICE CONTRACT
- Scope of services revised considering experience and knowledge gained fromthe construction of Angra 2, increasing participation of ELETRONUCLEARengineering.
- Service rates renegotiated considering market prices;- Redefinition of work order and invoicing procedure, changing contract
execution from cost-plus-fee to fixed price per work order;
AREVA CONTRACT RENEGOTIATIONCONTRACTS OVERVIEW
SERVICES BEING CONTRACTED
Public Hearing in 21-Ago-2009
Civil EngineeringServices
Electromechanical Engineering
• Nuclear Structures• Conventional Structures
• Structural Design• Complete Projects
External AreaDesign • Pipe Way Angra 3 to Angra 2
Nuclear Buildings, Mechanical, Electrical and I&C, Ventilation and thermal Insulation
Conventional Buildings, Mechanical, Electrical and I&C, Ventilation and thermal Insulation
ENGINEERINGSERVICES
ERECTIONSERVICES
OWNER´SENGINEERING
Erection Inspection
Civil Works Inspection
Fabrication Inspection
Technical Support
ANGRA 3 CONTRACTS OVERVIEW
MAIN ERECTION- BIDDING PROCESS
NPP Angra 2 ExperienceCONCEPT of INTEGRATED ENGINEERINGOne organization is responsible for the design, procurement, construction,erection, commissioning and overall management.Partially implemented especially in Brazilian supply of some systems andcomponents.HVAC, Feedwater tank, Reactor and Turbine cranes, Biocide System, etc
MAIN ERECTIONS-Contracts ConceptPiping and Mechanical equipment erection in 2 packagesElectrical and I&C erection in one package.First information referred to Main Nuclear System supply experience.Adjustment of known information to Country reality.Brazilian engineering approach proposed to the client.Furnas as client promoted a review by 4 consultancies: a German Company, aSpanish Company, an American Company and a French Company.The results converged to consider manpower and opportunities for schedulereduction.
CONTRACTS OVERVIEW
MAIN ERECTION- BIDDING PROCESS
NPP Angra 2 ExperienceErection was performed with some packages as integrated engineering and 3main contracts for main erection.The bidding process was established with one schedule of 44 months andadequated budget.The process was concluded, the erection was started and concluded in 47months, with an overprice of 31,8 % when compared to the original budget andwith 17 million manhours, which were 20% higher than the originally consideredamountAll the as-built information was considered in Angra 3 NPP budget preparation.
The FUSP Technical and Economical Evaluation was prepared with Angra 2 NPPas-built information and also considered in the Angra 3 NPP budget preparation.
CONTRACTS OVERVIEW
MAIN ERECTION- BIDDING PROCESS
NPP ANGRA 3 BUDGET PREPARATIONNPP Angra 2 as basic informationSimilar contract operationalization conditionsPackage split optimizationReview of documentation, especially of technical specificationsUse of as-built documentationUse of International consultancy for budget reviewEstablishment of the basic budget required 3 years of preparation.
CONTRACTS OVERVIEW
SUPPLYER ITEM INITIALOFFER
VALUEAGREEDED
CONFAB
Steel Containment MR$154,4 MR$ 97,0
GR1 / GR2 Tanks MR$ 44,4 MR$ 36,7
Containment Locks MR$ 24,3 MR$ 13,1
Fuel Pool LinnerFuel Pool PipingFuel Pool Leak Collecting System Linne
Negotiation not started
BARDELLA
Cooling Water Intake Structure Equipments MR$ 43,4 MR$ 26,5
Polar Crane MR$ 36,0 MR$ 29,5
Semi-Gantry Crane MR$ 31,6 MR$ 18,1
Turbine Building Crane MR$ 20,1 MR$ 10,9
Cooling Water Intake Structure Crane MR$ 3,9 MR$ 2,3(Last price)
NUCLEP
Condensers MR$ 73,0 MR$ 58,7
Accumulator Tamks MR$ 20,2 MR$ 17,1
Super Compacts Racks Negotiation not started
Embedded Special Support for LBA line in UJA MR$ 12,1 MR$ 12,1
Embedded Fixed Points for LBA and LAB Systems in UJA MR$ 12,1 MR$ 12,1
Pressure Equalizer Structure (Part) MR$ 12,1 MR$ 12,1
PWRs Rigid Insulation Clamps for LAB in UJA MR$ 1,0 MR$ 1,0
Ventilation Ducts for Connection between UKA and UKH MR$ 2,2 MR$ 2,2
Embedded parts for Reactor Pressure Vessel Support, Pool and Heavy Components Supports MR$ 12,6 MR$ 4,6
KSB Nuclear Centrifugal Pumps MR$ 31,9 MR$ 7,0
EBSE Welded Ferritic Pipes MR$ 17,2 MR$ 17,2
SIEMENS Generator's Transformer MR$ 55,9 Not concluded
NATIONAL CONTRACT RENEGOTIATIONSCONTRACTS OVERVIEW
BIDDING FOR SUPPLY NATIONALS
Remaining supply to becontracted
MATERIAL / COMPONENT TO BE ORDER
Additional Horizontal Centrifugal PumpsRegulating Dampers
FansLifts
Horizontal Centrifugal PumpsVPR Support
Horizontal Centrifugal PumpsCathodic Protection (External Área)
Welded Pipe - ESPESLugs and Ferritic Special Parts
PEB Internal Cathodic Protection System Standard Hoist H5Bridges Pack H3
Ferritic Special Parts Interior Sub-distribution Light System
Return DampersCondensate Collect Tank KPC
Heat Exchangers - GR1Heat Exchangers - GR3
SilencersPressure Equalizer Structure
Components System JMT / KBAHeat Exchangers - GR2VPR Lifting Beam Cover
Plastic TanksPower Cables and Accessories Low Voltage Subdistributors
Standard Air FiltersLocks Sealing Walls
Separator Drops GR31Low Voltage TransformersPumps Completion PUS
Oil SeparatorMotors M.T.
Decontamination Basins with AgitatorReheater Moisture Separator
Frequency ConvertersSpecial Doors
Filters KBE / KPB / SRP / KLXFans PUS
Cold Laboratory FurnitureHot Laboratory Furniture
Auxiliary Bridge External Area Transformer
Heavy Components SupportsDecontamination Room Finishing
Automatic FilterAuxiliary TransformersElectrolytic Cell Bank
Air BlowersInjectors and Sprinklers GN
CONTRACTS OVERVIEW
BIDDING FOR SERVICES
CONTRACT ESTIMATEDVALUE CONTRACTED COMPANY
Civil Engineering
Emergency Services MR$ 1,2 INTERTECHNE
Nuclear Structural Projects MR$ 17,7 In Phase Contract Signing: ENGEVIX
Conventional Completed Projects MR$ 6,2 Papers in Preparation of the Bid
Electromechanical Engineering
Primary Circuit Associated Projects MR$ 155,8 Failed Bidding - New announcement will be published in Jan-2011
Secondary Circuit Associated Projects MR$ 113,9 Opening proposed Commercial 17-Feb-2011
External Area Projects MR$ 3,2 In Phase Contract Signing: ENGEVIX
Flow diagram Drawings MR$ 1,1 In Phase Contract Signing: INTERTECHNE
138 / 500 KV Line Project MR$ 1,4 MARTE ENGENHARIA
Management Support
Fabrication Supervision MR$ 9,8 CONSULPRI
Civil Works Supervision MR$ 74,8 CONCREMAT
Electromechanical Erection Supervision MR$ 71,9 In Phase Contract Signing: DUCTOR
Implementation and Technical Support MR$ 100,5 LOGOS ENGENHARIA
Planning Support MR$ 3,9 STEI
International Engineering Support M EUR 16,9 Announcement of Final Phase of Development
Electromechanical Erection
Primary Circuit Associated BuildingsMR$ 1.497,0 To be launched
Secondary Circuit Associated Buildings
CONTRACTS OVERVIEW
SCHEDULE FOR THE BRAZILIAN NUCLEAR PROGRAM
MW e NPP 9 1300 MW e 11.027
NPP 8 1300 MW e 9.727
NPNPP 7 1300 MW e8.427
NPP 6 1300 MW e 7.127
NPP 5 1300 MW e5.827
NPP 4 1300 MW e 4.527
ANGRA 3 1300 MW e3.227
ANGRA 2 1300 MW e1.927
ANGRA 1 627MW e PREPARATIONCONSTRUCTION
7 2 7 3 7 4 7 5 7 6 7 7 7 8 7 9 8 0 8 1 8 2 8 3 8 4 8 5 8 6 8 7 8 8 8 9 9 0
1977
ANGRA 1
19851984
ANGRA 2
2000
......... ANGRA 3 .......
20152011
BNPP1BNPP2
BNPP3BNPP4
203020091986
0,10
0,10
0,18
0,09
0,05
EARTHQUAKE- DESIGN BASIS ACCIDENT
ELECTRIC SYSTEM EVOLUTION IN THE 90´sNEED FOR THERMAL REGULATION
installed hydro capacityincreasing …
… but without aproportional increase in
the water stock
Stor
age
in G
W m
onth
Installed Hydropower
MW
Reservoir capacity
Contracts
3 000 MWSE3 + SE4 + NE4
3 000 MWSE1 + SE2 + NE3
2 000 MWNE1 + NE2
1 405 MWANGRA 3
HIGH
3 000 MWSE1 + SE2 + NE3
2 000 MWNE1 + NE2
1 000 MWNE1
1 405 MWANGRA 3
MEDIUM
2 000 MWSE1 + SE2
1 000 MWNE2
1 000 MWNE1
1 405 MWANGRA 3
REFERENCE
2026-20302021-20252016-20202007-2015SCENARIOS
8 000 MW
6 000 MW
4 000 MW
2016-2030
NUCLEAR RENAISSANCE IN BRAZILPROJECTIONS FROM NATIONAL ENERGY PLAN 2030
AFTER ANGRA 3:4-6 x 1.000 MW NUCLEAR POWER STATIONS
Recife
AngraNPPs
Manaus
Brasília
São PauloItaipu
Porto Alegre
Fortaleza
SalvadorBelo
Horizonte
Angra
NORTHEAST
SOUTHEAST
NEW NPP SITE SELECTION
NORTH
MiDDLEWEST
Mato Grosso