Annexes
Annex 1: Inventory
Statement of Assets and Equipment
UNDP Country Office: Ministry of the Environment
Project Title : National Biodiversity Project: Conservation of IONA National Park
Reference number agreement: FED/2013/317-806
Award ID: 00074643´
Project ID: 00081396´
Period: 07/02/2013 – 31/12/2015
DONOR ACQUISITION DATE
ITEM DESCRIPTION (make and model)
PROJECT No.
CONDITION RESPONS. PERSON/entity
ITEM LOCATION
Quantity
US$ VALUE EUR VALUE SERIAL NO.
GEF 8/23/2013 Kensingtion Docking Station
´00081396 Good Project Office UNDP
Luanda/INBAC 1
213.98
164.12
A1113A001595
GEF 8/23/2013 Kensingtion Docking Station
´00081396 Good Project Office UNDP
Luanda/UNDP 1
213.98
164.12
A1113A001594
GEF 8/23/2013 UPS APC ´00081396 Good Project Office UNDP
Luanda/UNDP 1
427.96
328.25
3B1249X19075
GEF 8/23/2013 UPS APC ´00081396 Good Project Office UNDP
Luanda/UNDP 1
427.96
328.25
3B1249X18875
GEF 8/23/2013 DELL Desk top Computer
´00081396 Good Project Office UNDP
Luanda/UNDP 1
1,372.61
1,052.79
5RN8WX1
GEF 8/23/2013 DELL Lap Top Computer
´00081396 Good Project Office UNDP
Luanda/UNDP 1
1,393.48
1,068.80
8N3LZW1
GEF 8/23/2013 DELL Lap Top Computer
´00081396 Good Project Office INBAC
Luanda/INBAC 1
1,393.48
1,068.80
2L6LZW1
GEF 8/23/2013 DELL Projector ´00081396 Good Project Office INBAC
Luanda/INBAC 1
1,096.00
840.63
C0VM1S1
GEF 10/7/2013 Toyota Hilux DoubleCab
´00081396 Good Project Office INBAC
Luanda/INBAC 1
22,468.83 17,233.59
AHTFR22G-606072116
GEF 10/10/2013 HP Laserjet 500 Color MFP M570dn
´00081396 Good Project Office INBAC
Luanda/INBAC 1
1,533.02
1,175.83
CN59DD5584
GEF 11/28/2013 DELL Desk top Computer
´00081396 Good Project Office UNDP
Luanda/INBAC 1
1,143.36
876.95
4R7D45J
GEF 11/28/2013 HP 13" 15 4G 128GSSD W7
´00081396 Good Project Office UNDP
Luanda/INBAC 1
1,486.87
1,140.43
CND33309MF
GEF 12/16/2013 IRIDIUM Setlite Phone
´00081396 Good Project Office INBAC
Luanda/INBAC 1
2,507.18
1,923.01
Q639575
GEF 12/17/2013 Armario PP Alto 190*120*45 PER MED
´00081396 Good Project Office INBAC
Luanda/INBAC 1
1,562.50
1,198.44
n/a
GEF 12/17/2013 Armario pp Baixo P/bater chapa 750*100*43
´00081396 Good Project Office INBAC
Luanda/INBAC 1
694.79
532.91
n/a
TOTAL VALUE as of 31 December 2013 37,936.01 29,096.92
EU 8/1/2013 Toyota Land Cruiser Hard top 10
´00081396 Good Project Office INBAC
Luanda/INBAC 1
33,396.61
25,615.20
JTEEB71J907020346
EU 8/1/2013 Toyota Land Cruiser Double Cabin
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 1
32,446.18
24,886.22
JTEBB71JX04000742
EU 10/7/2013 Toyota Land Cruiser Hard top 10
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 1
31,396.62 24,081.21
JTEEB71J907019987
EU 12/19/2013 Cylindro de Gás ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 180.07
138.11 n/a
EU 12/20/2013 Gasoline Generator
´00081396 Defect IONA PARK MANAGEMENT
IONA/Espinhera
1 280.10
214.84 n/a
TOTAL VALUE as of 31 December 2013 97,699.58 74,935.58
YEAR 2014
GEF 3/11/2014 Qide Bike(RANGER800EFI)
´00081396 in need of repair
IONA PARK MANAGEMENT
IONA/Espinhera 1
17,206.00
13,197.00
4XATH76A0E4323504
GEF 3/11/2014 Qide Bike(RANGER800EFI)
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 1
17,206.00
13,197.00
4XATH76AXE4321145
GEF 5/27/2014 Secretaria PP 140*80 C/PAINEL
´00081396 Good Project Office INBAC
Luanda/INBAC 4
2,061.50
1,581.17
n/a
GEF 5/27/2014 Bloco PP ROD.3 Gavetas
´00081396 Good Project Office INBAC
Luanda/INBAC 5
2,774.24
2,127.84
n/a
GEF 5/27/2014 Divisoria Acrilica 120*20*500
´00081396 Good Project Office INBAC
Luanda/INBAC 2
606.16
464.93
n/a
GEF 5/27/2014 Divisoria Acrilica 120*20*500
´00081396 Good Project Office INBAC
Luanda/INBAC 2
672.04
515.45
n/a
GEF 5/27/2014 Secretaria PP 140*80 C/PAINEL
´00081396 Good Project Office INBAC
Luanda/INBAC 1
515.38
395.29
n/a
GEF 5/27/2014 Cadeira Operativa C.Alta utila C/B Preta
´00081396 Good Project Office INBAC
IONA/Espinhera 5
1,384.53
1,061.93
n/a
GEF 8/20/2014 Setlite Phone ´00081396 Good Project Office INBAC
IONA/Espinhera
1 2,357.40
1,808.12
300215010559320
GEF 8/20/2014 Setlite Phone ´00081396 Good Project Office INBAC
Luanda/INBAC 1
2,357.40
1,808.12
300215010555490
GEF 8/20/2014 Setlite Phone ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 2,357.40
1,808.12
300215010653050
GEF 8/25/2014 Fiscais equip & Material (IONA PARK)
´00081396 Fair IONA PARK MANAGEMENT
IONA/Espinhera KIT
4,377.00
3,357.16
n/a
TOTAL VALUE as of 31 December 2014 53,875.04 41,322.16
EU 1/8/2014 Guardafato ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 260.10
199.50
n/a
EU 1/9/2014 Inverter ´00081397 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 162.98
125.01
n/a
EU 4/14/2014 Computer Dell, 3010 MT, i5-34
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 2,105.82
1,615.17
X103010102E
EU 4/14/2014 Laptop, HP, i7, 12GB 1TB, 15"
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 2,387.29
1,831.05
F9U09EA
EU 4/14/2014 E) Photo Sony DSC-W710 16M 5X
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 6
935.42
717.46
DSC-W710/B
EU 4/14/2014 UPS, APC 1100Bx ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
2 469.12
359.81
BX1100CI
EU 4/14/2014 Printer, HP laserjet, MFP colo
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 990.36
759.61
CE863A
EU 4/14/2014 Printer, HP, Officejet 8600A
´00081396 Good Project Office UNDP
Luanda/UNDP 1
375.30
287.85
CM750A
EU 4/14/2014 Projector, Dell, M110 micro, 2000lumens
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 1
672.40
515.73
M110
EU 4/14/2014 Sony recorder UX543F
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
6 1,169.67
897.14
ICD-UX543/B
EU 5/12/2014 Metal Trunks 710 x 405 x 315cm
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
6 735.82
564.38
n/a
EU 5/12/2014 Double burner gas stove with legs
´00081396 fair IONA PARK MANAGEMENT
IONA/Espinhera
3 948.50
727.50
n/a
EU 5/12/2014 Folding tables polyethylene 183x 76cm
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 8
1,041.40
798.75
n/a
EU 5/12/2014 Temporal accommodation Tents IONA KITS
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera KIT
30,919.82
23,715.50
n/a
EU 5/27/2014 GPS, Garmin Etrex Vista
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
3 858.49
658.46
00000021717
EU 9/3/2014 Park stamp ´00081397 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 66.42
50.94
n/a
EU 8/11/2014 Toyota Land Cruiser Double Cabin
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 1
42,010.98
32,222.42
JTEBB71J204002999
EU 8/11/2014 Toyota Land Cruiser Single Cabin
´00081396 Good IONA PARK MANAGEMENT
Namibe/Luanda 1
40,543.98
31,097.23
JTELB71J507109077
EU 8/25/2014 Fiscais equip & Materiais (IONA PARK)
´00081396 Fair IONA PARK MANAGEMENT
IONA/Espinhera KIT
13,000.00
9,971.00
n/a
EU 10/6/2014 Martelos, picaretes etc
´00081397 Good IONA PARK MANAGEMENT
IONA/Espinhera
2 152.76
117.17
n/a
EU 10/9/2014 Rede Sombra ´00081396 Defect IONA PARK MANAGEMENT
IONA/Espinhera
1 340.39
261.08
n/a
EU 10/9/2014 Electro Panga ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 182.85
140.25
n/a
EU 10/9/2014 Jig Saw, Mitre Saw, Drill
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 315.90
242.30
n/a
EU 10/9/2014 Saigol Electrica ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
3 443.34
340.04
n/a
EU 10/9/2014 Discos de Corte ´00081397 Defect IONA PARK MANAGEMENT
IONA/Espinhera
2 20.76
15.92
n/a
EU 10/9/2014 Rebarbadeira ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 157.74
120.99
n/a
EU 10/10/2014 Estudio Konica SD Cards for Cameras
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
4 103.78
79.60
n/a
EU 10/27/2014 Electrical Panga ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 88.46
67.85
n/a
EU 10/28/2014 Plastic Tables ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 315.48
241.97
n/a
EU 10/28/2014 Gas Cylinders ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
2 282.27
216.50
n/a
EU 10/28/2014 Gas Regulators ´00081396 Defect IONA PARK MANAGEMENT
IONA/Espinhera
2 33.21
25.47
n/a
EU 10/29/2014 Fridge ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 327.94
251.53
n/a
EU 10/30/2014 Pots ´00081396 Defect IONA PARK MANAGEMENT
IONA/Espinhera
2 70.15
53.81
n/a
EU 10/30/2014 Gas stove ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 149.44
114.62
n/a
EU 10/30/2014 Deep Freezer ´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 341.09
261.62
n/a
EU 11/18/2014 SD cards for cameras
´00081397 Good IONA PARK MANAGEMENT
IONA/Espinhera
2 66.42
50.94
n/a
EU 11/19/2014 cutting & welding equipment
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 166.04
127.35
n/a
EU 12/30/2014 Truck Renault 4X4, 240.13 FLAT
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 114,797.00
88,049.30
VF644BLM9FB001847
TOTAL VALUE as of 31 December 2014 258,008.89 197,892.82
TOTAL VALUE as at 13 /12/2014
YEAR 2015
EU 1/30/2015 Armario para Armas
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
1 487.92
374.23
n/a
EU 7/9/2014 Teporal acomodation Tents IONA KITS
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera KIT
33,571.95
25,749.69
n/a
EU 8/21/2015 Beliches e Colchoes de mola
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
15 7,664.33
5,878.54
n/a
EU 8/21/2015 Camas de casal e Colchao e 2 bancas
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 3
2,398.10
1,839.34
n/a
EU 8/21/2015 Arnario p/ cozinha nas medidad 1.30x1.6c/ 4 portas
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
5
2,901.70
2,225.61
n/a
EU 8/21/2015 Prateleiras p/escritorio
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
8 2,557.97
1,961.97
n/a
EU 8/21/2015 Mesas nas medidas 1.7x0,90 c/6 cadeiras cada
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera 5
3,117.53
2,391.15
n/a
EU 8/21/2015 Mesas 0.90x0.90 c/ 2 cadeiras cada
´00081396 Good IONA PARK MANAGEMENT
IONA/Espinhera
2 974.75
747.63
n/a
TOTAL VALUE as of 31 December 2015 53,674.26 41,168.15
USD EUR
GEF 91,811.05 70,419.07
EU 409,382.73 313,996.55
Annex 2: Progress towards results matrix
Project Strategy Indicator1 Baseline
Level2
End-of-project
Target3
Level at 30
December
2015
Midterm
Level &
Assessm
ent
Achieve
ment
Rating4
Justification for Rating
Objective: Catalyze
an improvement in
the overall
management of
the protected
areas network,
through
rehabilitating Iona
National Park
Financial sustainability
scorecard for national system
of protected areas
3% at least 10% 10% S Calculated with UNDP-GEF Financial
Sustainability Scorecard that also
evaluates governance. Increase over
baseline is result of increased
implementation of environmental
policies, increased staffing and staff
capacity including in financial
management, increased fee collection,
etc.
Capacity development
indicator score for protected
area system
Systemic: 42%
Institutional:
39%
Individual:
35%
Systemic: 55%
Institutional:
50%
Individual:
45%
Institutional:
21%
Individual:
33%
MS According to Component 1, Element 9 of
the Financial Sustainability Scorecard,
institutional capacity is 5 of 24 = 21%.
According to Criterion 14 of the
Management Effectiveness Tracking
Tool, individual capacity is 1 of 3 = 33%
Total government budget
allocation (including
operational, HR and capital
US$1.5 million
(as at
2010/11)
At least US$8
million
$3.2 million MS Government spending for Iona NP in
2015 is $ 3.2 million according to INBAC.
1 As indicated above, this column is populated directly from project documentation (such as ProDoc, PIRs, etc.). Also in annexes the Log Frame of the
Project as well as added indicators are found. Therefore, further information on indicators, baselines level and end of project targets can be found there. 2 As indicated above, this column is populated directly from project documentation (such as ProDoc, PIRs, etc.). Also in annexes the Log Frame of the
Project as well as added indicators are found. Therefore, further information on indicators, baselines level and end of project targets can be found there. 3 As indicated above, this column is populated directly from project documentation (such as ProDoc, PIRs, etc.). Also in annexes the Log Frame of the
Project as well as added indicators are found. Therefore, further information on indicators, baselines level and end of project targets can be found there. 4 Six - point Progress Towards Results Rating Scale: HS, S, MS, MU, U, HU
budget) (US$ per annum) for
protected area management
Number of protected areas in
which the METT is adopted
as a tool to monitor
effectiveness of PA
management
0 At least 7 1 MU Only 1 of 7 PAs use METT methodology
(Iona NP)
Outcome 1)
Rehabilitation of
Iona National Park
Management Effectiveness
Tracking Tool scorecard:
Iona National Park
0.07 5 points out of
102 possible,
giving (Jan
2012) = 45%
37/102 = 36% S Scoring improved due to improvement
in all criteria
Number of park
management staff
appointed, equipped, trained
and deployed in the park
0 12 22 HS Staffing of the park is completed
Percentage (%) of park
visitors obtaining a permit to
traverse/overnight in the
park
0% At least 80% n.d. MS During 2015, 1936 park visitors were
registered. However, visitors through
Salondjamba and Pediva are registered,
but entry through Tombwa is not yet
controlled, therefore percent of visitors
being registered cannot be determined.
Proportion (%) of the plains
grassland habitats of the park
(~600km2) overgrazed by
livestock (goats and cattle)
More than
35% (by
2011/12)
Less than 20% n.d. MU There is very little presence of livestock
in the plains (as opposed to the
mountains), therefore overgrazing
occurs only around the relatively few
waterholes and its impact on wildlife
cannot by assessed through percent
area value, which in addition is almost
impossible to determine for whole park.
Increase in wildlife
populations:
Oryx
Hartmann’s Zebra
Springbok
Ostrich
1650
265
2400
400
At least 2000
At least 300
At least 3500
At least 500
n.d. MS Aerial survey of wildlife has not yet been
carried out. Qualitative observations
indicate increase in wildlife density
Number of critical natural
freshwater springs and wells
secured and accessible for
use by medium-sized and
large wildlife species
0 (of 16) 4 (of 16) ~10 S Natural wells have been mapped.
Problem is still the occasional use by
livestock during drought when wildlife is
most dependent on these water
sources.
Number of poaching
incidents (park visitors)
recorded in the park/annum
No data Less than 12 2 S Indicator not easy to interpret since
incomplete detection and effective
suppression of poaching would both
lead to low value.
Proportion (%) of
communities living in the
park that are adequately
represented in the park
management decision-
making processes.
0% More than
60%
0% U Although park staff interact with
communities and sobas, these are not
systematically involved in Iona Park’s
decision making process.
Number of job opportunities
(direct and indirect) created
for local communities living
in, or adjacent to, the park
a) Direct: 0 b)
Indirect: 0
a) Direct: at
least 10
b) Indirect: at
least 30
a) Direct: 12
members of
community
are
community
agents
MS Direct employment target obtained.
Need to ascertain sustainability by
formalizing hiring by GoA.
Indirect employment still at baseline
level, with no indication of generation of
(rangers) b)
Indirect: 0
employment for local community
members living in or adjacent to Iona
Park.
Average annual income (US$)
of households living in the
park
US$155/annu
m
At least
US$250/annu
m
n.d. U Full data unavailable, however (besides
the 12 rangers hired by the Project)
there has been no output or product
implemented that could feasibly
generate income and/or improve living
conditions of people living in the Park.
Outcome 2)
Strengthen
institutional
capacity to
manage the
protected areas
network
Strategic Plan, and a policy
framework, for the system of
protected areas formally
approved by government
No Yes Yes
MS PLERNACA is approved by GoA.
Refinement of plan through study
contracted by the project is underway.
Organizational structure for
protected areas and job
descriptions, remuneration
levels and conditions of
service for protected area
staff formally adopted by
government
No Yes No MS Key components of this work have been
incorporated in ongoing study on
strategic plan of protected area system.
A minimum structure of INBAC is in
place.
Recruitment of staff to
approved protected area
posts in the organogram of
the protected area agency
(as a % of posts with
permanent staff appointed)
0 At least 50% n.d. MS Organogram is being developed in study
funded by the project. Staffing of INBAC
has been increasing but percent value
cannot be determined in the absence of
an approved organogram.
Number of protected area
staff completing in-service
training and skills
development programmes
0 20 17 MS Training reported in GIS only, need to
train in other skills
Number of senior protected
area staff in a structured
mentoring programme
0 3 >3 S National and international park manager
of Iona NP and National Project
Coordinator are being mentored by
UNDP staff. Intensive and frequent
interaction between UNDP and INBAC
management.
Number of national parks
and strict nature reserves
with fully documented up-to-
date assessments of their
state and biodiversity value
0 7 0 MU By reporting deadline this activity had
not been initiated, although PAs to be
assessed had been identified and
consultants been selected.
Number of protected areas
where a structured
rationalisation and
rehabilitation programme is
adequately resourced and
under implementation
1 4 3 S Besides Iona NP, Kissama NP has been
rehabilitated with government funds
and Cangandala with the support of
Chevron.
Annex 3: Finance report 2015
Atlas Award ID: ´00064743
Business Unit
ÁGO10
Atlas Project ID- GEF+UNDP TRAC + EU ´00081396 Projecto Nacional de Biodiversidade: Conservação do Parque Nacional do IONA Award Title: PIMS 4581 Angola Nat BD
Proj Iona Conservation
Parceiro de Implementação
National Biodiversity Project: Conservation of IONA National Park
Códigos do Doador GEF: 10003
Ministério do Ambiente UNDP TRAC
´00012
EU: ´00280
Responsible Party/
Implementing Agent
Project ID
Fund ID
Donor Name ATLAS
Budget Code
Altlas Budget Description
TOTAL (USD)
TOTAL (EUR) TOTAL EXPENDITURE AS
OF 31 DEC 2015 (USD)
TOTAL EXPENDITURE AS OF 31 DEC 2015
(EUR) Budget Notes
Component 1: Reabilitation of Iona National Park do Parque Nacional de Iona
NIM 00081396 62000 GEF 71300
Local Consultants 185,000
137,037.04 6,165.83 4,729.19 3
NIM 00081396 62000 GEF 71600 Travel 3,000
2,222.22 1,980.76 1,519.24 2
NIM 00081396 62000 GEF 72100
Contractual Services - Companies 231,000
171,111.11 165,585.72 127,004.25 1.4
NIM 00081396 62000 GEF 72200
Equipment and Furniture 60,000
44,444.44 34,505.94 26,466.06 5
NIM 00081396 GEF 72400
Communic & Audio Visual Equip 200,000
148,148.15 170,210.65 130,551.57 6
NIM 00081396 62000 GEF 72500 Supplies 56,000
41,481.48 63,386.65 48,617.56 7
NIM 00081396 62000 GEF 72800
Information Technology equipment 15,000
11,111.11 3,196.57 2,451.77 8
Total- Componente 1 (GEF)/ Act. Atlas Nº1 750,000
555,555.55 445,032.12 341,339.64
NIM 00084599 00280 EU 71300
Local Consultants 110,000
81,481.48 - - 9.48
NIM 00084599 00280 EU 71400
Contractual Services - Individuals 1,170,770
867,237.04 460,772.53 353,412.53 10.35
NIM 00084599 00280 EU 71600 Travel 223,652
165,668.15 11,936.54 9,155.33 11,36,45,46
NIM 00084599 00280 EU 72100
Contractual Services - Companies 413,000
305,925.92 153,535.59 117,761.80 12.37
NIM 00084599 00280 EU 72200
Equipment and Furniture 455,000
337,037.04 332,713.49 255,191.25 13.38
NIM 00084599 00280 EU 72300
Materials and Goods 70,000
51,851.85 26,855.82 20,598.41 14.39
NIM 00084599 00280 EU 72500 Supplies 200,000
148,148.15 45,850.59 35,167.40 15
NIM 00084599 00280 EU 73200
Premises alterations 1,362,000
1,008,887.89 19,614.39 15,044.24 16.4
Total- Componente 1( EU) / Act. Atlas Nº4 4,004,422
2,966,237.52 1,051,278.95 806,330.95
TOTAL COMPONENTE 1 4,754,422 3,521,793.07
1,496,311.07
Component 2. Strengthen
Institutional Capacity to Manage the
Protected areas network
NIM 00081396 62000 GEF 71300
Local Consultants 24,000
17,777.78 15,398.04 11,810.30 17
NIM 00081396 62000 GEF 71600 Travel 68,000
50,370.37 17,698.28 13,574.58 47
NIM 00081396 62000 GEF 72100
Contractual Services - Companies 892,000
660,740.74 - - 21
NIM 00081396 62000 GEF 72200
Equipment and Furniture 28,000
20,740.74 32,702.28 25,082.65 18
NIM 00081396 62000 GEF 72800
Information Technology equipment 14,000
10,370.37 2,002.26 1,535.73 19
NIM 00081396 62000 GEF 73100
Rental & Maintenance-Premises 11,000
8,148.15 5,943.54 4,558.70 20
NIM 00081396 62000 GEF 74100
Professional Services 19,000
14,074.07 15,938.70 12,224.98 22
Total- Componente 2 (GEF)/ Act. Atlas Nº1
1,056,000
782,222.22 89,683.10 68,786.94
NIM 00084599 00280 EU 71200
International Consultants 60,000
44,444.45 - - 23
NIM 00084599 00280 EU 71600 Travel 30,000
22,222.22 10,520.84 8,069.48 49
NIM 00084599 00280 EU 72100
Contractual Services - Companies 363,500
269,259.26 65,915.92 50,557.51 42.24
NIM 00084599 00280 EU 74100
Professional Services 40,054
29,669.63 37,827.62 29,013.78 22
Total- Componente 2 ( EU) / Act. Atlas Nº4
493,554
365,595.56 114,264.38 87,640.78
NIM 00081396 04000 UNDP 71200
International Consultants 60,000
44,444.44 6,302.00 4,833.63 25
NIM 00081396 04000 UNDP 71300
Local Consultants 30,000
22,222.22 - - 26
NIM 00081396 04000 UNDP 71400
Contractual Services - Individuals 450,770
333,903.70 405,616.49 311,107.85 27
NIM 00081396 04000 UNDP 71600 Travel 45,000
33,333.33 61,208.73 46,947.10 28
Total- Componente 2 ( UNDP-TRAC) / Act. Atlas Nº6
585,770
433,903.69 473,127.22 362,888.58
TOTAL COMPONENTE 2 2,135,324 1,581,721.47
677,074.70
Project Management
NIM 00081396 62000 GEF 71400
Contractual Services - Individuals 194,000
143,703.70 131,323.60 100,725.20 29
Total-gestão do Projecto (GEF)/ Act. Atlas Nº2
194,000
143,703.70 131,323.60 100,725.20
NIM 00084599 00280 EU 71400
Contractual Services - Individuals 136,230
100,911.11 95,367.97 73,147.23 44.5
NIM 00084599 00280 EU 71600 Travel 40,000
29,629.63 29,077.57 22,302.50 30
NIM 00084599 00280 EU 72200
Equipment and Furniture 49,000
36,296.30 36,098.82 27,687.79 31
NIM 00084599 00280 EU 72400
Communic & Audio Visual Equip 22,648
16,776.30 14,978.85 11,488.78 32
NIM 00084599 00280 EU 72500 Supplies 39,707
29,412.59 14,870.80 11,405.90 33
NIM 00084599 00280 EU 74100
Professional Services 135,000
100,000.00 84,816.73 65,054.43 43
Total-gestão do Projecto (EU)/ Act. Atlas Nº5 422,585
313,025.93 275,210.74 211,086.64
NIM 00081396 04000 UNDP 71400
Contractual Services - Individuals 538,904
399,188.15 483,723.23 371,015.72 34
NIM 00081396 04000 UNDP 72100
Contractual Services - Companies 15,326
11,352.59 8,077.08 6,195.12 20
Total-gestão do Projecto (UNDP-TRAC)/ Act. Atlas Nº7 554,230
410,540.74 491,800.31 377,210.84
TOTAL GETSÃO DO PROJECTO 1,170,815 867,270.37
898,334.65
Grand Total( Excluding indirect cost 8,060,561
5,970,784.91 3,071,720.42 2,356,009.56
Indirect Cost (EU)
75100 F&A (GMS) 344,439
255,140.99 100,852.78 77,354.09
Grand Total( Including indirect cost 8,405,000
6,225,925.90 3,172,573.20 2,433,363.65
“Of the 2.433.363,65 EUR presented above, EUR 2.433.363,65 corresponds to eligible expenses (as per IPSAS terminology), EUR 0 (Zero) represent the amount of legal commitments currently in force between UNDP (or UNDP’s implementing partners) and a third party”.
Annex 4: Annual work plan 2016
Implementation modality: NIM
Implementing Partner: Ministry of the Environment (IP: 001354)
Donors: UNDP TRAC; GEF; EU Expected CPAP Output: Effective implementation of biodiversity strategy and action plan Outcome 1: Rehabilitation of Iona National Park
Output 1.1: Appoint, train, equip and deploy park staff
Output Results 1.1: Advertising, selecting and appointing a park manager to lead and mentor the park team
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
1.1.1 Expenses with the International Park Manager of Iona NP (line 10)
X X X X EU 112.200 N/A
1.1.2 Expenses with 20 park rangers during 12 months (line 35)
X X X X EU 144.000 N/A
1.1.3 Expenses with the National Park Manager of Iona NP (line 10)
X X X X EU 50.050 N/A
1.1.4 Vehicle maintenance (line 15) X X X X EU 30.000 N/A
1.1.5 Payment of services provided by customs broker (park rangers equipment) in 2014 (lines 5,13, 38)
X EU
GEF 5.000 7.000
N/A
1.1.6 Support and facilitate cross-border cooperation process; exchange visits with Namibia (Line 11)
X X EU 50.000
Organize visit by project staff, INBAC, MINAMB and UNDP to Namibia, in order to gather information on experiences with community conservation and organize technical collaboration and exchange. Initial plan is an approx. 3-day visit to Namibia in May
Output 1.2: Establish key park infrastructure, equipment and services
Output Results 1.1: Essential equipment purchased in order to allow the operation of Iona NP; construction of essential infrastructure
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
1.2.1 Supervision of the implementation of the detailed construction and renovation plan of Iona NP infrastructure
X X X X EU 15.000 Coordination field visits
1.2.2 Construction of a storage area, health center, training center, waste treatment facilities, water holes, and solar energy in the park (line 16)
X X X X EU 700.000
Part of the amount will be used to pay infrastructure that has already been implemented (renovation of housing at three posts). Remaining funds will be used to implement storage rooms and solar energy at the three posts. Technical and price information for contracting the installation of solar energy systems and storage rooms/garage for the three posts is currently being collected.
1.2.3 Purchase and installation of three diesel tanks and a fuel management system in Salondjamba, Espinheira and Pediva posts
X X EU 15.000 Fuel tanks will be installed in the three posts as soon as appropriate protected storage space has been created through 1.2.2.
1.2.4 Complete the installation and maintenance of the radio and satellite communication system in Iona NP (Line 6)
X X GEF 30.000 Funds already allocated. Need to finish the installation of the seventh antenna and radios depending on solar energy
1.2.6 Analyze the situation, develop ToR and hire a company for water supply and sanitation for the communities in the Park (line 40)
X X X X EU 372.000
Improve water supply and sanitation for permanent, fixed communities, including as an incentive for park residents to settle in those communities and reduce human and livestock presence in fragile areas that have little use value but are important for conservation, in line with the Management Plan. On the basis of an agreed Plan, hire company to provide the installation of water and sanitation facilities in identified locations.
Output 1.3: Develop an integrated park management plan
Output Results 1.3: Conduct a study about the Iona NP, by consolidating all existing information and data collected in the field; and develop an integrated park management plan, with the support of key stakeholders.
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
1.3.1 Travel for technical support, supervision and training of personnel related to the studies in Iona NP
X X X X GEF 3.000 Travel for the Management Plan public consultation
1.3.2 Preparation of the Strategic Management Plan (SMP) for the Iona NP
X X EU 33.600 Reviewing the zoning framework with the Park Management and SAAMA, consultation and approval meetings. Finalization of the SMP
1.3.5 Aerial survey of wildlife and livestock in the Iona NP to update the last survey (2003) (Line 4)
X X X X GEF 100.000
Project coordination and INBAC are identifying potential service providers in Angola and SADC, and will request proposals and budgets, to be followed by contracting and implementation before end 2016
1.3.6 Conduct hydrological study in Iona NP by hiring a consulting company (Line 3)
X X X X GEF 85.000
There is a consensus in the Technical Committee that a hydrological study is not a priority / need at this time. On the other hand, water supply in Salondjamba and Pediva posts is needed. The Park Management is requesting offers from companies and, when received, will request permission to reallocate funds.
Output 1.4: Build community and local government support for, and participation in, the conservation of the park
Output Results 1.4: Create mechanisms to allow a permanent participation of the communities in the decision-making and implementation of park management; and facilitate resolution of conflicts regarding use of resources that benefits all parties.
Schedule Activity Timeline Funding
Source Amount
USD Comments
Q1 Q2 Q3 Q4
1.4.1 Continue the livestock survey in the Iona NP, evaluate conflicts between humans and wildlife, the impact of livestock on biodiversity, suggest mitigation measures and implement pilot projects (line 3)
X X GEF 45.000 Is component of ongoing communities study. First part has been submitted in March, the other parts and final report is expected following a second visit to the park in April / May
1.4.2 Ensure permanent communication and local representation in the decision-making processes of the park; agree measures to minimize the impact of local communities on biodiversity and allow conflicts resolution; make participatory approach to training; organize meetings of community cooperation; travel of community members for this purpose; (Line 45)
X X X X EU 5.000 Park Manager will attend regular meetings between the Iona
commune and traditional chiefs (sobas) (~ 3x per year)
1.4.3 Identify, through consultation, sustainable forms of alternative livelihoods, including employment opportunities for members of local communities (3)
X X EU 55.000 Is component of ongoing communities study, see 1.4.1
1.4.4 Facilitate training, advice and exchange in order to support the development of skills for the community members, including travel costs (Line 11)
X X X EU 10.000 Exchange between Iona and Namibia’s communities to be planned during the visit to Namibia (see 1.1.6)
1.4.5 Identify, plan and implement, with the communities, confidence building interventions; Start the development and implementation of income generation activities for communities, including skills development and recruitment of community members (line 48, 37)
X X X X EU 60.000
160.000
Park management will develop a tourism plan that includes the communities. Part of the funds will be used to communicate the strategic management plan to communities once the zoning has been completed
1.4.6 Equipment for income generation activities for communities (line 38)
X X X X EU 25.000 To be used together with 1.4.5
1.4.7 Develop and start implementing a cross-border coordination plan at the local level (communities, local authorities, park staff), including cooperation meetings, exchanges and capacity building
X X X X EU 25.000 To be planned during the visit to Namibia (see 1.1.6)
1.4.8 Materials for income generation activities
X X X EU 55.000 To be used together with 1.4.5
Outcome 2: Strengthen institutional capacity to manage the protected areas system
Output 2.1: Prepare a Strategic Plan for the protected area system
Output Results 2.1: Action Plan for the PLERNACA’s implementation and establishment of effective national conservation areas network; strategies and policies of engagement of stakeholders in Conservation Areas
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
2.1.1 Consultancy for preparation of a Strategic Plan for the conservation areas system (Line 21). Company selection, contract award and implementation of study.
X X X X GEF 110.000 Company already contracted. Project will make periodic meetings with the company in order to monitor the work
Output 2.2: Develop the organizational and staffing structure for the protected area system
Output Results 2.2: Functional analysis of what exists, suggest a more practical and detailed proposal, identification of key issues and training plan
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
2.2.1 Development of an organizational structure and staffing for the conservation areas system. Company selection, contract award and implementation of study
X X X TRAC/PNUD 0 No funds available. Discuss with INBAC the possibility to develop this internally.
Output 2.3: Assess the current state of national parks and strict nature reserves
Output Results 2.3: After concluding a rapid assessment of all 8 NPs and 1 SNR, select 6 areas for further studies, prepare a state of art report for each area
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
2.3.1 Preparation of an Assessment of the conservation areas in Angola and rehabilitation plans (Line 21)
X X X X GEF 650.000 Companies are already contracted. Project will make periodic meetings with companies to monitor work.
2.3.2 Travel costs related to the 6 conservation areas report (Line 47)
X X X GEF 6.000 N/A
2.3.3 Publishing ToR (Line 22) X X X X GEF 5.000 completed
Output 2.4: Prepare detailed implementation plans for the rehabilitation of national parks
Output Results 2.4: Create appropriate conditions and prepare detailed implementation plans for 6 conservation areas
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
2.4.1 Monitor the preparation of 6 implementation plans (Line 47)
X X X X GEF 6.000 Seminars; workshops
2.4.2 Professional Services and translation (line 22)
X X X X EU 11.000 N/A
2.4.4 Develop a proposal and design the construction of the bridge at the entrance of Salondjamba, through contractual of a consultant company, including environmental impact assessment (Line 42)
X X X EU 283.000
MINAMB has contracted the study that still needs to be analyzed and paid. INBAC needs to check whether it is still possible to implement a simple bridge with remaining funds.
Outcome 3: Project management
Output 3.1: Project staff selected, appointed and deployed
Output Results 3.1: The project staff is operational
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
3.1.1 Project administrative assistant (Lines 29, 44)
X X X X GEF EU
24.000 24.000
N/A
3.1.2 National project coordinator (Line 29) X X X X GEF 54.000 N/A
3.1.3 Driver for the project office in Luanda (Line 50)
X X X X EU 11.500 N/A
3.1.4 Office, fuel and other supplies: vehicle maintenance in Luanda; cellphone and internet cost for the National project coordinator and project assistant; general supplies (Lines 32, 33)
X X X X EU 3.162 7.000
N/A
3.1.5 Project staff travel X X X X EU 10.000 Support to a meeting of all park managers in Bicuar in March 2016, organized by INBAC
Output 3.2: Project office in Luanda
Output Results 3.2: Luanda office established, furnished, staffed and operational
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
3.2.1 Contractual service Quarterly Narrative and Financial Report (to UNDP)
X X X X TRAC/PNUD 20.000 All funds allocated
GEF Report (PIR) X
Annual Report (to EU) X
Monitoring field visits X X
Output 3.3: Communication, coordination, visibility and mobilization of support
Output Results 3.3: Visibility and communication plan, data management and information implemented
Schedule Activity Timeline Funding
Source Amount USD Comments
Q1 Q2 Q3 Q4
3.3.1 Implementation of the visibility and communication plan, data management and information (Line 43)
X X X X EU 30.000
Finalize Iona NP’s movie and identify potential partners to promote it (public television, airlines, etc.) Conduct workshop with stakeholders and tour operators in Namibe
Annex 5: Communication and visibility
03 Setembro de 2015 | 11h42 - Actualizado em 03 Setembro de 2015 | 11h40
Representante das Nações Unidas defende cooperação no combate à caça furtiva
Menongue - O representante das Nações Unidas em Angola, Pier Paolo Balladelli, disse, no Cuando Cubango, que a
caça furtiva e o comércio ilegal de espécies ultrapassam as fronteiras nacionais e a regulamentação contra isto
necessita da cooperação internacional.
REPRESENTANTES DAS NAÇÕES UNIDAS DEFENDE COOPERAÇÃO NO COMBATE À CAÇA FURTIVA
FOTO: ARMANDIO MORAIS
Ao intervir na conferência internacional sobre a caça furtiva e os seus efeitos nefastos para o continente africano,
explicou que se pretende, com esta cooperação, a preservação de animais selvagens e o combate ao crime
organizado transnacional.
Segundo Paolo Balladelli, em muitos casos, a caça furtiva tende a fragilizar o Estado de direito e ameaçar a
segurança nacional, provoca a extinção de determinadas espécies, tem impacto profundo na degradação da
biodiversidade e nos serviços eco–sistémicos prestados para as economias nacionais, assim como para a redução
da pobreza, que depende da manutenção do fluxo de benefícios dos ecossistemas.
Afirmou que o marfim dos elefantes e os cornos dos rinocerontes continuam a ser os produtos mais procurados
nos mercados internacionais.
O representante disse, por outro lado, que no âmbito nacional, como signatária da Convenção Quadro das Nações
Unidas para a Conversação da Biodiversidade Biológica (CDB) e da Convenção sobre Comércio Internacional de
Espécies da Fauna e Flora Selvagens Ameaçadas de Extinção, Angola tem desenvolvido uma série de projectos em
parceria.
Realçou a parceria com a União Europeia e o GEF para a reabilitação e a conservação da biodiversidade. Estas
acções ressaltam claramente o compromisso do Executivo angolano na sustentabilidade dos processos de
desenvolvimento do país.
Destacou a iniciativa que norteou a organização da conferência internacional sobre a caça furtiva, pois cria o
ambiente propício para a troca de experiências, melhoria das práticas e promove o fortalecimento do Estado de
Direito dos países mais afectadas com esse tipo de crime organizado transnacional e promove o desenvolvimento
sustentável.
Fonte: http://www.portalangop.co.ao/angola/pt_pt/noticias/ambiente/2015/8/36/Representante-das-Nacoes-
Unidas-defende-cooperacao-combate-caca-furtiva,0cd8ef69-a598-4bff-a52b-63fd34a2e2ce.html
Combate à caça furtiva ganha dimensão
Manuel de Sousa | Namibe
17 de Agosto, 2015
Fotografia: Francisco Bernardo
O Parque Nacional do Iona, na província do Namibe, conta desde ontem com mais 20 fiscais florestais, duas
residências e uma nova cancela de entrada pela localidade de Sarojamba, no âmbito do projecto da
biodiversidade e conservação do espaço.
O projecto, inaugurado pela ministra do Ambiente, Fátima Jardim, está orçado em oito milhões de dólares e foi
financiado pelo Fundo Mundial do Ambiente, União Europeia, Programa das Nações Unidas para o
Desenvolvimento (PNUD), Executivo angolano e seus parceiros.
O programa faz parte da conservação que o Executivo, em conjunto com parceiros, tem feito nas áreas naturais do
país, criando condições de desenvolvimento sustentável, protecção das áreas naturais e ao mesmo tempo
oferecendo oportunidade de trabalho.
O representante do PNUD em Angola, Paollo Balladelli, disse que a execução do projecto no parque do Iona já esta
avançado, o que reforça a continuação da construção de infra-estruturas e estudos de evidências para conservação
da fauna.
“Estamos muito orgulhosos de estar aqui no parque do Iona e assistir estas inaugurações e de lançar outros
projectos para o benefício do meio ambiente deste imenso país”, referiu o diplomata.
Paollo Balladelli garantiu que os passos a seguir, além da continuação da construção de infra-estruturas, têm a ver
com a avaliação dos animais selvagens que existem no parque e criar condições para estes ficarem no espaço. Por
isso, disse que vão ser abertos furos de água e outras serviços, para que o parque seja o monumento da
conservação e assim receber muitos turistas no futuro, um projecto que é levado a efeito com a Namíbia.
O administrador municipal do Tômbwa, António Chindongo, disse que o projecto é muito importante na medida
em que vai ajudar a explorar todas as potencialidades do parque do Iona. As infra-estruturas vão facilitar o
controlo da entrada e saída dentro do parque, quer de turistas, quer de outros transeuntes e ter uma ideia geral
da população animal, classificá-los e dar um número próximo da realidade de cada uma das espécies.
A inauguração das infra-estruturas na localidade do Sarojamba é a primeira das três cancelas que se precisam,
sendo outras em Pediva e a terceira na zona da Erora, no extremo leste na fronteira com o Cunene.
O número do efectivo fiscal florestal ainda é insuficiente, mas o administrador municipal do Tômbwa disse que a
grande questão passa pela aquisição de equipamentos para que os fiscais façam um trabalho mais eficaz.
António Chidongo disse que são necessários meios que possam facilitar o trabalho dos fiscais na sua tarefa diária,
como viaturas todo-o-terreno e rádios de comunicação, numa altura em que estão a ser montados alguns
repetidores que vão ajudar a fazer o monitoramento.
Fonte: http://jornaldeangola.sapo.ao/politica/combate_a_caca_furtiva_ganha_dimensao
Annex 6: List of contracts above € 60,000
UNDP Country Office: Ministério do Ambiente
Project Title : National Biodiversity Project: Conservation of IONA National Park
Reference number agreement: FED/2013/317-806
Award ID: 00074643´
Project ID: 00081396´
Period: 07/02/2013 – 31/12/2015
DONOR CONTRACT
DATE NAME of
COMPANY DESCRIPTION of
CONTRACT QTY ITEM
PROJECT No.
% COMPLITION
RESPONS. ENTITY
CONTRACTION
US$ VALUE OF CONTRACT
EUR VALUE OF CONTRACT
EU
4/3/2014 TOYOTA
GIBRALTOR
LTA BETWEEN UNDP AND TOYOTA GIBRALTOR
5
´00081398 100 MINAMB
179,794.37 137,902.28
GEF 1 22,468.83 17,233.59
GEF
8/5/2014 MILICIAPRO
- Contracto deFormação dos
Agentes Comunitarios -Contracto de
aquisição de Kits de Material para os 20
Agentes Comunitario
1 ´00081398 100 MINAMB
123,482.76 94,711.28
EU
20,000.00 15,340.00
GEF 9/30/2014 CAPINHA LDA Estudo e Instalação de um Sistema de Comunicação no
1 ´00081396 90 MINAMB 160,000.00 122,720.00
Parque Nacional do IONA
EU 9/30/2014 CAPINHA LDA
Consultoria e Planeamento de Construções no Parque Nacional do IONA
1 ´00081398 85 MINAMB 120,000.00 92,040.00
EU
9/30/2014 SAAMA
Estudo do Estado do Parque Nacional do IONA e Elaboração
do Respectivo Plano de Gestão Integrada
1 ´00081398
61.5
MINAMB
87,897.04 67,417.03
GEF 32.39 42,102.96 32,292.97
EU 9/30/2014 SOAPRO
Estudo das Comunidades no Parque Nacional do IONA
1 ´00081398 60.73 MINAMB 130,000.00 99,710.00
EU BUKKEHAVE
CORPORATION A/S
LTA BTWN UNOPS and BUKKEHAVE 2012
1 ´00081398 100 MINAMB 114,797.00 88,049.30
GEF 12/4/2015 AMBIEU
Estudo Tecnicos de Avaliação do Estado Actual de Conservação em Angola e Elaboração de Planos de Reabilitsção(Parque Nacional do MUPA e Reserva Integral do Luando
1 ´00081398 15 MINAMB 150,000.00 115,050.00
GEF 12/4/2015 EUCALIPTUS
Estudo Tecnicos de Avaliação do Estado Actual de Conservação em Angola e Elaboração de Planos de Reabilitsção(Parque Nacionais do Maiombe e Cameia
1 ´00081398 15 MINAMB 240,000.00 184,080.00
GEF
12/4/2015 FUNDAÇÃO
KISSAMA
Elaboração do Plano Estrategico para o Sistema de Áreas e Conservação
1 ´00081398 15 MINAMB 110,000.00 84,370.00
GEF 12/11/2015 GERAÇÃO
VERDE
Estudo Tecnico de Avaliação do Estado Actual das Áreas de Conservação em Angola e Planos de detalhados para Reabilitsção das Áreas de Conservação(Parque Nacionais do Mavinga e Luengue-Luiana
1 ´00081398 15 MINAMB 260,000.00 199,420.00