annexure-3 : revised “ volume 2(r1)”
TRANSCRIPT
Annexure-3 : Revised “ Volume-2(R1)”
1
STANDARD BIDDING DOCUMENT
FOR
PROCUREMENT OF WORKS
Construction of Sewage Treatment Plants (STPs),
Pumping Stations, ETPs for Dairy Complexes,
Rehabilitation of existing STPs & Main Pumping
Stations for Abatement of Pollution in Buddha
Nallah, Ludhiana
including Operation & Maintenance for a period of
10 years (on DBOT basis) under AMRUT
at
Ludhiana, Punjab
(Value of the Project: Lump-Sum contract including 10 years O&M)
Volume -2 (Part -1) (R1)
SECTION-5
TECHNICAL CONDITIONS, SPECIFICATIONS & REQUIREMENTS
Standard Basic Specifications & General Requirement
February, 2020
Annexure-3 : Revised “ Volume-2(R1)”
2
Article I. Table of Contents
ARTICLE I. TABLE OF CONTENTS ......................................................................................................... 2
SAMPLING PROTOCOL FOR STP PROCESS ......................................................................................... 58
DESIGN REQUIREMENT ............................................................................................................................. 74
THE TERTIARY TREATMENT PLANT SHALL CONFORM TO THE SPECIFICATIONS AS MENTIONED BELOW: ................................................................................................................................... 87
DISC FILTER ASSEMBLY WITH FILTER CLOTH: .................................................................................. 87
1. COARSE SCREENS ............................................................................................................................. 108
2. RAW SEWAGE SUMP AND PUMPS ................................................................................................ 109
3. INLET CHAMBER ................................................................................................................................. 109
4. FINE SCREENS ..................................................................................................................................... 109
5. GRIT CHAMBERS ................................................................................................................................. 109
6. ANY BIOLOGICAL UNIT ..................................................................................................................... 110
7. SLUDGE SUMP AND PUMP ............................................................................................................... 110
8. CHLORINATION TANK ........................................................................................................................ 110
9. CENTRIFUGE/ BELT FILTER PRESS .............................................................................................. 110
THE TERTIARY TREATMENT PLANT SHALL CONFORM TO THE SPECIFICATIONS AS MENTIONED BELOW: ................................................................................................................................. 123
DISC FILTER ASSEMBLY WITH FILTER CLOTH: ................................................................................ 123
1. COARSE SCREENS ............................................................................................................................. 145
2. RAW SEWAGE SUMP AND PUMPS ................................................................................................ 145
3. INLET CHAMBER ................................................................................................................................. 145
4. FINE SCREENS ..................................................................................................................................... 145
5. GRIT CHAMBERS ................................................................................................................................. 146
6. ANY BIOLOGICAL UNIT ..................................................................................................................... 146
7. SLUDGE SUMP AND PUMP ............................................................................................................... 146
8. TERTIARY TREATMENT AND CHLORINATION TANK ............................................................... 146
9. CENTRIFUGE/ BELT FILTER PRESS .............................................................................................. 146
I. COARSE SCREENS ............................................................................................................................. 182
II. RAW SEWAGE SUMP AND PUMPS ................................................................................................ 182
III. INLET CHAMBER ............................................................................................................................ 182
IV. FINE SCREENS ................................................................................................................................ 182
V. GRIT CHAMBERS ............................................................................................................................ 182
VI. ANOXIC REACTOR ......................................................................................................................... 183
VII. SLUDGE SUMP AND PUMP .......................................................................................................... 183
VIII. CHLORINATION TANK................................................................................................................... 183
IX. CENTRIFUGE/ BELT FILTER PRESS ......................................................................................... 183
Annexure-3 : Revised “ Volume-2(R1)”
3
1. Abatement of Pollution in Buddha Nallah, Ludhiana
1.1. Introduction
Ludhiana is the largest city in the State of Punjab having populations of 1,618,879
persons as per census of year 2011. Total area of the city is 159.37 Sq. km. Projected
population of the town for year 2030 is 23.46 Lakh and 30.27 Lakh in 2045. The whole
city is presently covered with 100% sewerage and water supply facilities. The city is
divided into two parts by the Jalandhar-Delhi railway line passing through the city. The
sewerage system of the town on the North side of the railway line is covered under
Zone A and B whereas the town on the South side is covered under Zone C as detailed
below:-
Zone A: (Jamalpur) about 12% of the total area.
Zone B: (Bhattian) about 33% of the total area.
Zone C: (Balloke) about 55% of the total area.
In the Initial year of the current century, three Sewage Treatment Plants were installed
in the town under Sutlej Action Plan and further in the next decade more Sewage
Treatment Plants were added at Bhattian and Balloke as tabulated below:-
Table 1: Existing STPs and MPSs
S.No.
Location
of the
STP
Capacity
(in MLD) Technology
Year of
Commissioning
Present
Status
1 Zone A:
Jamalpur 48 UASB 2008
Defunct
2 Zone B:
Bhattian 111 UASB 2007 Functional
3 -Do- 50 SBR 2012 Functional
4 Zone C:
Balloke 152 UASB 2008 Functional
5 -Do- 105 SBR 2012 Functional
Total Waste Water Treatment Capacity available in the town is 466 MLD, whereas
domestic waste water generation is approx. 624 MLD.
1.2. Critical Issues of Waste Water collection and Treatment System in Ludhiana city:
i. Lack of adequate STP capacity for treating the entire quantum of waste water
generated in the city. As a result, the excess sewage is being dumped into the
Nallah through temporary disposal points.
ii. Mixing of industrial effluent in the domestic sewerage network is occurring at
several locations.
Annexure-3 : Revised “ Volume-2(R1)”
4
iii. Ingress of domestic and industrial waste water into the storm water drains
flowing into Buddha Nallah.
iv. Some drains and tributaries of Buddha Nallah are discharging polluted waste
water in Buddha Nallah.
v. Waste water from two major dairy complexes located at Tajpur and Haibowal
is being discharged into city sewers and Buddha Nallah.
vi. Presently, Industrial effluent is reaching the existing STPs. This has resulted in
a critical situation as it has led to the STP capacity being overwhelmed due to
which the treated discharge of the existing STPs falls way short of permissible
standards.
vii. At some places due to choking of the main sewer line, sewage is diverted to
the Nallah though temporary disposal points.
1.3. For abatement of pollution in Buddha Nallah and resultantly, improving the quality of
water in river Sutlej, recipient of Buddha Nallah discharge, Govt. of Punjab is
implementing the project for augmentation and upgradation/ rehabilitation of
wastewater treatment facilities in Ludhiana City. The objective of this project is to
collect and treat entire domestic waste water to the required levels, so as to ensure that
only the treated water flows into Buddha Nallah.
1.4. Project Proposal
1.4.1. Zone-wise Domestic Waste Water Flow in Buddha Nallah
The flow in Buddha Nallah was measured from October 27th, 2019 to October 29th,
2019, when the industry operations were closed due to Diwali and Vishawkarma Day.
Measured Flows in Buddha Nallah are as under:-
Sr.
No.
Description Avg. Flow in Buddha Nallah at the entry into MC
Limit (MLD)
Discharge
For Different STP Zones (MLD)
Jamalpur Bhattian Balloke
1 Total
Discharge 11 133 204 287
Domestic Waste water within MC Limit 624
1.4.2. Existing Temporary Pumping Stations discharging into Buddha Nallah
S. No
Location Capacity (In MLD)
1 Transport Nagar 35
2 Shingar Cinema 28
3 Gaushala 30
4 Sunder Nagar 8
5 Tibba Road 12
6 Kundan Puri 5
7 Upkar Nagar 13
Annexure-3 : Revised “ Volume-2(R1)”
5
8 Lifeline Hospital 23
9 Lord Mahavir Ayurveda Hospital 20
Total 195
1.4.3. Performance of existing STPs
a) Jamalpur (48 MLD UASB STP)
This plant is receiving very high volume of mixed waste water from residential and
industrial area (mainly textiles) and is not performing.
b) Bhattian (111 MLD UASB STP)
The STP is receiving mixed waste water from residential and industrial area (mainly
textiles) and is not performing upto the desired level on account of accumulation of
Sludge in the Reactors, Ponds and Sludge drying beds.
c) Bhattian (50 MLD SBR STP)
The STP is receiving mixed waste water from residential and industrial area (mainly
textiles) and is performing well and giving result near to desired levels. Pink colour is
observed at the discharge, of the treated sewage.
d) Balloke (152 MLD UASB STP)
The STP is receiving mixed waste water from residential area and dairy waste, due to
which it is not performing upto the desired levels on account of accumulation of
Sludge along with fodder particles in the Reactors, Ponds and Sludge drying beds.
e) Balloke (105 MLD SBR STP)
The STP is receiving mixed waste water from residential area and dairy waste, due to
which it is not performing upto the desired levels on account of accumulation of
sludge along with fodder particles, in aeration and selector zones. Due to which
number of Diffusers have been torn/chocked.
1.4.4. Project Objective/ Proposed improvements in first phase i.e. the present
contract:
a) To close 7 major pumping outlets into Buddha Nallah and construct new intermediate
pumping stations to divert the flow from these to the nearby STPs for treatment.
Sewage of two pumping stations i.e. Transport Nagar and Shingar Cinema will be
taken care of by the existing sewerage system after excess waste water starts
pumping through proposed IPS at Gaushala and Tibba Road.
b) Lay rising main connecting various proposed intermediate pumping stations to
Jamalpur STP and Balloke STP.
c) To rehabilitate 2 nos. of existing STPs based on UASB technology (111 MLD at
Bhattian and 152 MLD at Balloke) and one time repair of two nos. existing STPs
based on SBR technology (50 MLD at Bhattian & 105 at Balloke)
d) To rehabilitate the existing MPS at Bhattian and two MPS at Balloke.
e) To construct new STP for 225 MLD waste water at Jamalpur
f) To construct new STP of 60 MLD required capacity for waste water at Balloke
Annexure-3 : Revised “ Volume-2(R1)”
6
g) To construct 2 ETPs to handle the Dairy Waste Water from washings of Dairy
Complexes at Tajpur (2.25 MLD) and Haibowal (3.75 MLD).
Note: - For diversion of flow from existing outlet referred at (a) above, bidder can give alternative proposal (details in para 2.0).
2. Scope of Work in Brief
2.1. Scope of Work:
The brief description of scope is as under but not limited to:-
a) Jamalpur Zone
i. Construction of IPS at Sunder Nagar.
Construction of pumping station of 8 MLD average capacity, capable to cater the
peak discharge of 18 MLD along with the required pumps, with suitable head, to
discharge into the shaft of rising main.
ii. Rising Main from Sunder Nagar IPS to Gaushala point
The DI-K9 rising main is to be laid and commissioned. This rising main should be
of the suitable size to cater the peak discharge from Sunder Nagar pumping
station. The velocity in pipe at peak flow should not be more than 1.5 mtr/sec.
iii. Construction of IPS at Gaushala
Construction of Pumping Station at Gaushala to cater the capacity of 30 MLD
average flow along with the required pumps, to cater the peak discharge of 67.5
MLD, with the suitable head, to discharge into the shaft of rising main.
iv. Rising Main from Gaushala IPS to Tibba Road IPS
The DI-K9 rising main is to be laid and commissioned. This rising main should be
of the suitable size to cater the peak discharge from both Sunder Nagar &
Gaushala pumping stations. The velocity in pipe at peak flow should not be more
than 1.5 mtr/sec.
v. Construction of IPS at Tibba Road
Construction of Pumping Station at Tibba Road to cater the capacity of 12 MLD
average flow along with the required pumps, to cater the peak discharge of 27
MLD, with the suitable head, to discharge into the rising main.
vi. Rising Main from Tibba Road IPS to proposed MPS at Jamalpur
The DI-K9 rising main is to be laid and commissioned. This rising main should be
of the suitable size to cater the peak discharge from all the three pumping stations
at Sunder Nagar, Gaushala and Tibba Road. The velocity in pipe at peak flow
should not be more than 1.5 mtr/sec.
vii. Construction of 225 MLD capacity STP & MPS
A new STP upto tertiary level of 225 MLD (Average flow) capacity is to be
constructed at Jamalpur site to handle the domestic flow mixed with 20% industrial
flow from textile and dyeing industries. A new MPS of 225 MLD average flow, is
Annexure-3 : Revised “ Volume-2(R1)”
7
also to be constructed, along with the required pumps, to cater the peak discharge
of 450 MLD, with the suitable head, to discharge into the new STP/ETP.
viii. Construction of ETP and waste water collection system for Dairy Waste at
Tajpur Road
A new ETP is to be constructed at Dairy Complex on Tajpur Road to handle the
Dairy Waste i.e. cow dung and fodder waste, along with waste water generating
from washing of buffaloes and floors etc. The daily flow generated from this Dairy
Complex is about 2.25 MLD. Most of the flow from dairy is discharged during
morning hours and evening hours, resulting into a peak factor of approximately 5
during morning flows. The ETP is to be constructed for peak flow upto primary
treatment. After equalization tank, provided before secondary treatment, ETP shall
be designed for average flow of 2.25 MLD The treated water from the ETP shall be
discharged into Buddha Nallah, which is passing nearby. Conveyance network for
collecting dairy waste water from individual dairies upto ETP system is included in
the scope of work. The conveyance network is to be designed for peak flow.
b) Bhattian Zone
i. Rehabilitation Main Pumping Station at Bhattian.
Complete rehabilitation of common MPS catering to both the STPs i.e. 111 MLD
UASB & 50 MLD SBR, along with the required pumps, to cater the peak discharge
of 322 MLD, with suitable head, to discharge into the rising mains leading to STPs.
ii. One time repair of 50 MLD existing STP on SBR technology.
The existing 50 MLD STP commissioned in 2012 is performing near to the
designed efficiency. However, Refurbishment of STP, especially with respect to
the Electrical, Mechanical, Instrumentation and Chlorination System is proposed
so as to improve the efficiency of plant and ensure satisfactory working in the
future.
iii. Rehabilitation of existing 111 MLD STP based on UASB
The 111 MLD UASB plant commissioned in year 2007 consists of primary
treatment units, UASB reactors, polishing ponds and chlorination system. The
performance of plants is not upto the mark. Complete over hauling of the plant
especially Screens, Detroiters, Sludge Removal System, HDPE Down Pipes, PVC
Sheets, FRP Pipes/Boxes/Channels, Chlorination System, Gas Collection Dome,
Gas Flaring system, and removal of sludge from reactors, polishing ponds is
proposed. Sludge is to be disposed off at Dumping Station to be earmarked by
Municipal Corporation, Ludhiana. Repair and service of existing duel fuel engine +
generating sets is in scope of work. To improve efficiency of plant, provision of
surface aerators in existing final polishing units are proposed.
Any other repair/painting/modification as required for successful functioning of the
plant and preservation/ aesthetics of plant is also to be done.
iv. Arrangement for mechanical dewatering of sludge from existing 111 MLD
UASB Plant.
Annexure-3 : Revised “ Volume-2(R1)”
8
In the existing system the sludge from the reactors is collected in a sump from
where it is pumped to the 72 nos. Sludge Drying Beds (SDB). It is proposed to set
up new mechanical sludge dewatering unit and required allied works.
v. Additional Chlorination Plant at Bhattian.
Additional New Chlorination Plant along with leak absorption system with capacity
of 40 kg per hour is to be provided. A New Chlorination Plant will have the
provision to supply chlorinated water to both the Existing STPs i.e. 111 MLD UASB
and 50 MLD SBR.
c) Balloke Zone
i. Construction of MPS at Kundan Puri
Construction of pumping station of 5 MLD average capacity, capable to cater the
peak discharge of 12.5 MLD along with the required pumps, with suitable head, to
discharge into the existing sewer line after crossing the Budhha Nallah.
ii. Rising Main from Kundan Puri MPS to nearby intercepting sewer.
The DI-K9 rising main is to be laid and commissioned. This rising main should be
of the suitable size to cater the peak discharge from Kundan Puri pumping station
into nearby intercepting sewer across Buddha Nallah. The approximate length of
rising main shall be 100 mtr. The velocity in pipe at peak flow should not be more
than 1.50 mtr/sec.
iii. Construction of MPS at Upkar Nagar
Construction of pumping station of 13 MLD average capacity, capable to cater the
peak discharge of 29.25 MLD along with the required pumps, with suitable head, to
discharge into the rising main.
iv. Rising Main from Upkar Nagar to point near Lord Mahavir Ayurveda Hospital
The DI-K9 rising main is to be laid and commissioned from Upkar Nagar to point
near Lord Mahavir Ayurveda Hospital. This rising main should be of the suitable
size to cater the peak discharge from the permanent pumping station at Upkar
Nagar. The velocity in pipe at peak flow should not be more than 1.50 mtr/sec.
v. Construction of IPS at Backside of Lord Mahavir Ayurveda Hospital
New pumping station of 43 MLD at Backside of Lord Mahavir Ayurveda Hospital is
to be constructed with 43 MLD average flow capacity along with the required
pumps, to cater the peak discharge of 96.75 MLD, with the suitable head, to
discharge into the common rising main coming from Upkar Nagar across Buddha
Nallah to transfer the flow to Balloke STP site. At this IPS 23 MLD sewage will be
received from the nearby passing 1200 mm dia sewer coming from lifeline Hospital
and 20 MLD sewage will be received from the storm sewer which is carrying
domestic sewer during dry weather flow. For diversion of flow, provision of
adjustable gates will be made in the storm sewer line which shall be lifted during
storm period.
vi. Rising Main from Backside Lord Mahavir Ayurveda Hospital to STP Balloke
Annexure-3 : Revised “ Volume-2(R1)”
9
The DI-K9 rising main is to be laid and commissioned from Backside Lord Mahavir
Ayurveda Hospital to STP Balloke (In the new proposed chamber for receiving
sewage from this rising main and existing 90” as well as 60” sewer. This rising
main should be of the suitable size to cater the peak discharge from the pumping
stations at Upkar Nagar and Lord Mahavir Ayurveda Hospital. The velocity in this
pipe should not increase 1.5 mtr/sec at peak flow.
vii. Construction of New STP & MPS at Balloke
A new STP upto tertiary level of suitable capacity is to be constructed at Balloke
site to augment the capacity of existing SBR Plant. Presently, two STPs, one of
152 MLD based on UASB technology followed by polishing ponds and other of 105
MLD based on SBR Technology are existing at Balloke Site. It is proposed to
increase the total treatment capacity at this site from 257 MLD to 307 MLD. UASB
Plant is proposed to be rehabilitated and shall continue to handle 152 MLD
sewage. Part of 155 MLD sewage is proposed to be treated in existing SBR STP
and for remaining a new STP covered in the scope of the bid. The existing SBR
plant was planned for 105 MLD flow with parameters of raw sewage to be treated
in this plant given in the below table. However on the basis of testing of raw
sewage reaching the plant, the raw sewage parameters are increased as under:-
Sr.
No. Parameters Raw Sewage Unit
Previous
design basis
Proposed
design basis
1. Biochemical Oxygen
Demand (BOD5) 225 250 mg/l
2. Chemical Oxygen Demand
(COD) 500 500 mg/l
3. Total Suspended Solids
(TSS) 475 500 mg/l
It is estimated that the treatment capacity of existing SBR plant may reduce due to
increase in parameters values of raw sewage. A new STP upto tertiary level of 60
MLD average flow capacity is to be constructed at Balloke site.
A new MPS of suitable capacity is also to be constructed, along with the required
pumps, to cater the peak discharge with the suitable head, to discharge required
flow into the new STP. The interconnection/extension of incoming sewer lines into
the STP along with provision of required diversion chambers/gates is also included
in the scope.
viii. Construction of ETP for Dairy waste at Haibowal Village
A new ETP is to be constructed at Dairy Complex at Haibowal Village to handle
the Dairy Waste i.e. cow dung and fodder waste, along with waste water
generating after washing of buffaloes and floors etc. The daily flow generated from
this Dairy Complex is about 3.75 MLD. Most of the flow from dairy is discharged
during morning hours and evening hours, resulting into a peak factor of
approximately 5 during morning flows. The ETP is to be constructed for peak flow
upto primary treatment. After equalization tank, provided before secondary
treatment, ETP shall be design for average flow of 3.75 MLD The treated water
Annexure-3 : Revised “ Volume-2(R1)”
10
from the ETP shall be discharged into Buddha Nallah, which is passing nearby.
Conveyance network for collecting dairy waste water from individual dairies upto
ETP system is included in the scope of work. The conveyance network is to be
designed for peak flow.
ix. One time repair of existing STP on SBR technology at Balloke
The existing STP commissioned in 2012 needs refurbishment especially with
respect to the Electrical, Mechanical, Instrumentation and Chlorination System to
improve the efficiency of plant and ensure satisfactory working to treat atleast 95
MLD (average flow) sewage.
x. Rehabilitation of Main Pumping Station at Balloke for SBR Plant.
Complete rehabilitation of MPS catering to 105 MLD SBR based STP, to cater the
capacity up to 105 MLD average flow, along with the required pumps, to cater the
peak discharge up to 210 MLD, with suitable head, to discharge into the rising
main leading to STP.
xi. Rehabilitation of Main Pumping Station at Balloke for UASB Plant.
Complete rehabilitation of MPS UASB Plant to cater the capacity of 152 MLD
average flow, along with the required pumps, to cater the peak discharge of 304
MLD, with the suitable head, to discharge into the rising mains leading to STP.
xii. Rehabilitation of existing 152 MLD STP based on UASB
The 152 MLD UASB plant commissioned in year 2008 consists of primary
treatment units, UASB reactors, polishing ponds and chlorination system. The
performance of plants is not upto the mark. Complete over hauling of the plant
especially Screens, Degritters, Sludge Removal System, HDPE Down Pipes, PVC
Sheets, FRP Pipes/Boxes/Channels, Chlorination System, Gas Collection Dome,
and removal of sludge from reactors and polishing pond is proposed. Sludge is to
be disposed off at Dumping Station to be earmarked by Municipal Corporation,
Ludhiana. Bidder is to service and repair the existing Flaring System. Repair and
service of existing duel fuel engine + generating sets is in scope of work. To
improve efficiency of plant, provision of surface aerators in existing final polishing
units are proposed.
Any other repair/painting/modification as required for successful functioning of the
plant and preservation/ aesthetics of plant is also to be done.
xiii. Arrangement for mechanical dewatering of sludge from existing 152 MLD
UASB Plant.
In the existing system the sludge from the reactors is collected in a sump from
where it is pumped to the 96 nos. Sludge Drying Beds (SDB). It is proposed to set
up new mechanical sludge dewatering unit and required allied works.
xiv. Additional chlorination plant at Balloke.
Additional new chlorination plant along with leak absorption system with a capacity
of 60 kg per hour is to be provided for additional chlorination of effluent from UASB
Plant.
Annexure-3 : Revised “ Volume-2(R1)”
11
d) Others
i. The industries are laying a conveyance system for collection of Industrial waste
water and are in the process of setting up three common effluent treatment plants
to treat the industrial waste water. Waste water from some industries, might not
have been taken care by the industries. During execution of the project under
consideration, if any, additional conveyance system for industrial waste water
collection is to be laid, the same shall be in the scope of work in this bid however;
payment for such work shall be made additionally as per Punjab CSR Rates.
Note: - The above scope of work (defined in para 2.0) is indicative and minimum
requirements only. Bidder is to make own assessment of works to be done
to achieve the project objective to stope overflow into Budha Nallah from ‘7’
locations and treatment of waste water.
Alternative proposal
For diversion of flow from existing outlets referred at (a&c) of Sr.No.2 bidder
can give alternative proposal.
i. For transfer of waste water from existing outlets at Sunder Nagar, Gaushala, Tibba Road, Kundanpuri, Sunder Nagar, Upkar Nagar and Lord Mahavir Ayurveda Hospital, bidder is at liberty to give alternative proposal. The alternative proposal can be for transfer of flow of quantities mentioned above to any 3 of existing STP sites (Jamalpur, Bhattian and Balloke) by gravity flow or pumping or combination of gravity and pumping. The feasibility of alternative proposal shall be responsibility of bidder.
ii. In case of alternative proposal, for pumping mains DI K-9 pipe is to be used and for gravity lines RCC NP-3 sewer with HDPE lining is to be used.
iii. If alternative proposal given by bidder leads to change in the flow quantity of sewage to be treated in the new STPs, the bidder shall be required to construct the new STPs of revised capacities, keeping the total capacity equal to the indicative proposal of employer.
iv. In case of alternative proposal, bidder in his technical bid shall give complete details and feasibility of the proposal as well as daily power consumption for pumping of sewage diverted from these 7 outlets into the inlet chamber of STPs.
v. The bidder shall also workout the difference in power consumption for pumping in accordance to his proposal w.r.t. the employer’s proposal and give detail in technical bid.
vi. For financial evaluation of bids submitted with alternative proposal and bids submitted with employer’s proposal, Net Present Value of the power consumption difference between two proposals shall be added/subtracted to/from the financial bid (Capital cost + O&M cost + Net present value of guaranteed power) as the case may be in accordance to the following formula:
Difference in power consumption between alternative proposal and employer’s proposal = ‘B’ KVAH per day Energy charges = Rs .7.00 per KVAH
Annexure-3 : Revised “ Volume-2(R1)”
12
Annual Energy charges = 7.00 x 365 x ‘B’ = Rs 2555 B Net present value factor = 8.4726
Net present value of difference in power consumption = 8.4726 x 2555 B = Rs.21648 B
3. Detailed Scope for Capital Works:
3.1. Construction of 225 MLD capacity STP at Jamalpur
STP Jamalpur is receiving waste water through three sewerage pipelines. Jamalpur
zone has textile and dyeing industries. Presently influent from the industry is getting
mixed with domestic waste water part of which is reaching the STP site and remaining
overflows into Buddha Nallah.
On account of higher volume and high percentage of Industrial influent the existing 48
MLD UASB based STP is not performing at all and is proposed to be abandoned.
The industries are setting up 90 MLD CETP and separate conveying system for
collection of Industrial Waste Water. The project is in advanced stage of
implementation and likely to be commissioned in near future. However, some scattered
industries will continue to discharge waste water into the sewerage system.
Taking in account Commissioning of the CETP’s, a new STP upto tertiary level of 225
MLD (Average flow) capacity is to be constructed at Jamalpur site to handle the
domestic flow mixed with upto 20% industrial flow from textile and dyeing industries.
The tertiary treated water shall be utilisable for industrial / Agriculture Purpose.
a) Design Basis for 225 MLD STP:
Daily Average Flow for New STP 225 MLD
Peak factor 2.0
Raw Influent Characteristics are indicated in the following Table:
S. No.
Parameters Value Unit
1 pH 6.5 -9.0
2 Biochemical Oxygen Demand (BOD5) 250 mg/l
3 Chemical Oxygen Demand (COD) 500 mg/l
4 Total Suspended Solids (TSS) 500 mg/l
5 Total Kjeldahl Nitrogen (TKN) 45 mg/l
6 Total Phosphorous (TP) 7 mg/l
7 Fecal Coliforms Approx. 1
x 107
MPN/100 ml
The Bidder shall carry out the tests of raw influent by themselves to ascertain the
raw influent quality for treatment process. For design purposes the lower parameters
Annexure-3 : Revised “ Volume-2(R1)”
13
than the above mentioned parameter will not be allowed.
b) Treated Sewage Quality:
The Contractor shall design the process in such a way that the treated effluent quality
attains the following limits or even better:
Sr.
No.
Parameters Values Unit
1 pH 6.5 – 8.5
2 Biochemical Oxygen Demand(BOD5) <10 mg/l
3 Chemical Oxygen Demand (COD) ≤ 50 mg/l
4 Total Suspended Solids (TSS) ≤ 5 mg/l
5 Amonical Nitrogen as N < 5 mg/l
6 Total Nitrogen (TN) ≤ 10 mg/l
7 Total Phosphorous (TP) ≤ 1 mg/l
8 Fecal Coliforms ≤ 230 MPN/
100 ml
9 SAR (Sodium Absorption Ratio) ≤ 3.5
10 EC (Electrical Conductivity) ≤ 2000 Micro mhos / cm
11 RSC (Residual Sodium Carbonate) ≤ 2.5 mg/l
c) Detailed Scope of Work
The treatment plant is to be based on any suitable, sustainable and proven aerobic
technology including MBR & SBR with its variants. The technology offered should be
suitable for upgradation to achieve stringent effluent parameters in future. Accordingly,
the process design along with layout plan, hydraulics and P&I diagram indicating the
various units and their functions shall be submitted by the contractor and only after
approval of Engineer-in-Charge, the process shall be adopted by the contractor.
However, indicative process components are as under:
Sr. No.
Component Details
1
Primary Treatment
Inlet Chamber, (receiving water from
existing/proposed Main Pumping Station
at this site)
Four Working Step/ Matt type Mechanical Fine Screens and Two Manual Standby Fine Screens
Mechanical Grit Chambers with atleast 50% standby
Gates at the inlet and outlet of screens/ Grit Chambers
Annexure-3 : Revised “ Volume-2(R1)”
14
Sr. No.
Component Details
2 Biological Treatment
This shall include Biological Reactors, Sludge Re-Circulation, Aeration, Settling, Excess Sludge Removal, process with nitrification, de-nitrification and biological phosphorous removal.
Other operational requirement like Automation (PLC) for Flow Control, Level Control, Oxygen Level Control etc,
3 Sludge Handling System
Sludge withdrawal system
Sludge sump
Sludge pump house
Stabilization of primary sludge
Mechanism for Polymer chemical/dosing.
Sludge Dewatering mechanism like Combined Mechanical Thickener cum Belt Press or Centrifuge + gravity sludge thickener
The required buildings for Sludge Dewatering Units.
Sludge storage platform
Disposal of de-watered sludge, if required, to site earmarked by employer.
Recirculation of filtrate
4 Tertiary Treatment
Includes Filtration Units (Fiber Disc / Sand Filtration)
System for Pumping, if required, to pump secondary Treated water to the filtration units.
Backwash System including cleaning pumps if required.
Control panel & Instruments
Gates & Auto Valves
Piping
Back wash Recovery system consisting of flash mixer, clarifier, sludge holding Tank, Pump House and Dewatering unit.
5 Disinfection system for
treated waste water after Tertiary Treatment
Chlorine mixing / contact tank
Tonner House
Leak Detection, Leak Absorption and Other Required Safety Systems
Chlorination Room for Chlorinators and Booster pumps
6 Operation Buildings
Blowers room
H.T Substation
Meter room
Master Control Centre, Programmable Logic Controller Centre
Toilet block for field staff
Annexure-3 : Revised “ Volume-2(R1)”
15
Sr. No.
Component Details
Store Room/Tool Room
Workshop
Any other required buildings
7 Process piping / drain
piping/ channels
Pipes and drains pipe/channel required for complete working of the process
8 Site Development
Roads and pavement
Sewerage system and storm water drainage system including rain water harvesting
Water supply for drinking and process requirements.
Beautification of open spaces within the STP Site by Plantation/grass/bushes.
9 Disposal of treated
effluent
Disposal of treated effluent into Buddha Nallah through RCC open channel or Pipes upto Buddha Nallah.
Secondary pumping station, if required, for disposal into Buddha Nallah.
10 Miscellaneous
Stairs, railing and platforms
Painting / white washing of all buildings and pipes
Lowering of ground water table during construction, if required
Arrangement for disposal of screenings / grit / other wastes to the site earmarked by employer
Fire-fighting arrangement
11 Mechanical Works List
Manually Operated Fine Bar Screens
Mechanically operated Step/ Matt type screens
Mechanical Detritus mechanisms
Turbo Air Blowers with VFD
Various Sludge Pumps, for example:- Return Activated Sludge Pumps Surplus sludge Pumps Gravity Thickener Feed Pumps Belt Press Feed Pumps Centrifuge Feed Pumps Any other required pumps
Air diffusers (fine/coarse)
Combined Thickener cum Belt Press Machines or Centrifuge + Gravity Sludge Thickener Mechanism
Decanters / Weirs
Pumps for Supernatant
Chemical Feed Pumps and Mixers / Agitator
Manual and Auto Valves / Gates
Annexure-3 : Revised “ Volume-2(R1)”
16
Sr. No.
Component Details
Chain Pulley Block, Mono Rail, Electric Hoists
Service Water Pumps
Chlorination System including Chlorinators, Pumps, Tonners and Safety Equipments
All items and mechanism of filtration system which includes Pumps, Blowers, etc.
Pumps, if required, for lifting Secondary and Tertiary treated water.
Any other item as per proposed technology.
12 Electrical Works
VCB Panel
Transformers
Generating Sets
Main Electrical Panels
Cabling
Earthing
Lighting System
Energy Meter
Other items as specified and required
13 Instrumentation, Control
& Automation
Flow meters
At inlet of treatment plant, outlet of treatment plant and bye-pass to treatment plant
CCTV Cameras
SCADA & PLC System
Automation of various units / operations
Online monitoring system for raw and treated water quality
14 Miscellaneous Laboratory Equipment
15
All the existing buildings/ Structures are to be rehabilitated. Rehabilitation of buildings/ structures means complete renovation, repair and painting.
Repair/rehabilitation of existing roads/path ways.
Plantation within STP areas as per requirement.
Repair and painting of existing streets light poles.
Providing and fixing of LED lights alongwith new cabling for the existing street light points.
Note:The existing administrative building and laboratory and other buildings may be used after rehabilitation and painting etc.
16
Existing FPUs/ SDBs shall be dismantled and site is to be used for accommodating new STP and MPS. The sludge from FPU and SDBs and demolition waste shall be disposed off at Dumping Station to be earmarked by Municipal Corporation.
Annexure-3 : Revised “ Volume-2(R1)”
17
Sr. No.
Component Details
17 Any other component required as per process
The above list is indicative only. The bidder, as per his proposed technology, shall
include all the relevant required civil, electrical, mechanical components,
instrumentation, automation and site development works to achieve the results as
defined in the scope of work and approved by the Engineer-in-Charge.
3.2. Raw Sewage Pumping Station at Jamalpur
Average Flow : 225 MLD
Peak Factor : 2.0
Peak Design Flow : 450 MLD (18750 cum/hr)
Sr. No.
Component Details
i Raw Sewage Pumping Station
Receiving Chamber with gates
Gates at upstream of coarse screens
Gates at downstream of coarse screens
Four working ‘J’ Type Screens (each ‘J’ Type Screen shall be provided at upstream of mechanical coarse screen)
Four working mechanical Coarse Screens and Two Stand-By Manual Coarse Screens.
Raw sewage sump
Raw Sewage Pumps
Ultra-Sonic Type Flow meter on common rising main
Level transmitters in raw sewage sump
PLC/ RTU connected to SCADA of STP with provision for external links.
Mixer pumps/ submersible mixers in sewage sump to avoid settling of suspended matter.
Lifting arrangement for pumps.
Providing transformer and generating set.
Any other component required for efficient and reliable working of pumping station.
Bidder may choose a proposal for pumping station out of the following:
A single Pumping Station, for combined flow from sewer line and rising main from Tibba Road IPS.
Two Pumping station, one for flow from sewer line and other for flow from rising main.
3.3. Construction of new ETP at Tajpura for Dairy Waste
A new ETP is to be constructed at Dairy Complex on Tajpur Road to handle the Dairy
Waste i.e. cow dung and fodder waste, along with waste water generating after washing
Annexure-3 : Revised “ Volume-2(R1)”
18
of buffaloes and floors etc. The average flow generated from this Dairy Complex is about
2.25 MLD. Most of the flow from dairy is discharged during morning hours and evening
hours, resulting into a peak factor of approximately 5 during morning flows. The ETP is
to be constructed for peak flow upto primary treatment. After equalization tank, provided
before secondary treatment, ETP shall be design for average flow of 2.25 MLD. The
treated water from the ETP shall be discharged into Buddha Nallah, which is passing
nearby.
The scope of work includes RCC channels for collection and conveyance of dairy waste
water from individual diaries to the proposed ETP. The channels shall be covered with
slabs having provision of openings/removable slabs to maintain/ clean the channels. The
pumping station required for transferring the collected waste water from drains to ETP is
included in the scope of work. The land available for Tajpur ETP is in two parcels.
Specification of conveyance channels:-
Material of construction : RCC grade M-30 or higher
Design flow : Peak flow
Self-cleaning velocity : > 0.6 Mtr/second
Provision of catch pits at suitable location to retain solids
Covering slab for drains to be kept 0.20 Mtr above the ground/ road level.
Opening to be provided by lift able slabs/ manhole covers.
Note: In case drains, in addition to area proposed in the drawings are required the same
will be in the scope of contract on extra payment as per Punjab, Schedule of Rates
as applicable at the time of execution.
a. Design Basis:
Daily Average Flow for New ETP 2.25 MLD
Peak factor 5.0
b. Raw Influent Quality:
An abstract of Raw Dairy Waste Water characteristics is indicated in the following Table:
Sr. No.
Parameters Values Unit
1 pH 6.5 to 9
2 Biochemical Oxygen Demand (BOD5)
2000 mg/l
3 Chemical Oxygen Demand (COD) 3000 mg/l
4 Total Suspended Solids (TSS) 1000 mg/l
5 Total Kjeldahl Nitrogen (TKN) 150 mg/l
6 Total Phosphorous (TP) 10 mg/l
The Bidder shall carry out the tests of waste water by themselves to ascertain the
quality for treatment process. For design purposes the lower parameters than the
Annexure-3 : Revised “ Volume-2(R1)”
19
above mentioned parameter will not be allowed.
c. Treated Effluent Quality:
The Contractor shall design the process in such a way that the treated effluent quality
attains the following limits or better:
Sr. No. Parameters Valu
es Unit
1 pH 6.5 – 8.5
2 Biochemical Oxygen Demand (BOD5) < 10 mg/l
3 Chemical Oxygen Demand (COD) ≤ 50 mg/l
4 Total Suspended Solids (TSS) ≤ 10 mg/l
5 Fecal Coliforms ≤ 230 MPN/100ml
6 Ammonical Nitrogen as N < 5 mg/l
7 Total Nitrogen (TN) ≤ 10 mg/l
8 Total Phosphorous (TP) ≤ 1 mg/l
9 SAR (Sodium Absorption Ratio) ≤ 3.5
10 EC (Electrical Conductivity) ≤ 2000 Micro mhos /
cm
11 RSC (Residual Sodium Carbonate) ≤ 2.5 mg/l
d. Detailed Scope of Work for ETP
The treatment plant is to be based on suitable, sustainable and proven technology.
Accordingly, the process design along with layout plan, hydraulics and P&I diagram
indicating the various units and their functions shall be submitted by the contractor and
only after approval of Engineer-in-Charge, the process shall be adopted by the
contractor. However, indicative process components are as under:
Sr. No.
Component Details
1 Primary Treatment
Inlet Chamber (receiving water from proposed main pumping Station at this site)
One working Mechanical Step Type Fine Screen and 1 manual standby stand-by screen
One Mechanical Perforated Screen
One Manual Screen wire mesh (Mechanical Step Type Screen shall be followed by Mechanical Perforated Screen and Manual Mesh Screen)
Mechanical Grit Chambers with 100% standby.
Gates at the inlet and outlet of Fine screens
Flash Mixer with Agitator
Primary Clariflocculator with sludge collection
Annexure-3 : Revised “ Volume-2(R1)”
20
Sr. No.
Component Details
mechanism, scum removal arrangement
Equalization Tank with Pumps, Blowers and Grid for Mixing Arrangement
2 Anaerobic Treatment (Optional)
Anaerobic Reactors with Gas Collection mechanism and gas flaring system.
3 Biological Treatment
This shall include Biological Reactors, Sludge Re-Circulation, Aeration, Settling, and Excess Sludge Removal, process with in-built nitrification, de-nitrification and biological phosphorous removal.
Other operational requirement like Automation (PLC) for Flow Control, Level Control, Oxygen Level Control etc.
4 Tertiary Treatment Fiber Disc Filtration Units
Flash Mixer
Flocculator with Agitator Mechanism
Civil (RCC) Tank to house the Fiber Disc filter
Disc filter assembly with Filter Cloth
Drive Assembly
Backwash System which includes Suction Cleaning Pumps for back wash
Control panel & Instruments
Gates & Auto Valves
Piping
5 Disinfection system for treated waste water
Chlorine mixing / contact tank
Tonner House
Chlorination Room for Chlorinator, Booster pumps & space for Safety mechanism
6 Sludge Handling System
Sludge withdrawal system
Primary Sludge sump
Primary Sludge pump houses
Secondary Sludge sump
Secondary Sludge pump houses
Mechanism for Polymer chemical/dosing
Stabilization of primary sludge
Sludge Dewatering mechanism building like Centrifuge or Screw Press for primary as well as secondary sludge
Sludge storage platform
Disposal of de-watered sludge, if required, to site earmarked by employer.
Recirculation of filtrate
7 Operation Buildings Blowers room
H.T Substations
Meter rooms
Master Control Centre, Programmable Logic Controller Centre
Annexure-3 : Revised “ Volume-2(R1)”
21
Sr. No.
Component Details
Administrative blocks/ Operation building including toilets
Toilet blocks for field staff on both sites.
Store Room/Tool Room
Any other required building
8 Process piping / drain piping/ channels
Pipes and drains pipe/channel required for complete working of the process
9 Site Development Roads and pavement
Boundary walls
Sewerage system and storm water drainage system.
Water supply for drinking and process requirements.
Beautification of open spaces within the ETP Sites by Plantation/grass/bushes.
10 Disposal of treated effluent
Disposal into Buddha Nallah through RCC Pipe / channel
11 Miscellaneous Stairs, railing and platforms
Painting / white washing of all buildings and pipes
Lowering of ground water table during construction, if required
Arrangement for disposal of screenings / grit /other wastes to the site earmarked by employer.
Fire-fighting arrangement
12 Mechanical Works List Mechanical Step/ Matt type Fine Bar Screen
Mechanical perforated screen
Manual Mesh Screen
Mechanical Detritus mechanisms
Air Blowers with VFD
Various Sludge Pumps, for example:- Return Activated Sludge Pumps Surplus sludge Pumps Centrifuge / Screw Press Feed Pumps Any other required Pumps
Air diffusers (fine/coarse)
Decanters / Weirs
Pumps for Supernatant disposal
Chemical Feed Pumps and Mixers / Agitator
Manual and Auto Valves / Gates
Chain Pulley Blocks, Mono Rails, Electric Hoists
Service Water Pumps
Chlorination System including Chlorinators, Pumps and Tonners.
Any other item as per proposed technology.
13 Electrical Works VCB Panel
Annexure-3 : Revised “ Volume-2(R1)”
22
Sr. No.
Component Details
Transformers
Generating Sets
Main Electrical Panels
Cabling
Earthing
Street Lighting
Energy Meter
Other items as specified and required
14 Instrumentation, Control & Automation
Flow meters
At inlet of treatment plant, outlet of treatment plant and bye-pass to treatment plant
CCTV Cameras
SCADA & PLC System
Automation of various units/operations
Online monitoring system for raw and treated water quality
15 Any other component required as per process
Note : (1) Since the ETP is to be installed in two separate parcels some of
the provision shall be required at both the locations. This is
included in the scope of work.
(2) For testing of waste water samples (treated/untreated) laboratory
of nearby STP at Jamalpur shall be used.
The above list is indicative only. The bidder, as per his proposed technology, shall
include all the relevant required civil, electrical, mechanical, instrumentation,
automation and site development works to achieve the results as defined in the scope
of work and approved by the Engineer-in-Charge.
e. Raw Influent Pumping Station
Sr. No.
Component Details
i Raw Influent Pumping Station
Receiving Chamber with gate
Gates at upstream of coarse screens
Gates at downstream of coarse screens
One working J Type Mesh Screens (J Type Screen shall be provided at upstream of mechanical coarse screen)
One working mechanical Coarse Screens and One Stand-By Manual Coarse Screen.
Raw sewage sump
Raw Sewage Pumps
Ultra-Sonic Type Flow meter on rising main
Level transmitter in raw sewage sump
PLC/ RTU connected to SCADA of ETP
Transformer and generating set
Mixer pumps/ Submersible mixers
Lifting arrangement
Annexure-3 : Revised “ Volume-2(R1)”
23
Any other component required.
3.4. Rehabilitation Main Pumping Station at Bhattian
Complete rehabilitation of common MPS catering to both the STPs i.e. 111 MLD UASB
& 50 MLD SBR, to cater the capacity of 161 MLD average flow, along with the required
pumps, to cater the peak discharge of 322 MLD, with suitable head, to discharge into the
rising mains leading to STPs. Indicative scope of work is as under:-
S.No. Components Details
1 Mechanically operated medium screens suitable for 2750mm wide x 3000mm deep channel with total depth of approximately 8 m from channel bottom to top platform
Numbers 2
Clear Opening 20 mm
Construction material SS 304
2 Manual medium screen Number 1
Clear Opening 40 mm
Construction material SS 304
3 Submersible pump of capacity 1500 Cum per hour at 16 Mtr head
5 Nos
4 Providing and Installing conveyor belt
Length 7m
5 Automation of Pump operation All Raw Sewage pumps shall be automatically controlled, through Ultrasonic Level Transmitter, RTU/PLC. This automation shall be synchronised with existing PLC of 50 MLD SBR Bhattian. The PLC to have provision for external linkage.
6 Any other component required.
Note:- All mechanical, Electrical and Civil Items shall be taken for service and repairs, to
deliver designed discharge.
The above list is indicative only, and not limited to, above. The bidder, shall include all
the relevant required civil, electrical, mechanical, instrumentation, service and repair so
as to make the pumping station work efficiently with reliability.
3.5. Refurbishment of 50 MLD SBR based STP at Bhattian
The existing STP is in the operation, since 2012. Refurbishment of STP with respect to
electrical, mechanical, instrumentation and chlorination system is required. Complete
refurbishment to ensure that the plant performs to the desired level of treatment is
required. A broad assessment of items to be checked and serviced/replaced/repaired is
as under:-
Annexure-3 : Revised “ Volume-2(R1)”
24
Sr. No. Component Details
I. Inlet Flow Meter Servicing & Repair
II. Fine Screens (Mechanical & Manual) Servicing & Repair
III. Auto Inlet Gates to Reactors (4 No.) Servicing & Repair
IV. Auto Valves for Air Pipes, Sludge Pipes
Servicing & Repair
V. Air Blowers (6) Servicing & Repair
VFD of 2 Nos. to be replaced
VI. RAS/SAS Pumps Servicing & Repair
VII. Fine Air Diffusers Replacement as per condition
assessment
VIII. Decanters (4 No.) Servicing & Repair
IX. DO meters (4 No.) Replacement
X. Level Sensors Servicing & Repair
XI. Centrifuges Servicing & Repair
XII. Chlorination System and Leak Absorption System
Servicing & Repair
XIII. Sludge Sump Grid and Blowers Servicing & Repair
XIV. Existing Chlorination system in 50 MLD STP
Providing Leak Detection, Leak Absorption and Other Required Safety Systems
XV. After cooler in main line from blower to reactors Air Pipe Line
New provision
XVI. Any other component/ work required for satisfactory working of the plant.
The above list is indicative only, and not limited to, above. The bidder, shall include all
the relevant required civil, electrical, mechanical, instrumentation, automation and site
development works, so as to make the plant operative to desired efficiency level for the
flow to be treated in this plant.
Repairs and painting of all civil structures, piping etc. shall be a part of the scope.
3.5.1 After refurbishment, the treated effluent quality shall be as under:-
Sr.
No.
Parameters Values Unit
1 pH 6.5 – 8.5
2 Biochemical Oxygen Demand(BOD5) <10 mg/l
3 Chemical Oxygen Demand (COD) ≤ 50 mg/l
4 Total Suspended Solids (TSS) ≤ 10 mg/l
Annexure-3 : Revised “ Volume-2(R1)”
25
Sr.
No.
Parameters Values Unit
5 Amonical Nitrogen as N < 5 mg/l
6 Total Nitrogen (TN) ≤ 10 mg/l
7 Total Phosphorous (TP) ≤ 1 mg/l
8 Fecal Coliforms ≤ 230 MPN/
101 ml
9 SAR (Sodium Absorption Ratio) ≤ 3.5
10 EC (Electrical Conductivity) ≤ 2000 Micro mhos / cm
11 RSC (Residual Sodium Carbonate) ≤ 2.5 mg/l
3.6. Rehabilitation of existing 111 MLD STP based on UASB
The 111 MLD UASB plant commissioned in year 2007 consists of primary treatment
units, UASB reactors, polishing ponds and chlorination system. The performance of
plants is not upto the mark. Complete over hauling of the plant especially Screens,
Degritters, Sludge Removal System, HDPE Down Pipes, PVC Sheets, FRP
Pipes/Boxes/Channels, Chlorination System, Gas Collection Dome, Gas flaring system
and removal of sludge from reactors & polishing ponds is proposed. Repair and service
of existing duel fuel engine + generating sets is in scope of work. Any other
repair/painting/modification as required is also to be done.
The identified indicative scope of work is as per table below:
Sr. No. Component Details
1 Aluminium Proportional Weir with
markings One number 6 mm thick
2
10 x 10 m Detritus Tank scrapping
arrangement, Deflectors, weirs, Grit
washing and Grit conveying (Submerged
parts SS 304)
4
3
Construction of additional 10 x 10 m
Detritus tanks with scrapping
arrangement, Deflectors, weirs, Grit
washing and Grit conveying
2
4
Coating of existing FRP components:
External side with surface glass layer
using Isothlic resin on Gutter, Baffle
plate, gas hood and feed box etc.
Approx. 715 sqm
5 Supply and fabrication of FRP sheet
items (8mm thick) Approx. 650 sqm
6 Rigid PVC sheet 6mm Approx. 2763 sqm
7 PVC sheet angles 6mm thick Approx. 8068 sqm
8 50mm dia PVC pipe nylon impregnated pipe
2304 Mtrs
Annexure-3 : Revised “ Volume-2(R1)”
26
Sr. No. Component Details
9 HDPE pipes, 10kg/cm2 110mm o/d= 378m
160mm o/d=400m
10 HDPE Couplers 160mm dia 32 Nos
11
PP Ball valves 20mm NB=72 Pcs.
75mm NB= 144 Pcs.
160mm NB= 5 Pcs.
12 Peet valves 40mm= 90 Pcs.
13 Replacement of MS Gas holder 1 Number
14 MS Chequered Plate As per site requirement
15 Structural Steel Work As per site requirement
16 Repair/ replacement of railing As per site requirement
17 Fixed type surface aerator including civil structures and all required accessories. (submerged part shall be of SS-304)
Minimum 48 Nos, 5 HP
18
Epoxy coating of concrete surfaces. Inside of UASB reactors, chlorine contact tank, De-gritters screens and other units/ channels etc.
19 Any other component required for satisfactory working of the plant
The Bidder shall carry out the assessment to ascertain the repair/replacement
required so as to make the plant operational with the desired efficiency.
The Removal of Sludge from Reactors, Polishing Ponds and any other Unit
(except sludge drying beds) is included in the scope of work the sludge so
removed is to be disposed of and the location earmarked by the Municipal
Corporation, Ludhiana.
Treated Effluent Parameters after rehabilitation of UASB STP
Sr.
No.
Parameters Values Unit
1. Biochemical Oxygen Demand(BOD5) <30 mg/l
2. Total Suspended Solids (TSS) ≤ 50 mg/l
3. Fecal Coliforms ≤ 230 MPN/
100 ml
3.6.1 Utilisation of Gas Generated from 111 MLD UASB plant
The present Gas utilisation consists of Gas flaring system and Dual Fuel Engines (Diesel + Gas). Bidder is to repair/replace the existing Flaring System. The gas generated from the
plant shall be property of the bidder. Suitable credit for the gas shall be considered by
the bidder in the price bid. The duel fuel Engine + generating set shall be repaired/
serviced.
Annexure-3 : Revised “ Volume-2(R1)”
27
3.6.2 Arrangement for Mechanical Dewatering of Sludge generated from existing 111
MLD UASB plant at Bhattian
Presently, the sludge from 9 UASB Reactors is collected in sludge slumps near the
reactors. From sludge slumps it is pumped to existing sludge drying beds in the same
premises. To save on the manpower required for maintaining the sludge drying beds; it
is proposed to set up an arrangement for mechanical dewatering of sludge withdrawn
from UASB reactors. The indicative scope of work is as under:-
Sr. No.
Component Details
i New Sludge
Handling Unit
Sludge withdrawal system
Sludge sump
Sludge pump houses
Mechanism for Polymer/ chemical dosing
Sludge Dewatering mechanism including building like Combined Mechanical Thickener cum Belt Press or Centrifuge + gravity sludge thickener
Sludge storage platform
Recirculation of filtrate
Arrangement for disposal of de-watered sludge (land for disposal of dewatered sludge to be earmarked by Employer.
Any other component required
3.6.3 Additional Transformer and Generating Set for 111 MLD UASB Plant Surface
Aerator + Mechanical Dewatering system etc.
Additional new transformer and new generating set of sufficient capacity to operate
surface aerator to be provided in the final polishing units and all the equipment/ pumps
for mechanical dewatering of sludge generated from existing 111 MLD UASB plant at
Bhattian and other mechanisms like screens, de-gritters/ pre-aerators.
3.6.4 Additional Chlorination Plant at Bhattian
Additional New Chlorination Plant along with leak absorption system with a capacity of
40 kg per hour is to be provided. A New Chlorination Plant will have the provision to
supply chlorinated water to both the Existing STPs i.e. 111 MLD UASB and 50 MLD
SBR.
3.7. Construction of new 60 MLD STP at Balloke
A new STP upto tertiary level of 60 MLD (Average Flow) capacity is to be constructed at
Balloke:
Presently, inflow of sewage to Balloke STP is through existing three sewer lines (60
inch, 90 inch, 96 inch diameter sewers). To stop mixing of Dairy Waste with the
domestic sewage, an ETP is being set up at a separate site in Haibowal Village.
However, to further ensure that no Dairy Waste water flows to the existing 105 MLD
SBR plants and new proposed 60 MLD plant, it is proposed to make suitable
Annexure-3 : Revised “ Volume-2(R1)”
28
amendments/additions in the sewerage pipeline system so that the sewage from 96
inch sewer flows into UASB plant only (for indicative proposal refer drawing).
a) Design Basis for proposed plant:
Daily Average Flow for New STP 60 MLD
Peak factor 2.0
b) Raw Sewage Quality:
An abstract of Raw Sewage Characteristics is indicated in the following Table:
Sr.
No. Parameters Unit
1 pH 6.5 to 9
2 Biochemical Oxygen Demand
(BOD5) 250 mg/l
3 Chemical Oxygen Demand (COD) 500 mg/l
4 Total Suspended Solids (TSS) 500 mg/l
5 Total Kjeldahl Nitrogen (TKN) 45 mg/l
6 Total Phosphorous (TP) 7 mg/l
7 Fecal Coliforms 1 x 10
7 MPN/100 ml
The Bidder shall carry out the tests of raw sewage to ascertain the raw sewage
quality for treatment process. For design purposes the lower parameters than the
above mentioned parameter will not be allowed.
c) Treated Sewage Quality:
The Contractor shall design the process in such a way that the 155 MLD: (New STP +
Existing SBR based STP) treated effluent quality attains the following limits or even
better.
Sr. No.
Parameters Values Unit
1 pH 6.5 – 8.5
2 Biochemical Oxygen Demand (BOD5) < 10 mg/l
3 Chemical Oxygen Demand (COD) ≤ 50 mg/l
4 Total Suspended Solids (TSS) ≤ 5 mg/l
5 Ammonical Nitrogen as N < 5 mg/l
Annexure-3 : Revised “ Volume-2(R1)”
29
Sr. No.
Parameters Values Unit
6 Total Nitrogen (TN) ≤ 10 mg/l
7 Total Phosphorous (TP) ≤ 1 mg/l
8 Fecal Coliforms ≤ 230 MPN/100ml
9 SAR (Sodium Absorption Ratio) ≤ 3.5
10 EC (Electrical Conductivity) ≤ 2000 Micro mhos / cm
11 RSC (Residual Sodium Carbonate) ≤ 2.5 mg/l
d) Detailed Scope of Work
The treatment plant is to be based on any suitable, sustainable and proven aerobic
technology including MBR & SBR with its variants. The technology offered should be
suitable for upgradation to achieve stringent effluent parameters in future. Accordingly,
the process design along with layout plan, hydraulics and P&I diagram indicating the
various units and their functions shall be submitted by the contractor and only after
approval of Engineer-in-Charge, the process shall be adopted by the contractor.
However, indicative process components are as under:
Sr.
No.
Component Details
1
Primary Treatment
Inlet Chamber, (receiving water from
existing/proposed Main Pumping Station at
this site)
Two Working Step/ Matt type Mechanical Fine
Screens and One Manual Standby Fine
Screen
Mechanical Grit Chamber with atleast 50%
standby
Gates at the inlet and outlet of Fine screens &
inlet of Grit chamber
2 Biological Treatment
This shall include Biological Reactors, Sludge
Re-Circulation, Aeration, Settling, Excess
Sludge Removal, process with nitrification, de-
nitrification and biological phosphorous
removal. Other operational requirement like
Automation (PLC) for Flow Control, Level
Control, Oxygen Level Control etc.
3 Sludge Handling
System
Sludge withdrawal system
Sludge sump
Sludge pump house
Mechanism for Polymer chemical/dosing.
Stabilization of primary sludge
Sludge Dewatering mechanism like Combined
Annexure-3 : Revised “ Volume-2(R1)”
30
Sr.
No.
Component Details
Mechanical Thickener cum Belt Press or
Centrifuge + gravity sludge thickener
The required buildings for Sludge Dewatering
Units.
Sludge storage platform
Disposal of de-watered sludge, if required, to
site earmarked by employer.
Recirculation of filtrate
4
Disinfection system for
treated waste water
after Biological
Treatment
Chlorine mixing / contact tank
Tonner House
Leak Detection, Leak Absorption and Other
Required Safety Systems
Chlorination Room for Chlorinator, Booster
pumps
5 Operation Buildings
Blowers room
H.T Substation
Meter room
Master Control Centre, Programmable Logic Controller Centre
Any other required buildings
6 Process piping / drain
piping/ channels
Pipes and drains pipe/channel required for
complete working of the process
7 Site Development
Roads and pavement
Sewerage system and storm water drainage system including rain water harvesting
Water supply for drinking and process requirements. Beautification of open spaces within the STP
Site by Plantation/grass/bushes.
8 Disposal of treated
effluent
Disposal into Buddha Nallah through existing
twin RCC open channel or through
independent Pipes / channels upto Buddha
Nallah.
Assessment of feasibility and carrying capacity
of existing twin channel and modification/
strengthening, if required.
Secondary pumping station, if required, for
disposal into Buddha Nallah.
9 Miscellaneous
Stairs, railing and platforms
Painting / white washing of all buildings and
pipes
Lowering of ground water table during
Annexure-3 : Revised “ Volume-2(R1)”
31
Sr.
No.
Component Details
construction, if required
Arrangement for disposal of screenings / grit /
other wastes to the site earmarked by
employer.
Fire-fighting arrangement
10 Mechanical Works List
Manually Operated Fine Bar Screens
Mechanically operated Step/ Matt type
screens
Mechanical Detritus Mechanism
Turbo Air Blowers with VFD
Various Sludge Pumps, for example:-
Return Activated Sludge Pumps
Surplus sludge Pumps
Gravity Thickener Feed Pumps
Belt Press Feed Pumps/ Centrifuge Feed
Pumps
Any other pump required
Air diffusers (fine/coarse)
Combined Thickener cum Belt Press
Machines or Centrifuge + Gravity Sludge
Thickener Mechanism
Decanters / Weirs
Pumps for Supernatant
Chemical Feed Pumps and Mixers / Agitator
Manual and Auto Valves / Gates
Chain Pulley Blocks, Mono Rails, Electric
Hoists
Service Water Pumps
Chlorination System including Chlorinators,
Pumps and Tonners.
Any other item as per proposed technology.
11 Electrical Works
VCB Panel
Transformers
Generating Sets
Main Electrical Panels
Cabling
Earthing
Lighting System
Energy Meter
Other items as specified and required
12 Instrumentation,
Control & Automation
Flow meters - At inlet of treatment plant, outlet of treatment plant and bye-pass to treatment plant
CCTV Cameras
Annexure-3 : Revised “ Volume-2(R1)”
32
Sr.
No.
Component Details
SCADA & PLC System
Automation of various units / operations
Online monitoring system for raw and treated
water quality
13 Miscellaneous Laboratory Equipment
14 Any other component required as per process
The above list is indicative only. The bidder, as per his proposed, technology, shall include
all the relevant required civil, electrical, mechanical components, instrumentation,
automation and site development works as defined in the scope of work and approved by
the Engineer-in-Charge.
3.7.1. Construction of Raw Sewage Pumping Station for new STP at Balloke
Average Flow : 60 MLD
Peak Factor : 2.0
Peak Design Flow : To be worked out as per above
3.7.2. Raw Sewage Conveyance System
Raw sewage for this pumping station is to be received from difference sources 60 inch
incoming sewer from city area, rising main line from new proposed intermediate
pumping station and Surplus flow if any from 90 inch incoming sewer after feeding the
existing SBR STP. The sewage received from above referred sources is to be collected
in a sump from where the required quantity of sewage shall be transferred to this
pumping station. Excess quantity if any, is to be transferred to inlet sump of existing
MPS feeding 152 MLD existing UASB plant.
For indicative details incoming raw sewage refer drawing.
Sr. No.
Component Details
i Raw Sewage Pumping Station
Distribution chamber with gates
Receiving Chamber with gate
Gates at upstream of coarse screens
Gates at downstream of coarse screens
Two working J Type Mesh Screens (each J Type Screen shall be provided at upstream of mechanical coarse screen)
Two working mechanical Coarse Screens and one standby manual Coarse screen.
Raw Sewage Pumps
Ultra-Sonic Type Flow meter on rising main
Level transmitter in raw sewage sump
PLC/ RTU connected to SCADA of STP
Mixer pump sets/ Submersible mixers
Electric hoist
Sewage pipe line and gates for distribution of
Annexure-3 : Revised “ Volume-2(R1)”
33
flow from 3 existing sewer lines in to existing and proposed STPs
Any other component required
3.8. Construction of new ETP at Haibowal for Dairy Waste
A new ETP is to be constructed at Dairy Complex at Haibwal village to handle the Dairy
Waste i.e. cow dung and fodder waste, along with waste water generating after washing
of buffaloes and floors etc. The average flow generated from this Dairy Complex is about
3.75 MLD. Most of the flow from dairy is discharged during morning hours and evening
hours, resulting into a peak factor of approximately 5 during morning flows. The ETP is
to be constructed for peak flow upto primary treatment. After equalization tank, provided
before secondary treatment, ETP shall be design for average flow of 3.75 MLD. The
treated water from the ETP shall be discharged into Buddha Nallah, which is passing
nearby.
The scope of work includes RCC channels for collection and conveyance of dairy waste
water from individual diaries to the proposed ETP. The channels shall be covered with
slabs having provision of openings/removable slabs to maintain/ clean the channels. The
pumping station required for transferring the collected waste water from drains to ETP is
included in the scope of work.
Specification of conveyance channels:-
Material of construction : RCC grade M-30 or higher
Design flow : Peak flow
Self cleaning velocity : > 0.6 Mtr/second
Provision of catch pits at suitable location to retain solids
Covering slab for drains to be kept 0.20 Mtr above the ground/ road level.
Opening to be provided by lift able slabs/ manhole covers.
Note: In case drains, in addition to area proposed in the drawings are required the same
will be in the scope of contract on extra payment as per Punjab, schedule of rates
as applicable at the time of execution.
a) Design Basis:
Daily Average Flow for New ETP (MLD)
3.75
Peak factor 5.0 for primary treatment
b) Raw Influent Quality:
An abstract of Raw Dairy Waste Characteristics is indicated in the following Table:
Sr. No.
Parameters Values Unit
1 pH 6.5 to 9
2 Biochemical Oxygen Demand (BOD5)
2000 mg/l
Annexure-3 : Revised “ Volume-2(R1)”
34
Sr. No.
Parameters Values Unit
3 Chemical Oxygen Demand (COD) 3000 mg/l
4 Total Suspended Solids (TSS) 1000 mg/l
5 Total Kjeldahl Nitrogen (TKN) 150 mg/l
6 Total Phosphorous (TP) 10 mg/l
The Bidder shall carry out the sampling tests of raw Influent by themselves to
ascertain the raw influent quality for treatment process. The Employer will not be
responsible for the above and no relaxation will be given to the guarantee conditions
of desired treated effluent quality. For design purposes the lower parameters than the
above mentioned parameter will not be allowed.
c) Treated Effluent Quality:
The Contractor shall design the process in such a way that the: treated effluent quality attains the following limits or even better
Sr. No.
Parameters Values Unit
1 pH 6.5 – 8.5
2 Biochemical Oxygen Demand (BOD5) < 10 mg/l
3 Chemical Oxygen Demand (COD) ≤ 50 mg/l
4 Total Suspended Solids (TSS) ≤ 10 mg/l
5 Fecal Coliforms ≤ 230 MPN/100ml
6 Ammonical Nitrogen as N < 5 mg/l
7 Total Nitrogen (TN) ≤ 10 mg/l
8 Total Phosphorous (TP) ≤ 1 mg/l
9 SAR (Sodium Absorption Ratio) ≤ 3.5
10 EC (Electrical Conductivity) ≤ 2000 Micro mhos /
cm 11 RSC (Residual Sodium Carbonate) ≤ 2.5 mg/l
d) Detailed Scope of Work for ETP
The treatment plant is to be based on suitable, sustainable and proven technology.
Accordingly, the process design along with layout plan, hydraulics and P&I diagram
indicating the various units and their functions shall be submitted by the contractor and
only after approval of Engineer-in-Charge, the process shall be adopted by the
contractor. However, following guidelines / components may be followed by the
contractor are as under:
Annexure-3 : Revised “ Volume-2(R1)”
35
Sr. No. Component Details
1
Primary Treatment
Inlet Chamber (receiving water from proposed main pumping Station at this site)
1 Working Mechanical Step Type Fine Screen + 1 manual standby screen
One Mechanical Perforated Screen
One Manual Screen wire mesh (Mechanical Step/ Matt Type Screen shall be followed by Mechanical Perforated Screen and Manual Mesh Screen)
Mechanical Grit Chambers with 100% standby
Gates at the inlet and outlet of Fine screens, at inlet of grit chamber
Flash Mixer with Agitator
Primary Clariflocculator with Mechanism for sludge collection and scum removal
Equalization Tank with Pumps, Blowers and Grid for Mixing Arrangement
2 Anaerobic Treatment
(Optional)
UASB Reactors with Gas Collection mechanism and gas flaring system
3
Biological Treatment
This shall include Biological Reactors, Sludge Re-Circulation, Aeration, Settling, Excess Sludge Removal, process with nitrification, de-nitrification and biological phosphorous removal.
Other operational requirement like Automation (PLC) for Flow Control, Level Control, Oxygen Level Control etc.
4 Tertiary Treatment
Includes Fiber Disc Filtration Units
Flash Mixer
Flocculator with Agitator Mechanism
Civil (RCC) Tank to house the Fiber Disc filter
Disc filter assembly with Filter Cloth
Drive Assembly
Backwash System which includes Suction Cleaning Pumps for back wash
Control panel & Instruments
Gates & Auto Valves
Piping
5 Disinfection system for waste water from Reactors / settling
Chlorine mixing / contact tank
Tonner House
Chlorination Room for Chlorinator,
Annexure-3 : Revised “ Volume-2(R1)”
36
Sr. No. Component Details
units Booster pumps & space for Safety mechanism
6 Sludge Handling
System
Sludge withdrawal system
Primary Sludge sump
Primary Sludge pump houses
Secondary Sludge sump
Secondary Sludge pump houses
Mechanism for Polymer chemical/dosing
Stabilization of primary sludge
Sludge Dewatering mechanism building like Centrifuge or Belt Press
Sludge storage platform
Disposal of de-watered sludge, if required, to site earmarked by employer.
Recirculation of filtrate
7 Operation Buildings
Blowers room
H.T Substation
Meter room
Master Control Centre, Programmable Logic Controller Centre
Administrative block including toilets
Toilet block for field staff
Store room / tool room
Any other building required
8 Process piping / drain piping/ channels
Pipes and drains pipe/channel required for complete working of the process
9 Site Development
Roads and pavement
Sewerage system and storm water system.
Water supply for drinking and process requirements.
Beautification of open spaces within the STP Site by Plantation/grass/bushes.
10 Disposal of treated
effluent
Disposal into Buddha Nallah through RCC Pipe / channel
11 Miscellaneous
Stairs, railing and platforms
Painting / white washing of all buildings and pipes
Lowering of ground water table during construction, if required
Arrangement for disposal of screenings / grit / other wastes to the site earmarked by employer.
Annexure-3 : Revised “ Volume-2(R1)”
37
Sr. No. Component Details
Fire-fighting arrangement
12 Mechanical Works
List
Mechanically Operated Step Type Fine Bar Screens
Mechanically operated perforated screens
Manual Mesh Screen
Mechanical Detritus Mechanism
Air Blowers with VFD
Various Sludge Pumps, for example:- Return Activated Sludge
Pumps Surplus sludge Pumps Centrifuge / Screw Press
Feed Pumps Any other pump required
Air diffusers (fine/coarse)
Decanters / Weirs
Pumps for Supernatant
Chemical Feed Pumps and Mixers / Agitator
Manual and Auto Valves / Gates
Chain Pulley Blocks, Mono Rails, Electric Hoists
Service Water Pumps
Chlorination System including Chlorinators, Pumps and Tonners.
Any other item as per proposed technology.
13 Electrical Works
VCB Panel
Transformers
Generating Sets
Main Electrical Panels
Cabling
Earthing
Lighting System
Energy Meter
Other items as specified and required
14 Instrumentation,
Control & Automation
Flow meters - At inlet of treatment plant, outlet of treatment plant and bye-pass to treatment plant
CCTV Cameras
SCADA & PLC System
Automation of various units / operations
Online monitoring system for raw and treated water quality
15 Miscellaneous Laboratory Equipment
16 Any other component required as per process
Annexure-3 : Revised “ Volume-2(R1)”
38
Sr. No. Component Details
Note: For testing of waste water samples (treated/untreated) laboratory of nearby STP at Balloke shall be used.
The above list is indicative only. The bidder, as per his proposed technology, shall
include all the relevant civil, electrical, mechanical, instrumentation, automation and site
development works as defined in the scope of work and approved by the Engineer-in-
Charge.
All units upto primary treatment (Primary clarifloculator) shall be designed for peak flow.
All units after Equalisation Tank shall be designed for Average flow. Equalisation Tank is
to be located after primary units and before secondary units.
e) Raw Influent Pumping Station at ETP Premise at Haibowal
Sr. No.
Component Details
i Raw Influent Pumping Station
Receiving Chamber with gate
Gates at upstream of coarse screens
Gates at downstream of coarse screens
One working J Type Mesh Screens (each J Type Screen shall be provided at upstream of mechanical coarse screen)
One working mechanical Coarse Screen and One manual coarse screen.
Raw sewage sump
Raw sewage pumps
Level transmitter in raw sewage sump
PLC/ RTU connected to SCADA of STP
Transformer and generating set
Mixer pumps/ Submersible mixers
Lifting arrangement
Any other component required as per process
3.9. Refurbishment of Existing 105 MLD MPS & STP Balloke
The existing STP is in operation since 2012. Refurbishment of MPS & STP with respect
to electrical, mechanical, instrumentation and chlorination system is required. to ensure
that the plant performs to the desired level of treatment as defined above. All
mechanical, Electrical and Civil Items shall be taken for service and repairs, to deliver
optimum discharge flow.
All Raw Sewage pumps shall be automatically controlled, through Ultrasonic Level
Transmitter. This automation shall be synchronised with existing PLC of existing SBR
based STP.
A broad assessment of items to be checked and serviced/replaced/repaired is as under:
Sr. No.
Component Details
I. Two Mechanical coarse screens (20mm opening) for deep channel prior to wet well
Replacement
Annexure-3 : Revised “ Volume-2(R1)”
39
Sr. No.
Component Details
II. One Manual Coarse Screen Servicing & Repair
III. Three new Horizontal Centrifugal Non-Clog Raw Sewage Pumps (Discharge = 1450 cum per hour, head = 20 m)
Replacement
IV. Two submersible mixers Repair/ Replacement
V. Belt Conveyors System of fine screens Replacement
VI. Fine Screens (Mechanical & Manual) Servicing & Repair
VII. Auto Inlet Gates to Reactors (6 No.) Servicing & Repair
VIII. Auto Valves for Air Pipes, Sludge Pipes Servicing & Repair
IX. Air Blowers (15 No.) Servicing & Repair
X. RAS/SAS Pumps Servicing & Repair
XI. Fine Air Diffusers Replacement as per condition
assessment
XII. Decanters (6 No.) Servicing & Repair
XIII. DO meters (6 No.) Replacement
XIV. Level Sensors Servicing & Repair
XV. Centrifuges (4 No.) Replacement 1 No.
Servicing & Repair 3 No.
XVI. Chlorination System and Leak Absorption System
Servicing & Repair
XVII. Sludge Sump Grid and Blowers Servicing & Repair
XVIII. After cooler in main line from blower to reactors air pipe line
New provision
XIX. Any other component/ work required for satisfactory working of the plant
The above list is indicative only, and not limited to, above. The bidder, shall include all the
relevant civil, electrical, mechanical, instrumentation, automation and site development
works, so as to make the plant operative to desired efficiency level for the flow to be
treated in this plant as accessed by the Bidder.
3.9.1 Treated Sewage Quality after refurbishment of existing SBR STP:
Sr.
No.
Parameters Values Unit
1 pH 6.5 – 8.5
2 Biochemical Oxygen Demand(BOD5) <10 mg/l
3 Chemical Oxygen Demand (COD) ≤ 50 mg/l
4 Total Suspended Solids (TSS) ≤ 10 mg/l
Annexure-3 : Revised “ Volume-2(R1)”
40
5 Amonical Nitrogen as N < 5 mg/l
6 Total Nitrogen (TN) ≤ 10 mg/l
7 Total Phosphorous (TP) ≤ 1 mg/l
8 Fecal Coliforms ≤ 230 MPN/
100ml
9 SAR (Sodium Absorption Ratio) ≤ 3.5
10 EC (Electrical Conductivity) ≤ 2000 Micro mhos / cm
11 RSC (Residual Sodium Carbonate) ≤ 2.5 mg/l
3.10. Rehabilitation Main Pumping Station at Balloke for UASB Plant
Complete rehabilitation of MPS to cater the capacity of 152 MLD average flow, along
with the required pumps, to cater the peak discharge of 304 MLD, with the suitable head,
to discharge into the rising main. The indicative scope of work is as under:-
S. No.
Components Details
1. Mechanically operated medium screens suitable for 2750mm wide x 3000mm deep channel with total distance of approximately 8 m from channel bottom to top platform
Numbers 2
Clear opening 20mm
Construction material SS 304
2. Manual medium screen Number 1
Clear opening 40 mm
Construction material SS 304
3. Providing and Installing conveyor belt
Length as per site approximately 7 m
4. Raw Sewage Pumps 6 nos., CI casing, SS 316 impellers.
Capacity 2760 m3/hr at 17.3 m head with 270 HP 1000 RPM motor
5. Automation of Pump running All Raw Sewage pumps shall be automatically controlled through Ultrasonic Level Transmitter, RTU/PLC. This automation shall be synchronised.
6. Sluice valve 8 Nos
7. Non return valve 8 Nos
8. Pipes 700 mm dia As per site
9. CI Gates 8 Nos
10. Submersible Mixers As per requirement
11. Aluminium gate 4 Nos
12. Dewatering pumps ( 5 BHP) 2 Nos
13. Synchronising panel for existing two Diesel Generating Sets
1 No.
14. Auto transformer switches for eight pumps
8 Nos
15. Service and repair of all equipments As per requirement
Annexure-3 : Revised “ Volume-2(R1)”
41
16. Any other component required.
Note:- All mechanical, Electrical and Civil Items shall be taken for service and repairs, to
deliver designed discharge flow.
The above list is indicative only, and not limited to, above. The bidder shall include all
the relevant civil, electrical, mechanical, instrumentation, service and repair so as to
make the pumping station work efficiently with reliability.
3.11. Rehabilitation of existing 152 MLD STP based on UASB
The 152 MLD UASB plant commissioned in year 2008 consists of primary treatment
units, UASB reactors, polishing ponds and chlorination system. The performance of plant
is not upto the mark. Complete over hauling of the plant especially Screens, Degritters,
Sludge Removal System, HDPE Down Pipes, PVC Sheets, FRP Pipes/Boxes/Channels,
Chlorination System, Gas Collection Dome, Gas utilization system and removal of
sludge from reactors, polishing ponds and sludge drying beds is proposed. Any other
repair/painting/modification as required is also to be done.
The identified indicative scope of work is as per Table.
The Bidder shall carry out the assessment to ascertain the repair/replacement
required so as to make the plant operational with the desired efficiency.
The Removal of Sludge from Reactors, Polishing Ponds and any Other Unit is
included in the scope of work. The sludge so removed is to be disposed off at the
location earmarked by the Municipal Corporation, Ludhiana:
Sr. No.
Component Details
1 Aluminium Proportional Weir with markings
One number 6 mm thick
2
10 x 10 m Detritus Tank scrapping arrangement, Deflectors, weirs, Grit washing and Grit conveying submerged parts SS 304
4
3
Construction of additional 10 x 10 m Detritus tank with scrapping arrangement, Deflectors, weirs, Grit washing and Grit conveying
2
4 CI sluice valve for grit chamber drain 300 NB
5
Coating of existing FRP components: External side with surface glass layer using Isophthalic resin on Gutter, Baffle plate, gas hood and feed box etc.
Approx. 4390 sqm
6 Supply and fabrication of FRP sheet items (8mm thick)
Approx. 1000 sqm
7 Rigid PVC sheet 6mm Approx. 7365 sqm
8 PVC sheet angles 6mm thick Approx. 29599 sqm
9 50 mm dia PVC pipe nylon impregnated pipe
3072 m
10 HDPE pipes, 10kg/cm2 110mm o/d= 505m
180mm o/d=100m
11 180 mm PVC coupler 43 Nos
12 PP Ball valves 20mm NB=96 Pcs.
75mm NB= 192 Pcs. 160mm NB= 6 Pcs.
Annexure-3 : Revised “ Volume-2(R1)”
42
13 GI Peet valves with puddle pipe 40mm= 240 Pcs.
14 Replacement of MS Gas holder 1 Number
15 MS Chequered Plate As per site requirement
16 Structural Steel Work As per site requirement
17 Repair/ replacement of railing As per site requirement
18
Fixed type surface aerator including civil structures and all required accessories. (submerged part shall be of SS-304)
62 Nos
19 Any other component required for satisfactory working of the plant
3.11.1. Utilisation of Gas Generated from 152 MLD UASB plant
The present Gas utilisation consists of Gas flaring system and Dual Fuel Engines (Diesel + Gas).
Bidder is to repair/replace the existing Flaring System. The gas generated from the
plant shall be property of the bidder. Suitable credit for the gas shall be considered
by the bidder in the price bid. The duel fuel Engine + generating set shall be
repaired/ serviced.
3.11.2. Arrangement for Mechanical Dewatering of Sludge generated from existing
152 MLD UASB plant at Balloke
Presently, the sludge from 12 UASB Reactors is being collected in sludge slump
near the reactors. From sludge slump it is pumped to existing sludge drying beds in
the same premises. To save the land occupied by sludge drying beds and
manpower required for maintaining the sludge drying beds; it is proposed to set up
an arrangement for mechanical dewatering of sludge withdrawn from UASB
reactors. The indicative scope of work is as under:-
Sr. No.
Component Details
i New Sludge
Handling Unit
Sludge withdrawal system
Sludge sump
Sludge pump house
Mechanism for Polymer/ chemical dosing
Sludge Dewatering mechanism including building like Combined Mechanical Thickener cum Belt Press or Centrifuge + gravity sludge thickener
Recirculation of filtrate
Arrangement for disposal of de-watered sludge (land for disposal of dewatered sludge to be earmarked by Employer.
Any other component required
The bidder shall carry out assessment to ascertain the quantity and quality of sludge to
be handled and condition of the existing sludge handling systems.
3.11.3. Additional Transformer and Generating Set for 152 MLD UASB Plant Surface
Aerator + Mechanical Dewatering system etc.
Additional new transformer and new generating set of sufficient capacity to operate
surface aerator to be provided in the final polishing units and all the equipment/ pumps
Annexure-3 : Revised “ Volume-2(R1)”
43
for mechanical dewatering of sludge generated from existing 152 MLD UASB plant at
Balloke and other mechanisms like screens, de-gritters/ pre-aerators etc.
3.11.4. Additional Chlorination Plant at Balloke
Additional New Chlorination Plant along with leak absorption system with a capacity of
60 kg per hour is to be provided. A New Chlorination Plant will have the provision to
supply chlorinated water to both the Existing STPs i.e. 152 MLD UASB and 105 MLD
SBR.
3.11.5. Treated Effluent Parameters after rehabilitation of UASB STP
The treated effluent quality after refurbishment of STP is to be as under:-
Sr.
No.
Parameters Values Unit
4. Biochemical Oxygen Demand(BOD5) <30 mg/l
5. Total Suspended Solids (TSS) ≤ 50 mg/l
6. Fecal Coliforms ≤ 230 MPN/
101 ml
3.12. Three No. IPS and Rising main in Jamalpur zone
I. Construction of IPS at Sunder Nagar.
Presently waste water at this location is being directly discharged into Buddha Nallah
with the help of pumps which lift water from 36 inch diameter sewer. It is proposed to
transfer 8 MLD waste water from this location to Jamalpur STP by constructing a
permanent intermediate pumping station. Waste water in excess of this quantity, shall
continue to flow in the sewerage system.
Design Basis:
Daily Average Flow for IPS 8 MLD
Peak factor 2.25
Peak flow 18 MLD
Approx. Sewer Depth 3.5 to 4 Mtr.
Flow collection arrangement
Construction of manhole on existing sewer.
Suitable size pipe from manhole to receiving chamber of IPS.
Providing CI gate in the inlet chamber.
For details refer drawing.
II. Construction of IPS at Gaushala
Construction of Pumping Station at Gaushala to cater the capacity of 30 MLD average
flow along with the required pumps, to cater the peak discharge of 67.5 MLD, with the
suitable head, to discharge into the rising main leading to Jamalpur STP.
The sewage is to be diverted from two sources, (i) from existing trunk sewer and (ii)
drain from Transport Nagar. The collected sewage is to be pumped into the proposed
Annexure-3 : Revised “ Volume-2(R1)”
44
shaft for discharging the flow into STP Jamalpur. Required arrangement of gates for
diversion of flow is included in the scope.
Design Basis:
Daily Average Flow for IPS 30 MLD
Peak factor 2.25
Peak flow 67.5 MLD
Approx. Sewer Depth 4.5 to 5 Mtr.
Flow collection arrangement
Construction of manhole on existing sewer.
Suitable size pipe from manhole to receiving chamber of IPS.
Weir with gates in the existing drain, for interception.
Channel from drain (upstream of weir) to receiving chamber.
Gates in the channel/receiving chamber to control flow in different scenarios.
For details refer drawing.
III. Construction of IPS at Tibba Road
Construction of Pumping Station at Tibba Road to cater the capacity of 12 MLD
average flow along with the required pumps, to cater the peak discharge of 27 MLD,
with the suitable head, to discharge into the rising main leading to Jamalpur STP.
Design Basis:
Daily Average Flow for IPS 12 MLD
Peak factor 2.25
Peak flow 27 MLD
Approx. Sewer Depth 8.5 to 9 Mtr.
Flow collection arrangement
The incoming sewer at temporary pumping station (Tibba Road) is to be diverted
to proposed new pumping station receiving chamber by laying suitable size pipe.
Gates in the receiving chamber to control flow in different scenarios.
Dismantling of existing temporary pumping station.
For details refer drawing.
IV. Rising main from Sunder Nagar to STP Jamalpur
Sr. No.
Section/ component of rising main Design peak flow
1 From Sundar Nagar pumping station to elevated shaft no.1.
18 MLD
2 From shaft no.1 to shaft no.2 near Gaushala. 18 MLD
3 From Gaushala pumping station to shaft no.2. 67.5 MLD
4 Shaft no.2 to shaft no.3 near Tibba Road pumping station.
85.5 MLD
5 From Tibba Road pumping station to shaft no.3. 27 MLD
6 From shaft no.3 to collecting tank of main pumping station at STP Jamalpur.
112.5 MLD
Annexure-3 : Revised “ Volume-2(R1)”
45
DI K-9 pipe material is proposed for rising main.
The velocity in pipe at peak flow should not be more than 1.5 mtr/sec.
Elevated RCC shafts of required height to be built.
Air vents to be provided at suitable locations.
Note :-
The rising main is to be laid on the available route along with Buddha Nallah. However, in some stretches, where clear way is not available for laying rising main on the side of existing road, the rising main has to be laid over suitable pillar arrangement inside Buddha Nallah.
Crossing of Budha Nallah at various locations for laying rising mains
may be involved.
For details refer drawing.
3.13. Three No. IPS and Rising main in Balloke
I. Construction of IPS at Kundan Puri
Construction of pumping station of 5 MLD average capacity, capable to cater the
peak discharge of 12.5 MLD along with the required pumps, with suitable head, to
discharge into the existing sewer line after crossing the Budhha Nallah.
Design Basis:
Daily Average Flow for IPS 5 MLD
Peak factor 2.5
Peak flow 12.5 MLD
Approx. Sewer Depth 3.0 to 3.5 Mtr.
Flow collection arrangement
Construction of manhole on existing sewer.
Suitable size pipe from manhole to receiving chamber of IPS.
For details refer drawing.
II. Construction of MPS at Dusshera Ground- Upkar Nagar
Construction of pumping station of 13 MLD average capacity, capable to cater the
peak discharge of 29.25 MLD along with the required pumps, with suitable head, to
discharge into the rising main into shaft No. 4.
The sewage flow from existing storm sewer is to be diverted to the proposed IPS by
installing adjustable gate on the storm sewer.
Design Basis:
Daily Average Flow for IPS 13 MLD
Peak factor 2.25
Peak flow 29.25 MLD
Approx. storm Sewer Depth 2.5 to 3m
Flow collection arrangement
Construction of manhole / chamber on existing storm sewer
Providing adjustable gate in the chamber to divert flow
Suitable size pipe from manhole/ chamber to receiving chamber of IPS.
Annexure-3 : Revised “ Volume-2(R1)”
46
For details refer drawing.
III. Construction of IPS at Backside of Lord Mahavir Ayurveda Hospital
New pumping station of 43 MLD at Backside of Lord Mahavir Ayurveda Hospital is to
be constructed with 43 MLD average flow capacity along with the required pumps, to
cater the peak discharge of 96.75 MLD, with the suitable head, to discharge into the
common rising main coming from Upkar Nagar across Buddha Nallah to transfer the
flow to Balloke STP site.
23 MLD sewage will be diverted from the 1200 mm dia sewer near life line Hospital.
20 MLD sewage will be diverted from the storm sewer which is carrying domestic
sewer.
Design Basis:
Daily Average Flow for IPS 43 MLD
Peak factor 2.25
Peak flow 96.75 MLD
Approx. storm Sewer Depth Life Line sewer- 3.5 to 4 m Storm Sewer- 2.5 to 3 m
Flow collection arrangement
Construction of manhole / chamber on sewer near Life Line Hospital.
Providing suitable size pipe for transfer of sewage from existing manhole to
proposed IPS.
Providing chamber on existing Storm sewer near Lord Mahavir Hospital.
Crossing of Budha Nallah at different locations for laying of rising main if
required is in the scope of bidder.
Providing adjustable gate in the storm sewer chamber.
Providing pipe line to divert dry weather sewage flow from storm sewer.
Suitable size pipe from manhole/ chamber to receiving chamber of IPS.
For details refer drawing.
IV. Rising main from Kundanpuri IPS to nearby sewer
Sr. No. Section/ component of rising main Design peak flow
1. From IPS Kundan Puri to Existing sewer. 12.5 MLD
2. From Upkar Nagar pumping station to elevated shaft no.4.
29.25 MLD
3. From shaft no.4 to shaft no.5 near Lord Mahavir Hospital.
29.25 MLD
4. From Lord Mahavir Hospital Pumping station to shaft no.5.
96.75 MLD
5. Shaft no.5 to Balloke STP 126 MLD
DI K-9 pipe material is proposed for rising main.
The velocity in pipe at peak flow should not be more than1.5 mtr/sec.
Annexure-3 : Revised “ Volume-2(R1)”
47
Elevated RCC shafts of required height to be built.
Air vents to be provided at suitable locations.
Note:-
The rising main is to be laid on the available route along with Buddha Nallah.
However, in some stretch, where clear way is not available for laying rising
main on the side of existing road, the rising main has to be laid over suitable
pillar arrangement inside Buddha Nallah.
Crossing of Budha Nallah by rising main at various locations may be involved.
For details refer drawing.
3.14. General specifications for IPS
Sr. No.
Component Details
i. Civil Works Receiving chamber
Screen chamber
Wet well
MCC Room
ii Screens Gates at upstream of coarse screens
One working J Type Screen to be provided at upstream of mechanical coarse screens.
Gates at downstream of coarse screens
One working mechanical Coarse Screen and One manual coarse screen for peak flow upto 1250 m3/hour
For peak flow more than 1250 m3/hour two mechanical screens with one manual screen standby each of capacity half of the peak flow.
Clear opening of screen 20 mm
iii Wet Well RCC wet well with at least 5 minutes HRT for peak flow
iv Submersible Sewage Pumps
Number of pumps to be provided to cater peak flow, with 50% standby at peak flow.
v HT works Transformer and allied works as per required capacity.
vi DG Set Sufficient to operate pumps for average flow, screens and plant lighting etc.
vii Rising Main Rising main of DI-K9 Pipe to discharge point, as per proposed indicated scope of work and drawings.
Ultra-Sonic Type Flow meter on rising main of each IPS.
viii Instrumentation Level transmitter in raw sewage sump PLC/ RTU shall be connected and synchronized to master SCADA & PLC of STP concerned.
Annexure-3 : Revised “ Volume-2(R1)”
48
Sr. No.
Component Details
ix Operational building
MCC & PLC Room
Security room with toilet block
Operator room
x Gates and weirs Interception gates and weirs to be provided for complete flow control under different scenarios as per scheme.
xi Site development Boundary wall with gate
Road
Lighting
Plantation
Service water supply
Notes:- Applicable to IPS & MPS to be constructed under this bid.
1. The velocity in rising main at peak flow should not be more than 1.5 mtr/sec.
2. 100 mm free fall shall be provided at the inlet pipe of receiving chamber.
3. 100 mm free fall shall be provided at the downstream of coarse screens and
upstream of wet well.
3.15. Contract Limits: a) IPS & Rising Main:- The contract limit starts from the existing sewer lines or storm
line from where the waste water is to be diverted to the proposed IPS. This includes
construction of diversion weirs, wherever required and construction of diversion
chamber/manholes. The scope includes construction of columns/trusses/bridges for
crossing of Buddha Nallah or other drains as per site requirement. The scope of work
for IPS and rising main is upto final discharge point of rising main as below:-
IPS in Jamalpur Zone (Sunder Nagar, Gaushala & Tibba Road) and rising main upto STP Jamalpur
Inlet chamber of Proposed MPS at Jamalpur
IPS in Balloke Zone (Kundan Puri) Manhole of nearby existing sewer after crossing Buddha Nallah
IPS in Balloke Zone (Upkar Nagar & Backside of Lord Mahavir) and rising main upto STP Balloke
Inlet chamber of Proposed MPS at Balloke
b) MPS & STP at Jamalpur Site:-
Limit starts from inlet chamber of MPS and is upto disposal of treated water into
Buddha Nallah.
Dewatered sludge collection and disposal.
Disposal of screenings and grit
c) ETP for Dairy Complex at Tajpur:-
Construction of conveyance system including chambers for connection by
individual dairy owners.
Annexure-3 : Revised “ Volume-2(R1)”
49
Disposal of treated waste water into Buddha Nallah.
Dewatered sludge collection and disposal.
Disposal of screenings and grit
d) Arrangement for mechanical dewatering of sludge from existing 111 MLD UASB
Plant at Bhattian:-
Limits start at sludge withdrawal system from Reactors.
The recirculation of filtrate to existing MPS.
Dewatered sludge collection and disposal
e) Additional Chlorination Plant at Bhattian:-
Arrangement for transfer of treated water for use as Booster Water.
Arrangement for mixing of chlorine water solution to treated water of 50 MLD
SBR Plant and 111 MLD UASB Plant in the ratio required as per site conditions.
f) Construction of suitable capacity new STP & MPS at Balloke
Limits start at arrangement to divert waste water from existing 60 inch
diameter sewer and rising main from proposed IPS and 90 inch diameter sewer
to the proposed distribution chamber.
Disposal of treated effluent into the Buddha Nallah.
Dewatered sludge collection and disposal.
Disposal of screenings and grit
g) Arrangement for mechanical dewatering of sludge from existing 152 MLD UASB
Plant at Balloke:-
Limits start at sludge withdrawal system from Reactors.
The recirculation of filtrate to existing MPS.
Dewatered sludge collection and disposal.
h) Additional Chlorination Plant at Balloke:-
Arrangement for transfer of treated water for use as Booster Water.
Arrangement for mixing of chlorine water solution to treated water of 152 MLD
UASB Plant.
i) ETP for Dairy Complex at Haibowal:-
Construction of conveyance system including chambers for connection by
individual dairy owners.
Disposal of treated waste water into Buddha Nallah.
Dewatered sludge collection and disposal.
Disposal of screenings and grit
j) Water supply pipe line for drinking and general use i.e. toilet use and for process units
for STP shall be augmented/rehabilitated/provided new by the bidder (this includes
installation of new tube well, if required).
k) For operation of all the plants (IPS, MPS, ETP & SPS) Department will supply
electricity at HT Meter unit. Further works are in the scope of contractor.
Annexure-3 : Revised “ Volume-2(R1)”
50
l) Energy meter before MEP
The bidder shall have to provide sub-energy meters of suitable capacity for recording
the power consumption of STPs & ETPs.
3.16. Miscellaneous
The scope of work described under this paragraph is applicable to the entire works
covered in this Bid.
Bidders are advised to inspect the site and acquire knowledge about available site,
ground water table, type of soil, site accessibility, other site conditions, study and
analysis of existing related infrastructure of pumping stations, treatment plants, pipelines
etc. before tendering.
a) Additional work
i. In case of inlet parameters of sewage are continuously higher than the contract
value and to achieve desire treated effluent parameters, additions/ modifications are
to be done in the treatment plant, the same shall be done by the contractor after
approval from the employer.
ii. In case volume of water to be treated at Jamalpur STP site, new proposed STP at
Balloke is more than the agreed contract volume, additions/ modifications are to be
done in the treatment plant, the same shall be done by the contractor after approval
from the employer.
Note: For additional such works contractor shall be paid as per the quoted rates
for similar works, or the market rates for items for which rates are not
available in the contract mutually agreed by the contractor and employer.
b) Design
i. The bidder may get checked the soil bearing capacity, sub soil water level/ spring
level of the STP areas before submitting the bid. The successful bidder/contractor
shall get the bearing capacity of the plant area tested (in the presence of Engineer-
in-Charge or his authorized representatives) and design shall be based on the
tested bearing capacity. The maximum safe net bearing capacity for which the
structure are to be designed shall not be more than 8.6 ton per sqm. The
department may also get the bearing capacity tested if required at its own cost. In
case the results of bearing capacity test done by the contractor and done by the
Department are in variance, design value of bearing capacity shall be decided by
the Engineer-in-Chief, keeping in view the test results of bearing capacity reports got
done by the contractor and Engineer-in-Charge. Any financial claim on account of
difference in bearing capacity shall not be entertained. It is again reiterated that the
Contractor shall be responsible for soundness, safety and stability for the structures.
Bearing capacity of soil has to be calculated considering worst spring level.
ii. Ground survey of the sites for IPS, MPS, STP & Pumping Mains including existing
infrastructure set up is to be done by contractor.
iii. Preparation of Process Design, Hydraulic Design, Structural Design.
iv. Preparation of Electrical, Mechanical, Instrumentation and Automation Design.
v. Detailed Engineering & Working Drawings.
vi. Supply of equipment drawings, Technical Specifications / Catalogues.
Annexure-3 : Revised “ Volume-2(R1)”
51
vii. Manufacturer’s manual for Operation & Maintenance of the equipment supplied.
c) Design Submission
i. Service Improvement Plan (SIP) shall be submitted by the agency within 30 days of
award of work. SIP will be based on site survey, availability of routes, assessment of
flows, raw sewage characteristics etc. to achieve project objectives as per bid
ii. The agency shall submit, Master Design List and submit Layout Plan,
Hydraulic Flow Diagram and P&I Diagram along with related design
calculations within 30 days of approval of SIP (Service Improvement Plan).
The first set of working drawings/structural drawings along with related
design calculations shall be submitted within 30 days of approval regarding
Layout Plan, Hydraulic Flow Diagram and P&I Diagram. The remaining
working drawings/structural drawings and design will be submitted by the
firm to Engineer-in-Charge within three months of approval of Layout Plan,
Hydraulic Flow Diagram and P&I Drawing. Engineer-in-Charge shall approve
the design and drawings as per schedule of work submitted by firm and
agreed by Engineer-in-Charge.
iii. Design shall be approved by Engineer-in-Charge. If Engineer- in- Charge feels can
get the design/drawing checked from reputed Engineering College. The fee for
checking will be borne by the contractor.
iv. If changes in the submitted design/drawings are required, Engineer-in-Charge may
either himself do so prior to approval or may request the contractor to resubmit the
design/drawings after making the required amendments.
v. The designs shall take care of contract provisions, site requirements, CPHEEO
manual and various BIS Codes.
vi. In case, the design requirements are not specified in the bid document, CPHEEO
manual, BIS Code, the design shall be based on other standard literature and good
practices.
vii. The Contractor shall submit complete detailed design calculations of each of the
components such as substructure and superstructure together with general
arrangement drawings, construction drawings and explanatory sketches as required
by the Department.
viii. Separate calculations for substructures or superstructures submitted independent of
each other shall be deemed to be incomplete and will not be accepted by the
Department.
ix. Submissions of detailed design calculations and Good for Construction drawings
shall include the following as a minimum:
Detailed Design Calculations:
Pen Drive containing electronic files relevant to the structure’s modelling,
analysis and design calculations (Microsoft Excel, Staad Pro, etc.). Files
submitted shall be in editable format.
Print copy (5 Copies) of the contents as submitted in the Pen Drive.
d) Construction
i. Lowering of ground water table, if any, at site to take care of seepage from Buddha
Nallah or other drains during construction.
ii. Hydraulic testing of all water retraining systems.
Annexure-3 : Revised “ Volume-2(R1)”
52
iii. RCC access platform, walkway, staircase, all of minimum 1.2 mtr. width hand
railings 1.0 mtr. height shall be provided as a necessary item to all the units.
iv. Construction of bifurcation system for utilization of treated waste water towards
irrigation / industrial use, as per site feasibility.
v. Construction of outfall structure and protection of drain.
vi. Design and construction of suitable thrust block to support various rising mains.
vii. Make suitable provisions in design and construction to take care of surge
pressure/water hammering effects in the rising mains.
viii. During the entire construction, the operation of existing IPS at various locations,
MPS at Jamalpur, Bhattian & Balloke and STP at Bhattian and Balloke shall be kept
in working condition. However, if any closure is required by the contractor for
carrying out the construction work the contractor will submit detailed closure plan
and methodology for approval of Engineer-in-Charge. Only after such approval the
closure shall be allowed.
ix. All units shall be connected through RCC walkway.
e) Commercial
i. Repair and painting of all existing civil structures.
ii. Epoxy painting on the inner surface of all waste water retaining structures of existing
and proposed STPs/ ETPs.
iii. Disposal of sludge is in this scope of work. Sludge sale/disposal is the responsibility
of the contractor. It shall also be the responsibility of contractor to remove the sludge
from STP area, in case accumulation is more than the capacity of sludge storage
capacity platform. Contractor shall dispose of excess sludge in a manner and place
as decided by the Engineer-in-Charge, which shall not cause any nuisance or
obstruction to general public. Proceeds from sale of sludge if any belongs to the
contractor. Suitable credit from sale of sludge shall be considered by bidder
while submitting bid.
iv. Power factor to be maintained as per the requirements of PSPCL (Punjab State
Power Corporation Limited).
v. During the stabilization period and maintenance period Electricity Charges / Diesel
Charges (if any) will be borne by the department. All other consumable material and
required staff for Operation & Maintenance will be provided by bidder. If the plant is
not stabilized within 3 months electricity / diesel charges shall be borne by the
contractor.
vi. During Operation and maintenance period electricity charges for electric energy
supplied through PSPCL grid and Gen-set shall be borne by the department to the
extent of average guaranteed energy consumption worked out for the actual flow
quantity on the basis of guaranteed power consumption quoted by the agency for
full flow and actual average daily sewage treated in the plant for the electric bill
cycle, as per following steps:
Average daily Sewage treated as
percentage of
design flow of
STP
Maximum energy consumption
allowed as percentage of quoted
guaranteed power for design flow of
STP
<40% 60%
Annexure-3 : Revised “ Volume-2(R1)”
53
50% 70%
60% 80%
70% 90%
>70% 100%
Note:- For actual average flows in between the steps defined above; allowed energy consumption shall be worked out by linear proportion between two steps on daily basis.
vii. If the actual energy consumption during the energy consumption bill cycle period is
more than allowed energy consumption as referred above, then the excess energy
consumption shall be borne by the contractor. The excess energy consumption shall
be charged at the per unit rate worked out from the bill raised by PSPCL. Diesel
required shall be arranged by the contractor. Department will reimburse the payment
to contractor on production of bill and other relevant record (i.e. upto the Guaranteed
Power Consumption).
viii. Power as well as water required during construction shall be arranged by the
contractor.
f) Vehicles/ Office during construction period
i. The contractor shall provide ‘3’ vehicles DZIRE/ ETIOS or EQUIVALENT of Model
2017 or later for the construction period till commissioning of entire project, for use
by Authorities (Department/PMU/PMC/PDMC). The salary of Driver, cost of fuel,
service, maintenance, insurance etc. shall be included in lumpsum cost of the
contractor. The usages limit for each vehicle shall be 2500 Kilometres per month
ii. One number temporary site office of size 800 Sqft. at each site (Jamalpur STP/
Balloke STP /Bhattian STP fully air conditioned, with well-equipped furniture,
computer, printer/ scanner A3 size), Almirah, etc. with washroom.
g) Others
i. Supply of As-Built drawings after completion.
ii. Dismantled material from existing infrastructure shall be the property of the
contractor suitable credit for such material shall be considered by the bidder
while submitting bids. Detailed inventory of such material shall be prepared and
submitted to Engineer-in-charge for approval before removing such material
from site.
4. OPERATION AND MAINTENANCE
4.1. Scope of Work in Brief
The contractor shall operate and maintain the entire works and all other allied works
under this for 10 years O&M. It is to be noted that all costs on account of repairs of civil
and E&M works during the O&M, is to be borne by the contractor. Within his quoted cost,
Annexure-3 : Revised “ Volume-2(R1)”
54
the contractor is to ensure that all guarantees for quality and quantity are as per bid, and
are maintained during O&M period.
Sr. No. Component
1. Proposed 3 new intermediate pumping stations (IPSs) at Sunder Nagar, Gaushala and Tibba Road
2. Rising main from Sunder Nagar to STP Jamalpur including taping of pumping main from Gaushala and Tibba Road IPS
3. New main pumping station of 225 MLD (Average flow) at Jamalpur
4. New STP of 225 MLD at Jamalpur
5. 111 MLD UASB treatment plant at Bhattian
6. 50 MLD SBR treatment plant at Bhattian
7. Main pumping station at Bhattian
8. Rising main from Upkar Nagar to Balloke
9. Rising main from Kundanpuri to Existing manhole
10. Proposed 3 new intermediate pumping stations (IPSs) (Kundan Puri, Upkar Nagar & Lord Mahavir Hospital)
11. Main pumping station at Balloke feeding 152 MLD UASB plant
12. Main pumping station at Balloke feeding 105 MLD existing SBR plant
13. Main pumping station at Balloke for new proposed treatment plant
14. 152 MLD UASB treatment plant
15. Existing SBR treatment plant and new proposed treatment plant at Balloke.
16. ETP for dairy complex at Tajpur
17. ETP for dairy complex at Haibowal
18. Upkeep of plant and landscaping/ greenery, street lights, pathways etc.
The above list is indicative only, the scope of work shall include maintenance for the
complete infrastructure at 3 STP sites (Jamaplur, Bhattian & Balloke), 2 dairy ETP sites
(Tajpur & Haibowal), 6 proposed intermediate pumping stations, and rising mains. In case
of alternative proposal for intermediate pumping stations/ rising mains, the scope for
operation and maintenance shall include the infrastructure offered under alternative
proposal.
4.2. Treated Effluent Quality
During operation and maintenance contractor shall ensure treated effluent quality as
define in the scope of work
4.3. Detailed Scope of Work
The contractor, under the scope of this work shall carry out the following activities, but
these shall not limit requirement of other activities, which otherwise are required as per
terms and conditions of contract or to fulfill contractual responsibilities or are essential as
per good industrial practices. The contractor shall be responsible for:
a) To Operate and maintain the sewage treatment plants, intermediate pumping
stations, main pumping stations, dairy effluent treatment plants and rising mains in
accordance with the aim and purpose of treatment described above paragraphs.
This includes all civil, electrical, mechanical, instrumentation, laboratory and general
up keep of the area.
Annexure-3 : Revised “ Volume-2(R1)”
55
b) Continuous 24X7 operation of the pumping stations is to be ensured so that
incoming waste water / influent is pumped out to the treatment units without getting
accumulated in the conveyance system i.e. sewers/channels
c) Operation and maintenance of the existing infrastructure from the date of handing
over the infrastructure to contractor upto the date of commissioning of the entire
project. This is in addition to the 10 years period of the operation and maintenance
of the entire set up described above as the 10 year period shall commence after
commissioning of the entire project.
d) The contractor shall prepare a detailed operation schedule, preventing maintenance
schedule, need based maintenance/repairs and troubleshooting to be approved by
the Engineer-in-Charge. All the operation and maintenance activity shall be carried
out in accordance with the approved schedules.
e) During the operation and maintenance, the contractor or the Engineer-in-Charge
shall review these schedules periodically and revise these schedules as per site
conditions, operational results etc.
f) The contractor shall maintain sufficient quantity of spares, tools and consumables in
stock at site required for effective and efficient operation of the system.
g) It is an absolutely contractor’s responsibility to look after all sorts of maintenance
whether preventive, Minor, Major, or break-down.
h) At the end of each year of operation & maintenance period, an assessment of the
condition of the plant has to be done by the contractor and department jointly. On
that assessment the contractor shall, at no extra cost to the DEPARTMENT, repair
and re-condition all the civil, electrical, mechanical, instrumentation equipment to a
condition so that they are in running condition with regular preventive and
recommended maintenance as per manufacturer's recommendations.
During O&M, diffusers shall be checked regularly and replaced as per requirement.
After completion of 9 years O&M, all the electrical, mechanical, instrumentation, civil works,
piping and diffusers shall be thoroughly checked jointly by the contractor and engineer-in-
charge. As per findings of the joint inspection the defect shall be set right by way of repair/
service / replacement as the case may be.
i) The contractor shall operate and maintain all (E&M) equipment as per the
recommendations of the respective equipment manufacturer. However in case of
any doubt, the Department shall refer to best of the standards and the contractor
shall be bound to carry out the works accordingly.
j) The contractor shall use only the original and genuine spares of the original
equipment as per recommendations given in the maintenance booklet of the
manufactures/as per directions of the Engineer-in-charge. Test certificate of all
major equipment will be submitted from the manufacturer.
k) The contractor will regularly monitor the performance of sewage treatment plants
and dairy ETPs by conducting the analysis of the inlet sewage/influent and treated
effluent. In case the treated effluent is not meeting the desired standards, the
contractor, under intimation to Engineer-in-Charge, shall initiate and take adequate
actions to ensure satisfactory performance of the Plant.
l) The Contractor shall run the plant unit after ensuring proper voltage. He shall also
record all the power failures and voltage in daily log sheet. He will bring into the
notice of power supply agency as well as control room and Departmental Engineer
Annexure-3 : Revised “ Volume-2(R1)”
56
about the break down/power failure. He will also get the electricity restored
simultaneously.
m) The major repair work shall be carried on and completed under the exclusive
control, direction and supervision to the satisfaction of the Engineer-in-Charge. The
Engineer-in-charge shall have full power to reject or condemn any work or material
that he may deem unsuitable. The Engineer- in-charge shall have full powers to get
the same removed and replaced and deduct the expenditure incurred in the
process from any amount due or that may become due to the contractor.
n) Break down/damage of all equipment/instruments, due to any reason what so ever
it shall be the sole responsibility of the Contractor, without any additional cost to the
department.
o) All major break downs/failures (as defined in the agreed maintenance schedule)
shall be brought down to the notice of Engineer-in-Charge or his representative.
p) The indicating list of operation/maintenance activities is as follows, but not limited to:
Sr. No. Activity
1 Regular operation of all the units of all IPS, MPS, STP & ETP
2 Preventive scheduled maintenance for all civil, electrical & mechanical equipment and instruments.
3 Regular cleaning and maintenance of operation buildings including floors, toilet blocks, railing, doors, windows, light fixtures and ceiling etc.
4 Regular cleaning and maintenance of outdoor areas i.e. roads, pavements, lawns and light fixtures.
5 Regular disposal of screenings, grits, scum and sludge. The sludge produced shall be of desired consistency as specified in the bid document. The screenings and scum have to be drained dry (mechanically or manually) before disposal. These shall be disposed to a site earmarked by employer. However sludge being the property of contractor can be used by him for sale. However disposal of sludge at a site not earmarked by the employer shall not be allowed.
6 Maintenance of storm drainage system to avoid flooding of the installations.
7 Maintenance/ Replantation of plants/grass as per requirement.
8 Repair of civil structures, white washing and painting of all civil structures every two years or earlier if required.
9 Epoxy/ painting of all pipelines, railings, walls, electrical & mechanical equipment, instruments and other metal/wood work, every two years or earlier if required.
10 All the valves/gates which are not used regularly should be operated at least once a week and make sure that they are properly lubricated /greased.
11 All safety valves should be checked daily and ensured that they are working properly. In case of any fault the same should be attended immediately without any wait. Contractor shall keep all the safety devices in working order.
12 Launders/Weirs to be maintained clean round the clock.
13 During preventive/ breakdown maintenance, the pumping units or other machinery required if any shall have to be arranged by
Annexure-3 : Revised “ Volume-2(R1)”
57
Sr. No. Activity
the contractor at his own cost for completing the work.
14 Batteries are required to be maintained and replaced as and when needed.
15 To ensure proper functioning, daily/regular checking of following items is to be done and corrective measures, if required, to be taken immediately: Overflow from various units Sluice valves and gates Chokage of pipes Lubrication/Greasing of all moving parts of equipment,
gates and valves Electric connections to machinery/equipment Level Switches/sensors Various instruments Civil work of all the structures/buildings
Small bore Tube well and water supply pipe line etc.
16 Preventive/breakdown maintenance of all pumps, electrical, mechanical & instrument equipment, installed under the contract. All cost including cost of all material, equipment, etc. required for operation and/or maintenance (preventive and / or breakdown) to be borne by the contractor.
17 Maintenance of the lighting fixtures and the lighting system of the areas and replacement of all non-functional lighting fixtures within 24hours.
18 Maintenance of the stores for various equipment, spares and other materials. The maintenance of stores will include but shall not be limited to:
Loading/unloading materials received and issued for works.
Proper arrangement of material in stores to ensure its safety and easy availability.
Maintaining store area neat and tidy.
Keeping records and Accounting the incoming and consumed materials.
Watch & ward, safety of material, stores, installation etc. by the contractor.
19 Cleaning of sludge from Final Polishing Unit (FPU) by totally emptying at the end of 3rd, 6th and 9th year of O&M.
20 Working of all diffusers are required to be checked regularly and replaced as and when needed by the contractor.
21 Flushing of channels conveying dairy waste using mobile vehicles fitted with suitable pump and nozzle system.
q) All relays and HT equipment shall be calibrated and tested at least once a year and
the report shall be submitted to the Engineer-in-Charge.
r) In addition, the general hygienic standards must be maintained and adequate
plantation should be done.
Annexure-3 : Revised “ Volume-2(R1)”
58
4.3.1. Tests and Sampling Schedule During O&M Period
The sampling and testing schedule shall be carried out as detailed in the following table. The
Contractor’s schedule for tests and sampling shall also be maintained during the O&M
period.
SAMPLING PROTOCOL FOR STP PROCESS
Sr. No.
Parameter Frequency of Sampling
Type of Sample
1. Influent & Effluent Temperature Daily Grab
2. Influent & Effluent pH Daily Grab
3. Influent and Final Effluent BOD5 Daily Grab
4. Influent and Final Effluent COD Daily Grab
5. Influent and Final Effluent TSS Daily Grab
6. Influent and Effluent Ammonical Nitrogen Thrice a week Grab
7. Influent and Effluent Fecal Coliforms Daily Grab
8. Influent and Effluent Total Phosphorous Monthly Composite
9. Influent and Effluent Total Nitrogen Thrice a week Grab
10. Aeration Tank, D.O. MLSS and SVI Daily Grab
11. Primary Sludge VSS, TSS and Specific Gravity Thrice a week Grab
12. Secondary Sludge VSS, TSS and Specific Gravity
Thrice a week Grab
13. Dewatered Sludge after mechanical dewatering. Once a week Grab
Note:
1. BOD5, COD & TSS of treated sewage shall be checked on a composite sample
as directed by Engineer-in-charge.
2. The composite sample means a sample prepared by taking every two hours &
mixing then in proportion of the flow.
3. Timing for grab samples are to be decided by Engineer-in-Charge.
General
4.3.2. No equipment shall remain idle or un-attended or damaged for the period of more than 3
days. If any equipment is not repaired, rectified and or replaced within 3 days, the
contractor will be penalized.
4.3.3. Technical Audit
The Department has the right to conduct a technical audit of the Facility and to perform
any analysis or inspection it deems necessary. The Contractor shall at his own cost
provide all assistance to the Department required to complete these inspections. Such
audits may cover all or any of the obligations of the Contractor, including without limitation.
Annexure-3 : Revised “ Volume-2(R1)”
59
(a) Verification of the system capacity and save for normal wear and tear during the
O&M Period.
(b) Verification of the performance standards and useful life of the individual assets
of the Facility, save for normal wear and tear during the O&M Period.
(c) Verification of the capacity of the Facility to meet Output Standards during the
residual life of the Facility and save for normal deterioration expected during such
residual life.
(d) Sampling, testing and verification of the Output Standards for treated sewage,
sewage losses.
4.3.4. Faculty Visits
(a) At any time or at the end of each twelve month period, or at the initiative of the
Engineer-in-Charge, a visit shall be organized so that both parties can check the
condition of the installations at the facility.
(b) A report shall be drawn up to record the opinions of the both parties. The Engineer-in-
Charge reserves the right to call the equipment manufacturers or specialized
technicians for these visits. All expenses are to be borne by the contractor for the
purpose.
4.3.5. The Department will be at liberty to post its staff for surveillance/ inspection at the
plant along with access to all units, control room and records, log books, MIS
(Management Information system), data etc. round the clock as required. The
logbooks are attested by the staff from authorized Department officials and this record
shall be open for further inspection/checking by Department and all other Government
Agencies CPCB/PPCB etc. for further action/improvements/rectifications.
4.4. Man power
i) The staff employed will be provided with all the required safety equipment. It shall
be ensured that full safety measures are taken by the staff on duty. Staff
employed shall be experienced and trained to handle the respective
job/equipment.
ii) The work shall be carried out on a 24 hrs basis, without intermission and the staff
deployed by the contractor shall be in accordance with this contract.
iii) List of names of staff is to be given by the agency to the Engineer-in-charge and
advance intimation to be given before deputing/removing any staff from site
during the period of contract.
iv) Engineer-in-charge shall be authorized to direct the contracting agency to remove
any or all staff employed on O&M of the plant if in his opinion continued presence
of such staff is detrimental to safety or proper O&M of the plant. The contractor
shall comply with such directions & post suitable substitute(s) thereof immediately
within 24 hours. Whenever the Engineer-in-charge has informed the contractor in
writing that any person on the work is in his opinion unsatisfactory or incompetent,
or unfaithful or dishonest, untruthful or disorderly or to be otherwise
unsuitable/such person shall be discharged by the contractor from the work and
shall not be employed again on it.
v) The contractor shall give or provide all necessary superintendence during the
O&M and as long thereafter as the Engineer-in-charge may consider necessary.
Annexure-3 : Revised “ Volume-2(R1)”
60
Such superintendence shall be given by a competent person having adequate
knowledge of the Operation and Maintenance to be carried out (including the
methods and techniques required), the hazards likely to be encountered and
methods of preventing accident as may be required for the satisfactory working of
the entire plant.
vi) Minimum manpower requirement for Operation in 3 shifts for the IPS, MPS and
STP/ETP is as under. However, the contractor shall deploy additional man power
and experts as required to operate and maintain the system as per scope of work.
The contractor shall issue identity card to the manpower deployed.
vii) The contractor will employ no offence guilty person or indiscipline man. Right is
reserved by Department for suspension, dismissal, termination of any officer /
staff employed by contractor. He shall take prior permission to employ or to
terminate his personnel.
viii) The presence of staff should be marked in register to be maintained at office of
shift-in-charge at Sewage Treatment Plant that shall be considered as final.
ix) Indicative minimum manpower is as follows:
a) New STP & MPS Jamalpur and three IPS feeding Jamalpur STP
S. No.
Manpower Number
1 Plant Manager 1
2 Chemist 1
3 Laboratory Assistance 2
4 Plant Operators / Pump Operators 9
5 Electrician cum Mechanic 1
6 Sewer Men/Helpers 12
7 Chowkidar/ Mali 4
b) Bhattian
Existing MPS including modifications
Existing 50 MLD SBR STP and 111 MLD UASB STP including
modifications
S. No.
Manpower Number
1 Plant Manager 1
2 Chemist 1
3 Laboratory Assistance 2
4 Plant Operators 7
5 Electrician-cum-mechanic 1
7 Sewer Men/Helpers 15
8 Chowkidar/ Mali 3
c) Balloke
Two existing MPS including modifications
One new pumping station
152 MLD UASB Plant including modifications
Existing SBR based STP and one new STP
Three IPS and Rising main.
S. No.
Manpower Number
Annexure-3 : Revised “ Volume-2(R1)”
61
1. Plant Manager 1
2. Chemist 1
3. Laboratory Assistance 2
4. Plant Operators 15
5. Electrician 1
6. Mechanic 1
7. Sewer Men/Helpers 24
8. Chowkidar/ Mali 5
d) Two Dairy Waste ETPs at Tajpura & Haibowal including Conveyance System
S. No.
Total Manpower for both ETPs Number
1. Plant Manager 1
2. Laboratory Assistance 2
3. Plant Operators 7
4. Electrician-cum-mechanic 1
5. Sewer Men/Helpers 14
6. Chowkidar/ Mali 4
4.5. Reporting
a) The contractor will be responsible for keeping up-to-date record of documents
including History Card for equipment and maintaining every day log book relating to
various data analysis performed as decided by Engineer-in-Charge.
b) Sewage Treatment Plants/Effluent Treatment Plants / Pumping Stations
The indicating lists of recording activities during operation/maintenance period are
as follows, but not limited to:
Sr. No.
Activity
1 To maintain and update logbook, in which details of operational parameters at the inlet and outlet of STP / ETP are recorded every day.
2 To prepare and submit a weekly report of plant performance which will assist the Department in preparing the necessary documents for their purpose and records.
3 To maintain record of troubleshooting points and details of events causing trouble, which shall be used for updating the contents of manual.
4 To maintain the operational activity record of maintenance work whether preventive or break down.
Annexure-3 : Revised “ Volume-2(R1)”
62
5 To maintain and update logbook data:
Which includes History-Card of each equipment at regular interval
Running of all Electrical and Mechanical Items, Consumption of energy, fuel and other consumables etc. and
various analysis performed.
6 To maintain the operation and maintenance data of the following: Daily status record of STP, IPS & MPS Daily flow record Daily sampling record Operation record of mechanical screens Sludge Quality and Quantity on daily basis An inventory of the chemicals and spare parts available at the
end of the reporting period. O&M staff deployed by the contractor during the reporting
period. Any major repair works, if any with its remedial actions.
7 To maintain hard and Soft copy of data available on PLC monthly.
8 All records to be maintained in hard as well as Digital mode
c) Preparing data recording, correspondence work to Department and Government
Departments, etc. all should be done as per standard practices and by following
labour, factory, electrical, Punjab Pollution Control Board (PPCB), and all other
applicable laws, Indian standards etc. as applicable to Local, State and Central
Government of India.
d) Sample Indicative / Reporting Formats Are As Follows:
I. Hourly record of Flow as measured / recorded through the Notch / Weir
/ Flow meter:
Date/ Time
Head Over The Notch / Weir/Meter
Rate Of Flow
Average Rate Of Flow in Past Hour
Cumulative flow during
day
/ / Mtrs. M3 /hour M3 /hour M3 0800 0900 1000 1100 1200
II. REPORT FORMAT FOR DAILY TESTING SCHEDULE FOR VARIOUS
PARAMETERS
Test/ Parameter
Inlet To Receiving chamber
Outlet after Secondary Treatment
Outlet after Tertiary
Treatment
Annexure-3 : Revised “ Volume-2(R1)”
63
Any other performa as per the format decided by the Engineer in Charge.
e) Reporting for all IPS / MPS
i. Records of Operation and Maintenance of Pumping Station
Operational Records
Sr. No. Particulars Running Total Time
Remarks Reading Taken by From (Hrs) To (Hrs)
1.
Pump Operation Pump 1 Pump 2 Pump 3
ii. Monthly Report on Operation & Maintenance of Pumping Station (Electrical)
O & M Report for the Month: Year
iii. Maintenance:
Repair history of all mechanical, electrical and instrumentation control equipment Logbooks.
Every day power availability, input voltages, KVAH and KWH meter, power factor readings at pumping station.
Daily operation of pumps with readings for operating voltage, amperage and power factor, pressure on the manifold, pressure at outlet of pumps and flow rate in manifold.
In addition to maintenance of above log-books, the contractor is required to maintain one inspection book at pumping station. Submission of monthly report.
4.6. Consumables
a) All consumables, chemicals are to be arranged by the contractor himself. The work
also includes the use of oil, grease, lubricants required for operation and
maintenance of the Plant which will be arranged by the contractor himself.
Sr.
No.
Details
of Break
down
Details of
Break down
Maintenance
done
Details of
spares /
consumable
s consumed
Average
power
factor
Total
Average
KVA
Demand
over the
month
Total
KWH
Consum
ed
Remark
Annexure-3 : Revised “ Volume-2(R1)”
64
b) The contractor will determine operating parameters, select settling (Chemical doses
etc.) and generally optimize the process, and working of the treatment plant.
Excessive chemical dozing i.e. dose more than normal should be avoided.
c) The contractor should plan & procure all spares, Polyelectrolyte and all
consumables including chemicals, grease, lubricating oil, cleaning agents,
laboratory reagents, rubber bush, graphite packing, rubber sheet, nut-bolts, etc.
Further the contractor will plan about the requirement well in advance (At least 3
month) and procure the material from the market as per the DEPARTMENT
approved list & as per the O& M manual or as per the existing manufacturer’s brand.
d) All chemicals including chlorine gas consumed to operate the Sewage Treatment
Plant and other facilities under this contract will be borne by the contractor.
e) POL (petrol/ Diesel Oil & Lubricants) has to be arranged by the contractor as and
when needed as per manufactures recommendations for periodical maintenance of
entire plant. The Department will not provide such items. Only diesel for DG Set will
be reimbursed to the agency upto the extent of average guaranteed Power
consumption.
4.7. Commercial
a) The Contractor will ensure working of Plant round the clock. In case of any failure on
the part of tenderer for successful running and operation of the plant or unit, the
same will be attended by the Engineer-in-Charge and will be operated at the risk
and cost of the Contractor and necessary deduction will be made from the bills/
performance guarantee/ deferred payment of the tenderer or any other some
available with the department as decided by the Engineer-in-Charge, whose
decision will be final.
b) Waste water flow to operate and maintain the plant will be provided by the
department free of cost whereas the contractor will have to make his own
arrangement with regard to safe and potable water for the staff working at site and
for operational requirement.
c) The power charges will be borne by the department. However, power charges
beyond average guaranteed power consumption for the raw sewage treated shall be
borne by the bidder.
d) If at any moment it is noticed that due to violation of any of above procedure and
negligence of contractor any of the equipment is damaged, the action against
contractor shall be initiated immediately terminating the contractor / recovery of the
cost of equipment / loss due to negligence of the contractor from the bills/
performance guarantee/ deferred payment of the tenderer or any other some
available with the department as decided by the Engineer-in-Charge, whose
decision will be final.
e) In case of any theft/missing of equipment/part the successful Contractor will be
liable to pay the cost including damages to the department.
f) All Central/State Government/Semi-Government/Local Body’s Rules and
Regulations pertaining to this contract shall be followed and observed by the
contractor without any extra cost to the Department.
g) Contractor is responsible for watch and ward, security, storage, housing
accommodation at his own cost.
h) It is to be noted that all costs during the O&M period, excluding the cost of power/
diesel within the guaranteed power consumption for the sewage treated to be borne
Annexure-3 : Revised “ Volume-2(R1)”
65
by the contractor, within his quoted cost. The contractor is to ensure that the
following guarantees are maintained during the operation & maintenance period:
Quality of treated effluent
Working of automation system
Consumption of power
i) In the event of any damage/loss of life/theft of property, due to negligence on the
part of Contractor, the Contractor shall be solely responsible and liable for
compensation and damages. Regarding negligence and compensation the decision
of Engineer-in-Charge shall be final.
j) All necessary transports shall be arranged and made by the Contractor at his own
costs including transport vehicles required for safe disposal of screening material,
grit within the distance specified by the Engineer-in-Charge.
k) All the plant, building land, Sewage treated / untreated, etc. shall remain the
property of Department.
l) In addition to the regular in house testing at the STP/ETP Laboratory, monthly
testing of sample shall be carried out by PPCB before 20th of every month or by the
contractor from the laboratory approved by Punjab Pollution Control
Board/Engineer-in-Charge. The cost of testing from PPCB or from any other
accredited outside laboratory will be reimbursed to the contractor on actual basis on
production of the expenditure receipt.
m) POL (petrol/ Diesel Oil & Lubricants) has to be arranged by the contractor as and
when needed as per manufactures recommendations for periodical maintenance of
entire plant. The Department will not provide such items. Only diesel for DG Set will
be reimbursed to the agency upto the extent of average guaranteed Power
consumption.
n) The operation and maintenance of the existing set up at 3 STP sites (Jamalpur,
Bhattian & Balloke) and existing IPS (Sunder Nagar, Gaushala & Tibba Road) shall
be handed over to the contractor on approval of Service Improvement Plant.
o) The handing over of the operation and maintenance of existing infrastructure by the
Municipal Corporation, Ludhiana can be in one lot or in parts. The contractor would
be paid as per actual time of maintenance on pro rata basis upto the completion/
commissioning of entire infrastructure as per contract.
p) For the infrastructure to be developed by the contractor sectional commissioning
and commencement of operation and maintenance shall be accepted. For sectional
commissioning, the contractor shall be paid for actual period of operation and
maintenance on pro rata basis.
4.8. Service levels
a) The contractor shall have to issue identity cards with photographs to all the staff
employed for Operation and Maintenance. The list of the same shall be submitted to
the Department mentioning qualification & experience as well as display on board.
b) The Supervisor / Plant Manager of contractor will always remain in contact with the
Junior Engineer, Sub Divisional Engineer-in-Charge of the Plant deployed by the
Department and shall follow their instructions.
c) It is required that at least once in every quarter a technical expert other than the
regular maintenance Staff of the contractor will visit plant and will suggest if
required, to improve the efficiency and working of the plant etc. No separate
Annexure-3 : Revised “ Volume-2(R1)”
66
payment will be made for such visits. The visit must be recorded and outcome of the
visit / minutes of the meeting should be got signed by Department authorities without
which the visit shall not be considered.
d) The contractor shall assist the department in all formalities required from all
Government authorities i.e. Forest, PSPCL, PPCB etc. for having NOC, water
consent, Hazard waste concern, approval etc. shall be got done by the contractor.
e) Any other services required for smooth running is also in the scope of work.
4.9. Safety / Security
a) The contractor shall take all safety precautions under various Acts/Rules under
central/State Govt. from time to time and he shall be responsible for safety of its staff
and the consequences thereof. The contractor shall deploy round the clock security
personnel at entrance of plant’s premises and in the compound for the safety of the
plant and premises, equipment and personnel during this period.
b) Responsibility for damages
i. The care of the whole of the permanent works shall remain with the contractor
who shall be responsible for all accidents or damages from whatever cause
arising and chargeable for anything that may be stolen, removed, destroyed or
damaged to whomsoever belonging and also for making good all defects and
damages to the said works or to any property adjoining or any cause whatever,
whether such damage or defects were occasioned by the negligence of the
contractor or not or may be or might have been recovered during the progress
to be known after the completion whereof or whether payment may wholly or
partially have been made or the works approved as supposed to have been
properly done and no certificate of approval of any works by any officers or
members of the Board shall affect or prejudice the right of the PPCB against
the contractor or to be considered or held as at all conclusive as to the
sufficiency of any work materials.
ii. Adequate safety precautions against fire, flooding, lightening, electrical shocks,
accident due to moving/non-moving heavy/light equipment shall be strictly
observed by the contractor at his own cost.
iii. Suitable safety measures like gumboots, gloves, safety belts, ladders, safety
lamps, gas masks, Oxygen apparatus, insulated tools, alarms etc. shall be
provided by the contractor. Necessary medical first aid kit shall be made
available all the time. In absence of observance of above safety precautions,
the contractor shall be responsible for any unforeseen loss of the equipment or
persons dealing with it. Special care shall be taken by the contractor while
carrying out the work in sewage gas zone. Any incidence of human life or
accident will be totally contractor’s responsibility.
iv. The contractor shall ensure that the staff employed takes all necessary
precautions while carrying out the work either in shift duties or any general shift
as per Indian Electricity Rules/Factory Act/CPHEEO Manual, or manufacturer’s
special instructions for safety / gas handling. The staff should use Gas masks,
Oxygen apparatus, Gum Boots, Safety Belts and Safety Lamps, etc. while
carrying out the work in Bar Screens, sumps, etc.
v. The contractor will make arrangement for all necessary safety equipment for
persons working at Work as per Factory Act/Safety Rules. In the event of any
Annexure-3 : Revised “ Volume-2(R1)”
67
accident on or off site, in which the contractor or his personnel are involved, in
which an injury occurs to any person whether directly concerned with the
project or a third party, the contractor shall inform Department within 24 hrs. of
the occurrence of the event. The plant will be open to local/state/central
agencies for verification of safety/emission/acts compliance.
vi. During night hours, the main gate should be locked. However, shift duty staff
should be alert and open the gate during surprise checking of Department staff
or any other Government Authorities or his nominee without any wait. Only
bona-fide persons be allowed in the plant premises being a prohibited area.
Smoking and drinking are prohibited in the plant. The staff engaged shall wear
common uniform with name plate indicating name and designation during duty
hours.
c) The contractor has to make sure that proper fire extinguishers are used to cover
any kind of fire during any mishap within the total boundary area including plant
machinery. The expiry period of refills of various fire extinguishers should be
watched and maintained in top working conditions during the period of contract.
d) The contractor shall not remove/shift any equipment/machinery even temporarily
without written permission of the Engineer-in-charge or authorized representative.
e) Though the contractor has to operate and maintain all the equipment/machinery,
PLC, lighting (plant area, boundary walls, gate lighting etc.) but the machine of the
equipment under warranty should not be dismantled without prior permission of the
Engineer-in-charge. The list of such equipment (Under warranty), if any, will be
given by the contractor. The contractor has to provide necessary protection
systems wherever necessary including alarms and fire extinguishers.
4.10. Release of Hazardous Substances or Hazardous Waste
i. The Contractor, after first notifying the PPCB shall be responsible for fulfilling all
requirements associated with any release of any substance into the environment
(from the facility or the site) as required by Applicable law or by any Legal
Entitlement including but not limited to the notification or reporting of releases /
Hazardous substances or Hazardous Waste. The Contractor shall prepare a
memorandum evidence such notification or reporting and provide copies thereof to
the Board, along with any documents provided to the relevant regulatory agency
regarding such release.
ii. The contractor shall process and obtain the clearance of all such agencies however
necessary support and help should be provided by PWSSB/M.C. as required for the
purpose, including all clearances during 10 years O&M period. He shall be fully
responsible to comply with all requirements of Laws including hazardous
substances, emission standards for air, discharge standards for effluent oil, sub-soil
pollution.
iii. The contracting agency shall not release any hazardous/toxic materials inside the
premises.
a) Gas coming out of sewage is hazardous containing Methane, CO, CO2 and
H2s etc. Therefore, necessary precaution and measures are to be taken in
regard to human life and installations. The Contractor shall know all
Central/State Government/Semi-Government/Local Bodies rules regulations to
this contract without any excuse.
Annexure-3 : Revised “ Volume-2(R1)”
68
b) Contractor will comply with all safety rules and regulations and all inter
disciplinary as followed by the Department. The Department will not be
responsible for any accident /injury to the staff of the contractor. Further the
Department will not provide any insurance or medical facility to the staff of
contractor. The responsibility lies with the contractor.
4.11. OPERATION AND MAINTENANCE MANUAL
(i) The contractor shall prepare a detailed program (referred to as O&M Manual)
covering the operation and maintenance of the treatment Plant as a whole. This
program shall include the work and activities described in this Chapter, as
relevant to the specific items and technology notwithstanding the program
submitted and approved, the Contractor is deemed to have tendered for and
covered in his price, the responsibility for operating and maintaining the
treatment plant for the full period of the contract, thereafter handing it over as
specified.
(ii) The contractor shall provide 4 copies of draft O&M Manual of STP / ETP /
Pumping Station to the department, at the time of the commissioning of the
project/ component. The draft of the O&M Manual shall be subject to the review
and approval of Department, which shall have the right to make any changes
and revisions to the O&M Manual as it may deem appropriate. The Contractor
shall revise such draft O&M Manual prior to the commencement of the O&M
period.
(iii) The O&M Manual for STP / ETP / Pumping Station shall include the daily,
weekly, monthly, quarterly, half yearly and annual checks and remedies if
necessary to be performed for effective operation of the plant, elaborate details,
all operating and maintenance procedures and policies which are required,
advisable and / or necessary for the Facility to achieve full compliance with the
operational guarantees and to achieve maintenance and repair standard for the
Facility which will ensure compliance with the maintenance specifications.
(iv) At the end of the construction period, the contractor shall revise the draft O&M
Manual to reflect any updates, changes or revisions it deems appropriate, inter-
alia based on its experience and as necessary to reflect any modifications or
adjustments to the plant. Without limiting the above, the contractor shall annually
review, revise, update and modify the draft O&M Manual as may be necessary
or appropriate. Any revision to the draft O&M Manual shall be subject to the
review and approval of Department.
(v) During the term of this Agreement, the contractor shall promptly notify
Department of any revisions, additions or modifications which he, in his
professional opinion, believes should be made to the O&M Manual, whether as
a result of additional experience in operating and maintaining the Facility,
changes in influent quality or volume, changes or modifications to any
equipment, part, component or structure incorporated in the Facility. Such
notification shall set forth the reason for the proposed revision. Any proposed
revision shall be subject to the approval of the Department. In addition, during
the term of this Agreement, Department shall have the right to have relevant
changes, revisions, or additions to the O&M Manual as it, shall deem
appropriate to ensure full compliance with the O&M Standards.
Annexure-3 : Revised “ Volume-2(R1)”
69
(vi) The contractor shall submit 5 copies of the final O & M manual along with a soft
copy in Microsoft Word Format for STP / ETP / Pumping Stations.
a) Co-ordination with other contractors and / or agencies responsible for the
Execution, operation and maintenance of services.
b) Updating and periodic submissions of the operation and maintenance
manual. The contractor shall take up all periodic maintenance works
provided in the approved O&M manual.
c) The contractor shall provide on the job training to the Departments staff as
per specifications. At the end of the one year of O&M period, an
assessment of the condition of the plant will be done by Departments
Representative and based on the assessment, the contractor shall, at no
extra cost to the Department/DULB, repair and re-condition all the civil
works, electrical & mechanical instrumentation, equipment in the
concluding month of the O&M period to a condition so that they are in
running condition.
d) Updating and periodic submissions of the operation and maintenance
manual as defined in specifications for O&M works. The contractor shall
take up all periodic maintenance works provided in the approved O&M
manual.
e) Co-ordination with other contractors and / or agencies responsible for the
Execution, operation and maintenance for regional schemes and Electric
Supply Company.
f) The contractor shall be solely responsible for the safety and security of
the goods in the store and its accountability and will be responsible for
any loss or damages in stores for any reason. He shall maintain insurance
cover against the value of the goods in the stores without any additional
costs on the Department.
4.12. Spares
a) Contractor is advised to maintain the spare parts as per pre planned schedule.
b) The contractor will provide the necessary tools and tackles required for day-to-day
maintenance.
c) Frequency of spares used in maintenance of electrical, mechanical equipment must
be recorded for updating the contents of manual.
d) Providing adequate spares and maintaining adequate inventory of accessories or
equipment itself for repair of system so that the electrical, mechanical, pipe and pipe
appurtenances, can work efficiently as per the guarantees given or minimum
required efficiencies asked for in the contract, without any additional cost. At the end
of the contract the contractor shall hand over the spares, tools, tackles to the
department.
4.13. Taking Over
The plant will be taken over by Department on satisfactory completion of the
Operation & Maintenance period of the plant after following conditions:
(i) The plant /equipment are in good, smooth running condition.
Annexure-3 : Revised “ Volume-2(R1)”
70
(ii) The result of the treated wastewater quality (for last three months of operation) of
the plant is within the limits specified.
(iii) In case of major repairs /replacement of equipment, the performance guarantee
for such unit/equipment is extended by six months from the date of putting back
in to satisfactory operation of such unit/equipment in case such putting back is at
the end of completion of operation & maintenance period.
(iv) All records of operation & maintenance are handed over to Department in proper
condition.
(v) In case taking over is delayed on account of contractor's failure, the operation &
maintenance period will be extended further till it meets the requirement without
any extra cost to Department. The contractor will also be penalized for such
delays.
4.14. Penalties
a) As per agreement, staff should always remain present as per schedule; otherwise
penalty towards absence of any staff shall be recovered from the Contractor as
per liquidated damages for deficiencies. The contractor shall make the
arrangement of reliever for weekly off/holiday etc.
b) Monitoring should be done as per guidelines given by Engineer-in-Charge.
Contractor has to maintain all the parameter of effluent within stipulated limit as
per contract or he will be penalized for not maintaining the parameters given by
Department. All expenditure incurred for the same like, suite fee, court fee, case
fee, or the penalty as decided by Engineer of Department and penalty charged by
PPCB, NGT or any other Law enforcing Government Agency, will be charged to
contractor and deducted from the bills/ performance guarantee/ deferred payment
of the tenderer or any other some available with the department as decided by
the Engineer-in-Charge, whose decision will be final.
c) Contractor will have to maintain required Power Factor as per PSPCL rules and
regulations. In case penalty is levied by PSPCL for not maintaining the Power
Factor the same will be recovered from the contractor.
d) Liquidated damages for failure to achieve the functional guarantees
The Employer will be entitled to recover any such damages from the monthly
progressive payments to be made to the Contractor in the month in which the
failure occurred.
e) The Contractor shall not be liable for Non-Performance penalty to the extent such
failure is attributable to an Event in which the Contractor has taken necessary
steps to mitigate the effects of the event and operate the system in accordance
with the standards of a reasonable and prudent way.
f) Output & Overall guarantee
The contractor is fully responsible for treating all the Sewage limited to design
capacity of STP / ETP, reaching at the STP/ ETP. The performance of the
contractor shall be treated as unsatisfactory, if he fails to treat the complete
sewage or does not maintain the guarantees listed in the contract.
g) Liquidated damages for Operation & Maintenance shall also be applicable
as under:
1. Liquidated damages for deficiencies in Operation & Maintenance for STP and
MPS are listed as below:
Annexure-3 : Revised “ Volume-2(R1)”
71
Sr
No Description Nature of Deficiency Liquidate damages
A) Deficiency in Manpower
Plant Manager Not Present on duty Recovery will be made
on per day basis for an
amount double the DC
rate as applicable on
the date of deficiency.
Chemist Not Present on duty
Laboratory Assistant Not Present on duty
Plant operator Not Present on duty
Electrician Not Present on duty
Mechanic Not Present on duty
Sewer man/Helper Not Present on duty
Watchman cum
gardener
Not Present on duty
B) Deficiency in service
1 Cleaning of site Not attended up to 1
day
Rs.500 per day beyond
1 Day per site.
2 Non-compliance with
safety measure (e.g. not
wearing safety belt,
helmets, etc.) and first
aid facilities.
Any time on duty Rs.500 per occurrence
per site
3 Non-observation of
Preventive Maintenance
Schedule
Any time on duty Rs.500 per occurrence
per site
4 Delay in getting the
equipment not repaired/
rectified/replaced within
3 days.
Penalized with no limit
@ Rs.2000/day delay
each Individual
equipment of Plants.
C) Liquidated damage for power consumption
1 Power consumption
(For STP only)
Actual power
consumption exceeds
the guaranteed power
consumption (calculated
for the quantity of
sewage treated during
the month based on the
guaranteed power
consumption quoted by
the bidder and accepted
by the Employer)
The Excess power
cost will be recovered
from the contractor.
Note: Manpower deployed shall be allowed one weekly rest and three casual leaves
per quarter for the purpose of calculating deficiency in manpower
deployment.
2. Liquidated damages for non-compliance of treated effluent standards shall be
applicable for all of the components:
Annexure-3 : Revised “ Volume-2(R1)”
72
Event triggering the
recovery of Liquidated
Damages
During the O & M Period
Liquidated
Damages
Frequency
Non-conformance with BOD
Standards
Rs 200.00 Per MLD for every day of
non-conformance per
STP/ETP
Non-conformance with TSS
Standards
Rs 200.00 Per MLD for every day of
non-conformance per
STP/ETP
Non-conformance with
faecal coliform
Rs 1400.00 Per MLD for every week of
non-conformance per
STP/ETP
Non-conformance with other
parameter as per DNIT
Rs. 200.00 Per MLD per parameter
per STP/ETP for each
testing as per contract.
5. TIMELINE FOR COMPLETION OF PROJECT COMPONENTS
S.No
Component Timeline (Months from Commencement of the
Project)
1 Construction and Commissioning of IPS at Sunder Nagar, Gaushala and Tibba Road
24
2 Providing and Laying of rising main from Sunder Nagar-Gaushala-Tibba Road-STP Jamalpur
24
3 Construction and Commissioning of 225 MLD capacity STP & MPS at Jamalpur
24
4 Construction and Commissioning of ETP for Dairy Waste at Tajpura Road
24
5 Rehabilitation of Existing Main Pumping Station at Bhattian
12
6 One time repair of 50 MLD existing STP on SBR Technology at Bhattian
12
7 Rehabilitation of Existing 111 MLD STP based on UASB Technology at Bhattian
12
8 Arrangement for Mechanical dewatering of sludge from existing 111 MLD UASB Plant at Bhattian
12
9 Additional Chlorination Plant at Bhattian 12
10 Construction and commissioning of IPS at Kundan Puri, Upkar Nagar and Lord Mahavir Ayurveda Hospital
24
Annexure-3 : Revised “ Volume-2(R1)”
73
11 Providing and Laying of rising main from Upkar Nagar-Lord Mahavir Ayurveda Hospital-Balloke STP
24
12 Providing and Laying of rising main from Kundan Puri IPS to Sewer Manhole
24
13 Construction and Commissioning of 225 MLD capacity STP & MPS at Jamalpur
24
14 Construction and Commissioning of ETP for Dairy Waste at Haibowal Village
24
15 One time repair of 105 MLD existing STP on SBR Technology at Balloke
12
16 Rehabilitation of Existing Pumping Stations (2 No.) at Balloke.
12
17 Rehabilitation of Existing 152 MLD STP based on UASB Technology at Balloke
12
18 Arrangement for Mechanical dewatering of sludge from existing 152 MLD UASB Plant at Balloke
12
19 Additional Chlorination Plant at Balloke 12
Annexure-3 : Revised “ Volume-2(R1)”
74
6. DETAILED DESIGN CRITERIA OF NEW 60 MLD STP AT BALLOKE
Raw Sewage Pumping Station for New STP at Balloke
Design Requirement
Design Requirement described here are in general for various works. However
specifications for only those Materials /Equipment/ Instruments shall be applicable
which are required or provided at site. If the specification of any items are not
described here then specifications as per the relevant IS code or prevalent as per the
department practice will be applicable as approved by Engineer-in-charge.
6.1. Components of Main Pumping Station
6.1.1. Civil Works
i. Distribution chamber ii. Receiving Chamber iii. Screening Channel iv. Wet well/Collecting Tank v. Panel Room vi. Roads & Pavements vii. Platform /Foundation for Diesel Generating Set &Transformer viii. Cable Trench, wire mesh around transformer ix. White washing/painting etc. x. Hand Railing xi. Pumping main from MPS to inlet chamber of STP xii. Valve chamber/platform to house common header, all valves, NRVs etc.
The component of MPS shall be worked out by the bidder so as to ensure
treatment from existing SBR based STP and new proposed STP using sewage
from 90” & 60” existing sewers.
I. Distribution Chamber
Rising main from IPS of Lord Mahavir Ayurveda Hospital shall be directed to
distribution chamber along with 90” and 60” existing sewer lines, for flexibility in
handling of incoming Sewage (Refer Drawing). Suitable retention time shall be
provided for designing of this chamber. C.I gates (Manually Operated) of suitable
size shall be provided at the inlet of Distribution chamber. Adequate RCC Platforms
shall be provided at the upper level to enable operation. Railings shall be provided
around the entire periphery of the platform.
Following are the Connections from / to Distribution chamber
Tapping from 90” Sewer line
Tapping from 60” Sewer line
Proposed Rising main from shaft No.5 near Lord Mahavir Ayurvedic Hospital
Distribution chamber to Existing Main Pumping Station
II. Receiving Chamber
The deep gravity outfall sewer, from Distribution chamber, will discharge the raw
sewage into a Receiving chamber. The function of the Receiving chamber is to
Annexure-3 : Revised “ Volume-2(R1)”
75
distribute the flow to screens. The Receiving Chamber shall be designed for peak
flow. The Receiving chamber shall consist of sluice gates on upstream for flow
regulation. The receiving chamber shall be of adequate size to meet the
requirements of workability inside it. C.I gate (Manually Operated) of suitable size
shall be provided at the inlet of receiving chamber. The entire construction is in
minimum M-30 grade concrete and as per IS 3370. RCC access platform minimum
1200 mm wide with GI pipe railing as per specifications shall be provided:
Number of Units : 1 (One)
Minimum Detention period : 30 Sec at Peak Flow
Min Free board : 0.50 m
III. J Type Removable Bar Thrash Screens
Manual Trash screen to be installed in front of coarse mechanical screens to prevent large and medium sized floating wastes from entering into intake structure of pumping station.
The manual screen should comprise of flat bars spaced apart in vertical with 50mm
opening within a sturdy frame structure inserted in vertical guide channel. Structure
provided should be with perforated basket at its bottom and guide roller on both
sides for easy removal. Guide channel extend upto to top of platform for guiding
upward movement. The height of trash screen should be 0.5 m above sewer crown.
Material of construction should be in SS-304. Flat size shall be of 10 mm thick
50mm wide.
Number of Units : 2 Working each of
50% Peak Flow capacity
Velocity through Screen at Average Flow : 0.6 maximum
(m/sec)
Velocity through Screen at Peak Flow (m/sec): 1.2 maximum
Height of Mesh Screen : 0.50 m above sewer crown
Wheeled Trolley : 2 No.
All other accessories, whether specified or not, but required for completeness of
contract shall be in contractor’s scope. Railings shall be provided around the entire
periphery of the platform and structure.
The provision of EOT crane, any kind of cleaning/raking mechanism, collection
bins/portable screen container, water jetting arrangements & trolley etc. shall be
provided.
IV. Coarse Screen
Two mechanical screens working and one manual screen standby of 20 mm clear
spacing shall be provided with each screen designed for 50% of peak flow capacity.
The mechanical and manual bar screens shall be made of 10 mm thick Stainless
Steel (SS 304) flats respectively. The mechanical coarse screens shall be of
Inclined Rake Type of 20 mm opening as per the specifications detailed elsewhere
in the bid document. Bin and chute arrangement shall be provided to take the
screenings. The screenings dropped from chute will be collected in a wheel burrow.
Annexure-3 : Revised “ Volume-2(R1)”
76
Manually operated CI gates are provided at the upstream and downstream ends to
regulate the flow.
Adequate RCC Platforms shall be provided at the upper level to enable operation.
Railings shall be provided around the entire periphery of the platform. The entire
structure is to be minimum M-30 concrete and as per IS 3370 including the platform.
RCC staircase 1200 mm wide shall be provided for access from the ground level to
the top of the unit & to the operating platform.
Number of Units : 2 Mechanical (Working) + 1 Manual
(Standby) each of 50% Peak Flow
capacity
Approach Velocity at Average Flow (m/sec) : 0.3
Velocity through Screen at Average Flow : 0.6 maximum
(m/sec)
Velocity through Screen at Peak Flow (m/sec) :1.2 maximum
Height of Screen bars upto dead plate : 1 m above sewer crown
Wheeled Trolley : 1 No.
J Type Manual Thrash Screen
Mechanical coarse Screens
Manual coarse
Screens
1 Balloke 2 2 1
All other accessories, whether specified or not, but required for completeness of
contract shall be in contractor’s scope.
V. Wet Well
The Main pumping station (MPS) shall be a rectangular concrete structure. The
sump well is to be in R.C.C of min Grade M-30 and shall be designed for peak flow.
The maximum operational liquid level in wet well shall be such that, minimum
100mm Freefall is maintained from Invert of Screen Chamber to Water level of wet
well. The capacity of the wet well sump should be kept such that the detention time
of the sump should be at least 5 minutes peak flow. The wet well shall be divided
into two equal compartments upto full height with sluice gates in common wall.
The pumps shall be installed equally in two compartments. Area of gate(s) should
be sufficient so as to divide the flow into any of the compartments, at a velocity not
more than 1.2 m/sec.
The arrangement of the Pumps shall be as per Manufacturer’s data i.e. Spacing
between the Pumps, minimum space between the Pump and Wall etc. Adequate
submergence of the pump shall be provided as per the manufactures
recommendations. The size of wet well shall be sufficient to accommodate one
additional pump in each compartment, in future.
RCC Staircase to be provided in each compartment of wet well from full supply level
of sump. Aluminium ladder (removable) from last landing of staircase to the bottom
of wet well.
Annexure-3 : Revised “ Volume-2(R1)”
77
IS: 3370 and IS: 4111 (Part 4) shall be followed for the design and construction of
Wet Well.
Basis for Design
All underground or partly underground liquid containing structures shall be designed
for the following conditions:
(a) Liquid depth up to full height of wall and free board. No relief due to lateral soil
pressure from outside to be considered;
(b) Reservoir empty (i.e. no liquid or any material inside the storage area): full lateral
earth pressure at rest due to surrounding saturated soil and surcharge pressure as
applicable, shall be considered;
(c) Partition wall between two compartments of wet well to be designed as one
compartment empty and other full;
(d) Structures shall be designed for uplift in empty conditions considering the depth of
the highest water table recorded in the area.
(e) Walls shall be designed under operating conditions to resist earthquake forces
developed due to mobilization of earth and dynamic liquid loads;
Underground or partially underground structures shall also be checked against
stresses developed due to any combination of full and empty compartments with
appropriate ground/uplift pressures on the base slab.
VI. Sewage Pumps
Coarse-screened sewage shall be pumped from wet well. Pump operation shall be
automatically controlled based on wet well level. There will be high level and low
level alarm and tripping system installed. It will house non clog submersible pumps,
which will always be submerged in sewage with minimum submergence as required
by the manufacturer. Pumps will have automatic coupling arrangement at discharge
end, a guide pipe and chain for easy removal and lowering of pumps. Vibration shall
be limited as per BS 4675 Part I:
Type of Pumps : Submersible type non-clog design Liquid : Raw Sewage Specific gravity : 1.05 Solid Passage Size : Maximum 100 mm No of working Pumps : 4 Nos Capacity of Pump : Peak flow/ No of working pumps Standby Pumps : 50% of working pumps. VFD for pump : 2 Pumps one in each compartment is to have the
provision of VFD for flow variation
One electrically operated 3-way movement Trolley (EOT) having capacity equal to 1.5
times the weight of heaviest part to be lifted shall be provided over the sump well for
movement of pumps. The horizontal, transverse as well vertical shall be electrically
operated. The gantry is to be fixed on RCC framed structure and not on a cantilever
arm from columns.
Annexure-3 : Revised “ Volume-2(R1)”
78
VII. Rising main
Sewage from wet well will be pumped to STPs (Existing SBR based and new
Proposed STP) through rising main of size suitable to carry peak flow.
Material of rising main : Cement lined DI (K9) pipe
Size of rising main : Capable of carrying peak flow as specified
Velocity in rising main at peak flow : maximum 2.5 m / sec
VIII. Piping & Specials
This shall include providing, laying, cutting, jointing, testing, etc. of pipes along with
specials:
a) RCC Channels from inlet chamber of screens upto sump/ collecting tank.
b) DI K-9 Delivery line for individual pump upto common header.
c) Expander, Sluice valves, Bends, Non Return Valves in the individual delivery
of all the pumps. Tees and Sluice valve in the common header.
d) DI K-9 Common header upto Inlet of STP.
e) The size of pipe shall be calculated so as to meet the following velocity
criteria:-
Minimum Velocity : 0.60 m/sec
Maximum Velocity : 2.5 m/sec
f) All other required fittings such as bends, tees etc.
g) Thrust block of M-20 grade, for pipe support, etc.
h) Necessary bypass arrangement shall be provided to be used during the
shutdown of the plant. Pipe and Valve arrangement upto suitable discharge-
point shall be provided.
IX. Painting, White Washing and allied works
The internal and external surfaces of the walls and ceiling of all building structures
shall be applied with two coats of Birla / JK Wall Putty followed by two coats of
primer followed by min two coats of first quality plastic emulsion paint.
All the structural steel, pipes, specials etc. shall have two coats of Epidec RTC
Primer followed by two coats of epoxy paint.
All the internal walls and base of water retaining structures of MPS shall be provided
with min two coats of coal tar epoxy.
X. Roads & Pathways with proper drainage
Roads and Pathways shall be provided with interlocking paver blocks over 150 mm
thick and 100 mm thick respectively cement concrete of 1:4:8 in stone ballast.
Thickness of paver blocks on roads is 80 mm thick and on pathways the thickness
of paver blocks is 60 mm. Paver blocks shall confirm to specification of code IS
15658 Paver blocks will be ISI Marked.
XI. MPS Panel Room
It shall be RCC framed structure and 3.5 m clear height. It shall house panels of
MPS pumps, screens, sluice gates, valves etc. It shall also house PLC Panels and
HMI screen for display of various parameters of MPS. Preferably the MPS panel
Annexure-3 : Revised “ Volume-2(R1)”
79
room building is to be adjoining to the administrative building of STP so as to have a
better monitoring.
Local Push Button Station (LPBS) shall be provided near each Pump set/ Motor for
emergency stop and start thereof. LPBS shall have Start/Stop push button with
Local/Remote Selector Switch. Each push button shall have 2NO+2NC contact for
interlocking purposes. The stop push button shall be mushroom type with stay put
feature and lockable in pressed position to avoid accidental operation of drive from
MCC, PLC during shutdown.
LPBS shall be suitable for use in outdoor open locations with minimum IP-55 degree
of protection and rain canopy.
6.1.2. Mechanical Works
i) J Type Manual Coarse screens, Manual and Mechanical Coarse Screen, Belt
Conveyor for screens
ii) CI Sluice Gate shall be provided at following locations for flow control
a) Inlet of Receiving Chamber – 1No. b) Upstream of coarse screens of MPS – 3 Nos c) Downstream of coarse screens of MPS – 3 Nos d) RCC Partition Walls of Wet Well – 1 No e) Gates for Distribution chamber – 3 Nos. f) Any other gate as required
iii) Non clog Submersible Centrifugal Pumps sets with motor
iv) Piping works, Dismantling Joint, NRV, Sluice Valve with appurtenance
v) Lifting Arrangement –Monorail with electric horizontal and vertical operation
6.1.3. Electrical, Instrumentation & Control Works
i) HT VCB Panel
ii) Transformer ONAN with on load tap changer
iii) Silent Diesel Generating Set with AMF Panel suitable for average flow plus
other miscellaneous load.
iv) Electrical Panel with
a) Incomer for normal & DG supply & interlocks power analyzer, surge protection device
b) Individual Starter Panels with VFD and soft starters for pumpset c) Automatic Power Factor Control (APFC) Capacitor Panel d) Alarm Annunciation Panel e) Feeder for other loads f) Interface with PLC & SCADA compatibility
v) HT & LT Cable, Instrument & data cable
vi) Cabling system
vii) Earthing & Lightening Protection
viii) Lighting System (Indoor & Outdoor)
ix) Junction Box for cables
x) UPS for PLC
xi) Instrumentation & Control
Annexure-3 : Revised “ Volume-2(R1)”
80
This includes supply, erection, testing and commissioning of various instruments &
control system. Brief details are as under:
S No
Instrument Location Quantity
1. Differential Level sensor / Transmitter
Mechanical Coarse Screens As required
2. Pressure gauge Common discharge header of non-clog sewage pumps/Rising main
1
3. Radar Type level transmitter (non-contact type)
Main Collection Sump ( For level Status & level based control)
2
4. Programmable Logic Controller (PLC)
Panel Room 1
5. Any other Item As per requirement As per
requirement
PLC for MPS shall be as per control philosophy & specification.
PLC shall operate pumps based on pre-set levels of sewage in collection tank and
VFD operation. At mid-level of sewage, number of pumps as per average flow shall
operate, whereas at high level, number of pumps as per peak flow shall operate. At
low level, all pumps shall stop. Provision shall be made to operate all pumps in
rotation. Pumps operation shall be closely co-ordinated with STPs sewage
requirement through STP PLC/SCADA
PLC cum Instrumentation Control Panel shall be provided with 6” HMI to enable
level based operation of pumps and display of level and flow.
Provision shall also be made for display of level and flow in STP, SCADA Room.
Single PLC for MPS and STP is preferred. Contractor is free to provide separate
PLC for MPS.
PLC to have provision for exporting data to external device
Annexure-3 : Revised “ Volume-2(R1)”
81
6.2. Sewage Treatment Plant
i) Flow Measurement
Flow measurement shall be done online using an ultrasonic flow meter on the rising
main of raw sewage pumping station located at STP area.
ii) Inlet Chamber
Inlet Chamber will receive raw sewage from the raw sewage pumping station.
Number of Units : (1) One
Min. Detention period : 30 sec on peak flow
Min free board : 0.5 m
Following provisions shall also to be made as per detailed design.
CI/DI double flanged Puddle Collar
CI/DI double flanged Vertical Pipes
1 no. CI /DI double flanged Sluice Valves
CI/DI Horizontal pipe having length as per Site Requirement.
Minimum 150 mm i/d CI/DI pipes along with sluice valves for scouring purposes.
iii) Screening Chamber
Two mechanical Step/MATT type screens (working) with one manual (standby)
screen are proposed in the screening chamber. Each screen shall be designed for
peak flow.
RCC Platforms minimum 1.2 meter wide with GI railing shall be provided at suitable
level and location to enable operation of the units.
The component / unit shall be designed for following:
Number of Units : 2 Nos. Mechanical Working + 1 No.
Manual Standby each of 50% peak flow
Approach Velocity at Average Flow
(m/sec.)
: 0.3 minimum
Velocity through Screen at Average
Flow (m/sec.)
: 0.6 maximum
Velocity through Screen at Peak Flow
(m/sec.)
: 1.2 maximum
Free board : Min 0.5m on upstream side of the screen
at maximum water level
Minimum Length : 6 m
Mechanical Screens Manual Fine
Screens
1 Balloke 2 1
The entire construction shall be in minimum M-30 grade reinforced cement concrete
and as per IS 3370. RCC Platform/Walkway, minimum 1.20 m wide with G.I Hand
Railing as per specifications shall be provided. RCC Staircase, minimum 1.20 m wide
Annexure-3 : Revised “ Volume-2(R1)”
82
with G.I. Hand Railing as per specifications shall be provided for access from
Finished Ground Level to the top of the Unit & to the Operating Platform/Walkway.
The clear spacing shall be 6 mm for Mechanical Fine Screen and spacing of 10 mm
for Manual Fine Screen. The Mechanical and Manual Screens shall be made of SS
304 flats (3 mm for Mechanical and 10 mm for Manual Screen).
Minimum 3mm thick panels of stainless steel 304 construction shall incorporate 6mm
diameter perforations.
Conveyor Belt and Chute arrangement shall be provided to take the screenings.
Screenings dropped from Chute shall be collected in a wheelbarrow. Manually
operated CI/Aluminum Sluice Gates shall be provided at the upstream and
downstream ends to regulate the flow.
Detailed specifications of mechanical bar screen are given in Mechanical Section.
iv) Mechanical Grit Chamber
Mechanical grit chamber with atleast 50 % and one Manual Bypass Channel
(Standby) shall be provided after Fine Screen Channels. The entire construction shall
be in minimum M-30 grade reinforced cement concrete and as per IS 3370. RCC
Platform/Walkway, minimum 1.20 m wide with G.I. Hand Railing as per specifications
shall be provided. RCC Staircase, minimum 1.20 m wide with G.I. Hand Railing as
per specifications shall be provided for access from Finished Ground Level to the top
of the Unit & to the Operating Platform/Walkway.
Each Grit Chamber shall have the following features:
One tapered Inlet Channel running along one side with adjustable Influent
Deflectors for entry of sewage into the Grit Chamber.
One tapered Outlet Channel for collecting the de-gritted sewage, which overflow
over an adjustable Weir into the Outlet Channel. It shall be designed in such a
way that no settling takes place in it.
One sloping Grit Classifying Channel into which the collected grit shall be
classified.
The grit from Classifier shall be collected in a Wheeled Trolley.
A Grit Scraping Mechanism.
Material of construction of grit mechanism: SS 304
Screw Classifier or Reciprocating Rake Mechanism to remove the grit.
Manually Operated C.I. / Aluminum Sluice Gates shall be provided at entrance of
the Inlet Channel of the Grit Chambers as well as Bypass Channel to regulate the
flow.
No. of Units : Total flow in all working units equal to Peak Flow
Type : Mechanical
Size of grit particle : 0.15 mm and above
Specific gravity of grit : 2.65
Maximum Surface Overflow Rate: 959 m3/m2/day
Free Board : 0.5 m min.
Side Water Depth : 0.90 m min.
Annexure-3 : Revised “ Volume-2(R1)”
83
Wheelbarrow : 3 Nos. minimum
All other accessories, whether specified or not, but required for completion of
Contract shall form the part of Bidder‘s Scope.
Proper bypass channel between the units shall be provided with a sluice gate at the
inlet.
v) Distribution Box/Splitter Box
A Distribution Box / Splitter Box shall be provided downstream of Grit Chambers
prior to Biological Reactors for uniform flow distribution to Biological Reactors. The
Distribution Box shall be equipped with suitable motorized Sluice Gates and outlet
Weirs.
vi) Biological Treatment
The bidder can adopt any suitable, sustainable & proven technology including
SBR & MBR with its variants for biological treatment of sewage.
Anaerobic Reactors
No of Reactors Suitable
Anaerobic Hydraulic Retention Time As per CPHEEO
Min. Liquid Depth of Reactor 5.0 mt.
Min. free board 0.5 mt.
Material of Construction -Civil R.C.C. (M-30) or higher
Mixers Suitable- SS 304 MOC.
Anoxic Reactors
Design Anoxic HRT As per CPHEEO
No of Reactors Suitable
Mixers Suitable- SS 304 MOC.
Min. Liquid Depth of Basin 5.0 mt.
Min. free board 0.5 mt.
Material of Construction -Civil R.C.C. (M-30) or higher
Primary Clarifier
No. of Units Suitable
Surface Loading Rate at Average flow 35-40 m3/m2/day
Weir loading rate at average flow 125 m3/m/day (max.)
Area required per unit Suitable
Side water depth (upto top of weir) 3.0 m (Minimum)
Material of Construction -Civil R.C.C. (M-30) or higher
Type of Mechanism Central Driven / Peripheral Type
Drive RPM As per manufacturer standard
MOC/Paint Wetted parts SS 304
Non Wetted Parts- MS/Epoxy Painted
Sludge Drain Valves (KGV)
Location At Sludge Removal pipe line
Size Suitable
Annexure-3 : Revised “ Volume-2(R1)”
84
Type Knife Gate Valves - Automatically
operated
6.3. Biological Reactors, Settling and Decanting System
Primarily treated sewage shall be fed into the Reactors for biological treatment to
remove BOD, COD, Suspended Solids, Biological Nitrogen and Phosphorous.
The Reactors along with provisions for sludge re-circulation, excess sludge disposal,
aeration system, settling, decanting and other operational requirements like
automation, level control, flow control, oxygen level control etc. shall be provided.
Number of Units : As per bidder design
Design parameters : All design parameters like, MLSS, HRT, F/M, DO
level, recirculation ratio etc. shall be as per CPHEEO
manual for the offered technology.
Free Board : Minimum 0.50 m
Aeration System : As per bidder design subject to CPHEEO guidelines.
Automation : Operation of the Reactors shall be fully automatic,
controlled through PLC.
Miscellaneous
requirements
: The treated waste water shall be available on
continuous basis.
The Reactors to treat design flow sewage
irrespective of flow variation pattern of inflow
sewage.
Any other
requirement
: As per bidder technology and design to meet the
desired outlet parameters.
Secondary Clarifier
No. of Units Suitable
Surface Loading Rate at peak flow 40-45 m3/m2/day for activated sludge
25-30 m3/m2/day for extended aeration
sludge
Weir loading rate at average flow 185 m3
/m/day (max.)
Solids loading rate at peak flow 210 kg/m2
/day for activated sludge
170 kg/m2
/day for extended aeration
sludge
Area required per unit Suitable
Side water depth (upto top weir) 3.0 m (Minimum)
Material of Construction -Civil R.C.C. (M-30) or higher
Type of Mechanism Central Driven / Peripheral Type
Drive RPM As per manufacturer’s standard
MOC/Paint MS/Epoxy Painted- Wetted parts SS 304
Sludge Drain Valves (KGV) of Secondary Clarifier
Location At Sludge Removal pipe line
Size Suitable
Type Knife Gate Valves - Automatically
operated
Annexure-3 : Revised “ Volume-2(R1)”
85
Return and Excess Sludge Sump with Pump House
Return Sludge Pumps
No. of Return Sludge Pump suitable
Capacity of Return Sludge Pump suitable
Type of Pump Submersible Non-clog / Horizontal
Centrifugal Non-clog type
Pump Head As per hydraulic design
Valves at delivery, Suction and
common header lines
Knife Gate Valves - Electrically operated
Excess Sludge Pumps
No. of Excess Sludge Pumps suitable
Capacity and head of Excess Sludge
Pumps
suitable
The entire construction shall be in minimum M-30 grade reinforced cement concrete
and as per IS 3370. RCC Platform/Walkway, minimum 1.20 m wide with G.I Hand
Railing as per specifications shall be provided. RCC Staircase, minimum 1.20 m wide
with G.I Hand Railing as per specifications shall be provided for access from Finished
Ground Level to the top of the Unit & to the Operating Platform/Walkway. Plinth
protection along periphery shall be provided as per technical specifications
6.3.1. Return Sludge and Excess Sludge Pumps
a. Return Sludge Pumps
Capacity and Head As per requirements
Type Submersible / Horizontal Centrifugal
Liquid Biological Sludge of 0.8 – 1% solids consistency
Specific Gravity 1.05
Solid size 40 mm (Maximum)
Temperature Min. 25 C
Efficiency more than 60%
Quantity 1 No. per Basin + 1 No. Store Standby
b. Excess Sludge Pumps
Capacity and Head As per requirements
Type Submersible / Horizontal Centrifugal
Liquid Biological Sludge of 0.8 – 1% solids consistency
Specific Gravity 1.05
Solid size 40 mm (Maximum)
Temperature Min. 25 C
Efficiency more than 60%
Quantity 1 No. per Basin + 1 No. Store Standby
6.3.2. Decanting Device
The Decanter Device shall be Moving Weir Arm Device of SS304 with top mounted
Gear Box, Electric Drive, Scum Guard, Down comers, Collection Pipe, Bearings.
Weir loading for each decanter shall not exceed 125 m3/hr/m of the inlet weir.
Annexure-3 : Revised “ Volume-2(R1)”
86
6.4. Aeration System for Selected Biological Treatment
Oxygen Required
BOD Oxidation Oxygen Requirement 1.2 x Inlet BOD Load
Nitrification Oxygen Requirement 4.56 x TKN Nitrification
Total Requirement BOD Oxidation + Nitrification Oxygen
Requirement
Oxygen Credit (from De-Nitrification)
Oxygen release during denitrification
= 2.86 mg O2/mgN
Max O2 credit of denitrification can be
only 50% of nitrification
Alpha value for Submerged Diffuser 0.65 (Maximum)
Beta value for Submerged Diffuser 0.95 (Maximum)
Fouling Factor for Diffuser 0.9
Oxygen Demand Safety Factor 5 %
Oxygen content in Air (by weight) 23%
Type of aeration Energy efficient diffused aeration
system.
Blower details:-
Type : Turbo Blowers
Capacity : As per design
Discharge Head : Suitable
No. of units : As per design requirement with minimum 50% standby
All Air Blower shall be provided with VFD.
The operation of Aeration System shall include PLC based control. The
operation and speed of Air Blowers shall be automatically adjusted using
parameters like Oxygen required, Dissolved Oxygen, Temperature and Liquid
Level in the Rector such that the DO is supplied as per demand and power
utilisation for operation of Air Blowers is optimised.
The main Air Header/Ring Main shall be in MS as per relevant IS Code, painted
with corrosion resistant paint as per Manufacture’s recommendations. The Air
Header/Ring Main shall be supported on saddles at suitable intervals or shall
be protected against external corrosion in case laid below ground. The Sub-
headers distributing air to various locations shall have Auto Valves to facilitate
air switch over between different demand locations. The Sub-header shall
supply air to Fixed Type Diffuser Grids at various locations through vertical Air
Supply Pipes. These Air Supply Pipes above water level shall be in MS,
painted with corrosion resistant paint and below water shall be in SS 304. All
under water Lateral Pipes shall be of UPVC. Junctions between horizontal Sub-
header and vertical Air Supply Pipes shall be suitably protected against
corrosion due to dissimilar materials.
All other accessories, whether specified or not, but required for completeness
shall form part of bidder scope.
The aeration facility shall be installed for average flow.
Annexure-3 : Revised “ Volume-2(R1)”
87
Fine Bubble Type, PU / EPDM Membrane Diffusers shall be acceptable with
minimum Membrane Diffusers to Floor Coverage Area of 5%. Diffusers shall be
submerged, fine bubble / fine pore, high transfer efficiency, low maintenance
and non-buoyant type. Diffusers shall be panel / Disc / tubular type. Complete
Diffuser as a unit shall be assembled at the manufacturing factory level. The
grid supports shall of adjustable type made of SS 304.
6.5. Tertiary Filtration System: Fiber Disc filter
Tertiary Treatment Plant shall be designed for average flow and provided in the form
of Disc filters which shall consists of following:
• Civil (RCC) Tank to house the Fiber Disc filter
• Disc filter assembly with Filter Cloth
• Drive Assembly
• Backwash System
• Control panel & Instruments
The Tertiary Treatment Plant shall conform to the specifications as mentioned below:
Disc filter assembly with Filter Cloth:
Disc filter shall comprise multiple high strength and separable discs (proposed by
manufacturer). Each Disc shall be subdivided into smaller sections to constitute a
prefab disc frame (module) so as to ensure easy replacement and maintenance.
Each disc consists of multiple panels.In case of replacement of fiber cloth, the left and
right of the fiber cloth shall be replaced quickly without disassembling of segments
(Disc frames). Each disc shall be mounted on the centre drum by strap band (steel
band) for the exact roundness and it shall not be fixed by Stud bolts. The additional
sealing material shall not be needed for assembling of filter cloth to segment and the
fiber cloth itself shall be acted as the sealing material. Filter cloth shall envelop some
parts of backside of filter frame and the several springs shall be used to fix the filter
cloth. The drum shall be round type and shall have the enough area in order to
discharge the treated water without trouble. The material of the filter cloth shall be
polyester; the filter frame that fixes the filter cloth, the disc frame and the segment
cover shall be ABS resin. Central drum shall be SS304. Maximum Filtration rate shall
be 10-12 m3/m2/hr. Nominal pore size of filter cloth shall be approx. 10 micron.
Filter shall be designed for average flow or decant flow whichever is higher. Suitable
no. of units shall be provided. Raw water shall flow into the respective Disc filter by
gravity. The structure shall ensure that Suspended Solids (SS) are filtered (treated)
from outside to inside of the filter cloth installed on both sides of the disc filter, and
that filtered water is discharged through the centre drum to the treated waterway.
Sr
No TECHNICAL DATA OF FILTER
1. Type of Disc filter Fully submerged outside to inside
type
2. Type of filter cloth Pile cloth with ABS frame
Annexure-3 : Revised “ Volume-2(R1)”
88
3. MOC of filter cloth Polyester
4. Nominal pore size, (microns) Approx. 10
5. Maximum Filtration rate (m3/m2/hr) 10 -12
6. Total reject and backwash % < 3
7. Backwash System Automatic Backwash system
based on time and level
8. Head loss across the disc filter unit
(mm) As per design
9. Thickness of drum 4 mm. (minimum)
10. MOC of Centre drum SS 304
11. Filtration mode Continuous
Drive Assembly:
Drive part of Disc filter shall be of Worm geared type with motor chain drive. The drive
comprises Drive Motor, Reduction Gears, Chain and Sprocket. Power shall be
transmitted by the SS 304 chain. A protective cover made of SS 304 shall be equipped
for the drive motor, reduction gear and the chain. The rpm of the disc filter drive shall
be adjustable by the inverter that is attached in the field control panel.
Backwash system
Cleaning device consists of Suction cleaning unit, which conducts the suction cleaning
in the each side of disc, the automatic valve and the suction cleaning pump. Cleaning
device shall clean the contaminated filter cloth thoroughly by the suction unit on both
sides of disc with automatic valve and suction cleaning pump which shall be activated
by the water level switch that contacts the water level raised with the increase of the
loss of head. Disc filter should be operated for filtration without the stop during
backwash and suction of sludge. Suction cleaning unit shall be made of or the even
cleaning efficiency without dead zone for all area of filter cloth.
Back wash Recovery system shall consist of flash mixer, Flocculator, Clarifier, Back
wash sludge sump. Sludge generated shall be dewatered using centrifuge. Overflow
from Clarifier shall be sent to FDF.
6.6. Disinfection System
Disinfection (Chlorination) Units
Disinfection (Chlorination) Units including Chlorination Tank and Chlorinator cum
Chlorine Tonner House shall be designed for Average Flow or Decant Flow whichever
is higher.
6.6.1. Chlorination Tank and Chlorinator cum Chlorine Tonner House
Treated sewage shall be taken to Chlorination Tank by RCC Channel/DI K-9 pipe. Gas
Chlorine shall be added for disinfection at suitable dosing rate. Baffle walls shall be
provided in the Tank to facilitate hydraulic mixing of treated sewage. The entire
construction shall be in minimum M-30 grade reinforced cement concrete and as per IS
3370.
Design Flow : Maximum Decant Flow
Number of Units : 1 No.
Annexure-3 : Revised “ Volume-2(R1)”
89
Hydraulic Retention Time : 30 Minutes (excluding Outlet Channel after Weir)
Free Board : 0.50 m min.
A Chlorinator cum Chlorine Tonner House shall be provided above/near Chlorination
Tank to house Chlorination Systems. It shall be RCC (M25) Frame cum Brick Masonry
Structure with Rolling Shutter, Windows & Ventilators, Electrical Hoist with Electrical
Travelling Trolley of minimum 3 Ton capacity or 1.5 times the weight of the single Unit
whichever is more to lift the Pumps/Chlorine Tonners and Safety Equipment including
Sand Buckets, Fire Extinguishers and Fire Alarms etc. Also it shall be provided with
IPS Flooring, Internal & External Plaster and Internal & External Painting. Plinth
Protection shall be provided along the periphery as per specifications.
All other accessories, whether specified or not, but required for completion of Contract
shall form the part of Bidder’s Scope.
6.6.2. Chlorination System
Gas Chlorination System comprising Vacuum Chlorinators (2 Nos.), Water Feed
Pumps (2 Nos.), Interconnecting Piping and Appurtenances, Chlorine Gas Detector,
Empty Chlorine Tonners (Suitable for 30 days’ Storage) with Tri unions, Lifting Device
and Suspended Weighing Scale, Residual Chlorine Test Kit, Safety Equipment (e.g.
Exhaust Fan, Canisters, Gasmasks etc.), Mandatory Spares, Chlorine Leak Detection
and Chlorine Leak Absorption System including FRP Half Hoods, Caustic Solution
Tank, Caustic Recirculation Pump, Centrifugal Fan, Interconnecting Piping and Ducts
complete and other required ancillary shall be provided.
The system must have the provision for linking its operation to PLC of STP so that
quantity of chlorine usage can be varied automatically as per treated water flow from
SBR Basins.
Design Flow : Maximum Decant Flow
Type : Vacuum Type
Chlorine Dosing : As per process requirement subject to Infrastructure
arrangement for at least 5 ppm dose.
Quantity of Chlorinator : 2 Nos. (1 Working + 1 Standby)
All other accessories, whether specified or not, but required for completion of
Contract shall form the part of Bidder’s Scope.
Treated water after chlorination unit shall be disposed off in Buddha Nallah through
RCC pipe.
6.7. Sludge Handling System
6.7.1. Sludge withdrawal from various units.
Sludge withdrawal shall be either by gravity or through pumping. DI Pipes shall be
preferably used for transportation of sludge. Sludge withdrawn from various units shall
be collected in a single sludge sump and shall be fed to :
a. Gravity Thickener followed by Centrifuge dewatering machine or
b. Combined Mechanical Thickener cum Belt Press.
Annexure-3 : Revised “ Volume-2(R1)”
90
6.7.2. Sludge Sump
Sludge sump shall be provided to collect the excess sludge from various units. There
shall be one common Sludge Sump. The Sump shall be equipped with coarse Bubble
Air Grid made from stainless steel pipes to facilitate mixing of contents of sludge sump
on continuous basis. Alternatively Submersible mixers of suitable numbers can be
provided:
Number of Units : 1 (one) no.
Free Board : 0.5 m
Capacity : Minimum 6 hour holding of average daily
sludge production
Minimum SWD : 3.0 m
6.7.3. Sludge thickener unit with Centrifuge
The Gravity RCC Sludge thickener unit(s) of suitable size shall be provided for gravity
sludge thickening to reduce the capacity of Centrifuge equipment. The excess sludge
from biological Reactors / settling tanks will be taken to thickener. Thickener is
expected to produce thickened sludge with minimum dry solid concentration of 3%.
Design criteria
1. Hydraulic loading As per CPHEEO Manual
2. Solid loading As per CPHEEO Manual
Continuous gravity thickener shall be
circular RCC units with minimum 3.0
m side water depth. Side depth shall
be based on three considerations.
Free board 600 mm
Sludge Thickener Mechanism The mechanism shall comprise of the following main components of suitable size as per design requirements: All wetted parts shall be SS 304.
Bridge Superstructure spanning the tank diameter with central drive maintenance platform
Drive assembly complete with drive head, chain and sprocket, geared motor etc. Feed Well Center Shaft Cone scraper Rake arms Tie rods for rake arms Plow blades & squeegees
Material of Construction Tank RCC Bridge MSEP Feed Well SS 304 Walkway MS Chequered Plate / Grating Handrail 40 mm i/d GI pipe, Class B Rake Arm SS 304 Vertical shaft SS 304
Blades SS 304
Annexure-3 : Revised “ Volume-2(R1)”
91
v-notch weir FRP / SS 304 Squeegees Neoprene Anchor Bolt SS 304 Fasteners- Under Water SS 304 Fasteners- Above Water GI / SS 304
Sludge dewatering mechanism can be centrifuge type or belt filter press type of suitable design and capacity.
6.7.4. Sludge Pumps
Sludge Transfer Pumps shall be provided to feed sludge to sludge dewatering units. The pump shall be suitable for handling biological sludge. All pumps including standby shall be installed.
Pumps Capacity and Head : Sufficient for handling total daily sludge in working hours i.e. max 22 hours
Type : Screw Pump/ Reciprocating pump Liquid : Bio-sludge for thickener and dewatering
machine. Solid Size handling : 40 mm (Maximum) Specific Gravity : 1.05 Efficiency : More than 50 % Installation : Fixed Quantity : Minimum 2 no. (1W + 1S) for dewatering
mechanism feeding Minimum 2 no. (1W + 1S) for thickener feed
6.7.5. Centrifuge Units
The centrifuge shall be solid bowl centrifuge of co-current / counter current design.
The centrifuge shall have sufficient clarifying length and differential RPM so that
separation of solids is effective. The centrifuge shall have central lubrication system.
The centrifuge and its accessories shall be mounted on a common base frame so that
entire assembly can be installed on an elevated structure.
Suitable drive with V-belt arrangement and turbo-coupling shall be provided along
with overload protection device. Centrifuge shall be with SS-304 wetted parts.
Differential speed and bowl speed should be adjusted by changing the pulleys;
differential speed may be adjustable by use of epicyclical-gear. The bowl shall be
protected with flexible connections so that vibrations are not transmitted to other
equipment. The base frame shall be in epoxy painted steel construction and provided
with anti-vibration pads. All steps necessary to prevent transmission of structure
borne noise shall be taken. Adequate sound proofing shall be carried out.
A hoist shall be provided above centrifuge for maintenance purpose. The hoist shall
be such that it shall be possible to erect or de-erect the centrifuge while one
centrifuge is in operation.
Number of centrifuges : At least 2 Nos. (1W + 1 SB) Type : Horizontal Operating Hours : 22 hrs. per day maximum Mixing arrangement of Polyelectrolyte : Online mixing
Annexure-3 : Revised “ Volume-2(R1)”
92
and sludge Dewatering polyelectrolyte dosing system is to be provided to dose poly electrolyte
solution to the incoming sludge at entrance to the centrifuge.
6.7.6. Combined Belt Thickener cum Belt filter press units
The Sludge Dewatering Device shall consist of combo units which includes
Mechanical Thickener and Belt Filter Press along with all appurtenances. It shall be
designed to adequately condition and dewater the sludge so that the dewatered
sludge cake is produced that easily discharges from the Belt Filter Press to collection
trolley. Flocculator arrangement in SS-304 of suitable capacity shall be provided at
the inlet of each Belt Filter Press for mixing of sludge and DWPE. All other
accessories, whether specified or not, but required for complete operation shall form
part of contractors scope.
Number of Belt filter press : Min 2 Nos (1 W + 1 SB)
Operating Hour : 22 hours per day maximum
Design
Inlet Sludge Consistency : 0.8-1.0 %
Outlet sludge consistency : Minimum 20%
Mixing arrangement of
Polyelectrolyte and sludge
: Online-mixing
Dewatering polyelectrolyte Dosing system is to be provided to dose Poly Electrolyte
solution to the incoming sludge at entrance to the belt filter press. The supernatant
from Belt Filter shall be taken by gravity to Wet Well of MPS/Inlet of STP. The pipes
below Ground shall be RCC NP-3, with HDPE lining, whereas the pipes above
ground shall be of SS-304. Combo unit including Mechanical Thickener and Belt filter
press shall be capable of handling sludge consisting of minimum 0.8% solids by
weight. The dewatered cake shall be based on minimum consistency of 20% by
weight dry solids. MOC shall be SS-304. General Equipment furnished and installed
under this section shall be fabricated, assembled, erected and placed in proper
operating condition in full conformity with the drawings, specifications, engineering
data, instructions, and recommendations of the equipment manufacturer, unless the
engineer notes exceptions.
Workmanship and design: All components of the sludge dewatering equipment
shall be engineered for long, continuous, and uninterrupted service. The unit shall be
fully enclosed “multi-stage” type comprised with three belts. Gravity section shall be
comprised with an individual speed variable gear motor. All bearings, electrical and
pneumatic components shall be located on periphery of the frame allowing easy
access for the operator for overhauls. Sufficient number of removable inspection
hatches shall be located on each side of the unit to observe the factions of the unit.
The sludge dewatering system shall consist of belt filter press (es) and all
appurtenances. Each belt filter press shall be a fully enclosed having monologue
frame construction, complete prefabricated unit consisting of at least a sludge
conditioning system, a gravity drainage section, a pressure section, a belt alignment
and tensioning system and a belt washing system. Only units having an effective belt
Annexure-3 : Revised “ Volume-2(R1)”
93
width of 1.0– 3.0 meter shall be considered acceptable under this specification. The
unit(s) shall be the “multi-stage” Belt Filter Press (es) type.
6.8. Manual and Auto Valves / Gates
The bidder shall have to provide required No. of valves operated manually as well as with automation for running of plant.
6.8.1. Chain Pulley Block, Mono Rail, Electric Hoists
Mono Rails
This includes supply, erection, testing and commissioning of adequate capacity mono rails.
Lifting electric hoist arrangement for various unit of STP
This includes supply, erection, testing and commissioning of lifting equipment with all accessories suitable in various units of the STP.
Sr. No.
Description of unit
Type of lifting Type of movements
1. Dewatering mechanism
Electric operated hoist
Two movements e.g. vertical, and Transverse
2. Sludge Pump House
Electric operated hoist
A chain pulley block of adequate capacity
3. Tonner shed Electric operated hoist
Two-way movements e.g. vertical, Transverse
4. Raw Sewage Pumping Station
Electric operated hoist
Three-way movements e.g. vertical, longitudinal and transverse
The above list is indicative. Actual required / Installation capacity of Electric Hoist, shall vary as per process requirement, which shall be approved by EIC.
Chain Pulley Blocks This includes supply, erection, testing and commissioning of adequate capacity
chain pulley block with all the accessories. It should be compatible with the lifting
chain of the pump.
Chain Pulley Block of adequate Capacity : As per requirement
6.8.2. Sludge Pump House(s)
Pump house shall be near sludge sump. This shall be RCC frame and brick masonry
structure. Minimum height of the pump house shall be 4 m from the plinth level. It shall
be provided with rolling shutter and doors and windows. A chain pulley block of
adequate capacity along with girder and pillar arrangement shall be provided.
The pump house shall be painted from inside and outside with approved colour and
make as directed by Engineer-in-Charge. The pump house shall house-
Pumps for feed to dewatering mechanism (working + standby)
Air blowers for Sludge Sump (working + standby) or Submersible Mixers
DWPE dosing pumps (working + standby)
Annexure-3 : Revised “ Volume-2(R1)”
94
6.8.3. Chemical Dosing Tanks
Suitable number and capacity dosing tanks with required inner lining and agitators are
to be provided.
Polyelectrolyte Dosing System shall consist of Dosing Tanks equipped with Slow
Speed Agitators and Diaphragm type Metering Pumps. Polyelectrolyte shall be dosed
online at the inlet of Centrifuges. Minimum dosage of polyelectrolyte shall be 0.50 –
1.50 Kg/Ton of dry solids at 0.1% solution strength. The solution will be dosed using
mechanically actuated Diaphragm type Metering Pumps. Dedicated Dosing Pumps
shall be provided and shall be interlocked with Combined Mechanical Thickener cum
Belt Press /Centrifuge in such a way that they Start/Stop along with Belt Press /
Centrifuge.
Dosing Tanks:
Design Capacity : As per requirement
Number of Units : As per requirement
Hydraulic Retention Time : Suitable for min. 8 hours of Operation
Free Board : 500 mm
Dosing Pumps : As per design.
Capacity and Head : As per requirement
Type : Mechanically Actuated Diaphragm Type Metering
Pump
Liquid : Polyelectrolyte Solution of 0.1%Strength
Quantity : one each per dewatering machine
6.8.4. Civil Structure for Mechanical De-watering including
Building of sufficient size to accommodate mechanical dewatering Units Combined
Mechanical Thickener cum Belt Press or Centrifuges (Working + Standby) shall be
constructed with sufficient floor height above Ground Level to park sludge collection
vehicle directly under the sludge discharge line of centrifuge. The room shall have a
RCC roof at a height suitable for installing EOT. Minimum floor area of the building
shall be sufficient to accommodate mechanical dewatering unit. It should be framed
RCC structure with the top roof also in RCC. The dewatered sludge shall have a
minimum solids concentration of 20% or more (measured as dry solids w/w basis) so
that it can disposed by open body Trucks/Trolleys.
6.8.5. Sludge Storage Platform
A sludge storage platform shall be provided at a suitable location within the plant area
for storage of de-watered sludge, minimum for a 7 days storage capacity. Flooring of
the platform shall be 75 mm thick PCC (1:2:4) laid over 100 mm thick stone ballast.
Level of platform shall be at least 20 cm above the level of approach road. From
sludge storage platform, the sludge shall be disposed of by the contractor.
6.8 Operations Buildings
6.8.1 Office, PLC Room etc.
The building shall be constructed to house the following as a minimum:
a) PLC/Main LT (MCC) Room –as required
b) Office rooms for the officers and staff with Lavatory cum Toilet block of required
Annexure-3 : Revised “ Volume-2(R1)”
95
size/area along with sanitary fittings as decided by the Engineer –in- Charge.
i) One passage app. 2m wide.
ii) Workshop cum Tool Room
iii) Stair case up to terrace will be provided.
The height of ceiling shall be minimum 3.5 M from the floor level or higher to suit the
requirement. Adequate no. of toilets and wash basin shall be provided separately for
men and women and a separate toilet attached to the office room shall be provided. A
covered service water overhead tank of capacity 5 cum shall be provided to cater to the
water requirement of building and process requirement.
One no. bore well with pumps of capacity 10-15 cum per hour to cater to the water
requirement for building etc.
Office Building/Admin Building Rooms
The Existing Administrative Block & laboratory for UASB based Sewage Treatment
Plant may be used after renovation/repair & painting.
6.8.2 Blower Room
Sufficient area blower room with a minimum clear height of 5.00 mtr shall be
constructed to accommodate all the blowers for biological Reactors and other
requirements. Minimum space on other three sides of blower room will be 1.5 m from
the blowers. The blower room shall have sufficient ventilation, lighting and working
space. Control panels for air blower shall be placed in air conditioned room, in blower
room, if required. The room will be equipped with sufficient capacity EOT lifting
arrangement to facilitate removal of blower/motor etc. for repairs. The room will also
have rolling shutter or aluminium glazed doors and windows.
6.8.3 Staff Quarters
The bidder shall have to construct two Nos. Single storey quarters for the operational
staff. The covered area shall have 80 m2 each. The provision in the staff quarter
consists of one bedroom, one drawing cum dinning, kitchen, store and toilet. The
construction material for walls shall be brick work in Cement Sand mortar 1:5, RCC
roof slab shall be (M 25). The door and windows shall be of commercial hollock wood.
6.8.4 Other Buildings
One toilet block for operators, one guard room with toilet and one meter room of
sufficient size as approved by Engineer-in-Charge shall be constructed.
6.8.5 The Painting specifications common to all the buildings
Sr.No Description Specifications
1 Roof Water Proofing Brick Bat Coba
2 Plaster
i Walls inside Cement Mortar 1:4, 20 mm thick
ii Walls outside Cement Mortar 1:4, 12.5 mm thick
iii Roof including cantilevers Cement Mortar 1:3, 10 mm thick
3 Painting
Annexure-3 : Revised “ Volume-2(R1)”
96
i External Cement based paint
ii Internal Plastic emulsion
4 Dado/ Skirting Same material as on flooring 2.10 m high
in toilet block and 0.15 m high in all other
rooms / spaces
5 Doors / windows Aluminum
6.8.6 Schedule of Finishes
Sr.
No.
Unit Flooring Doors Windows /
Ventilators
1 MCC Room, PLC &
Control Room
Marbonite flooring of
approved make. The
size of Marbonite tiles
shall be min 600 mm
x 600 mm & thickness
minimum 12 mm
Solid Core
Flush Door
with heavy
duty Brass
Fittings of
approved
make
Aluminum of
approved
make
2 Reactor Air Blower
Room, Workshop &
Tool Room, Chlorinator
cum Chlorine Tonner
House, Thickener
Dilution Water Pump
Houses, Electrical HT
Substation, DG House
IPS Flooring with
Abrasion Resistant
Additives of approved
make
MS Rolling
Shutter
of
approved
make
Aluminum of
approved
make
3 Centrifuge / Thickener
cum Belt Press House
Anti -Skid Tile
Flooring of approved
make
--- ---
4 Vehicle Parking Area Coloured Pre-cast
Heavy Duty Paving
Blocks with Lacquer
Finish
--- ---
5 Toilet Blocks Coloured Glazed Tiles UPVC of
approved
make
UPVC of
approved make
6 Staircase: Inside
Building
Grey Granite Flooring
of approved make
--- ---
Adequate number of Toilets and Washbasins shall be provided separately for Men &
Women at each floor. A covered Overhead Tank of capacity 5 m3 shall be provided
along with an Underground Water Tank of capacity minimum 10 m3 to cater to the water
requirements of the Building.
In addition, the Building shall be provided with Passages, Wooden/Aluminium/Glass
Doors / Windows / Ventilators and Safety Equipment including Sand Buckets, Fire
Annexure-3 : Revised “ Volume-2(R1)”
97
Extinguishers and Fire Alarms etc. Adequate Flooring shall be provided in various
Rooms/Areas as per requirement or as per instructions of the Engineer-in-charge. Internal
& External Plaster with Painting shall be done as per instructions of the Engineer-in-
charge. Plinth Protection shall be provided along the periphery as per specifications.
The Building shall be provided with the following:
6.9 SUB STATION (HT METER ROOM, HT PANEL ROOM, TRANSFOMER, PCC &
MCC PANEL ROOM)
Two nos. Transformers, 1 each for STP and Pumping Station of full capacity and as
per PSPCL norms shall be provided at STP area.
The Electrical Substation shall be provided to accommodate components comprising
HT Panel, Outdoor Transformers, Power Control Centres etc. Outdoor Transformers
shall be installed in open adjacent to Sub-Station building covered with fence and gate
with fire wall between two transformers as per IE rules and PSPCL norms. Location of
HT Meter Room shall be as per PSPCL norms.
Sub-Station building shall be RCC (M25) Frame and Brick Masonry Structure equipped
with Rolling Shutters, Windows/Ventilators, Exhaust Fans and Safety Equipment
including Sand Buckets, Fire Extinguishers and Fire Alarms etc. complete as per
PSPCL norms and IE rules. Also it shall be provided with IPS Flooring, Internal and
External Plaster with Painting and Plinth Protection along the periphery as per
specifications.
DG Set Area
The DG Set area with shed, foundation for DG, Safety Equipment including Sand
Buckets and Fire Extinguishers shall be provided adjacent to Sub-Station building to
accommodate DG Set including AMF Panel, Fuel Tank and other Accessories. DG Set
shall cater to entire load of STP and average flow plus other misc. load of MPS.
Separate DG Set shall be provided for STP and MPS.
Sr.
No.
Item of work Work
1 Personal Computer in
PLC/Control Room
2 Nos. of latest version & configuration complete.
2 Printer in PLC/Control
Room
1 No. of A3 Size Laser colour Printer of latest
version & configuration complete.
3 Telecommunication
Facility
Min. 1 No Telephone Line with a Broad Band
facility. The chargers will be borne by the
Contractor up to the O & M Period.
4 Plant Model 1 No. Wall Mounted Process Model ( Display
Model) with Flow Diagram (Minimum size 3 m
x 1.5m)
1 No. 3D Model with display of flow direction
and lighting.
5 Air Conditioner Adequate nos. of Air conditioners shall be provided
as directed by Executive Engineer.
Annexure-3 : Revised “ Volume-2(R1)”
98
6.10 Process piping / drain piping/ channels
This shall include inter connecting pipelines / channels between different units of
STP and fulfillment of contract limits.
All pipe networks shall be designed for peak flow.
Combination of pipes and channels can be used for conveyance of waste water
as per requirement of site conditions.
The sizes of pipes shall be calculated to meet following criteria:
Piping: Guide Line for Velocity
Notwithstanding the above, the Tenderer shall submit a Pipe Line Schedule with Tag
No., Flow, Size, Type, Material of Construction etc. with detailed P & ID for approval
of the Engineer-in-charge prior to any further engineering or procurement/fabrication
and installation.
Generally, the Material of Construction shall be selected based on the following
guide lines. The Tenderer can make suitable selection depending on Service, Type
of Flow (i.e. Gravity or Pressurized) and Diameter of Pipe.
Piping: Guide Lines for MOC
Sr. No.
Service Design Velocity m/s
Limitations
1 Gravity Lines for Sewage & Water
0.6 – 1.2 Designed as pipe line flowing full.
2 Pressure Lines for Sewage & Water
0.6 – 1.5
3 Air (Pressurized Lines) 12 – 18
4 Scum & Sludge Lines 0.6 – 1.5 Irrespective of flow, Diameter shall not be less than 150 mm for Gravity Lines.
5 Chemical Feed Lines 0.6 – 1.5 Irrespective of flow, Diameter shall not be less than 20 mm.
Sr.
No.
Service Type of Flow MOC
1 Waste Water / Sludge Gravity RCC NP-3 Class with HDPE lining
/ DI-K9 2 Waste Water / Sludge Pressurized CI / DI K-9
3 Service Water Gravity /
Pressurized
Inside Room – CPVC /MDPE / GI
Outside Room – DI for 80mm &
above/ GI for lower sizes.
Annexure-3 : Revised “ Volume-2(R1)”
99
Valve: Guide Line
Sr.
No.
Service Type MOC End
Connection
A Sewage / Sludge
1
Gravity /
Pressurized
Knife Gate CI Body & SS 304
Gate & SS 410
Spindle
Flanged
2 Delivery of Pump Swing Check CS Body & SS 304
Internals
Wafer
3
Suction & Delivery of
Pump
Knife Gate CI Body & SS 304
Gate & SS 410
Spindle
Flanged
B Service Water
1 Gravity /
Pressurized
Ball CS Body & SS 304
Internals
Flanged
2 Delivery of Pump Swing Check CS Body & SS 304
Internals
Wafer
3 Suction & Delivery of
Pump
Butterfly CI Body & SS 304
Internals
Flanged
C Air
1 Pressurized Ball CS Body & SS 304
Internals
Flanged
2 Delivery of Blower Swing Check CS Body & SS 304
Internals
Wafer
3 Suction & Delivery of
Blower
Butterfly CI Body & SS 304
Internals
Flanged
D Chemicals
1 (a) Gravity /
Pressurized
Ball As per Chemical
CompatibilityChart
Flanged
1 (b) Gravity /
Pressurized
Diaphragm As per Chemical
CompatibilityChart
Flanged
4
Air Lines: Headers,
Vertical Down-comers
Pressurized Above Water: MS "C" Class, Sand Blasted and Epoxy Painted
Under Water: SS 304
Under Ground : MS with Coating
and Wrapping
In Blower Room: Pipe Insulation
with Resin Bonded Glass wool in
Rigid Board. Kindly refer detail
Mechanical specifications.
5 (a) Air Grid Piping: Aeration
Zone
Pressurized UPVC Schedule 40
5 (b) Air Grid Piping:
Selector Zone
Pressurized SS 304
6 Chemicals Gravity /
Pressurized
SS 304 except Chlorine & FeCl3
7 Chlorine & FeCl3 Gravity /
Pressurized
Schedule 40 UPVC
Annexure-3 : Revised “ Volume-2(R1)”
100
Sr.
No.
Service Type MOC End
Connection
1 (c) Gravity /
Pressurized
Plug As per Chemical
Compatibility Chart
Flanged
Notwithstanding the above, the Tenderer shall submit a Valve Schedule with Tag No.,
Flow, Size, Type, Material of Construction, End Connection etc. with detailed P &ID
for approval prior to any further engineering or procurement/fabrication and
installation.
6.11 Security Cabins
Security Cabin with toilet of size 3.00 m x 3.00 m shall be provided at entry Gate of the
Plant. It shall be RCC (M25) Frame and Brick Masonry Structure equipped with Doors,
Windows/Ventilators, etc. complete. Also, it shall be provided with Flooring, Internal and
External Plaster with Painting and Plinth Protection along the periphery as per
specifications.
6.12 Site Development
Site development of whole land should be done by the bidder maintaining plinth level
around structures, top level of roads/pavements, lawns, landscaping etc. Lawns should
be 15 cm below top level of roads and pavements.
6.12.1 Roads & Pavement
Roads and pavement shall be proposed by the contractor, so as to access each and
every unit of the constructed works. These roads and footpaths shall be 4.2 m and 2.2m
wide respectively. The roads/pavements shall be made of paver blocks. Cement
Concrete Kerb & Channel (1:2:4) shall be provided on both sides of the road. The Kerb
& Channel shall be 30 cm x 60 cm x 10 cm. Dowel shall be provided on both side of the
road with earth filling in proper slope and compaction as per direction of Engineer-in-
Charge.
6.12.2 Sewerage System, Drainage System and Storm Water System
The waste water collected through down take pipes of grit chamber / screen channel,
inlet chamber and other units shall be carried through RCC Pipe / UPVC Pipe upto inlet
chamber of STP/MPS. This may require provision of pumping arrangement.
In addition to this the waste water of operation building shall also be carried to this
sewerage system. Provision shall be made for collection of sludge filtrate from sludge
platform and mechanical dewatering for its connection to proposed sewerage system.
The required no. of manholes shall be constructed as per drawing submitted by the
bidder and approved by Engineer-in-Charge before execution of the work. The bedding
and haunches of pipes shall be as per the specifications approved by the Engineer-in-
Charge.
The bidder shall also provide suitable arrangement for disposal of storm water of the
plant area.
6.12.3 Water Supply Arrangement
The bidder shall provide internal water supply scheme in the plant area. The main water
supply lines shall be of suitable size and of Ductile Iron (K-7) Pipe. However, service
Annexure-3 : Revised “ Volume-2(R1)”
101
connection to buildings / equipment / process units will be of MDPE/CPVC/ G.I. Class B.
The supply of water shall be made through small tube-well to be bored within the plant
area. The bidder shall have to provide complete water supply system including
underground water storage tank of suitable capacity (subject to minimum of 20 Cum)
and overhead tanks wherever required. The water supply system shall include making
provision of hydrants / nozzles for washing of the various units / pipelines. A booster
pump of suitable capacity shall be provided for pumping the water to above said units.
Provision for all required pipes, specials, overflow pipes and bell cock sluice valves shall
also be included.
a) Small Tube well: It shall consist of a bore of suitable size and depth with PVC casing pipe
/ filter housing a submersible pump set of suitable capacity complete in all respect for
pumping out water to meet the requirement of plant operation, watering of plants, cleaning
and staff requirement for daily use. Water should be suitable for construction and drinking
purposes.
6.12.4 Rain water harvesting
Roof top rain water harvesting is to be done for all the buildings. The system shall
confirm to the details and specifications in the relevant document published by Central
Ground Water Board, Ministry of Water Resources to be stipulated. The following
technical criteria, to be taken into consideration while designing rain water harvesting
system.
Hydrogeology of the area, nature and aerial extent of the acquifers
Nature and type of soil cover
Quantity and intensity of rainfall specially one hour peak rainfall
Clogging potential i.e. silt content of source water
Topography / applicable methods (infection or infiltration)
All recharge structures shall be designed based on availability of space, run off, depth of
water table and lithology of the area.
General methods to be adopted are described below:
Rain water from roof of building should be collected at one or more places through rain
water drain pipes extended up to the bottom of the building. Then collected water should
be diverted into a sump called filter chamber of required size and from sump to
recharging pits or other components through RCC pipe of required size and thickness /
strength. The bottom half of the filter chamber has to be filled with broken bricks /
pebbles and followed by a layer of coarse sand. A nylon mesh has to be provided in
between the two layers. The top portion of filter chamber should be covered with RCC
slab. The inlet rain water drain pipe should be on the top of the filter chamber and outlet
pipe connecting the filter chamber to the recharging structure should be at the bottom.
One filter chamber should not be connected to more than 22 square meter area of roof
of any building. The rain water then should be diverted towards recharging structure
which may be of following types.
A. Recharging Pits
In alluvial area where permeable rocks are exposed on the land surface or at very
shallow depth, roof top rain water harvesting can be done through recharge pits.
This technique is suitable for buildings having a roof area of 100 square meters and is
constructed for recharging the shallow aquifers.
Annexure-3 : Revised “ Volume-2(R1)”
102
Recharge Pits may be of any shape and size and shall generally be constructed 1 m
to 2 m wide and 2 m to 3 m deep which shall be back filled with boulders (5-20 cm),
gravels (5-10 mm) and coarse sand (1.5-2 mm) in graded from-Boulders at the
bottom, gravels in between and coarse sand at the top. For smaller roof area, pit may
be filled with broken bricks / cobbles.
A mesh should be provided at the roof so that leaves or any other solid waste / debris
is prevented from entering the filter chamber / pit.
B. Recharge Trench
Recharge trenches are suitable for buildings having roof area of 200-300 square
meter and where permeable strata are available at shallow depths.
Trench may be 0.5 to 1 meter wide, 1 to 1.5 meter deep and 10 to 20 meter long
depending upon availability of water to be recharged and available land.
These recharge trenches shall be back filled with boulders (5-20 cm), gravels (5-10
mm) and coarse sand (1.5 to 2 mm) in graded form- boulders at the bottom, gravel in
between and coarse sand at the top.
A mesh should be provided at the roof so that leaves or any other solid waste / debris
is prevented from entering the filter chamber / trench.
C. Trench with recharge well
In areas where the surface soil is impervious and large quantities of roof water is
available within a very short period of heavy rainfall, the use of trench / pits is made to
store the water in a filter media and subsequently recharge to ground water through
specially constructed recharge wells.
This technique is ideally suited for areas where permeable horizon is within 3 m
below ground level.
Recharge well of 100-300 mm diameter is constructed to a depth of at least 3 m to 5 m
below the water level. Based on the lithology of the areas, well assembly should be
designed with slotted pipe against the shallow and deeper aquifer.
A lateral trench of 1.5m to 3m width and 10m to 30m length, depending upon the
availability of water is constructed with the recharge well in center.
The number of recharge wells in the trench can be decided on the basis of water
availability and local vertical permeability of the soil.
The trench is backfilled with boulders, gravels and coarse sand to act as a filter media
for the recharge wells.
If the aquifer is available at greater depth say more than 20m, a shallow shaft of 2m to
5m diameter and 3-5 meters deep may be constructed depending upon availability of
runoff. Inside the shaft a recharge well of 100mm-300mm dia. is constructed for
recharging the available water to the deeper aquifers. At the bottom of the shaft a filter
media is provided to avoid choking of recharge well.
Bye-pass arrangement with provision of suitable valve shall be installed in the rain
water drain pipe just before every filter chamber to reject the first shower.
Annexure-3 : Revised “ Volume-2(R1)”
103
6.12.5 Disposal of treated effluent
6.12.5.1 Treated Effluent Channel / Pipe
The treated effluent after disinfection is to be either used for irrigation or disposed of
into the adjoining drain. Hence bifurcation chamber of suitable size with 2 control gates
and weirs is required to regulate the flow as per irrigation demand. The carrying system
can be either a RCC Channel or pipe. The pipe can be RCC with HDPE lined.
In case provision of secondary pumping station is required to pump the treated waste
water into the drain or achieve water level as prescribed elsewhere in the bid
document, the necessary arrangements like construction of sump, pump chamber,
suction and delivery mains, control valves / gates and all electrical mechanical systems
shall also be in the scope of work.
6.12.6 Miscellaneous
6.12.6.1 Stairs
RCC / MS staircase (minimum 1.2 m wide) shall be provided to access all the platforms
provided/required for all the units above ground level. The tread shall be 250 mm and
rise shall not exceed 175 mm. The width of the staircase and their type shall be as
approved by Engineer-in-Chief before execution of the work.
6.12.6.2 Railings
Railing shall be provided along all the platforms above the ground level and staircases.
The railings shall consist of three horizontal rows of 40 mm i/d GI pipe, Class B
supported on CI pedestals 1 m high fixed at interval of 1.5 m c/c.
6.12.6.3 Painting, Whitewashing and Allied Works
Operations Buildings
All the units/items/equipment of the Operations Building shall be painted/coated
wherever required. All the internal surfaces of the walls and ceiling of buildings shall be
painted with plastic emulsion paint. All the external surfaces of operations building shall
be cement based paint.
Water Retaining Structures
The inner concrete surfaces of all the water retaining structures including channel shall
be painted (two coats) with approved make anticorrosive/epoxy paint.
Pipes and specials
All the MS / CI / DI pipes and specials and other equipment shall be painted with two
coats of approved make anti corrosive paints.
6.12.6.4 Lowering of ground water table during construction
The ground water table, if encountered, during construction shall be lowered sufficiently
so as to enable construction in dry conditions
6.13 Electrical & Instrumentation Works
It shall be the Contractor’s responsibility to obtain adequate incoming HT power from
State Electricity Authority (PSPCL) based on total plant load and as per PSPCL norms.
Annexure-3 : Revised “ Volume-2(R1)”
104
The Employer will pay the charges for obtaining the above connection whereas
necessary liasoning for the same shall be done by the Contractor in consultation with
Engineer-in-charge.
Two nos. Transformers, 1 each for STP and Pumping Station of full capacity and as
per PSPCL norms shall be provided. These shall be step down Transformers
suitable for outdoor installation and as per specification given in Volume-2 Part-4.
The entire Plant shall be operated on 415 V, 3-Phase, 50 Hz, 4-Wire system. The
Contractor’s Scope of Work shall include the following:
Obtaining incoming HT Power from PSPCL including necessary liasonoing,
documentation etc. complete.
HT Cable with Termination Kit from “Source” to the Electrical HT Substation
located at the Sewage Treatment Plant.
HT Substation including 4-Pole Structure, HT Panel, Transformers, Power Control
Centre with APFC Capacitor Panel etc. complete.
Motor Control Centres.
Silent DG Set with AMF Panel & other accessories for entire load of STP and
average flow plus other misc. load of MPS.
LT Bus-Duct
Power, Control and Instrumentation Cables including trays, ducts, support etc.
ACDB, DCDB, Battery & Battery Charger, UPS
Earthing for Electrical equipment as well as Instruments, PLC/SCADA.
Lightening Protection
Complete Indoor & Outdoor Lighting System.
Local Control Panel, Field JB, welding receptacles.
Local Push Button Stations near respective Drives.
Fire detection & Alarm system, plant communication.
Flow Meters at inlet, outlet & by-pass.
Level Transmitter, DO Transmitter, Pressure Gauge, Auto Valves
Online Monitoring System for raw and treated sewage quality.
CCTV System
Safety items (shock treatment chart, first aid box, CO2 fire extinguisher, insulating
mat, hand gloves, caution boards, LED signage, sand buckets, discharge rods
etc.)
All civil works required for complete installations.
Any other item / accessories required as per process requirement and for
successful completion of the Project.
The Contractor shall design/execute the System as per specifications (Volume-2 Part-
4), I.E. Rules and Regulations, requirements of PSPCL and other local Authorities
and actual site conditions.
Also, the Contractor shall provide PLC/SCADA based Automation for entire plant as
described in below clause.
6.14 PLC/PC/SCADA Based Automation System for entire plant
The complete Plant shall be designed for automatic operation through Programmable
Logic Control (PLC) and Supervisory Control and Data Acquisition (SCADA). This
shall be achieved by either individual equipment PLCs with SCADA/HMI or single
Annexure-3 : Revised “ Volume-2(R1)”
105
PLC and SCADA for entire Sewage Treatment including pumping stations. Operation
of primary treatment units and sludge dewatering units shall be manual however
indication of operation of primary treatment units and sludge dewatering units shall be
on PLC/SCADA. These shall be located at control room of the STP.
The plant shall have provision for operations in following modes:
Automatic – Auto operation through PLC/digital controller.
Manual – Operator intervention through SCADA/HMI.
Local – Local operation through local control panel located near equipment.
a) Audio Visual Alarms
Audio visual alarms shall be initiated under emergency or equipment trip conditions,
other than usual service alarms. Salient features of the proposed control system shall
be as follows:
Dynamic display of all Units, equipment and drives shall be available on SCADA
screen.
It shall Acquire, process and manage the processed data.
It shall safeguard the process by means of interlocks and alarms.
Auto/Manual operation of each drive shall be made by selecting a soft switch on
SCADA/HMI screen.
In Auto mode, each drive shall operate based on pre-set sequence and interlock.
Also automatic change over from working to standby drive shall happen after a
drive reaches pre-set hours of operation.
In Manual mode, each drive shall be operated in Local/Remote mode by selecting
a soft switch on SCADA/HMI screen. In Local mode, each drive shall be operated
from the Local Push Button Station (LPBS) located nearby. In Remote mode,
operation from LPBS shall be disabled and each drive shall be operated manually
from PLC. Also provision for working/standby selection of drives by selecting a soft
switch on SCADA screen shall be provided.
Run/Trip indication of all drives shall be displayed on SCADA/HMI screen.
Open/Close indication of all Auto Sluice Gates and Auto Valves shall be displayed
on SCADA/HMI screen.
Annunciation & Alarm facility shall be available in PLC/HMI/SCADA. In the event of
a Fault, the symbol representing the equipment/drive shall continue flashing on
SCADA/HMI screen with equipment/drive description appearing at bottom of the
SCADA/HMI screen and electric Hooter shall continue blowing until the Fault
Alarm is acknowledged.
Data logging of Running Hours of each drive, Alarms, Historical Trends of
monitored Parameters, etc. shall be envisaged in SCADA.
Report generation for plant performance.
The process system must have pre-configured software packages which can be
adapted to the process by parameterization.
The monitor images must be designed to be user-friendly by hierarchical breakdown
with the possibility of selective display and optimum selection possibilities.
Changing of parameters and other software units must be possible "online", i.e. with
the system running.
Annexure-3 : Revised “ Volume-2(R1)”
106
Different alarms colors provide information on their priorities.
For the system engineering offered, the Contractor must take measures, e.g. by the
installation of surge voltage arresters or surge voltage filters, to ensure that internal
and external surge voltages do not impair the function of his parts of the system.
The programs and data entered must be backed up in a non-volatile read-only
memory.
A limit value and plausibility check must be provided in the software of the process
station for the measured values and messages. Exceeding of limit values or
deviations detected by the above checks must trigger an event and cause a message
to be sent.
Further demanded features of the process system:
Integrated, detailed error message and fault detection concept with display on the
HMI/SCADA for quick localization of faults. The system operator must be able to
identify the fault from the error.
Essentially maintenance-free
Robust against external interferences of all kinds
Proven design and solder-free connection technique
Protection of the equipment against surge voltages
Automatic fault detection and quick troubleshooting in the PLC system by
integrated, hierarchically structured diagnostic devices
Power supply in wide admissible voltage range
Simple function-oriented operation
The process system (PLC, HMI/SCADA) shall be protected against power failure by
an uninterruptible power supply (UPS). When the critical charge state of the UPS is
reached, the process system is automatically shut down.
b) Mode selector switch
A mode selector switch is to be installed on the MCC or distribution board. It serves for
pre-selection between Automatic mode and Manual/Local mode.
The following switching functions must be provided:
Automatic – Manual/Local
Automatic: In this position, only automatic operation is possible; the local switches
have no function (Except emergency stop).
Local: Automatic mode cannot be started. The drives can be operated individually
without interlock with the local switches.
Local switches (LPBS)
Each drive must be equipped with a local switch positioned in such a location that the
corresponding machine or conveyor can be switched on in Manual/Local mode and can
be monitored visually at all times.
The local switch must have the following switching functions:
START – STOP (for drives with one direction of rotation)or
FORWARD – STOP - REVERSE (for reversible drives)
Annexure-3 : Revised “ Volume-2(R1)”
107
If a unit has several drives (e.g. conveyor belt drive and travel drive), the local
switches should be installed if possible in one switch box or at least installed next to
one another.
Each local switch must be adequately labelled in plain text so that no operator errors
can occur.
c) PLC
The automatic start-up of the whole system, sequential operations and the automatic
shutdown, allowing for external control influences, e.g. EMERGENCY STOP, etc., is
performed by programmable logic controller (PLC).
This performs not only the control of the system, but also the display of the operating
state in the HMI/SCADA.
The interlocks of the individual process groups and their signalling must be performed by
the PLC.
A system must be selected which is sufficiently protected against external interference in
the supply, control and signalling lines. The aim is that the program can continue to run
without fault signals in the event of transient earth faults in the supply grid. In the event
of prolonged power failures, on the other hand, a controlled restart must be triggered
(under-voltage trip of the non-automatic circuit breaker).
PLC Specifications: Technical
The PLC shall be non-redundant.
PLC of individual equipment shall be selected to carry out necessary operations
without overloading the PLC memory.
The PLC shall have adequate I/O per card.
There shall be 15% spare I/O of each type.
The CPU shall not be loaded more than 60% of its capacity.
Retentively shall be 100% to save the recorded data and saving the programmed
logic, other attributes connected with system for power & system failure.
Change in programme / modifications to programme shall be possible by a portable
laptop.
It is preferred to have all PLC’s in the plant from same manufacturer.
HMI/SCADA system
The HMI system shall be designed as a minimum 6”, colour, touch-screen on the
panel. Whereas SCADA system must be computer based.
All displays must be designed by the Contractor with graphic sophistication and all
texts in the visualization system must be displayed in English.
A sub-menu for each operating mode and further menus for editing the system
parameters, fault archive, etc., must be developed. It must be as simple as possible to
switch between the various menus and to edit the system parameters.
When designing the user interface or the assignment of the function keys, attention
must be paid that the function key assignment remains the same in all sub-menus so
that it is possible to jump to another menu without first having to jump back to the main
menu.
It must be possible to edit the following parameters at the touch-panel and SCADA:
Operating mode
Changes in the speeds of frequency converter-controlled equipment
Start-up times
Annexure-3 : Revised “ Volume-2(R1)”
108
Shutdown times
Duration of the operation of warning devices
Limit values for sensors, etc.
Faults, level messages, pressed EMERGENCY STOP buttons, etc., must also be
clearly displayed at the bottom of the screen, irrespective of the selected screen page
or sub-menu.
It must be possible to output all important menu items to the printer. The corresponding
interfaces must be provided.
The display of the function plans, images, etc. is affected in direct dialog with the
system by means of the mouse and keyboard.
The central SCADA shall generate various reports to analyze plant performance. The
process is documented via the laser printer.
d) Computer hardware and software
All programs required for operation of the system must be correspondingly compatible.
The corresponding licenses must be supplied for the standard programs. The operating
systems must be agreed upon with the Client. Minimum requirements shall meet:
CPU
1. Processor Intel i 7 10th Gen
2. Processor speed 4 GHz or higher
3. Configuration Tower
4. Architecture 64 bit
5. System memory
(RAM)
16 GB
6. Hard disk 256 GB SSD+ 1 TB HDD
7. DVD Drive Combo (Read/Write)
8. Operating system Microsoft Windows 10 professional
9. Communication
ports
USB – 4 Nos., Ethernet – 1 Nos.
10. Graphic
accelerator
2 GB
11. Power supply 240V, 50Hz, 1Phase
12. Keyboard Internet Keyboard (with USB interface)
13. Mouse Optical, 3 buttons (with USB interface)
Monitor
14. Type Full HD LED color monitor
15. Screen size 24” or higher
16. Resolution 1920 x 1080
17. Power supply 240V, 50Hz, 1Phase
Complete Project shall operate in auto mode. As a minimum, following controls
must be considered in Bidder’s Control Philosophy:
1. Coarse screens
Each mechanical coarse screen shall be installed with ultrasonic differential level
transmitter / level switch, across it; the same shall be operated on the basis of set
Annexure-3 : Revised “ Volume-2(R1)”
109
differential level in SCADA. Also if differential level is not reached for certain time
period, the screen shall be operated on the basis of set time in SCADA.
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA. In manual mode the screen operation will be done from SCADA screen.
Physical switch over of screens in plant will be done by operator using manual
gates.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered
in PLC for auto operation of coarse screen.
2. Raw Sewage Sump and Pumps
The sump will employ an Ultrasonic level transmitter to measure level. The
combined operation of Raw Sewage Pumps will be dependent on rate of change
of level with reference to time. The selection of Auto/Manual and Working/Stand-
by shall be made available in SCADA. In manual mode the pump Start/Stop will
be done through SCADA screen.
A clamp on type Ultrasonic or Electromagnetic flow transmitter shall be provided
at common header of pumps for measurement of flow to sewage treatment plant.
PLC shall calculate instantaneous flow as well as cumulative flow, both shall be
displayed on SCADA.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered
in PLC for auto operation of Raw Sewage Pumps.
3. Inlet chamber
A clamp on type Ultrasonic flow transmitter shall be provided on rising main of
inlet chamber for measurement of flow coming to Sewage Treatment Plant. PLC
shall calculate instantaneous flow as well as cumulative flow, both shall be
displayed on SCADA.
4. Fine screens
Each mechanical fine screen shall be installed with ultrasonic differential level
transmitter / level switch, across it; the same shall be operated on the basis of set
level in SCADA. Also if level is not reached for certain time period, the screen
shall be operated on the basis set time in SCADA.
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA. In manual mode the screen operation will be done from SCADA screen.
Physical switch over of screens in plant will be done by operator using manual
gates.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered
in PLC for auto operation of fine screen.
5. Grit Chambers
Each grit chamber will consist of Detroiter (1No.), Organic Return Pump (1No.)
and Screw Conveyor for grit removal (1No.). As such Detroiter, Organic Return
Pump and Screw Conveyor will not have auto operation; these will be started and
stopped from SCADA screen as required.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC
for operation of Grit chamber equipment.
Annexure-3 : Revised “ Volume-2(R1)”
110
6. Any Biological Unit
Complete operation and control of plant will be done through a separate PLC and
SCADA. However it shall have necessary inputs and generate required outputs to
operate in co-ordination upstream and downstream units of balance plant.
Alternatively contractor may provide single PLC and SCADA for entire Sewage
Treatment Plant.
Necessary interlocks, controls, alarms, report generation, etc. shall be
considered.
Each reactor shall be equipped with Level Transmitter, DO Transmitter for
monitoring and recording of critical operation parameters through SCADA.
7. Sludge sump and pump
An ultrasonic type level transmitter shall be used for measurement of level in
sludge sump.
Screw pumps/ Reciprocating will be used to feed sludge to mechanical
dewatering unit. These will operate as per level in sludge sump.
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA for sludge pumps. In manual mode the Start/Stop of pump will be done
from SCADA screen.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC
for operation of chlorination system.
8. Chlorination tank
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA for booster pumps. In manual mode the Start/Stop of pump will be done
from SCADA screen. Though chlorinator will have standalone operation,
feedback for the equipment shall be taken to PLC and displayed SCADA for
monitoring purpose.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC
for operation of chlorination system.
9. Centrifuge/ Belt Filter Press
The drives and instruments of mechanical dewatering units shall be connected to
PLC for its auto operation. Starting of dewatering system will be a manual
process.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC
for auto operation of centrifuges.
Annexure-3 : Revised “ Volume-2(R1)”
111
7. Detailed Scope of Work for 225 MLD STP JAMALPUR
Design Requirement described here are in general for various works. However
specifications for only those Materials /Equipment/ Instruments shall be
applicable which are required or provided at site. If the specification of any items
are not described here then specifications as per the relevant IS code or
prevalent as per the department practice will be applicable as approved by
Engineer-in-charge.
7.1. Raw Sewage Pumping Station of 225 MLD Capacity at STP Premise
7.1.1. Components of Main Pumping Station
Civil Works
i. Receiving Chamber ii. Screening Channel iii. Wet well/Collecting Tank iv. Panel Room v. Roads & Pavements vi. Platform /Foundation for Diesel Generating Set & Transformer vii. Cable Trench, wire mesh around transformer viii. White washing/painting etc. ix. Hand Railing x. Pumping main from MPS to inlet chamber of STP xi. Valve chamber/platform to house common header, all valves, NRVs etc.
i) Receiving Chamber
The deep gravity outfall sewers will discharge the raw sewage into a Receiving
chamber. The function of the Receiving chamber is to distribute the flow to Screens.
The Receiving Chamber shall be designed for peak flow. The Receiving chamber
shall consist of sluice gates on upstream for flow regulation. The receiving chamber
shall be of adequate size to meet the requirements of workability inside it. C.I gate
(Manually Operated) of suitable size shall be provided at the inlet of receiving
chamber. The entire construction is in minimum M-30 grade concrete and as per IS
3370. RCC access platform minimum 1200 mm wide with GI pipe railing as per
specifications shall be provided on one side of the chamber:
Average flow : 225 MLD
Peak factor : 2.0
Peak Flow : 450 MLD
Number of Units : 1 (One)
Min. Detention period : 30 Sec at Peak Flow
Min Free board : 0.50 m
ii) J Type Removable Bar Thrash Screens
Manual Trash screen to be installed in front of coarse mechanical screens to
prevent large and medium sized floating wastes from entering into intake structure
of pumping station.
The manual screen should comprise of flat bars spaced apart in vertical with 50mm
opening within a sturdy frame structure inserted in vertical guide channel. Structure
Annexure-3 : Revised “ Volume-2(R1)”
112
provided should be with perforated basket at its bottom and guide roller on both sides
for easy removal. Guide channel extend upto top of platform for guiding upward
movement. The height of trash screen should be 0.5 m above sewer crown. Material
of construction should be in SS-304. Flat size shall be of 10 mm thick 50mm wide.
Average flow : 225 MLD
Peak factor : 2.0
Peak Flow : 450MLD
Number of Units : 4 (Working) each of
25 % Peak Flow capacity
Velocity through Screen at Average Flow (m/sec):0.6 maximum
Velocity through Screen at Peak Flow (m/sec) : 1.2 maximum
Height of Mesh Screen : 0.50 m above sewer crown
Wheeled Trolley : 4 No.
All other accessories, whether specified or not, but required for completeness of
contract shall be in contractor’s scope. Railings shall be provided around the entire
periphery of the platform and structure.
The provision of EOT crane, any kind of cleaning/raking mechanism, collection
bins/portable screen container, water jetting arrangements & trolley etc. shall be
provided.
iii) Coarse Screen
Four mechanical screen working and two manual screen standby of 20 mm clear
spacing shall be provided with each screen designed for 25% of peak flow capacity.
The mechanical and manual bar screens shall be made of 10 mm thick Stainless
Steel (SS 304) flats respectively. The mechanical coarse screens shall be of Inclined
Rake Type of 20 mm opening as per the specifications detailed elsewhere in the
tender. Bin and chute arrangement shall be provided to take the screenings. The
screenings dropped from chute will be collected in a wheel burrow. Manually
operated CI gates are provided at the upstream and downstream ends to regulate
the flow.
Adequate RCC Platforms shall be provided at the upper level to enable operation.
Railings shall be provided around the entire periphery of the platform. The entire
structure is to be in minimum M-30 concrete and as per IS 3370 including the
platform. RCC staircase 1200 mm wide shall be provided for access from the ground
level to the top of the unit & to the operating platform.
Average flow : 225 MLD
Peak factor : 2.0
Peak Flow : 450 MLD
Flow MLD
Peak factor
J Type Manual Thrash Screen
Mechanical coarse
Screens
Manual coarse
Screens
1 Jamalpur 225 2 4 4 2
Number of Units : 4 Mechanical (Working) + 2 Manual
Annexure-3 : Revised “ Volume-2(R1)”
113
(Standby) each of 25% Peak Flow
Approach Velocity at Average Flow (m/sec) : 0.3
Velocity through Screen at Average Flow : 0.6 maximum
(m/sec)
Velocity through Screen at Peak Flow (m/sec):1.2 maximum
Height of Screen bars upto dead plate : 1 m above sewer crown
Wheeled Trolley : 2 No.
All other accessories, whether specified or not, but required for completeness of
contract shall be in contractor’s scope.
iv) Wet Well
The Main pumping station (MPS) shall be a rectangular concrete structure. The sump
well is to be in R.C.C of min Grade M-30 and shall be designed for peak flow. The
maximum operational liquid level in wet well shall be such that, minimum 100 mm
Freefall shall be maintained between Invert of Screen Chamber and Water level of wet
well. The capacity of the wet well sump should be kept such that the detention time of
the sump should be 5 minutes peak flow. The wet well shall be divided into two equal
compartments upto full height with sluice gates in common wall.
The pumps shall be installed equally in two compartments. Area of gate(s) should be
sufficient so as to divide the flow into any of the compartments, at a velocity not more
than 1.2 m/sec.
The arrangement of the Pumps shall be as per Manufacturer’s data i.e. Spacing
between the Pumps, minimum space between the Pump and Wall etc. Adequate
submergence of the pump shall be provided as per the manufactures
recommendations. The size of wet well shall be sufficient to accommodate one
additional pump in each compartment, in future.
RCC Staircase to be provided in each compartment of wet well from full supply level of
sump. Aluminium ladder (removable) from last landing of staircase to the bottom of wet
well.
IS: 3370 and IS: 4111 (Part 4) shall be followed for the design and construction of Wet
Well.
Basis for Design
All underground or partly underground liquid containing structures shall be designed for
the following conditions:
(a) Liquid depth up to full height of wall and free board. No relief due to lateral soil
pressure from outside to be considered;
(b) Reservoir empty (i.e. no liquid or any material inside the storage area): full lateral
earth pressure at rest due to surrounding saturated soil and surcharge pressure as
applicable, shall be considered;
(c) Partition wall between two compartments of wet well to be designed as one
compartment empty and other full;
Annexure-3 : Revised “ Volume-2(R1)”
114
(d) Structures shall be designed for uplift in empty conditions considering the depth of
the highest water table recorded in the area.
(e) Walls shall be designed under operating conditions to resist earthquake forces
developed due to mobilization of earth and dynamic liquid loads;
Underground or partially underground structures shall also be checked against stresses
developed due to any combination of full and empty compartments with appropriate
ground/uplift pressures on the base slab.
v) Sewage Pumps
Coarse-screened sewage shall be pumped from wet well. Pump operation shall be
automatically controlled based on wet well level. There will be high level and low level
alarm and tripping system installed. It will house non clog submersible pumps, which
will always be submerged in sewage with minimum submergence as required by the
manufacturer. Pumps will have automatic coupling arrangement at discharge end, a
guide pipe and chain for easy removal and lowering of pumps. Vibration shall be
limited as per BS 4675 Part I
Type of Pumps : Submersible type non-clog design
Liquid : Raw Sewage
Specific gravity : 1.05
Solid Passage Size : Maximum 100 mm.
No of working Pumps : 10 Nos.
Capacity of Pump : Peak flow/ No of working pumps
Standby Pumps : 50% of working pumps.
VFD for pump : 2 Pumps in each compartment is to have the
provision of VFD for flow variation
One electrically operated 3-way movement Trolley (EOT) having capacity equal to 1.5
times the weight of heaviest part to be lifted shall be provided over the sump well for
movement of pumps. The horizontal, transverse as well vertical shall be electrically
operated. The gantry is to be fixed on RCC framed structure and not on a cantilever arm
from columns.
vi) Rising main:
Sewage from wet well will be pumped to STP, through rising main of size suitable to
carry peak flow.
Material of rising main : Cement lined DI (K9) pipe
Size of rising main : Capable of carrying peak flow as specified in bid
document
Velocity in rising main at peak flow : Maximum 2.5 m / sec
vii) Piping & Specials
This shall include providing, laying, cutting, jointing, testing, etc. of pipes along with
specials:
Annexure-3 : Revised “ Volume-2(R1)”
115
(i) RCC Channels from inlet chamber of screens upto sump/ collecting tank.
(ii) DI K-9 Delivery line for individual pump upto common header.
(iii) Expander, Sluice valves, Bends, Non Return Valves in the individual delivery
of all the pumps. Tees and Sluice valve in the common header.
(iv) DI K-9 Common header upto Inlet of STP.
(v) The size of pipe shall be calculated so as to meet the following velocity
criteria:-
a. Minimum Velocity : 0.60 m/sec
b. Maximum Velocity : 2.5 m/sec
(vi) All other required fittings such as bends, tees etc.
(vii) Thrust block of M-20 grade, for support, etc.
(viii) Necessary by pass arrangement shall be provided to be used during the
shutdown of the plant. Pipe and Valve arrangement upto suitable discharge
point shall be provided.
viii) Painting, White Washing and allied works
The internal and external surfaces of the walls and ceiling of all building structures shall
be applied with two coats of Birla / JK Wall Putty followed by two coats of primer
followed by min two coats of first quality plastic emulsion paint.
All the structural steel, pipes, specials etc. shall have two coats of Epidec RTC Primer
followed by two coats of epoxy paint.
All the internal walls and base of water retaining structures of MPS shall be provided
with min two coats of coal tar epoxy.
ix) Roads & Pathways with proper drainage
Roads and Pathways shall be provided with interlocking paver blocks over 150 mm
thick and 100 mm thick respectively cement concrete of 1:4:8 in stone ballast.
Thickness of paver blocks on roads is 80 mm thick and on pathways the thickness of
paver blocks is 60 mm. Paver blocks shall confirm to specification of code IS 15658
Paver blocks will be ISI Marked.
x) MPS Panel Room
It shall be RCC framed structure and 3.5 m clear height. It shall house panels of MPS
pumps, screens, sluice gates, valves etc. It shall also house PLC Panels and HMI
screen for display of various parameters of MPS. Preferably the MPS panel room
building is to be adjoining to the administrative building of STP so as to have a better
monitoring.
Local Push Button Station (LPBS) shall be provided near each Pump set/ Motor for
emergency stop and start thereof. LPBS shall have Start/Stop push button with
Local/Remote Selector Switch. Each push button shall have 2NO+2NC contact for
interlocking purposes. The stop push button shall be mushroom type with stay put
feature and lockable in pressed position to avoid accidental operation of drive from
MCC, PLC during shutdown.
LPBS shall be suitable for use in outdoor open locations with minimum IP-55 degree of
protection and rain canopy.
7.1.2. Mechanical Works
Annexure-3 : Revised “ Volume-2(R1)”
116
i. J Type Manual Coarse screens, Manual and Mechanical Coarse Screen, Belt Conveyor for screens
ii. CI Sluice Gate shall be provided at following locations for flow control
a) Inlet of Receiving Chamber – 1 no. b) Upstream of coarse screens of MPS – 6 Nos c) Downstream of coarse screens of MPS – 6 Nos d) RCC Partition Walls of Wet Well – 1 No e) Any other gate as required
iii. Non clog Submersible Centrifugal Pumps sets with motor iv. Piping works, Dismantling Joint, NRV, Sluice Valve with appurtenance v. Lifting Arrangement –Monorail with electric horizontal and vertical operation
7.1.3. Electrical, Instrumentation & Control Works
i. HT VCB Panel ii. Transformer ONAN with on load tap changer iii. Silent Diesel Generating Set with AMF Panel suitable for average flow plus
other miscellaneous load. iv. Electrical Panel with
a) Incomer for normal & DG supply & interlocks power analyzer, surge protection device
b) Individual Starter Panels with VFD and soft starters for pumpset c) Automatic Power Factor Control (APFC) Capacitor Panel d) Alarm Annunciation Panel e) Feeder for other loads f) Interface with PLC & SCADA compatibility
v. HT & LT Cable, Instrument & data cable vi. Cabling system vii. Earthing & Lightening Protection viii. Lighting System (Indoor & Outdoor) ix. Junction Box for cables x. UPS for PLC xi. Instrumentation & Control
This includes supply, erection, testing and commissioning of various instruments &
control system. Brief details are as under:
S No Instrument Location Quantity
1. Differential Level sensor / Transmitter
Mechanical Coarse Screens As required
2. Pressure gauge Common discharge header of non-clog sewage pumps/Rising main
1
3. Radar Type level transmitter (non-contact type)
Main Collection Sump ( For level Status & level based control)
2
4. Programmable Logic Controller (PLC)
Panel Room 1
5. Any other Item As per requirement As per
requirement
PLC for MPS shall be as per control philosophy & specification.
PLC shall operate pumps based on pre-set levels of sewage in collection tank and
Annexure-3 : Revised “ Volume-2(R1)”
117
VFD operation. At mid-level of sewage, number of pumps as per average flow shall
operate, whereas at high level, number of pumps as per peak flow shall operate. At
low level, all pumps shall stop. Provision shall be made to operate all pumps in
rotation. Pumps operation shall be closely co-ordinated with STPs sewage
requirement through STP PLC/SCADA
PLC cum Instrumentation Control Panel shall be provided with 6” HMI to enable
level based operation of pumps and display of level and flow.
Provision shall also be made for display of level and flow in STP, SCADA Room.
Single PLC for MPS and STP is preferred. Contractor is free to provide separate
PLC for MPS.
PLC to have provision for exporting data to external device.
7.2. STP i) Flow Measurement
Flow measurement shall be done online using an ultrasonic flow meter on the rising
main of raw sewage pumping station located at STP area.
ii) Inlet Chamber
Inlet Chamber will receive raw sewage from the raw sewage pumping station.
Number of Units : (1) One
Min. Detention period : 30 sec on peak flow
Min free board : 0.5 m
Following provisions shall also be to be made as per detailed design:
CI/DI double flanged Puddle Collar
CI/DI double flanged Vertical Pipes
1 no. CI /DI double flanged Sluice Valves
CI/DI Horizontal pipe having length as per Site Requirement.
Minimum 150 mm i/d CI/DI pipes along with sluice valves for scouring
purposes.
iii) Screening Chamber
Four mechanical Step/MATT type screen (working) with two manual (standby)
screens are proposed in the screen chamber. The screen channels shall be
designed for peak flow.
RCC Platforms minimum 1.2 meter wide with GI railing shall be provided at suitable
level and location to enable operation of the units.
The component / unit shall be designed for following:
Number of Units : 4 Nos. Mechanical Working + 2 No.
Manual Standby each of 25% peak flow.
Approach Velocity at Average Flow
(m/sec.)
: 0.3 minimum
Velocity through Screen at Average
Flow (m/sec.)
: 0.6 maximum
Velocity through Screen at Peak Flow : 1.2 maximum
Annexure-3 : Revised “ Volume-2(R1)”
118
(m/sec.)
Free board : Min 0.5m on upstream side of the screen
at maximum water level
Minimum Length : 6 m
Flow
(MLD)
Peak
factor
Mechanical Screens
Manual Fine
Screens
1 Jamalpur 225 2.0 4 2
The entire construction shall be in minimum M-30 grade reinforced cement concrete
and as per IS 3370. RCC Platform/Walkway, minimum 1.20 m wide with G.I Hand
Railing as per specifications shall be provided. RCC Staircase, minimum 1.20 m
wide with G.I. Hand Railing as per specifications shall be provided for access from
Finished Ground Level to the top of the Unit & to the Operating Platform/Walkway.
The clear spacing shall be 6 mm for Mechanical Fine Screen and spacing of 10 mm
for Manual Fine Screen. The Mechanical and Manual Screens shall be made of SS
304 flats (3 mm for Mechanical and 10 mm for Manual Screen).
Minimum 3mm thick panels of stainless steel 304 construction shall incorporate
6mm diameter perforations.
Conveyor Belt and Chute arrangement shall be provided to take the screenings.
Screenings dropped from Chute shall be collected in a wheel Burrow. Manually
operated CI/Aluminum Sluice Gates shall be provided at the upstream and
downstream ends to regulate the flow.
Detailed specifications of mechanical screen are given in Mechanical Section.
iv) Mechanical Grit Chamber
Mechanical grit chambers are proposed after fine screen units. The mechanical grit
chambers shall be Square Mechanical Detritus Tank.
Mechanical Grit Chambers with 50% standby and Manual Bypass Channel
(Standby) shall be provided after Fine Screen Channels. Each Grit Chamber shall
be designed for 1/6th of Peak Flow whereas Bypass Channel shall be designed for
1/6th of Peak Flow.
The entire construction shall be in minimum M-30 grade reinforced cement
concrete and as per IS 3370. RCC Platform/Walkway, minimum 1.20 m wide with
G.I. Hand Railing as per specifications shall be provided. RCC Staircase, minimum
1.20 m wide with G.I. Hand Railing as per specifications shall be provided for
access from Finished Ground Level to the top of the Unit & to the Operating
Platform/Walkway.
Each Grit Chamber shall have the following features:
One tapered Inlet Channel running along one side with adjustable
Influent Deflectors for entry of sewage into the Grit Chamber.
One tapered Outlet Channel for collecting the de-gritted sewage, which
overflow over an adjustable Weir into the Outlet Channel. It shall be
designed in such a way that no settling takes place in it.
One sloping Grit Classifying Channel in to which the collected grit shall be
classified.
Annexure-3 : Revised “ Volume-2(R1)”
119
The grit from Classifier shall be collected in a Wheeled Trolley.
A Grit Scraping Mechanism.
Material of construction of grit mechanism: SS 304
Screw Classifier or Reciprocating Rake Mechanism to remove the grit.
Manually Operated C.I. / Aluminum Sluice Gates shall be provided at
entrance of the Inlet Channel of the Grit Chambers as well as Bypass
Channel to regulate the flow.
No. of Units : Total flow in all working units equal to peak flow
Type : Mechanical
Size of grit particle : 0.15 mm and above
Specific gravity of grit : 2.65
Maximum Surface
Overflow Rate : 959 m3/m2/day
Free Board : 0.5 m min.
Side Water Depth : 0.90 m min.
Wheelbarrow : 6 Nos. minimum
All other accessories, whether specified or not, but required for completion of
Contract shall form the part of Bidder‘s Scope.
Proper bypass channel between the units shall be provided with a sluice gate at the
inlet.
v) Distribution Box/Splitter Box
A Distribution Box / Splitter Box shall be provided downstream of Grit Chambers
prior to Biological Reactors for uniform flow distribution to Biological Reactors. The
Distribution Box shall be equipped with suitable motorized Sluice Gates and outlet
Weirs.
vi) Biological Treatment
The bidder can adopt any suitable, sustainable & proven technology including SBR
& MBR with its variants for biological treatment of sewage.
Anaerobic Reactors
No of Reactors Suitable
Anaerobic Hydraulic Retention Time As per CPHEEO
Min. Liquid Depth of Reactor 5.0 mt.
Min. free board 0.5 mt.
Material of Construction -Civil R.C.C. (M-30) or higher
Mixers Suitable- SS 304 MOC.
Anoxic Reactors
Design Anoxic HRT As per CPHEEO
No of Reactors Suitable
Mixers Suitable- SS 304 MOC.
Min. Liquid Depth of Basin 5.0 mt.
Min. free board 0.5 mt.
Material of Construction -Civil R.C.C. (M-30) or higher
Annexure-3 : Revised “ Volume-2(R1)”
120
Primary Clarifier
No. of Units Suitable
Surface Loading Rate at Average flow 35-40 m3/m2.day
Weir loading rate at average flow 125 m3
/d/m2 (max.)
Area required per unit Suitable
Side water depth (upto top weir) 3.0 m (Minimum)
Material of Construction -Civil R.C.C. (M-30) or higher
Type of Mechanism Central Driven / Peripheral Type
Drive RPM As per manufacturer standard
MOC/Paint Wetted parts SS 304
Non Wetted Parts- MS/Epoxy Painted
Sludge Drain Valves (KGV)
Location At Sludge Removal pipe line
Size Suitable
Type Knife Gate Valves - Automatically
operated
7.3. Biological Reactors, Settling and Decanting System
Primarily treated sewage shall be fed into the Reactors for biological treatment to
remove BOD, COD, Suspended Solids, Biological Nitrogen and Phosphorous.
The Reactors along with provisions for sludge re-circulation, excess sludge disposal,
aeration system, settling, decanting and other operational requirements like
automation, level control, flow control, oxygen level control etc. shall be provided.
Number of Units : As per bidder design
Design parameters : All design parameters like, MLSS, HRT, F/M, DO
level, recirculation ratio etc. shall be as per CPHEEO
manual for the offered technology.
Free Board : Minimum 0.50 m
Aeration System : As per bidder design subject to CPHEEO guidelines.
Automation : Operation of the Reactors shall be fully automatic,
controlled through PLC.
Miscellaneous
requirements
: The treated waste water shall be available on
continuous basis.
The Reactors to treat design flow sewage
irrespective of flow variation pattern of inflow
sewage.
Any other
requirement
: As per bidder technology and design to meet the
desired outlet parameters.
Secondary Clarifier
No. of Units Suitable
Surface Loading Rate at peak flow 40-45 m3/m2.day for activated sludge
25-35 m3/m2.day for extended aeration
Annexure-3 : Revised “ Volume-2(R1)”
121
Weir loading rate at average flow 185 m3/d/m (max.)
Solids loading rate at peak flow 210 kg/d/m2 (max.) for activated sludge
170 kg/d/m2 (max.) for extended
aeration
Area required per unit Suitable
Side water depth (upto top weir) 3.0 m (Minimum)
Material of Construction -Civil R.C.C. (M-30) or higher
Type of Mechanism Central Driven / Peripheral Type
Drive RPM As per manufacturer standard
MOC/Paint MS/Epoxy Painted- Wetted parts SS 304
Sludge Drain Valves (KGV) of Secondary Clarifier or SBR Basins
Location At Sludge Removal pipe line
Size Suitable
Type Knife Gate Valves - Automatically
operated Return and Excess Sludge Sump with Pump House
Return Sludge Pumps
No. of Return Sludge Pump suitable
Capacity of Return Sludge Pump suitable
Type of Pump
Submersible Non-clog / Horizontal
Centrifugal Non-clog type
Pump Head As per hydraulic design
Valves at delivery, Suction and
common header lines
Knife Gate Valves - Electrically operated
Excess Sludge Pumps
No. of Excess Sludge Pumps suitable
Capacity and head of Excess Sludge
Pumps
suitable
The entire construction shall be in minimum M-30 grade reinforced cement concrete
and as per IS 3370. RCC Platform/Walkway, minimum 1.20 m wide with G.I Hand
Railing as per specifications shall be provided. RCC Staircase, minimum 1.20 m wide
with G.I Hand Railing as per specifications shall be provided for access from Finished
Ground Level to the top of the Unit & to the Operating Platform/Walkway. Plinth
protection along periphery shall be provided as per technical specifications.
7.3.1 Return Sludge and Excess Sludge Pumps
a. Return Sludge Pumps
Capacity and Head As per requirements
Type Submersible / Horizontal Centrifugal
Liquid Biological Sludge of 0.8 – 1% solids consistency
Specific Gravity 1.05
Solid size 40 mm (Maximum)
Temperature Min. 25 C
Efficiency more than 60%
Quantity 1 No. per Basin + 1 No. Store Standby
Annexure-3 : Revised “ Volume-2(R1)”
122
b. Excess Sludge Pumps
Capacity and Head As per requirements
Type Submersible / Horizontal Centrifugal
Liquid Biological Sludge of 0.8 – 1% solids consistency
Specific Gravity 1.05
Solid size 40 mm (Maximum)
Temperature Min. 25 C
Efficiency more than 60%
Quantity 1 No. per Basin + 1 No. Store Standby
7.3.2 Decanting Device
The Decanter Device shall be Moving Weir Arm Device of SS 304 with top
mounted Gear Box, Electric Drive, Scum Guard, Down comers, Collection Pipe,
Bearings.
Weir loading for each decanter shall not exceed 125 m3/m/hr of the inlet weir.
7.4. Aeration System for Selected Biological Treatment
Oxygen Required
BOD Oxidation Oxygen Requirement 1.2 x Inlet BOD Load
Nitrification Oxygen Requirement 4.56 x TKN Nitrification
Total Requirement BOD Oxidation + Nitrification Oxygen
Requirement
Oxygen Credit (from De-Nitrification)
Oxygen release during denitrification
= 2.86 mg O2/mgN
Max O2 credit of denitrification can
be only 50% of nitrification
Alpha value for Submerged Diffuser 0.65 (Maximum)
Beta value for Submerged Diffuser 0.95 (Maximum)
Fouling Factor for Diffuser 0.9
Oxygen Demand Safety Factor 5 %
Oxygen content in Air (by weight) 23%
Type of aeration Energy efficient diffused aeration
system.
Blower details:-
Type : Turbo Blowers
Capacity : As per design
Discharge Head : Suitable
No. of units : As per design requirement with 50% standby
All Air Blower shall be provided with VFD.
The operation of Aeration System shall include PLC based control. The
operation and speed of Air Blowers shall be automatically adjusted using
parameters like Oxygen required, Dissolved Oxygen and Temperature and
Liquid Level in the Rector such that the DO is supplied as per demand and
power utilisation for operation of Air Blowers is optimised.
Annexure-3 : Revised “ Volume-2(R1)”
123
The main Air Header/Ring Main shall be in MS as per relevant IS Code, painted
with corrosion resistant paint as per Manufacture’s recommendations. The Air
Header/Ring Main shall be supported on saddles at suitable intervals or shall
be protected against external corrosion in case laid below ground. The Sub-
headers distributing air to various locations shall have Auto Valves to facilitate
air switch over between different demand locations. The Sub-header shall
supply air to Fixed Type Diffuser Grids at various locations through vertical Air
Supply Pipes. These Air Supply Pipes above water level shall be in MS,
painted with corrosion resistant paint and below water shall be in SS 304. All
under water Lateral Pipes shall be of UPVC. Junctions between horizontal Sub-
header and vertical Air Supply Pipes shall be suitably protected against
corrosion due to dissimilar materials.
All other accessories, whether specified or not, but required for completeness
shall form part of Contractors scope.
The aeration facility shall be installed for average flow.
Fine Bubble Type, PU / EPDM Membrane Diffusers shall be acceptable with
minimum Membrane Diffusers to Floor Coverage Area of 5%. Diffusers shall be
submerged, fine bubble / fine pore, high transfer efficiency, low maintenance
and non-buoyant type. Diffusers shall be panel / Disc / tubular type. Complete
Diffuser as a unit shall be assembled at the manufacturing factory level. The
grid supports shall of adjustable type made of SS 304.
7.5. Tertiary Filtration System: Fiber Disc filter (FDF)
Tertiary Treatment Plant shall be designed for average flow and provided in the form
of Disc filters which shall consists of following:
• Civil (RCC) Tank to house the Fiber Disc filter
• Disc filter assembly with Filter Cloth
• Drive Assembly
• Backwash System
• Control panel & Instruments
The Tertiary Treatment Plant shall conform to the specifications as mentioned below:
Disc filter assembly with Filter Cloth:
Disc filter shall comprise multiple high strength and separable discs (proposed by
manufacturer). Each Disc shall be subdivided into smaller sections to constitute a
prefab disc frame (module) so as to ensure easy replacement and maintenance.
Each disc consists of multiple panels. In case of replacement of fiber cloth, the left
and right of the fiber cloth shall be replaced quickly without disassembling of
segments (Disc frames). Each disc shall be mounted on the centre drum by strap
band (steel band) for the exact roundness and it shall not be fixed by Stud bolts. The
additional sealing material shall not be needed for assembling of filter cloth to
segment and the fiber cloth itself shall be acted as the sealing material. Filter cloth
shall envelop some parts of backside of filter frame and the several springs shall be
used to fix the filter cloth. The drum shall be round type and shall have the enough
area in order to discharge the treated water without trouble. The material of the filter
cloth shall be polyester; the filter frame that fixes the filter cloth, the disc frame and
Annexure-3 : Revised “ Volume-2(R1)”
124
the segment cover shall be ABS resin. Central drum shall be SS304. Maximum
Filtration rate shall be 10-12 m3/m2/hr. Nominal pore size of filter cloth shall be
approx. 10 micron.
Filter shall be designed for average flow or decant flow whichever is higher. Suitable
no. of units shall be provided. Raw water shall flow into the respective Disc filter by
gravity. The structure shall ensure that Suspended Solids (SS) are filtered (treated)
from outside to inside of the filter cloth installed on both sides of the disc filter, and
that filtered water is discharged through the centre drum to the treated waterway.
Sr
No TECHNICAL DATA OF FILTER
12. Type of Disc filter Fully submerged outside to inside
type
13. Type of filter cloth Pile cloth with ABS frame
14. MOC of filter cloth Polyester
15. Nominal pore size, (microns) Approx. 10
16. Maximum Filtration rate (m3/m2/hr) 10 -12
17. Total reject and backwash % < 3
18. Backwash System Automatic Backwash system
based on time and level
19. Head loss across the disc filter unit
(mm) As per design
20. Thickness of drum 4 mm. (minimum)
21. MOC of Centre drum SS 304
22. Filtration mode Continuous
Drive Assembly:
Drive part of Disc filter shall be of Worm geared type with motor chain drive. The drive
comprises Drive Motor, Reduction Gears, Chain and Sprocket. Power shall be
transmitted by the SS 304 chain. A protective cover made of SS 304 shall be
equipped for the drive motor, reduction gear and the chain. The rpm of the disc filter
drive shall be adjustable by the inverter that is attached in the field control panel.
Backwash system
Cleaning device consists of Suction cleaning unit, which conducts the suction
cleaning in the each side of disc, the automatic valve and the suction cleaning pump.
Cleaning device shall clean the contaminated filter cloth thoroughly by the suction unit
on both sides of disc with automatic valve and suction cleaning pump which shall be
activated by the water level switch that contacts the water level raised with the
increase of the loss of head. Disc filter should be operated for filtration without the
stop during backwash and suction of sludge. Suction cleaning unit shall be made of or
the even cleaning efficiency without dead zone for all area of filter cloth.
Back wash Recovery system shall consist of flash mixer, Flocculator, Clarifier, Back
wash sludge sump. Sludge generated shall be dewatered using centrifuge. Overflow
from Clarifier shall be sent to FDF.
Annexure-3 : Revised “ Volume-2(R1)”
125
7.6. Disinfection System
Disinfection (Chlorination) Units
Disinfection (Chlorination) Units including Chlorination Tank and Chlorinator cum
Chlorine Tonner House shall be designed for Average Flow or Decant Flow
whichever is higher.
7.6.1 Chlorination Tank and Chlorinator cum Chlorine Tonner House
Treated sewage after filtration process unit shall be taken to Chlorination Tank by
RCC Channel/DI K-9 pipe. Gas Chlorine shall be added for disinfection at suitable
dosing rate. Baffle walls shall be provided in the Tank to facilitate hydraulic mixing of
treated sewage. The entire construction shall be in minimum M30 grade reinforced
cement concrete and as per IS 3370.
Design Flow : Average Flow or Decant Flow whichever is more
Number of Units : 1 No.
Hydraulic Retention Time : 30 Minutes (excluding Outlet Channel after Weir)
Free Board : 0.50 m min.
A Chlorinator cum Chlorine Tonner House shall be provided above/near Chlorination
Tank to house Chlorination Systems. It shall be RCC (M25) Frame cum Brick
Masonry Structure with Rolling Shutter, Windows & Ventilators, Electrical Hoist with
Electrical Travelling Trolley of minimum 3 Ton capacity or 1.5 times the weight of the
single Unit whichever is more to lift the Pumps/Chlorine Tonners and Safety
Equipment including Sand Buckets, Fire Extinguishers and Fire Alarms etc. Also it
shall be provided with IPS Flooring, Internal & External Plaster and Internal &
External Painting. Plinth Protection shall be provided along the periphery as per
specifications.
All other accessories, whether specified or not, but required for completion of
Contract shall form the part of Bidder’s Scope.
7.6.2 Chlorination System
Gas Chlorination System comprising Vacuum Chlorinators (2 Nos.), Water Feed
Pumps (2 Nos.), Interconnecting Piping and Appurtenances, Chlorine Gas Detector,
Empty Chlorine Tonners (Suitable for 15 days’ Storage) with Tri unions, Lifting Device
and Suspended Weighing Scale, Residual Chlorine Test Kit, Safety Equipment (e.g.
Exhaust Fan, Canisters, Gasmasks etc.), Mandatory Spares, Chlorine Leak
Detection and Chlorine Leak Absorption System including FRP Half Hoods, Caustic
Solution Tank, Caustic Recirculation Pump, Centrifugal Fan, Interconnecting Piping
and Ducts complete and other required ancillary shall be provided.
The system must have the provision for linking its operation to PLC of STP so
that quantity of chlorine usage can be varied automatically as per treated water
flow from filtration units.
Design Flow : Average Flow or Filtered Flow whichever is more
Type : Vacuum Type
Chlorine Dosing : As per process requirement subject to Infrastructure
arrangement for at least 5 ppm dose.
Quantity of Chlorinator : 2 Nos. (1Working + 1Standby)
Annexure-3 : Revised “ Volume-2(R1)”
126
All other accessories, whether specified or not, but required for completion of
Contract shall form the part of Bidder’s Scope.
Treated water after chlorination unit shall be disposed off in Buddha Nallah through
RCC pipe.
7.7. Sludge Handling System
7.7.1 Sludge withdrawal from various units.
Sludge withdrawal shall be either by gravity or through pumping. DI Pipes shall be
preferably used for transportation of sludge. Sludge withdrawn from various units shall
be collected in a single sludge sump and shall be fed to:
a. Gravity Thickener followed by Centrifuge dewatering machine
or
b. Combined Mechanical Thickener cum Belt Press.
7.7.2 Sludge Sump
Sludge sump shall be provided to collect the excess sludge from various units. There
shall be one common Sludge Sump. The Sump shall be equipped with coarse Bubble
Air Grid made from stainless steel pipes to facilitate mixing of contents of sludge sump
on continuous basis. Alternatively Submersible mixers of suitable numbers can be
provided
Number of Units : 1 (one) nos.
Free Board : 0.5 m
Capacity : Minimum 6 hr holding of average daily
sludge production
Minimum SWD : 3.0 m
7.7.3 Sludge thickener unit with Centrifuge
The Gravity RCC Sludge thickener unit(s) of suitable size shall be provided for gravity
sludge thickening to reduce the capacity of Centrifuge equipment. The excess sludge
from biological Reactors / settling tanks will be taken to thickener. Thickener is
expected to produce thickened sludge with minimum dry solid concentration of 3%.
Design criteria
1. Hydraulic loading As per CPHEEO Manual
2. Solid loading As per CPHEEO Manual
Continuous gravity thickener shall be
circular RCC units with minimum 3.0
m side water depth. Side depth shall
be based on three considerations.
Free board 600 mm
Sludge Thickener Mechanism
The mechanism shall comprise of the following main components of suitable size as per design requirements: All wetted parts shall be SS 304.
Bridge Superstructure spanning the tank diameter with central drive maintenance platform
Annexure-3 : Revised “ Volume-2(R1)”
127
Drive assembly complete with drive head, chain and sprocket, geared motor etc.
Feed Well Center Shaft Cone scraper Rake arms Tie rods for rake arms Plow blades & squeegees
Material of Construction Tank RCC Bridge MSEP Feed Well SS 304 Walkway MS Chequered Plate / Grating Handrail 40 mm i/d GI pipe, Class B Rake Arm SS 304 Vertical shaft SS 304
Blades SS 304 v-notch weir FRP / SS 304 Squeegees Neoprene Anchor Bolt SS 304 Fasteners- Under Water SS 304 Fasteners- Above Water GI / SS 304
Sludge dewatering mechanism can be centrifuge type or belt filter press type of suitable design and capacity.
7.7.4 Sludge Pumps
Sludge Transfer Pumps shall be provided to feed sludge to sludge dewatering units. The pump shall be suitable for handling biological sludge. All pumps including standby shall be installed.
Pumps Capacity and Head : Sufficient for handling total daily sludge in 22 hours maximum
Type : Screw Pump/ Reciprocating pump Liquid : Bio-sludge for thickener and dewatering
machine. Solid Size handling : 40 mm (Maximum) Specific Gravity : 1.05 Efficiency : More than 50 % Installation : Fixed Quantity : Minimum 2 no. (1W + 1S) for dewatering
mechanism feeding Minimum 2 no. (1W + 1S) for thickener feed
7.7.5 Centrifuge Units
The centrifuge shall be solid bowl centrifuge of co-current / counter current design. The
centrifuge shall have sufficient clarifying length and differential RPM so that separation
of solids is effective. The centrifuge shall have central lubrication system. The
centrifuge and its accessories shall be mounted on a common base frame so that
entire assembly can be installed on an elevated structure.
Suitable drive with V-belt arrangement and turbo-coupling shall be provided along with
overload protection device. Centrifuge shall be with SS-304 wetted parts.
Annexure-3 : Revised “ Volume-2(R1)”
128
Differential speed and bowl speed should be adjusted by changing the pulleys;
differential speed may be adjustable by use of epicyclical-gear. The bowl shall be
protected with flexible connections so that vibrations are not transmitted to other
equipment. The base frame shall be in epoxy painted steel construction and provided
with anti-vibration pads. All steps necessary to prevent transmission of structure borne
noise shall be taken. Adequate sound proofing shall be carried out.
A hoist shall be provided above centrifuge for maintenance purpose. The hoist shall be
such that it shall be possible to erect or de-erect the centrifuge while one centrifuge is
in operation.
Number of centrifuges : At least 2 Nos. (1W + 1 SB) Type : Horizontal Operating Hours : 22 hrs. per day maximum Mixing arrangement of Polyelectrolyte and sludge
: Online mixing
Dewatering polyelectrolyte dosing system is to be provided to dose poly electrolyte
solution to the incoming sludge at entrance to the centrifuge.
7.7.6 Combined Belt Thickener cum Belt filter press units
The Sludge Dewatering Device shall consist of combo units which includes Mechanical
Thickener and Belt Filter Press along with all appurtenances. It shall be designed to
adequately condition and dewater the sludge so that the dewatered sludge cake is
produced that easily discharges from the Belt Filter Press to collection trolley.
Flocculator arrangement in SS-304 of suitable capacity shall be provided at the inlet of
each Belt Filter Press for mixing of sludge and DWPE. All other accessories, whether
specified or not, but required for complete operation shall form part of contractors
scope.
Number of Belt filter press : Min 2 Nos (1 W + 1 SB)
Operating Hour : 22 hours per day maximum Design
Inlet Sludge Consistency : 0.8 -1.0 %
Outlet sludge consistency : Minimum 20%
Mixing arrangement of Polyelectrolyte and
sludge
: Online-mixing
Dewatering polyelectrolyte Dosing system is to be provided to dose Poly Electrolyte
solution to the incoming sludge at entrance to the belt filter press. The supernatant
from Belt Filter shall be taken by gravity to Wet Well of MPS/Inlet of STP. The pipes
below Ground shall be RCC NP-3, with HDPE lining, whereas the pipes above
ground shall be of SS-304. Combo unit including Mechanical Thickener and Belt filter
press shall be capable of handling sludge consisting of minimum 0.8% solids by
weight. The dewatered cake shall be based on minimum consistency of 20% by
weight dry solids. MOC shall be SS-304. General Equipment furnished and installed
under this section shall be fabricated, assembled, erected and placed in proper
operating condition in full conformity with the drawings, specifications, engineering
data, instructions, and recommendations of the equipment manufacturer, unless the
engineer notes exceptions.
Annexure-3 : Revised “ Volume-2(R1)”
129
Workmanship and design: All components of the sludge dewatering equipment
shall be engineered for long, continuous, and uninterrupted service. The unit shall be
fully enclosed “multi-stage” type comprised with three belts. Gravity section shall be
comprised with an individual speed variable gear motor. All bearings, electrical and
pneumatic components shall be located on periphery of the frame allowing easy
access for the operator for overhauls. Sufficient number of removable inspection
hatches shall be located on each side of the unit to observe the factions of the unit.
The sludge dewatering system shall consist of belt filter press (es) and all
appurtenances. Each belt filter press shall be a fully enclosed having monologue
frame construction, complete prefabricated unit consisting of at least a sludge
conditioning system, a gravity drainage section, a pressure section, a belt alignment
and tensioning system and a belt washing system. Only units having an effective belt
width of 1.0– 3.0 meter shall be considered acceptable under this specification. The
unit(s) shall be the “multi-stage” Belt Filter Press (es) type.
7.8. Manual and Auto Valves / Gates
The bidder shall have to provide required No. of valves operated manually as well as with automation for running of plant.
7.8.1 Chain Pulley Block, Mono Rail, Electric Hoists
Mono Rails This includes supply, erection, testing and commissioning of adequate capacity mono rails.
Lifting electric hoist arrangement for various unit of STP This includes supply, erection, testing and commissioning of lifting equipment with all accessories suitable in various units of the STP.
Sr. No.
Description of unit
Type of lifting Type of movements
5. Dewatering mechanism
Electric operated hoist
Two movements e.g. vertical, and Transverse
6. Sludge Pump House
Electric operated hoist
A chain pulley block of adequate capacity
7. Tonner shed Electric operated hoist
Two-way movements e.g. vertical, Transverse
8. Raw Sewage Pumping Station
Electric operated hoist
Three-way movements e.g. vertical, longitudinal and transverse
The above list is indicative. Actual required / Installation capacity of Electric Hoist,
shall vary as per process requirement, which shall be approved by Engineer-in-
charge.
Chain Pulley Blocks
This includes supply, erection, testing and commissioning of adequate capacity chain
pulley block with all the accessories. It should be compatible with the lifting chain of
the pump.
Annexure-3 : Revised “ Volume-2(R1)”
130
Chain Pulley Block of adequate Capacity : As per requirement
7.8.2 Sludge Pump House(s)
Pump house shall be near sludge sump. This shall be RCC frame and brick masonry
structure. Minimum height of the pump house shall be 4 m from the plinth level. It
shall be provided with rolling shutter and doors and windows. A chain pulley block of
adequate capacity along with girder and pillar arrangement shall be provided.
The pump house shall be painted from inside and outside with approved colour and
make as directed by Engineer-in-Charge. The pump house shall house:
Pumps for feed to dewatering mechanism (working + standby)
Air blowers for Sludge Sump (working + standby) or Submersible Mixers
DWPE dosing pumps (working + standby)
7.8.3 Chemical Dosing Tanks
Suitable number and capacity dosing tanks with required inner lining and agitators are
to be provided.
Polyelectrolyte Dosing System shall consist of Dosing Tanks equipped with Slow
Speed Agitators and Diaphragm type Metering Pumps. Polyelectrolyte shall be dosed
online at the inlet of Centrifuges. Minimum dosage of polyelectrolyte shall be 0.50 –
1.50 Kg/Ton of dry solids at 0.1% solution strength. The solution will be dosed using
mechanically actuated Diaphragm type Metering Pumps. Dedicated Dosing Pumps
shall be provided and shall be interlocked with Combined Mechanical Thickener cum
Belt Press /Centrifuge in such a way that they Start/Stop along with Belt Press /
Centrifuge.
Dosing Tanks:
Design Capacity : As per requirement
Number of Units : As per requirement
Hydraulic Retention Time: Suitable for min. 8 hours of Operation Free Board
Dosing Pumps : As per design.
Capacity and Head : As per requirement
Type : Mechanically Actuated Diaphragm Type Metering
Pump
Liquid : Polyelectrolyte Solution of 0.1%Strength
Quantity : one each per dewatering machine
7.8.4 Civil Structure for Mechanical De-watering including
Building of sufficient size to accommodate mechanical dewatering Units Combined
Mechanical Thickener cum Belt Press or Centrifuges (Working + Standby) shall be
constructed with sufficient floor height above Ground Level to park sludge collection
vehicle directly under the sludge discharge line of centrifuge. The room shall have a
RCC roof at a height suitable for installing EOT. Minimum floor area of the building
shall be sufficient to accommodate mechanical dewatering unit. It should be framed
RCC structure with the top roof also in RCC. The dewatered sludge shall have a
minimum solids concentration of 20% or more (measured as dry solids w/w basis) so
that it can disposed by open body Trucks/Trolleys.
7.8.5 Sludge Storage Platform
Annexure-3 : Revised “ Volume-2(R1)”
131
A sludge storage platform shall be provided at a suitable location within the plant area
for storage of de-watered sludge, minimum for a 7 days storage capacity. Flooring of
the platform shall be 75 mm thick PCC (1:2:4) laid over 100 mm thick stone ballast.
Level of platform shall be at least 20 cm above the level of approach road. From
sludge storage platform, the sludge shall be disposed of by the contractor.
7.9. Operations Buildings
7.9.1 Office, PLC Room etc.
The building shall be constructed to house the following as a minimum:
i. PLC/Main LT (MCC) Room –as required
ii. Office rooms for the officers and staff with Lavatory cum Toilet block of
required size/area along with sanitary fittings as decided by the Engineer –in-
Charge.
- One passage app. 2m wide.
iii. Workshop cum Tool Room
iv. Stair case up to terrace will be provided.
The height of ceiling shall be minimum 3.5 M from the floor level or higher to
suit the requirement. Adequate no. of toilets and wash basin shall be
provided separately for men and women and a separate toilet attached to the
office room shall be provided. A covered service water overhead tank of
capacity 5 cum shall be provided to cater to the water requirement of building
and process requirement.
Office Building/Admin Building Rooms
The Existing Administrative Block & laboratory for UASB based Sewage Treatment
Plant may be used after renovation/repair & painting.
7.9.2 Blower Room
Sufficient area blower room with a minimum clear height of 5.00 mtr shall be
constructed to accommodate all the blowers for biological Reactors and other
requirements. Minimum space on other three sides of blower room will be 1.5 m from
the blowers. The blower room shall have sufficient ventilation, lighting and working
space. Control panels for air blower shall be placed in air conditioned room, in
blower room, if required. The room will be equipped with sufficient capacity EOT
lifting arrangement to facilitate removal of blower/motor etc. for repairs. The room will
also have rolling shutter or aluminium glazed doors and windows.
7.9.3 Staff Quarters
The bidder shall have to construct two Nos. Single storey quarters for the operational
staff. The covered area shall have 80 m2 each. The provision in the staff quarter
consists of one bedroom, one drawing cum dinning, kitchen, store and toilet. The
construction material for walls shall be brick work in Cement Sand mortar 1:5, RCC
roof slab shall be (M 25). The door and windows shall be of commercial hollock wood.
7.9.4 Other Buildings
One toilet block for operators, one guard room with toilet and one meter room of
sufficient size as approved by Engineer-in-Charge shall be constructed.
Annexure-3 : Revised “ Volume-2(R1)”
132
7.9.5 Painting specifications common to all the buildings
Sr.
No
Description Specifications
1 Roof Water Proofing Brick Bat Coba
2 Plaster
i Walls inside Cement Mortar 1:4, 20 mm thick
ii Walls outside Cement Mortar 1:4, 12.5 mm thick
iii Roof including cantilevers Cement Mortar 1:3, 10 mm thick
3 Painting
i External Cement based paint
ii Internal Plastic emulsion
4 Dado/ Skirting Same material as on flooring 2.10 m high
in toilet block and 0.15 m high in all other
rooms / spaces
5 Doors / windows Aluminum
7.9.6 Schedule of Finishes
Sr.
No.
Unit Flooring Doors Windows /
Ventilators
1 MCC Room, PLC &
Control Room
Marbonite flooring of
approved make. The
size of Marbonite tiles
shall be min 600 mm
x 600 mm & thickness
min – 12 mm
Solid Core
Flush Door
with heavy
duty Brass
Fittings of
approved
make
Aluminium of
approved
make
2 Reactor Air Blower
Room, Workshop &
Tool Room, Chlorinator
cum Chlorine Tonner
House, Thickener
Dilution Water Pump
Houses, Electrical HT
Substation, DG House
IPS Flooring with
Abrasion Resistant
Additives of approved
make
MS Rolling
Shutter
of
approved
make
Aluminium of
approved
make
3 Centrifuge / Thickener
cum Belt Press House
Anti -Skid Tile
Flooring of approved
make
--- ---
4 Vehicle Parking Area Coloured Pre-cast
Heavy Duty Paving
Blocks with Lacquer
Finish
--- ---
5 Toilet Blocks Coloured Glazed Tiles UPVC of
approved
make
UPVC of
approved make
Annexure-3 : Revised “ Volume-2(R1)”
133
Sr.
No.
Unit Flooring Doors Windows /
Ventilators
6 Staircase: Inside
Building
Grey Granite Flooring
of approved make
--- ---
Adequate number of Toilets and Washbasins shall be provided separately for Men &
Women at each floor. A covered Overhead Tank of capacity 5 m3 shall be provided
along with an Underground Water Tank of capacity minimum 10 m3 to cater to the
water requirements of the Building
In addition, the Building shall be provided with Passages, Wooden/Aluminium/Glass
Doors / Windows / Ventilators and Safety Equipment including Sand Buckets, Fire
Extinguishers and Fire Alarms etc. Adequate Flooring shall be provided in various
Rooms/Areas as per requirement or as per instructions of the Engineer-in-charge.
Internal & External Plaster with Painting shall be done as per instructions of the
Engineer-in-charge. Plinth Protection shall be provided along the periphery as per
specifications.
The Building shall be provided with the following:
7.10. SUB STATION (HT METER ROOM, HT PANEL ROOM, TRANSFOMER, PCC &
MCC PANEL ROOM)
Two nos. Transformers, 1 each for STP and Pumping Station of full capacity and as
per PSPCL norms shall be provided at STP area.
The Electrical Substation shall be provided to accommodate components comprising
HT Panel, Outdoor Transformers, Power Control Centres etc. Outdoor Transformers
shall be installed in open adjacent to Sub-Station building covered with fence and
gate with fire wall between two transformers as per IE rules and PSPCL norms.
Location of HT Meter Room shall be as per PSPCL norms.
Sub-Station building shall be RCC (M25) Frame and Brick Masonry Structure
Sr.
No.
Item of work Work
1 Personal Computer in
PLC/Control Room
2 Nos. of latest version & configuration complete.
2 Printer in PLC/Control
Room
1 No. of A3 Size Laser colour Printer of latest
version & configuration complete.
3 Telecommunication
Facility
Min. 1 No Telephone Line with a Broad Band
facility. The chargers will be borne by the
Contractor up to the O & M Period.
4 Plant Model 1 No. Wall Mounted Process Model (Electronic
Plant Display Model) with Flow Diagram
(Minimum size 3 m x 1.5m)
1 No. 3D Model with display of flow direction
and lighting.
5 Air Conditioner Adequate nos. of Air conditioners shall be provided
as directed by Executive Engineer.
Annexure-3 : Revised “ Volume-2(R1)”
134
equipped with Rolling Shutters, Windows/Ventilators, Exhaust Fans and Safety
Equipment’s including Sand Buckets, Fire Extinguishers and Fire Alarms etc.
complete as per PSPCL norms and IE rules. Also it shall be provided with IPS
Flooring, Internal and External Plaster with Painting and Plinth Protection along the
periphery as per specifications.
DG Set Area
The DG Set area with shed, foundation for DG, Safety Equipment’s including Sand
Buckets and Fire Extinguishers shall be provided adjacent to Sub-Station building to
accommodate DG Set including AMF Panel, Fuel Tank and other Accessories. DG
Set shall cater to entire load of STP and average flow plus other misc. load of MPS.
Separate DG Set shall be provided for STP and MPS. Multiple units of DG sets can
be provided for STP.
7.11. Process piping / drain piping/ channels
This shall include inter connecting pipelines / channels between different units of
STP and fulfillment of contract limits.
All pipe networks shall be designed for peak flow.
Combination of pipes and channels can be used for conveyance of waste
water as per requirement of site conditions.
The sizes of pipes shall be calculated to meet following criteria:
Piping: Guide Line for Velocity
Notwithstanding the above, the Tenderer shall submit a Pipe Line Schedule with Tag
No., Flow, Size, Type, Material of Construction etc. with detailed P & ID for approval of
the Engineer-in-charge prior to any further engineering or procurement/fabrication and
installation.
Generally, the Material of Construction shall be selected based on the following guide
lines. The Tenderer can make suitable selection depending on Service, Type of Flow
(i.e. Gravity or Pressurized) and Diameter of Pipe.
Sr. No.
Service Design
Velocity m/s Limitations
1 Gravity Lines for Sewage & Water
0.6 – 1.2 Designed as pipe line flowing full.
2 Pressure Lines for Sewage &Water
0.6 – 1.5
3 Air (Pressurized Lines) 12 – 18
4 Scum & Sludge Lines 0.6 – 1.5 Irrespective of flow, Diameter shall not be less than 150 mm for Gravity Lines.
5 Chemical Feed Lines 0.6 – 1.5 Irrespective of flow, Diameter shall not less than 20 mm.
Annexure-3 : Revised “ Volume-2(R1)”
135
Piping: Guide Lines for MOC
Valve: Guide Line
Sr.
No.
Service Type MOC End
Connection
A Sewage / Sludge
1
Gravity /
Pressurized
Knife Gate CI Body & SS 304
Gate & SS 410
Spindle
Flanged
2 Delivery of Pump Swing Check CS Body & SS 304
Internals
Wafer
3
Suction & Delivery of
Pump
Knife Gate CI Body & SS 304
Gate & SS 410
Spindle
Flanged
B Service Water
1 Gravity /
Pressurized
Ball CS Body & SS 304
Internals
Flanged
Sr.
No. Service Type of Flow MOC
1 Waste Water / Sludge Gravity RCC NP-3 Class with HDPE
lining / DI-K9
2 Waste Water / Sludge Pressurized CI / DI K-9
3 Service Water Gravity /
Pressurized
Inside Room – CPVC /MDPE /
GI
Outside Room – DI for 80mm &
above/ GI for lower sizes.
4
Air Lines: Headers,
Vertical Down-comers Pressurized
Above Water: MS "C" Class,
Sand Blasted and Epoxy
Painted
Under Water: SS 304
Under Ground : MS with
Coating and Wrapping
In Blower Room: Pipe
Insulation with Resin Bonded
Glass wool in Rigid Board.
Kindly refer detail Mechanical
specifications.
5a Air Grid Piping: Aeration
Zone Pressurized UPVC Schedule 40
5b Air Grid Piping: Selector
Zone Pressurized SS 304
6 Chemicals Gravity /
Pressurized
SS 304 except Chlorine &
FeCl3
7 Chlorine & FeCl3 Gravity /
Pressurized Schedule 40 UPVC
Annexure-3 : Revised “ Volume-2(R1)”
136
Sr.
No.
Service Type MOC End
Connection
2 Delivery of Pump Swing Check CS Body & SS 304
Internals
Wafer
3 Suction & Delivery of
Pump
Butterfly CI Body & SS 304
Internals
Flanged
C Air
1 Pressurized Ball CS Body & SS 304
Internals
Flanged
2 Delivery of Blower Swing Check CS Body & SS 304
Internals
Wafer
3 Suction & Delivery of
Blower
Butterfly CI Body & SS 304
Internals
Flanged
D Chemicals
1a Gravity /
Pressurized
Ball As per Chemical
Compatibility Chart
Flanged
1b Gravity /
Pressurized
Diaphragm As per Chemical
Compatibility Chart
Flanged
1c Gravity /
Pressurized
Plug As per Chemical
Compatibility Chart
Flanged
Notwithstanding the above, the Tenderer shall submit a Valve Schedule with Tag No.,
Flow, Size, Type, Material of Construction, End Connection etc. with detailed P &ID
for approval prior to any further engineering or procurement/fabrication and
installation.
7.12. Security Cabin
Security Cabin of size 4.00 m x 3.00 m with washroom shall be provided at entry Gate
of the Plant. It shall be RCC (M25) Frame and Brick Masonry Structure equipped with
Doors, Windows/Ventilators, etc. complete. Also, it shall be provided with Flooring,
Internal and External Plaster with Painting and Plinth Protection along the periphery
as per specifications.
7.13. Site Development
Site development of whole land should be done by the bidder maintaining plinth level
around structures, top level of roads/pavements, lawns, landscaping etc. Lawns
should be 15 cm below top level of roads and pavements.
7.13.1. Roads & Pavement
Roads and pavement shall be proposed by the contractor, so as to access each and
every unit of the constructed works. These roads and footpaths shall be 4.2 m and
2.2m wide respectively. The roads/pavements shall be made of paver blocks. Cement
Concrete Kerb & Channel (1:2:4) shall be provided on both sides of the road. The
Kerb & Channel shall be 30 cm x 60 cm x 10 cm. Dowel shall be provided on both
side of the road with earth filling in proper slope and compaction as per direction of
Engineer-in-Charge.
Annexure-3 : Revised “ Volume-2(R1)”
137
7.13.2. Sewerage System, Drainage System and Storm Water System
The waste water collected through down take pipes of grit chamber / screen channel,
inlet chamber and other units shall be carried through RCC Pipe / UPVC Pipe upto
inlet chamber of STP/MPS. This may require provision of pumping arrangement.
In addition to this the waste water of operation building shall also be carried to this
sewerage system. Provision shall be made for collection of sludge filtrate from sludge
platform and mechanical dewatering for its connection to proposed sewerage system.
The required no. of manholes shall be constructed as per drawing submitted by the
bidder and approved by Engineer-in-Charge before execution of the work. The
bedding and haunches of pipes shall be as per the specifications approved by the
Engineer-in-Charge.
The bidder shall also provide suitable arrangement for disposal of storm water of the
plant area.
7.13.3. Water Supply Arrangement
The bidder shall provide internal water supply scheme in the plant area. The main
water supply lines shall be of suitable size and of Ductile Iron (K-7) Pipe. However,
service connection to buildings / equipment / process units will be of MDPE/CPVC/
G.I. Class B. The supply of water shall be made through small tube-well to be bored
within the plant area. The bidder shall have to provide complete water supply system
including underground water storage tank of suitable capacity (subject to minimum of
20 Cum) and overhead tanks wherever required. The water supply system shall
include making provision of hydrants / nozzles for washing of the various units /
pipelines. A booster pump of suitable capacity shall be provided for pumping the
water to above said units. Provision for all required pipes, specials, overflow pipes
and bell cock sluice valves shall also be included.
Small Tube well: It shall consist of a bore of suitable size and depth with PVC casing
pipe / filter housing a submersible pump set of suitable capacity complete in all
respect for pumping out water to meet the requirement of plant operation, watering of
plants, cleaning and staff requirement for daily use. Water should be suitable for
construction and drinking purposes.
7.13.4. Rain water harvesting
Roof top rain water harvesting is to be done for all the buildings. The system shall
confirm to the details and specifications in the relevant document published by
Central Ground Water Board, Ministry of Water Resources to be stipulated. The
following technical criteria, to be taken into consideration while designing rain water
harvesting system.
Hydrogeology of the area, nature and aerial extent of the aquifers
Nature and type of soil cover
Quantity and intensity of rainfall specially one hour peak rainfall
Clogging potential i.e. silt content of source water
Topography / applicable methods (infection or infiltration)
All recharge structures shall be designed based on availability of space, run
off, depth of water table and lithology of the area.
General methods to be adopted are described below:
Rain water from roof of building should be collected at one or more places through
rain water drain pipes extended up to the bottom of the building. Then collected water
Annexure-3 : Revised “ Volume-2(R1)”
138
should be diverted into a sump called filter chamber of required size and from sump
to recharging pits or other components through RCC pipe of required size and
thickness / strength. The bottom half of the filter chamber has to be filled with broken
bricks / pebbles and followed by a layer of coarse sand. A nylon mesh has to be
provided in between the two layers. The top portion of filter chamber should be
covered with RCC slab. The inlet rain water drain pipe should be on the top of the
filter chamber and outlet pipe connecting the filter chamber to the recharging structure
should be at the bottom. One filter chamber should not be connected to more than 22
square meter area of roof of any building. The rain water then should be diverted
towards recharging structure which may be of following types.
Recharging Pits
In alluvial area where permeable rocks are exposed on the land surface or at
very shallow depth, roof top rain water harvesting can be done through
recharge pits.
This technique is suitable for buildings having a roof area of 100 square
meters and is constructed for recharging the shallow aquifers.
Recharge Pits may be of any shape and size and shall generally be
constructed 1 m to 2 m wide and 2 m to 3 m deep which shall be back filled
with boulders (5-20 cm), gravels (5-10 mm) and coarse sand (1.5-2 mm) in
graded from-Boulders at the bottom, gravels in between and coarse sand at
the top. For smaller roof area, pit may be filled with broken bricks / cobbles.
A mesh should be provided at the roof so that leaves or any other solid waste /
debris is prevented from entering the filter chamber / pit.
Recharge Trench
Recharge trenches are suitable for buildings having roof area of 200-300 square
meter and where permeable strata are available at shallow depths.
Trench may be 0.5 to 1 meter wide, 1 to 1.5 meter deep and 10 to 20 meter long
depending upon availability of water to be recharged and available land.
These recharge trenches shall be back filled with boulders (5-20 cm), gravels (5-10
mm) and coarse sand (1.5 to 2 mm) in graded form- boulders at the bottom,
gravel in between and coarse sand at the top.
A mesh should be provided at the roof so that leaves or any other solid waste /
debris is prevented from entering the filter chamber / trench.
Trench with recharge well
In areas where the surface soil is impervious and large quantities of roof water is
available within a very short period of heavy rainfall, the use of trench / pits is
made to store the water in a filter media and subsequently recharge to ground
water through specially constructed recharge wells.
This technique is ideally suited for areas where permeable horizon is within 3 m
below ground level.
Recharge well of 100-300 mm diameter is constructed to a depth of at least 3 m to
5 m below the water level. Based on the lithology of the areas, well assembly
should be designed with slotted pipe against the shallow and deeper aquifer.
A lateral trench of 1.5m to 3m width and 10m to 30m length, depending upon the
availability of water is constructed with the recharge well in center.
Annexure-3 : Revised “ Volume-2(R1)”
139
The number of recharge wells in the trench can be decided on the basis of water
availability and local vertical permeability of the soil.
The trench is backfilled with boulders, gravels and coarse sand to act as a filter
media for the recharge wells.
If the aquifer is available at greater depth say more than 20m, a shallow shaft of
2m to 5m diameter and 3-5 meters deep may be constructed depending upon
availability of runoff. Inside the shaft a recharge well of 100mm-300mm dia. is
constructed for recharging the available water to the deeper aquifers. At the
bottom of the shaft a filter media is provided to avoid choking of recharge well.
Bye-pass arrangement with provision of suitable valve shall be installed in the rain
water drain pipe just before every filter chamber to reject the first shower.
7.14. Disposal of treated effluent
7.14.1. Treated Effluent Channel / Pipe
The treated effluent after disinfection is to be either used for irrigation or disposed of
into the adjoining drain. Hence bifurcation chamber of suitable size with 2 control gates
and weirs is required to regulate the flow as per irrigation demand. The carrying system
can be either a RCC Channel or pipe. The pipe can be RCC with HDPE lined.
In case provision of secondary pumping station is required to pump the treated waste
water into the drain or achieve water level as prescribed elsewhere in the bid
document, the necessary arrangements like construction of sump, pump chamber,
suction and delivery mains, control valves / gates and all electrical mechanical systems
shall also be in the scope of work.
7.15. Miscellaneous
7.15.1 Stairs
RCC / MS staircase (minimum 1.2 m wide) shall be provided to access all the platforms
provided/required for all the units above ground level. The tread shall be 250 mm and
rise shall not exceed 175 mm. The width of the staircase and their type shall be as
approved by Engineer-in-Chief before execution of the work.
7.15.2 Railings
Railing shall be provided along all the platforms above the ground level and staircases.
The railings shall consist of three horizontal rows of 40 mm i/d GI pipe, Class C
supported on CI pedestals 1 m high fixed at interval of 1.5 m c/c.
7.15.3 Painting, Whitewashing and Allied Works
Operations Buildings
All the units/items/equipment of the Operations Building shall be painted/coated
wherever required. All the internal surfaces of the walls and ceiling of buildings shall be
painted with plastic emulsion paint. All the external surfaces of operations building shall
be cement based paint.
Water Retaining Structures
The inner concrete surfaces of all the water retaining structures including channel shall
be painted (two coats) with approved make anticorrosive/epoxy paint.
Pipes and specials
Annexure-3 : Revised “ Volume-2(R1)”
140
All the MS / CI / DI pipes and specials and other equipment shall be painted with two
coats of approved make anti corrosive paints.
7.15.4 Lowering of ground water table during construction
The ground water table, if encountered, during construction shall be lowered sufficiently
so as to enable construction in dry conditions
7.16. Electrical & Instrumentation Works
It shall be the Contractor’s responsibility to obtain adequate incoming HT power from
State Electricity Authority (PSPCL) based on total plant load and as per PSPCL norms.
The Employer will pay the charges for obtaining the above connection whereas
necessary liasoning for the same shall be done by the Contractor in consultation with
Engineer-in-charge.
Two nos. Transformers, 1 each for STP and Pumping Station of full capacity and as
per PSPCL norms shall be provided. These shall be step down Transformers
suitable for outdoor installation and as per specification given in Volume-2 Part-4.
The entire Plant shall be operated on 415 V, 3-Phase, 50 Hz, 4-Wire system. The
Contractor’s Scope of Work shall include the following:
Obtaining incoming HT Power from PSPCL including necessary liasonoing,
documentation etc. complete.
HT Cable with Termination Kit from “Source” to the Electrical HT Substation
located at the Sewage Treatment Plant.
HT Substation including 4-Pole Structure, HT Panel, Transformers, Power
Control Centre with APFC Capacitor Panel etc. complete.
Motor Control Centres.
Silent DG Set with AMF Panel & other accessories for entire load of STP and
average flow plus other misc. load of MPS.
LT Bus-Duct
Power, Control and Instrumentation Cables including trays, ducts, support etc.
ACDB, DCDB, Battery & Battery Charger, UPS
Earthing for Electrical equipment as well as Instruments, PLC/SCADA.
Lightening Protection
Complete Indoor & Outdoor Lighting System.
Local Control Panel, Field JB, welding receptacles.
Local Push Button Stations near respective Drives.
Fire detection & Alarm system, plant communication.
Flow Meters at inlet, outlet & by-pass.
Level Transmitter, DO Transmitter, Pressure Gauge, Auto Valves
Online Monitoring System for raw and treated sewage quality.
CCTV System
Safety items (shock treatment chart, first aid box, CO2 fire extinguisher,
insulating mat, hand gloves, caution boards, LED signage, sand buckets,
discharge rods etc.)
All civil works required for complete installations.
Any other item / accessories required as per process requirement and for
successful completion of the Project.
Annexure-3 : Revised “ Volume-2(R1)”
141
The Contractor shall design/execute the System as per specifications (Volume-2 Part-
4), I.E. Rules and Regulations, requirements of PSPCL and other local Authorities
and actual site conditions.
Also, the Contractor shall provide PLC/SCADA based Automation for entire plant as
described in below clause.
7.17. PLC/PC/SCADA BASED AUTOMATION SYSTEM FOR ENTIRE PLANT
The complete Plant shall be designed for automatic operation through Programmable
Logic Control (PLC) and Supervisory Control and Data Acquisition (SCADA). This shall
be achieved by either individual equipment PLCs with SCADA/HMI or single PLC and
SCADA for entire Sewage Treatment including pumping stations. Operation of primary
treatment units and sludge dewatering units shall be manual however indication of
operation of primary treatment units and sludge dewatering units shall be on
PLC/SCADA. These shall be located at control room of the STP.
The plant shall have provision for operations in following modes –
i) Automatic – Auto operation through PLC/digital controller.
ii) Manual – Operator intervention through SCADA/HMI.
iii) Local – Local operation through local control panel located near equipment.
a) Audio Visual Alarms Audio visual alarms shall be initiated under emergency or equipment trip conditions,
other than usual service alarms. Salient features of the proposed control system shall
be as follows:
Dynamic display of all Units, equipment and drives shall be available on
SCADA screen.
It shall Acquire, process and manage the processed data.
It shall safeguard the process by means of interlocks and alarms.
Auto/Manual operation of each drive shall be made by selecting a soft switch
on SCADA/HMI screen.
In Auto mode, each drive shall operate based on pre-set sequence and
interlock. Also automatic change over from working to standby drive shall
happen after a drive reaches pre-set hours of operation.
In Manual mode, each drive shall be operated in Local/Remote mode by
selecting a soft switch on SCADA/HMI screen. In Local mode, each drive shall
be operated from the Local Push Button Station (LPBS) located nearby. In
Remote mode, operation from LPBS shall be disabled and each drive shall be
operated manually from PLC. Also provision for working/standby selection of
drives by selecting a soft switch on SCADA screen shall be provided.
Run/Trip indication of all drives shall be displayed on SCADA/HMI screen.
Open/Close indication of all Auto Sluice Gates and Auto Valves shall be
displayed on SCADA/HMI screen.
Annunciation & Alarm facility shall be available in PLC/HMI/SCADA. In the
event of a Fault, the symbol representing the equipment/drive shall continue
flashing on SCADA/HMI screen with equipment/drive description appearing at
bottom of the SCADA/HMI screen and electric Hooter shall continue blowing
until the Fault Alarm is acknowledged.
Data logging of Running Hours of each drive, Alarms, Historical Trends of
Annexure-3 : Revised “ Volume-2(R1)”
142
monitored Parameters, etc. shall be envisaged in SCADA.
Report generation for plant performance.
The process system must have pre-configured software packages which can be
adapted to the process by parameterization.
The monitor images must be designed to be user-friendly by hierarchical breakdown
with the possibility of selective display and optimum selection possibilities.
Changing of parameters and other software units must be possible "online", i.e. with
the system running.
Different alarms colours provide information on their priorities.
For the system engineering offered, the Contractor must take measures, e.g. by the
installation of surge voltage arresters or surge voltage filters, to ensure that internal and
external surge voltages do not impair the function of his parts of the system.
The programs and data entered must be backed up in a non-volatile read-only
memory.
A limit value and plausibility check must be provided in the software of the process
station for the measured values and messages. Exceeding of limit values or deviations
detected by the above checks must trigger an event and cause a message to be sent.
Further demanded features of the process system:
Integrated, detailed error message and fault detection concept with display on
the HMI/SCADA for quick localization of faults. The system operator must be
able to identify the fault from the error.
Essentially maintenance-free
Robust against external interferences of all kinds
Proven design and solder-free connection technique
Protection of the equipment against surge voltages
Automatic fault detection and quick troubleshooting in the PLC system by
integrated, hierarchically structured diagnostic devices
Power supply in wide admissible voltage range
Simple function-oriented operation
The process system (PLC, HMI/SCADA) shall be protected against power failure by
an uninterruptible power supply (UPS). When the critical charge state of the UPS is
reached, the process system is automatically shut down.
b) Mode selector switch A mode selector switch is to be installed on the MCC or distribution board. It serves for
pre-selection between Automatic mode and Manual/Local mode.
The following switching functions must be provided:
Automatic – Manual/Local
Automatic: In this position, only automatic operation is possible; the local switches
have no function (Except emergency stop).
Local: Automatic mode cannot be started. The drives can be operated individually
without interlock with the local switches.
Annexure-3 : Revised “ Volume-2(R1)”
143
Local switches (LPBS)
Each drive must be equipped with a local switch positioned in such a location that the
corresponding machine or conveyor can be switched on in Manual/Local mode and can
be monitored visually at all times.
The local switch must have the following switching functions:
START – STOP (for drives with one direction of rotation)or
FORWARD – STOP - REVERSE (for reversible drives)
If a unit has several drives (e.g. conveyor belt drive and travel drive), the local
switches should be installed if possible in one switch box or at least installed next
to one another.
Each local switch must be adequately labelled in plain text so that no operator
errors can occur.
c) PLC The automatic start-up of the whole system, sequential operations and the automatic
shutdown, allowing for external control influences, e.g. EMERGENCY STOP, etc., is
performed by programmable logic controller (PLC).
This performs not only the control of the system, but also the display of the operating
state in the HMI/SCADA.
The interlocks of the individual process groups and their signaling must be performed
by the PLC.
A system must be selected which is sufficiently protected against external interference
in the supply, control and signaling lines. The aim is that the program can continue to
run without fault signals in the event of transient earth faults in the supply grid. In the
event of prolonged power failures, on the other hand, a controlled restart must be
triggered (under-voltage trip of the non-automatic circuit breaker).
PLC Specifications: Technical
The PLC shall be non-redundant.
PLC of individual equipment shall be selected to carry out necessary
operations without overloading the PLC memory.
The PLC shall have adequate I/O per card.
There shall be 15% spare I/O of each type.
The CPU shall not be loaded more than 60% of its capacity.
Retentively shall be 100% to save the recorded data and saving the
programmed logic, other attributes connected with system for power & system
failure.
Change in programme / modifications to programme shall be possible by a
portable laptop.
It is preferred to have all PLC’s in the plant from same manufacturer.
HMI/SCADA system
The HMI system shall be designed as a minimum 6”, colour, touch-screen on the panel.
Whereas SCADA system must be computer based.
All displays must be designed by the Contractor with graphic sophistication and all texts
in the visualization system must be displayed in English.
Annexure-3 : Revised “ Volume-2(R1)”
144
A sub-menu for each operating mode and further menus for editing the system
parameters, fault archive, etc., must be developed. It must be as simple as possible to
switch between the various menus and to edit the system parameters.
When designing the user interface or the assignment of the function keys, attention must
be paid that the function key assignment remains the same in all sub-menus so that it is
possible to jump to another menu without first having to jump back to the main menu.
It must be possible to edit the following parameters at the touch-panel and SCADA:
Operating mode
Changes in the speeds of frequency converter-controlled equipment
Start-up times
Shutdown times
Duration of the operation of warning devices
Limit values for sensors, etc.
Faults, level messages, pressed EMERGENCY STOP buttons, etc., must also be
clearly displayed at the bottom of the screen, irrespective of the selected screen page
or sub-menu.
It must be possible to output all important menu items to the printer. The corresponding
interfaces must be provided.
The display of the function plans, images, etc. is affected in direct dialog with the
system by means of the mouse and keyboard.
The central SCADA shall generate various reports to analyse plant performance. The
process is documented via the laser printer.
d) Computer hardware and software All programs required for operation of the system must be correspondingly compatible.
The corresponding licenses must be supplied for the standard programs. The operating
systems must be agreed upon with the Client. Minimum requirements shall meet:
CPU
1. Processor Intel i 7 10th Gen
2. Processor speed 4 GHz or higher
3. Configuration Tower
4. Architecture 64 bit
5. System memory
(RAM)
16 GB
6. Hard disk 256 GB SSD+ 1 TB HDD
7. DVD Drive Combo (Read/Write)
8. Operating system Microsoft Windows 10 professional
9. Communication
ports
USB – 4 Nos., Ethernet – 1 Nos.
10. Graphic
accelerator
2 GB
11. Power supply 240V, 50Hz, 1Phase
12. Keyboard Internet Keyboard (with USB interface)
13. Mouse Optical, 3 buttons (with USB interface)
Monitor
14. Type Full HD LED color monitor
Annexure-3 : Revised “ Volume-2(R1)”
145
15. Screen size 24” or higher
16. Resolution 1920 x 1080
17. Power supply 240V, 50Hz, 1Phase
Complete Project shall operate in auto mode. As a minimum, following controls must
be considered in Bidder’s Control Philosophy:
1. Coarse screens
Each mechanical coarse screen shall be installed with ultrasonic differential level
transmitter / level switch, across it; the same shall be operated on the basis of
set differential level in SCADA. Also if differential level is not reached for certain
time period, the screen shall be operated on the basis of set time in SCADA.
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA. In manual mode the screen operation will be done from SCADA screen.
Physical switch over of screens in plant will be done by operator using manual
gates.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered
in PLC for auto operation of coarse screen.
2. Raw Sewage Sump and Pumps
The sump will employ an Ultrasonic level transmitter to measure level. The
combined operation of Raw Sewage Pumps will be dependent on rate of change
of level with reference to time. The selection of Auto/Manual and Working/Stand-
by shall be made available in SCADA. In manual mode the pump Start/Stop will
be done through SCADA screen.
A clamp on type Ultrasonic or Electromagnetic flow transmitter shall be provided
at common header of pumps for measurement of flow to sewage treatment plant.
PLC shall calculate instantaneous flow as well as cumulative flow, both shall be
displayed on SCADA.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered
in PLC for auto operation of Raw Sewage Pumps.
3. Inlet chamber
A clamp on type Ultrasonic flow transmitter shall be provided on rising main of
inlet chamber for measurement of flow coming to Sewage Treatment Plant. PLC
shall calculate instantaneous flow as well as cumulative flow, both shall be
displayed on SCADA.
4. Fine screens
Each mechanical fine screen shall be installed with ultrasonic differential level
transmitter / level switch, across it; the same shall be operated on the basis of set
level in SCADA. Also if level is not reached for certain time period, the screen
shall be operated on the basis set time in SCADA.
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA. In manual mode the screen operation will be done from SCADA screen.
Physical switch over of screens in plant will be done by operator using manual
gates.
Annexure-3 : Revised “ Volume-2(R1)”
146
Necessary interlocks, controls, alarms, report generation, etc. shall be considered
in PLC for auto operation of fine screen.
5. Grit Chambers
Each grit chamber will consist of Detroiter (1No.), Organic Return Pump (1No.)
and Screw Conveyor for grit removal (1No.). As such Detroiter, Organic Return
Pump and Screw Conveyor will not have auto operation; these will be started and
stopped from SCADA screen as required.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC
for operation of Grit chamber equipment.
6. Any Biological Unit
Complete operation and control of plant will be done through a separate PLC and
SCADA. However it shall have necessary inputs and generate required outputs to
operate in co-ordination upstream and downstream units of balance plant.
Alternatively contractor may provide single PLC and SCADA for entire Sewage
Treatment Plant.
Necessary interlocks, controls, alarms, report generation, etc. shall be
considered.
Each reactor shall be equipped with Level Transmitter, DO Transmitter for
monitoring and recording of critical operation parameters through SCADA.
7. Sludge sump and pump
An ultrasonic type level transmitter shall be used for measurement of level in
sludge sump.
Screw/ Reciprocating pumps will be used to feed sludge to mechanical
dewatering unit. These will operate as per level in sludge sump.
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA for sludge pumps. In manual mode the Start/Stop of pump will be done
from SCADA screen.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC
for operation of chlorination system.
8. Tertiary Treatment and Chlorination tank
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA for booster pumps. In manual mode the Start/Stop of pump will be done
from SCADA screen. Though chlorinator will have standalone operation,
feedback for the equipment shall be taken to PLC and displayed SCADA for
monitoring purpose.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC
for operation of chlorination system.
9. Centrifuge/ Belt Filter Press
The drives and instruments of mechanical dewatering unit shall be connected to
PLC for its auto operation. Starting of dewatering system will be a manual
process.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC
for auto operation of centrifuges.
Annexure-3 : Revised “ Volume-2(R1)”
147
8. Design parameters for ETP’s at Tajpura & Haibowal:
Design Basis:
Flow for New ETP: 2.25 MLD at Tajpura &3.75 MLD at Haibowal
Peak factor: 5
Raw Influent Quality of both ETP’s are similar:
An abstract of Raw Dairy Waste Characteristics is indicated in the following Table:
Sr. No.
Parameters Values Unit
1 pH 6.5 to 9
2 Biochemical Oxygen Demand
(BOD5) 2000
mg/l
3 Chemical Oxygen Demand (COD) 3000 mg/l
4 Total Suspended Solids (TSS) 1000 mg/l
5 Total Kjeldahl Nitrogen (TKN) 350 mg/l
6 Total Phosphorous (TP) 10 mg/l
The Bidder shall carry out the sampling tests of raw sewage by themselves to
ascertain the raw influent quality for treatment process. The Employer will not be
responsible for the above and no relaxation will be given to the guarantee conditions
of desired treated effluent quality. For design purposes the lower parameters than
the above mentioned parameter will not be allowed.
Treated Sewage Quality:
The Contractor shall design the process in such a way that the: (2.25 &3.75 MLD )
treated effluent quality attains the following limits or even better
Sr. No.
Parameters Values Unit
1 pH 6.5 – 8.5
2 Biochemical Oxygen Demand (BOD5) < 10 mg/l
3 Chemical Oxygen Demand (COD) ≤ 50 mg/l
4 Total Suspended Solids (TSS) ≤ 10 mg/l
5 Fecal Coliforms ≤ 230 MPN/100ml
6 Ammonical Nitrogen as N < 5 mg/l
7 Total Nitrogen (TN) ≤ 10 mg/l
8 Total Phosphorous (TP) ≤ 1 mg/l
9 SAR (Sodium Absorption Ratio) ≤ 3.5
10 EC (Electrical Conductivity) ≤ 2000 Micro mhos /
cm 11 RSC (Residual Sodium Carbonate) ≤ 2.5 mg/l
Annexure-3 : Revised “ Volume-2(R1)”
148
Design requirement described here is in general for various Items. However design
requirement of only those Items shall be applicable which are required or provided at
site. If design requirement of any item is not described here then requirement as per
CPHEEO Manual / relevant IS code or prevalent as per the department practice will
be applicable as approved by Engineer-in-charge.
8.1. Raw Effluent Pumping Station in ETP Premises
8.1.1 Civil Works
Components of Main Pumping Station
1. Receiving Chamber 2. Screening Channel 3. Wet well/Collecting Tank 4. Panel Room 5. Roads & Pavements 6. Platform /Foundation for Diesel Generating Set &Transformer 7. Cable Trench, wire mesh around transformer
8. White washing/painting etc. 9. Hand Railing 10. Pumping main from IPS to inlet chamber of ETP 11. Valve chamber/platform to house common header, all valves, NRVs etc.
i) Receiving Chamber
The gravity outfall channel will discharge the raw effluent into a Receiving chamber. The
function of the Receiving chamber is to distribute the flow for screens. The Receiving
Chamber shall be designed for peak flow. The Receiving chamber shall consist of sluice
gates on upstream for flow regulation. The receiving chamber shall be of adequate size
to meet the requirements of workability inside it. C.I gate (Manually Operated) of suitable
size shall be provided at the inlet of receiving chamber. The entire construction is in
minimum M-30 grade concrete and as per IS 3370. RCC access platform minimum 1200
mm wide with GI pipe railing as per specifications shall be provided on one side of the
chamber:
Peak Factor : 5.0
Number of Units : 1 (One)
Detention period : 30 Sec at Peak Flow
Min Free board : 0.50 m
ii) J Type Removable Bar Thrash Screens
Manual Trash screen to be installed in front of coarse mechanical screens to prevent
large and medium sized floating wastes from entering into intake structure of pumping
station.
The manual screen should comprise of flat bars spaced apart in vertical with 50mm
opening within a sturdy frame structure inserted in vertical guide channel. Structure
provided should be with perforated basket at its bottom and guide roller on both sides for
easy removal. Guide channel extend upto to top of platform for guiding upward
movement. The height of trash screen should be 0.5 m above sewer crown. Material of
construction should be in SS-304. Flat size shall be of 10 mm thick 50mm wide:
Number of Units : 1 Manual (Working) of 100 % Peak Flow capacity
Annexure-3 : Revised “ Volume-2(R1)”
149
Velocity through Screen at Average Flow (m/sec)
: 0.6 maximum
Velocity through Screen at Peak Flow (m/sec)
: 1.2 maximum
Height of Mesh Screen : 0.50 m above sewer crown / Channel Full Supply Level
Wheeled Trolley : 1 No.
All other accessories, whether specified or not, but required for completeness of contract
shall be in contractor’s scope. GI Hand Railings shall be provided around the entire
periphery of the platform and structure.
The provision of EOT crane, any kind of cleaning/raking mechanism, collection
bins/portable screen container, water jetting arrangements & trolley etc. shall be
provided.
iii) Coarse Screen
One mechanical screen working and one manual screen standby of 20 mm clear spacing
shall be provided with each screen designed for peak flow capacity.
The mechanical and manual bar screens shall be made of 10 mm thick Stainless Steel
(SS 304) flats respectively. The mechanical coarse screens shall be of Inclined Rake
Type of 20 mm opening as per the specifications detailed elsewhere in the bid document.
Bin and chute arrangement shall be provided for collection of screenings in a wheel
burrow/trolley. Manually operated CI gates are provided at the upstream and downstream
end to regulate the flow.
Adequate RCC Platforms shall be provided at the upper level to enable operation.
Railings shall be provided around the entire periphery of the platform. The entire structure
is to be in minimum M-30 concrete and as per IS 3370 including the platform. RCC
staircase 1200 mm wide shall be provided for access from the ground level to the top of
the unit & to the operating platform.
Flow
(MLD)
Peak
factor
J Type Thrash Screen
Mechanical coarse
Screens
Manual coarse
Screens
1 Tajpura 2.25 5.0 1 1 1
2 Haibowal 3.75 5.0 1 1 1
Peak factor : 5
Number of Units : 1 Mechanical (Working) + 1 Manual
(Standby) each of Peak Flow capacity
Flow Approach Velocity at Average Flow (m/sec) : 0.3 minimum
Velocity through Screen at Peak Flow (m/sec) : 1.2 maximum
Height of Screen bars upto dead plate : 1 m above sewer crown / FSL of
channel
Wheeled Trolley : 2 No.
All other accessories, whether specified or not, but required for completeness of contract
shall be in contractor’s scope.
iv) WET WELL
The Main pumping station (MPS) shall be a rectangular / Circular concrete structure. The
sump well is to be in R.C.C of minimum Grade M-30 and shall be designed for peak flow.
Annexure-3 : Revised “ Volume-2(R1)”
150
The maximum operational liquid level in wet well shall be such that, Minimum 100mm
Freefall to be maintained from the Invert of Screen Chamber to Water level of wet well.
The capacity of the wet well sump should be kept such that the detention time of the sump
should be at least 5 minutes of peak flow. The wet well shall be divided into two equal
compartments upto full height with sluice gates in common wall.
The pumps shall be installed equally in two compartments. Area of gate(s) should be
sufficient so as to divide the flow into any of the compartments, at a velocity not more than
1.2 m/sec.
The arrangement of the Pumps shall be as per Manufacturer’s data i.e. Spacing between
the Pumps, minimum space between the Pump and Wall etc. Adequate submergence of
the pump shall be provided as per the manufactures recommendations. The size of wet
well shall be sufficient to accommodate one additional pump in each compartment, in
future.
RCC Staircase / Aluminium ladder from Top of wet well to the bottom of wet well shall be
provided.
IS: 3370 and IS: 4111 (Part 4) shall be followed for the design and construction of Wet
Well.
Basis for Design
All underground or partly underground liquid containing structures shall be designed for
the following conditions:
(a) Liquid depth up to full height of wall and free board. No relief due to lateral soil
pressure from outside to be considered;
(b) Reservoir empty (i.e. no liquid or any material inside the storage area): full lateral
earth pressure at rest due to surrounding saturated soil and surcharge pressure as
applicable, shall be considered;
(c) Partition wall between two compartments of wet well to be designed as one
compartment empty and other full;
(d) Structures shall be designed for uplift in empty conditions considering the depth of
the highest water table recorded in the area.
(e) Walls shall be designed under operating conditions to resist earthquake forces
developed due to mobilization of earth and dynamic liquid loads;
Underground or partially underground structures shall also be checked against stresses
developed due to any combination of full and empty compartments with appropriate
ground/uplift pressures on the base slab.
v) Sewage Pumps
Coarse-screened effluent shall be pumped from wet well. Pump operation shall be
automatically controlled based on wet well level. There will be high level and low level
alarm and tripping system installed. It will house non clog submersible pumps, which will
always be submerged in sewage with minimum submergence as required by the
manufacturer. Pumps will have automatic coupling arrangement at discharge end, a guide
pipe and chain for easy removal and lowering of pumps. Vibration shall be limited as per
Annexure-3 : Revised “ Volume-2(R1)”
151
BS 4675 Part I.
Type of Pumps : Submersible type non-clog design
Liquid : Raw Sewage
Specific gravity : 1.05
Solid Passage Size : Maximum 100 mm.
No of working Pumps : 4 Nos.
Capacity of Pump : Peak flow/ No of working pumps
Standby Pumps : 50% of total capacity of working pumps
One electrically operated 3-way movement Trolley (EOT) having capacity equal to 1.5
times the weight of heaviest part to be lifted shall be provided over the sump well for
movement of pumps. The horizontal, transverse as well vertical shall be electrically
operated. The gantry is to be fixed on RCC framed structure and not on a cantilever arm
from columns.
vi) Rising main
Effluent from wet well will be pumped to ETP or to drain through rising main of size
suitable to carry peak flow:
Material of rising main: Cement lined DI (K9) pipe
Size of rising main : Capable of carrying peak flow
Velocity in rising main at peak flow : 1.5 m / sec
Flushing connections needs to be provided.
vii) Piping & Specials
This shall include providing, laying, cutting, jointing, testing, etc. of pipes along with
specials:
a) RCC Channels from inlet chamber of screens upto sump/ collecting tank.
b) DI K-9 Delivery line for individual pump upto common header.
c) Expander, Sluice valves, Bends, Non Return Valves in the individual delivery
of all the pumps. Tees and Sluice valve in the common header.
d) DI K-9 Common header upto Inlet of ETP.
e) The size of pipe shall be calculated so as to meet the following velocity
criteria:-
Minimum Velocity : 0.60 m/sec
Maximum Velocity : 1.5 m/sec
f) All other required fittings such as bends, tees etc.
g) Thrust block of M-20 grade, for pipe support, etc.
h) Necessary bypass arrangement shall be provided to be used during the
shutdown of the plant. Pipe and Valve arrangement upto suitable discharge
point shall be provided.
viii) Painting, White Washing and allied works
The internal and external surfaces of the walls and ceiling of all building structures shall
be applied with two coats of Birla / JK Wall Putty followed by two coats of primer followed
by min two coats of first quality plastic emulsion paint.
Annexure-3 : Revised “ Volume-2(R1)”
152
All the structural steel, pipes, specials etc shall have two coats of Epidec RTC Primer
followed by two coats of epoxy paint.
All the internal walls and base of water retaining structures of MPS shall be provided with
min two coats of coal tar epoxy.
ix) Roads & Pathways with proper drainage
Roads and Pathways shall be provided with interlocking paver blocks over 150 mm thick
and 100 mm thick respectively cement concrete of 1:4:8 in stone ballast. Thickness of
paver blocks on roads is 80 mm thick and on pathways the thickness of paver blocks is 60
mm. Paver blocks shall confirm to specification of code IS 15658 Paver blocks will be ISI
Marked.
x) MPS Panel Room
It shall be RCC framed structure and 3.5 m clear height. It shall house panels of MPS
pumps, screens, sluice gates, valves etc. It shall also house PLC Panels and HMI screen
for display of various parameters of MPS. Preferably the MPS panel room building is to be
adjoining to the administrative building of ETP so as to have a better monitoring.
Local Push Button Station (LPBS) shall be provided near each Pump set/ Motor for
emergency stop and start thereof. LPBS shall have Start/Stop push button with
Local/Remote Selector Switch. Each push button shall have 2NO+2NC contact for
interlocking purposes. The stop push button shall be mushroom type with stay put feature
and lockable in pressed position to avoid accidental operation of drive from MCC, PLC
during shutdown.
LPBS shall be suitable for use in outdoor open locations with minimum IP-55 degree of
protection and rain canopy.
8.1.2 Mechanical Works
1. J Type Manual Coarse screens, Manual and Mechanical Coarse Screen, Belt Conveyor for screens
2. CI Sluice Gate shall be provided at following locations for flow control
i. Inlet of Receiving Chamber-1 No. ii. Upstream of coarse screens of MPS – 2 Nos iii. Downstream of coarse screens of MPS – 2 Nos iv. RCC Partition Walls of Wet Well – 1 No v. Any other gate as required
3. Non clog Submersible Centrifugal Pump sets with motor 4. Piping works, Dismantling Joint, NRV, Sluice Valve with appurtenance 5. Lifting Arrangement –Monorail with Manual horizontal and vertical operation
8.1.3 Electrical, Instrumentation & Control Works
1 Electrical Panel with
a) Incomer for normal & DG supply & interlocks power analyzer, surge protection device
b) Individual Starter Panels with VFD and soft starters for pumpset c) Automatic Power Factor Control (APFC) Capacitor Panel d) Alarm Annunciation Panel
Annexure-3 : Revised “ Volume-2(R1)”
153
e) Feeder for other loads f) Interface with PLC & SCADA compatibility
2 HT & LT Cable, Instrument & data cable 3 Cabling system 4 Earthing & Lightening Protection 5 Lighting System (Indoor & Outdoor) 6 Junction Box for cables 7 UPS for PLC 8 Instrumentation & Control
This includes supply, erection, testing and commissioning of various instruments & control
system. Brief details are as under:
S No Instrument Location Quantity
1. Differential Level sensor / Transmitter
Mechanical Coarse Screens As required
2. Pressure gauge Common discharge header of non-clog sewage pumps/Rising main
1
3. Radar Type level transmitter (non-contact type)
Main Collection Sump ( For level Status & level based control)
2
4. Programmable Logic Controller (PLC)
Panel Room 1
5. Any other Item As per requirement As per
requirement
PLC for MPS shall be as per control philosophy & specification.
PLC shall operate pumps based on pre-set levels of sewage in collection tank and
VFD operation. At mid-level of sewage, number of pumps as per average flow shall
operate, whereas at high level, number of pumps as per peak flow shall operate. At
low level, all pumps shall stop. Provision shall be made to operate all pumps in
rotation. Pumps operation shall be closely co-ordinated with ETPs sewage
requirement through ETP PLC/SCADA
PLC cum Instrumentation Control Panel shall be provided with 6” HMI to enable
level based operation of pumps and display of level and flow.
Provision shall also be made for display of level and flow in ETP, SCADA Room.
Single PLC for MPS and ETP is preferred. Contractor is free to provide separate
PLC for MPS.
PLC to have provision for exporting data to external device.
Annexure-3 : Revised “ Volume-2(R1)”
154
8.2. ETP
i) Flow Measurement
Flow measurement shall be done online using an ultrasonic flow meter on the rising
main of raw sewage pumping station located at ETP area.
ii) Inlet Chamber
Inlet Chamber will receive raw sewage from the raw sewage pumping station.
Number of Units : (1) One
Min. Detention period :30 sec on peak flow
Min free board : 0.5 m
Following provisions shall also be to be made as per detailed design.
CI/DI double flanged Puddle Collar
CI/DI double flanged Vertical Pipes
1 no. CI / DI double flanged Sluice Valves
CI/DI Horizontal pipe having length as per contract limits.
Minimum 150 mm i/d CI/DI pipes along with sluice valves for scouring
purposes.
iii) Screening Chamber
One mechanical Step /MATT type Fine screen (working) with one manual (standby)
screens, followed by one Mechanical perforated (working) screen and one Manual
Mesh (working) screen are proposed in the screen chamber.
The screen channels shall be designed for peak flow.
RCC Platforms minimum 1.2 mt wide with hand railing shall be provided at suitable
level and location to enable operation of the units.
The component / unit shall be designed for following:
Number of Units : 1 Nos. Mechanical Working + 1 No.
Manual Standby
1 No. Perforated Mechanical Working
1 No. Mesh Screen Manual.
Velocity through Screen at Average
Flow (m/sec.)
: 0.6 maximum
Velocity through Screen at Peak
Flow (m/sec.)
: 1.2 maximum
Free board : Min 0.5m on upstream side of the
screen at maximum water level
Minimum Length : 6 m
Mechanical Fine Screen (working) of 6 mm opening, Mechanical Perforated
screen of 6 mm opening, Manual mesh screen of 5 mm opening shall be placed
in series.
Flow
(MLD)
Peak
factor
Mechanical Step/MATT
type screen
Mechanical Perforated Screens
Manual Mesh
Screens
Manual Fine
Screens
1 Tajpura 2.25 5.0 1 1 1 1
2 Haibowal 3.75 5.0 1
1 1 1
Annexure-3 : Revised “ Volume-2(R1)”
155
The entire construction shall be in minimum M-30 grade reinforced cement concrete
and as per IS 3370. RCC Platform/Walkway, minimum 1.20 m wide with G.I. Hand
Railing as per specifications shall be provided. RCC Staircase, minimum 1.20 m wide
with G.I Hand Railing as per specifications shall be provided for access from Finished
Ground Level to the top of the Unit & to the Operating Platform/Walkway.
The clear spacing between two bars shall be 6 mm for Mechanical Fine Screen and 10
mm for Manual Fine Screen. The Mechanical and Manual Screens shall be made of SS
304 flats (3 mm for Mechanical and 10 mm for Manual Screen).
Each mechanical Fine screen shall be followed by perforated screen of 6mm opening
and Manual Mesh screen of 5 mm opening.
Minimum 3mm thick panels of stainless steel 304 construction shall incorporate 6mm
diameter perforations.
Conveyor Belt and Chute arrangement shall be provided to take the screenings.
Screenings dropped from Chute shall be collected in a wheel Burrow. Manually
operated CI / Al Sluice Gates shall be provided at the upstream and downstream ends
to regulate the flow.
Detailed specifications of all mechanical bar screens are given in Mechanical Section.
iv) Mechanical Grit Chamber
Mechanical grit chambers are proposed after fine screen units. The mechanical grit
chambers shall be Square Mechanical Detritus Tank designed for each capable of
handling peak flow.
One Mechanical Grit Chamber (Working) and one Standby Mechanical Grit chamber
along with one Manual Bypass Channel Standby) shall be provided after Fine Screen
Channels. Each Grit Chamber shall be designed for Peak Flow and Bypass Channel
shall be designed for 100% of Peak Flow. The entire construction shall be in minimum
M-30 grade reinforced cement concrete and as per IS 3370. RCC Platform/Walkway,
minimum 1.20 m wide with G.I Hand Railing as per specifications shall be provided.
RCC Staircase, minimum 1.20 m wide with G.I Hand Railing as per specifications shall
be provided for access from Finished Ground Level to the top of the Unit & to the
Operating Platform/Walkway.
Each Grit Chamber shall have the following features:
One tapered Inlet Channel running along one side with adjustable Influent
Deflectors for entry of sewage into the Grit Chamber.
One tapered Outlet Channel for collecting the de-gritted sewage, which
overflow over a adjustable Weir into the Outlet Channel. It shall be designed
in such a way that no settling takes place in it.
One sloping Grit Classifying Channel in to which the collected grit shall be
classified.
The grit from Classifier shall be collected in a Wheeled Trolley .
A Grit Scraping Mechanism.
Material of construction of grit mechanism: SS 304
Annexure-3 : Revised “ Volume-2(R1)”
156
Screw Classifier or Reciprocating Rake Mechanism to remove the grit.
Manually Operated C.I. Sluice Gates shall be provided at entrance of the Inlet
Channel of the Grit Chambers as well as Bypass Channel to regulate the flow.
Peak Factor : 5
No. of Units : 1 Mechanical (Working) + 1 Mechanical
(Standby) + Manual (Standby) channel each
of 100% of Peak Flow capacity
Type : Mechanical
Size of grit particle : 0.15 mm and above
Specific gravity of grit : 2.65
Maximum Surface
Overflow Rate : 650 m3/m2/day
Free Board : 0.5 m
Minimum Side Water Depth : 0.90 m
Wheel Barrow : 2 Nos. minimum
All other accessories, whether specified or not, but required for completion of Contract
shall form the part of Bidder‘s Scope.
Proper bypass channel between the units shall be provided with a sluice gate at the
inlet.
v) Primary Clariflocculator
Flash Mixer with mixing arrangement needs to be provided.
Design and construction requirements:
Clariflocculator mechanism shall be suitable for installation in RCC tank as per
following specifications.
No. of Units Suitable
Surface Loading Rate at Average flow 30-40 m3/m2.day
Weir loading rate at average flow 125 m3
/d/m2 (max.)
Area required per unit Suitable
Side water depth (upto top weir) 3.0 m (Minimum)
Material of Construction -Civil R.C.C. (M-30) or higher
Type of Mechanism Central Driven / Peripheral Type
Drive RPM As per manufacturer standard
MOC/Paint Wetted parts SS 304
Non Wetted Parts- MS/Epoxy Painted
Sludge Drain Valves (KGV)
Location At Sludge Removal pipe line
Size Suitable
Type Knife Gate Valves - Automatically
operated
After physio chemical treatment the effluent shall be directed to Equalization Tank. All
wetted parts shall be SS 304 in Primary Clarifloculator.
Annexure-3 : Revised “ Volume-2(R1)”
157
vi) EQUALIZATION TANK
Equalization Tank shall be provided suitably in which sewage will equalize by providing
min. 8 hrs. retention time, with aeration grid and air blower of suitable capacity. The
pumped sewage from the Equalization tank shall be directed to ETP. Suitable number
of Blowers with SS 304 Grid shall be provided for Mixing of Influent.
All units upto primary treatment (Primary clarifloculator) shall be designed for peak
flow, after Equalization Tank all units shall be designed for Average flow.
Anaerobic Treatment
The screened & grit free sewage shall be directed to anaerobic biological treatment.
preferably UASB (Upflow Anaerobic Sludge Blanket) Reactor with min. HRT of 24 hrs.
Arrangement for safe collection of Biogas product during Anaerobic Treatment is must.
After UASB treatment the effluent shall be fed into the biological treatment unit to
remove BOD, COD, Suspended Solids, Biological Nitrogen and Phosphorous for
producing quality of treated effluent after Reactor to be guaranteed as per Table above
in tender.
8.3 BIOLOGICAL TREATMENT
8.3.1 Biological Reactors, Settling and Decanting System
Primarily treated sewage shall be fed into the Reactors for biological treatment to
remove BOD, COD, Suspended Solids, Biological Nitrogen and Phosphorous.
The Reactors along with provisions for sludge re-circulation, excess sludge disposal,
aeration system, settling, decanting and other operational requirements like
automation, level control, flow control, oxygen level control etc. shall be provided.
Number of Units : As per bidder design
Design parameters : All design parameters like, MLSS, HRT, F/M, DO level,
recirculation ratio etc. shall be as per CPHEEO manual
for the offered technology.
Free Board : Minimum 0.50 m
Aeration System : As per bidder design subject to CPHEEO guidelines.
Automation : Operation of the Reactors shall be fully automatic,
controlled through PLC.
Any other
requirement
: As per bidder technology and design to meet the desired
outlet parameters.
8.3.2 General
The Sequential Batch Reactor (SBR) Process shall be an advanced activated sludge
process with in-built nitrification, de-nitrification and biological phosphorous removal.
The process shall utilize a Fill-and-Draw Reactor with complete-mix regime and
operating in true-batch mode. The complete process shall be divided into Cycles with
each Cycle is of duration of 3 – 6 hours. All the subsequent treatment Steps –
Fill/Aeration, Settling and Decanting must take place sequentially and independently
without overlapping. During Fill/Aeration phase, the sewage shall be filled into SBR
Basins and part of the treated sewage along with activated sludge shall be recycled
with the help of Recycle Pumps. Air shall be supplied for aeration with the help of Air
Blowers. During settling phase, the Filling/Aeration shall be stopped and the mixed
Annexure-3 : Revised “ Volume-2(R1)”
158
content shall be allowed to settle under perfect settling conditions. During Decanting
phase, the supernatant shall be removed form top with the help of Decanters and
excess sludge shall be wasted with the help of Waste Pumps. Cycle acceleration /
overlapping during Peak flow shall not be allowed. Bidder shall provide DO sensor, in
each aeration zone of SBR basin /preferably on header of RAS Pump.
8.3.3 Process Design
Sequential Batch Reactor (SBR) Units shall be installed and equipped for average
flow . The SBR Process shall have following independent steps without overlapping
each other:
Fill & Aeration
Settling (Sedimentation/Clarification)
Decanting (Draw)
Filling, during Settling or Decanting will not be acceptable.
Nos. of SBR Basins with adequate volume shall be provided. In addition,
0.50 m Free Board shall be provided to each Basin. Maximum Liquid Depth of each
Basin shall be restricted up to 6.0 m.
The system should work on a gravity influent condition. No influent / sewage
Equalization Tanks or flash filling is accepted.
The entire construction shall be in M30 grade reinforced cement concrete and as
per IS 3370. 5.4.8 RCC Platform/Walkway, minimum 1.20 m wide with G.I Hand
Railing as per specifications shall be provided. RCC Staircase, minimum 1.20 m
wide with G.I Hand Railing as per specifications shall be provided for access from
Finished Ground Level to the top of the Unit & to the Operating Platform/Walkway.
Plinth protection along periphery shall be provided as per technical specifications.
Cycle Time 3 to 6 hrs
MLSS 3500 to 5000 mg/l
MLVSS/MLSS 0.7
F/M Ratio (BOD) 0.1 to 0.15
Solids Retention Time Minimum 10 days
Free Board 0.5 m (Minimum)
BOD Oxidation Oxygen
Requirement
1.2 x Inlet BOD Load
Nitrification Oxygen Requirement 4.56 x TKN Nitrification
Total Requirement BOD Oxidation + Nitrification Oxygen
Requirement
Oxygen Credit (from De-
Nitrification)
Oxygen release during denitrification =
2.86 mg O2/mgN
Max O2 credit of denitrification can be
only 50% of nitrification
Alpha value for Submerged
Diffuser
0.65 (Maximum)
Beta value for Submerged
Diffuser
0.95 (Maximum)
Fouling Factor for Diffuser 0.9
Oxygen Demand Safety Factor 5 %
Annexure-3 : Revised “ Volume-2(R1)”
159
Oxygen content in Air (by weight) 23%
Type of aeration Energy efficient diffused aeration system.
Decanting Device
Type Moving Weir Type/Swing Down
Quantity Minimum 1.0 numbers of decanter per
basin
8.3.4 Decanting Device
The Decanter Device shall be Moving Weir Arm Device of SS304 with top
mounted Gear Box, Electric Drive, Scum Guard, Down comers, Collection Pipe,
Bearings.
Weir loading for each decanter shall not exceed 125 m3/hr/m of the inlet weir.
8.3.5 Aeration System
The aeration facility shall be installed for average flow.
Fine Bubble Type, PU/ EPDM Membrane Diffusers shall be acceptable with
minimum Membrane Diffusers to Floor Coverage Area of 5%. Diffusers shall be
submerged, fine bubble / fine pore, high transfer efficiency, low maintenance and
non-buoyant type. Diffusers shall be tubular type. Complete Diffuser as a unit shall
be assembled at the manufacturing factory level. The grid supports shall of
adjustable type made of SS 304.
The Air Blower Arrangement shall be capable of handling Total Water Level and
Bottom Water Level operation conditions controlled by process sensors such as
DO, Temperature and Level.
Each set of Air Blowers shall have sufficient dedicated standby. All Air Blower
shall be provided with VFD.
The Air Blowers shall be Turbo or Roots Blower type and head for Air Blowers
shall be decided on the basis of S.O.R. of Diffusers and maximum Liquid Depth in
Basin duly considering the losses governing point of delivery (Diffusers) and the
Air Blowers. Air Blowers shall be complete with Motor and accessories like Base
Frame, Anti Vibratory Pad, Reactive Silencer, Non-Return Valve, Air Filter etc. as
per requirements. Further, Air Blowers shall have acoustic enclosure to ensure
that the noise level at 1.00 m from Air Blowers is below 85 db. The Air Blower
House shall have Rolling Shutter, Windows, Exhaust Fans, Safety Equipment with
sufficient Ventilation, Lighting and Working Space. It shall be equipped with
sufficient capacity Electrical Hoist with Travelling Trolley (Min. 3 Ton or 1.5 times
the weight of Air Blower whichever is more) or Manual Fork lift to facilitate removal
of Air Blower / other Accessory for repairs.
The operation of Aeration System shall include PLC based control. The operation
and speed of Air Blowers shall be automatically adjusted using parameters like
Oxygen Uptake Rate, Dissolved Oxygen and Temperature and Liquid Level in the
Basin such that the DO is supplied as per demand and power utilisation for
operation of Air Blowers is optimised.
The main Air Header/Ring Main shall be in MS as per relevant IS Code, painted
with corrosion resistant paint as per Manufacture’s recommendations. The Air
Header/Ring Main shall be supported on saddles at suitable intervals or shall be
protected against external corrosion in case laid below ground. The Sub-header
shall have Auto Valves to facilitate switch over of Aeration Cycle from one Basin to
Annexure-3 : Revised “ Volume-2(R1)”
160
other by PLC. The Sub-header shall supply air to Fixed Type Diffuser Grids at
various locations through vertical Air Supply Pipes. These Air Supply Pipes above
water level shall be in MS, painted with corrosion resistant paint and below water
shall be in SS 304. All under water Lateral Pipes shall be of UPVC. Junctions
between horizontal Sub-header and vertical Air Supply Pipes shall be suitably
protected against corrosion due to dissimilar materials.
All other accessories, whether specified or not, but required for completeness
shall form part of Contractors scope.
8.3.6 Air Blowers
The air blower arrangement shall be capable of handling Total Water Level and Bottom
Water Level operation conditions, controlled by process sensors such as DO,
temperature and level.
All blowers including standby shall be operated through Variable Frequency Drive
(VFD). The blowers shall be Turbo/Positive displacement (roots) type, and head for
blowers shall be decided on the basis of Standard Oxygenation Rate of diffusers and
maximum liquid depth in tank duly considering the losses at governing point of delivery
(diffusers) and the blowers. The number of standby blower shall be minimum 50% (fifty
percent) of the number of working blowers. Blowers shall be complete with motor and
accessories like base frame, anti-vibratory pad, silencer, non-return valve, air filter etc.
as per requirements. Vibration due to operation of blowers should not damage the
structures. Further, blowers shall have acoustic enclosure to ensure that the noise level
at 1 m from blowers is below 85db.
The blower shall be operated through PLC on variable frequency drives and capable to
operate at different speeds as per requirement of the system.
The header / rising main shall be adequately supported at suitable intervals. The sub
header shall have auto valves to facilitate switch of aeration cycle from one reactor to
other by PLC operation. The header shall supply air to reactor at various locations
through air supply pipes. Air supply pipe above water level shall be in MS and below
water level it shall be SS-304. All under water Grid Lateral Pipes shall be of UPVC.
Blower details:-
MOC : CI
Type : Tri lobe type
Capacity : As per design
Discharge Head : Suitable
No. of units : As per design requirement
Head for blowers shall be decided on the basis of S.O.R. of diffusers and
maximum liquid depth in Basin duly considering the losses governing point of
delivery (diffusers) and the blowers
The operation of Aeration System shall include PLC based control. The operation
and speed of Air Blowers shall be automatically adjusted using parameters like
Oxygen Uptake Rate, Dissolved Oxygen and Temperature and Liquid Level in the
Basin such that the DO is supplied as per demand and power utilisation for
operation of Air Blowers is optimised.
The main Air Header/Ring Main shall be in MS as per relevant IS Code, painted
with corrosion resistant paint as per Manufacture's recommendations. The Air
Header/Ring Main shall be supported on saddles at suitable intervals or shall be
Annexure-3 : Revised “ Volume-2(R1)”
161
protected against external corrosion in case laid below ground. The Sub-header
shall have Auto Valves to facilitate switch over of Aeration Cycle from one Basin to
other by PLC. The Sub-header shall supply air to fixed type Diffuser Grid through
vertical Air Supply Pipes. These Air Supply Pipes above water level shall be in
MS, painted with corrosion resistant paint and below water shall be in SS 304. All
under water Lateral Pipes shall be of UPVC. Junctions between horizontal Sub-
header and vertical Air Supply Pipes shall be suitably protected against corrosion
due to dissimilar materials.
The Air Blower House shall have Rolling Shutter, Windows, Exhaust Fans, Safety
Equipment with sufficient Ventilation, Lighting and Working Space. It shall be
equipped with Forklift of suitable capacity or Electrical Hoist with Travelling Trolley
to facilitate lifting / removal / transportation of Air Blower for repair and
maintenance, if required.
Air Blowers for Biological Treatment (Roots or Turbo Type)
Blower details:-
Type : Turbo / Roots type
Capacity : As per design
Discharge Head : Suitable
No. of units : As per design requirement
8.3.7 Return Sludge and Excess Sludge Pumps
a. Return Sludge Pumps
Capacity and Head : As per requirements
Type : Submersible / Horizontal Centrifugal
Liquid : Biological Sludge of 0.8 – 1% solids consistency
Specific Gravity : 1.05
Solid size : 40 mm (Maximum)
Temperature : Min. 25 C
Efficiency : more than 60%
Quantity : 1 No. per Basin + 1 No. Store Standby
b. Excess Sludge Pumps
Capacity and Head : As per requirements
Type : Submersible / Horizontal Centrifugal
Liquid : Biological Sludge of 0.8 – 1% solids consistency
Specific Gravity : 1.05
Solid size : 40 mm (Maximum)
Temperature : Min. 25 C
Efficiency : more than 60%
Quantity : 1 No. per Basin + 1 No. Store Standby
8.3.8 Automation and Control for Biological Reactor
a) PLC based Automation System with application software based on Rockwell or
equivalent to control Reactor System including all Gates, Air Blowers, Pumps,
Valves and Decanters as per Bidder’s/Technology Provider’s own design including
I/Os with 20 % Spares and UPS.
b) HMI Panel shall comprise latest Personal Computer with 22” LCD Monitor, Multi
Media Kit, Printer, Internet Connection, RS-View, RS-Links (Gateway Version),
Annexure-3 : Revised “ Volume-2(R1)”
162
Process and Operator Software with dynamic Flow Charts, Pictures, Screens,
Alarms, Historical Trends, Reports etc.
c) SCADA based Automation System to monitor the following parameters continuously
in each Reactors:
Fill Volume
Discharge Volume
Temperature
DO Level
Oxygen Uptake Rate
Air Blower Speed
Decanter Speed
d) Effluent from Reactor after biological treatment shall be fed to Tertiary treatment,
which consist of Flash mixer, flocculator and Filtration system. Chemicals can be
dosed for better coagulation and flocculation pre filtration.
8.4 Fiber Disc filter (FDF)
Tertiary Treatment Plant shall be designed for average flow and provided in the form of
Disc filters which shall consists of following:-
• Civil (RCC) Tank to house the Fibre Disc filter
• Disc filter assembly with Filter Cloth
• Drive Assembly
• Backwash System
• Control panel & Instruments
The Tertiary Treatment Plant shall conform to the specifications as mentioned below:
8.4.1 Disc filter assembly with Filter Cloth
Disc filter shall comprise multiple high strength and separable discs (proposed by
manufacturer). Each Disc shall be subdivided into smaller sections to constitute a prefab
disc frame (module) so as to ensure easy replacement and maintenance. Each disc
consists of multiple panels. In case of replacement of fibre cloth, the left and right of the
fibre cloth shall be replaced quickly without disassembling of segments (Disc frames).
Each disc shall be mounted on the centre drum by strap band (steel band) for the exact
roundness and it shall not be fixed by Stud bolts. The additional sealing material shall
not be needed for assembling of filter cloth to segment and the fibre cloth itself shall be
acted as the sealing material. Filter cloth shall envelop some parts of backside of filter
frame and the several springs shall be used to fix the filter cloth. The drum shall be
round type and shall have the enough area in order to discharge the treated water
without trouble. The material of the filter cloth shall be polyester; the filter frame that fixes
the filter cloth, the disc frame and the segment cover shall be ABS resin. Central drum
shall be SS304. Maximum Filtration rate shall be 10-12m3/m2/hr. Nominal pore size of
filter cloth shall be approx. 10 micron.
Filter shall be designed for average flow or decant flow whichever is higher. Suitable no.
of units shall be provided. Raw water shall flow into the respective Disc filter by gravity.
The structure shall ensure that Suspended Solids (SS) are filtered (treated) from outside
to inside of the filter cloth installed on both sides of the disc filter, and that filtered water
is discharged through the centre drum to the treated waterway.
Annexure-3 : Revised “ Volume-2(R1)”
163
Sr
No TECHNICAL DATA OF FILTER
1. Type of Disc filter Fully submerged outside to inside
type
2. Type of filter cloth Pile cloth with ABS frame
3. MOC of filter cloth Polyester
4. Nominal pore size, (microns) Approx. 10
5. Maximum Filtration rate (m3/m2/hr) 10 -12
6. Total reject and backwash % < 3
7. Backwash System Automatic Backwash system
based on time and level
8. Head loss across the disc filter unit
(mm) As per design
9. Thickness of drum 4 mm. (minimum)
10. MOC of Centre drum SS 304
11. Filtration mode Continuous
a) Drive Assembly:
Drive part of Disc filter shall be of Worm geared type with motor chain drive. The drive
comprises Drive Motor, Reduction Gears, Chain and Sprocket. Power shall be
transmitted by the SS 304 chain. The reduction gear shall be installed on the base for
access f or the tension adjustment. A protective cover made of SS304 shall be
equipped for the drive motor, reduction gear and the chain. The rpm of the disc filter
drive shall be adjustable by the inverter that is attached in the field control panel.
b) Backwash system
Cleaning device consists of Suction cleaning unit, which conducts the suction cleaning
in the each side of disc, the automatic valve and the suction cleaning pump. Cleaning
device shall clean the contaminated filter cloth thoroughly by the suction unit on both
side of disc with automatic valve and suction cleaning pump which shall be activated by
the water level switch that contacts the water level raised with the increase of the loss
of head. Disc filter should be operated for filtration without the stop during backwash
and suction of sludge. Suction cleaning unit shall be made of or the even cleaning
efficiency without dead zone for all area of filter cloth.
Back wash Recovery system shall consist of flash mixer, Flocculator, Clarifier, Back
wash sludge sump. Sludge generated shall be dewatered using centrifuge. Overflow
from Clarifier shall be sent to FDF.
c) Control panel & Instruments
Control panel shall be SS304, double door (Inner & outer door), IP55, self- standing,
floor-mounted type in case if it is outdoor. Indoor control panels shall be CRCA, powder
coated and self- standing, floor-mounted type. Control panel shall contain PLC, HMI
(6”, colour, touch screen), circuit breaker, relay, terminal blocks, push button switch,
indication lamp, etc. on the door. Control panel shall accommodate an inverter/VFD to
control the rotation velocity of the disc drive. Automatic/Manual switch and indication
lamp shall be equipped in case of breakdown of the automatic interlocking device.
Annexure-3 : Revised “ Volume-2(R1)”
164
Control panel shall have a nameplate displaying the name of the equipment; operation
switch shall have a nameplate indicating its intended use.
8.5 Disinfection System
Disinfection (Chlorination) Units
Disinfection (Chlorination) Units including Chlorination Tank and Chlorinator cum
Chlorine Tonner House shall be designed for Average Flow or Decant Flow whichever
is higher.
8.5.1 Chlorination Tank and Chlorinator cum Chlorine Tonner House
Treated sewage after filtration process unit shall be taken to Chlorination Tank by RCC
Channel/DI K-9 pipe. Gas Chlorine shall be added for disinfection at suitable dosing
rate. Baffle walls shall be provided in the Tank to facilitate hydraulic mixing of treated
sewage. The entire construction shall be in minimum M-30 grade reinforced cement
concrete and as per IS 3370.
Design Flow : Average Flow or Decant Flow whichever is more
Number of Units : 1 No.
Hydraulic Retention Time : 30 Minutes (excluding Outlet Channel after Weir)
Free Board : 0.50 m min.
A Chlorinator cum Chlorine Tonner House shall be provided above/near Chlorination
Tank to house Chlorination Systems. It shall be RCC (M25) Frame cum Brick Masonry
Structure with Rolling Shutter, Windows & Ventilators, Electrical Hoist with Electrical
Travelling Trolley of minimum 3 Ton capacity or 1.5 times the weight of the single Unit
whichever is more to lift the Pumps/Chlorine Tonners and Safety Equipment including
Sand Buckets, Fire Extinguishers and Fire Alarms etc. Also it shall be provided with
IPS Flooring, Internal & External Plaster and Internal & External Painting. Plinth
Protection shall be provided along the periphery as per specifications.
All other accessories, whether specified or not, but required for completion of Contract
shall form the part of Bidder’s Scope.
8.5.2 Chlorination System
Gas Chlorination System comprising Vacuum Chlorinators (2 Nos.), Water Feed
Pumps (2 Nos.), Interconnecting Piping and Appurtenances, Chlorine Gas Detector,
Empty Chlorine Tonners (Suitable for 30 days’ Storage) with Trunions, Lifting Device
and Suspended Weighing Scale, Residual Chlorine Test Kit, Safety Equipment (e.g.
Exhaust Fan, Canisters, Gasmasks etc.), Mandatory Spares, Chlorine Leak Detection
and Chlorine Leak Absorption System including FRP Half Hoods, Caustic Solution
Tank, Caustic Recirculation Pump, Centrifugal Fan, Interconnecting Piping and Ducts
complete and other required ancillary shall be provided. The system must have the
provision for linking its operation to PLC of STP so that quantity of chlorine usage can
be varied automatically as per treated water flow from biological reactor.
Design Flow : Average Flow or Decant Flow whichever is more
Type : Vacuum Type
Capacity of Chlorinator : Suitable as per design
Quantity of Chlorinator : 2 Nos. (1 Working + 1 Standby)
Annexure-3 : Revised “ Volume-2(R1)”
165
All other accessories, whether specified or not, but required for completion of Contract
shall form the part of Bidder’s Scope.
Treated water after chlorination unit shall be disposed off in Buddha Nallah through
RCC pipe.
8.6 Sludge Handling System
8.6.1 Sludge withdrawal from various units.
Sludge withdrawal shall be either by gravity or through pumping. DI Pipes shall be
preferably used for transportation of sludge. Primary Sludge withdrawn from
Clariflocculator units shall be collected in a sludge sump and shall be fed to dewatering
machine. Sludge Collected from UASB and Biological Reactor shall be collected in
sludge sump and shall be fed to dewatering machines.
8.6.2 Sludge Sump
Sludge sump shall be provided to collect the excess sludge from various units. Sludge
Sump and Dewatering Handling units shall be separate for Primary and Secondary
Sludge.
The Sump shall be equipped with coarse Bubble Air Grid made from stainless steel
pipes to facilitate mixing of contents of sludge sump on continuous basis. Alternatively
Submersible mixers of suitable numbers can be provided
Number of Units : 1 (one) nos.
Free Board : 0.5 m
Capacity : Minimum 6 hr holding of average daily
sludge production
Minimum SWD : 3.0 m
Sludge dewatering mechanism can be centrifuge type or belt filter press type of suitable design and capacity.
8.6.3 Sludge Pumps
Sludge Transfer Pumps shall be provided to feed sludge to sludge dewatering units.
The pump shall be suitable for handling biological sludge. All pumps including standby
shall be installed.
Pumps Capacity and Head : Sufficient for handling total daily sludge in 18 hours
Type : Submersible sewage pump
Liquid : Bio-sludge for thickener and dewatering machine.
Solid Size handling : 40 mm (Maximum)
Specific Gravity : 1.05
Efficiency : More than 60%
Installation : Fixed
Quantity : Minimum 2 no. (1W + 1S) for dewatering mechanism feeding
Annexure-3 : Revised “ Volume-2(R1)”
166
8.6.4 Centrifuge Units
The centrifuge shall be solid bowl centrifuge of co-current / counter current design. The
centrifuge shall have sufficient clarifying length and differential RPM so that separation
of solids is effective. The centrifuge shall have central lubrication system. The centrifuge
and its accessories shall be mounted on a common base frame so that entire assembly
can be installed on an elevated structure.
Suitable drive with V-belt arrangement and turbo-coupling shall be provided along with
overload protection device. Centrifuge shall be with SS-304 wetted parts.
Differential speed and bowl speed should be adjusted by changing the pulleys;
differential speed may be adjustable by use of epicyclical-gear. The bowl shall be
protected with flexible connections so that vibrations are not transmitted to other
equipment. The base frame shall be in epoxy painted steel construction and provided
with anti-vibration pads. All steps necessary to prevent transmission of structure borne
noise shall be taken. Adequate sound proofing shall be carried out.
A suitable hoist shall be provided above centrifuge machines for maintenance purpose.
The hoist shall be such that it shall be possible to erect or de-erect the centrifuge while
one is in operation.
Number of centrifuges : At least 2 Nos. (1W + 1 SB)
Type : Horizontal
Operating Hours : 18 hrs. per day maximum
Mixing arrangement of Polyelectrolyte and sludge
: Online mixing
Dewatering polyelectrolyte dosing system is to be provided to dose poly electrolyte
solution to the incoming sludge at entrance to the centrifuge.
8.6.5 Combined Belt Thickener cum Belt filter press units
The Sludge Dewatering Device shall consist of combo units which includes Mechanical
Thickener and Belt Filter Press along with all appurtenances. It shall be designed to
adequately condition and dewater the sludge so that the dewatered sludge cake is
produced that easily discharges from the Belt Filter Press. Flocculator arrangement in
SS-304 of suitable capacity shall be provided at the inlet of each Belt Filter Press for
mixing of sludge and DWPE. All other accessories, whether specified or not, but
required for complete operation shall form part of contractors scope.
Number of Belt filter press : Min 2 Nos (1 W + 1 SB)
Operating Hour : 18 hours per day maximum Design
Inlet Sludge Consistency : 0.8-1.0 %
Outlet sludge consistency : Minimum 20%
Mixing arrangement of Polyelectrolyte and
sludge
: Online-mixing
Annexure-3 : Revised “ Volume-2(R1)”
167
Dewatering polyelectrolyte Dosing system is to be provided to dose Poly Electrolyte
solution to the incoming sludge at entrance to the belt filter press. The supernatant from
Belt Filter shall be taken by gravity to Wet Well of MPS/Inlet of STP. The pipes below
Ground shall be RCC NP-3, with HDPE lining, whereas the pipes above ground shall be
of SS-304. Combo unit including Mechanical Thickener and Belt filter press shall be
capable of handling sludge consisting of minimum 0.8% solids by weight. The
dewatered cake shall be based on minimum consistency of 20% by weight dry solids.
MOC shall be SS-304. General Equipment furnished and installed under this section
shall be fabricated, assembled, erected and placed in proper operating condition in full
conformity with the drawings, specifications, engineering data, instructions, and
recommendations of the equipment manufacturer, unless the engineer notes
exceptions.
Workmanship and design: All components of the sludge dewatering equipment shall
be engineered for long, continuous, and uninterrupted service. The unit shall be fully
enclosed “multi-stage” type comprised with three belts. Gravity section shall be
comprised with an individual speed variable gear motor. All bearings, electrical and
pneumatic components shall be located on periphery of the frame allowing easy access
for the operator for overhauls. Sufficient number of removable inspection hatches shall
be located on each side of the unit to observe the factions of the unit. The sludge
dewatering system shall consist of belt filter press (es) and all appurtenances. Each belt
filter press shall be a fully enclosed having monologue frame construction, complete
prefabricated unit consisting of at least a sludge conditioning system, a gravity drainage
section, a pressure section, a belt alignment and tensioning system and a belt washing
system. Only units having an effective belt width of 1.0– 3.0 meter shall be considered
acceptable under this specification. The unit(s) shall be the “multi-stage” Belt Filter
Press (es) type.
8.7 Manual and Auto Valves / Gates
The bidder shall have to provide required No. of valves operated manually as well as with automation for running of plant.
8.7.1 Chain Pulley Block, Mono Rail, Electric Hoists
Mono Rails
This includes supply, erection, testing and commissioning of adequate capacity mono rails.
Lifting electric hoist arrangement for various unit of ETP
This includes supply, erection, testing and commissioning of lifting equipment with all accessories suitable in various units of the ETP
Sr. No.
Description of unit
Type of lifting
Type of movements Capacity
1 Blower room Electric operated hoist
Three-way movements e.g. vertical, longitudinal and transverse
Minimum 1.5 times the weight of blower/motor
2 Dewatering mechanism
Electric operated hoist
Three-way movements e.g. vertical, longitudinal and transverse
Minimum 1.5 times the weight to be lifted.
Annexure-3 : Revised “ Volume-2(R1)”
168
Sr. No.
Description of unit
Type of lifting
Type of movements Capacity
3 Sludge Pump House
Manual operated hoist
Chain Pulley Block/ Monorail
of adequate capacity
Minimum 1.5 times the weight to be lifted.
4 Tonner shed Electric operated hoist
Three-way movements e.g. vertical, longitudinal and transverse
Minimum 3.0 ton capacity
5 Raw Sewage Pumping Station
Manual operated hoist
Three-way movements e.g. vertical, longitudinal and transverse
Minimum 3.0 ton capacity
The above list is indicative. Actual required / Installation capacity of electric hoist, ``
Chain Pulley Blocks
This includes supply, erection, testing and commissioning of adequate capacity chain pulley block with all the accessories. It should be compatible with the lifting chain of the pump.
Chain Pulley Block of adequate Capacity : As per requirement
8.7.2 Sludge Pump House(s)
Pump house shall be near sludge sump. This shall be RCC frame and brick masonry
structure. Minimum height of the pump house shall be 4 m from the plinth level. It shall
be provided with rolling shutter and doors and windows. A chain pulley block of
adequate capacity along with girder and pillar arrangement shall be provided.
The pump house shall be painted from inside and outside with approved colour and
make as directed by Engineer-in-Charge. The pump house shall house-
Pumps for feed to dewatering mechanism (working + standby)
Air blowers for Sludge Sump (working + standby) or Submersible Mixers
DWPE dosing pumps (working + standby)
8.7.3 Chemical Dosing Tanks
Suitable number and capacity dosing tanks with required inner lining and agitators are
to be provided.
Polyelectrolyte Dosing System shall consist of Dosing Tanks equipped with Slow
Speed Agitators and Diaphragm type Metering Pumps. Polyelectrolyte shall be dosed
online at the inlet of Centrifuges. Minimum dosage of polyelectrolyte shall be 0.50 –
1.50 Kg/Ton of dry solids at 0.1% solution strength. The solution will be dosed using
mechanically actuated Diaphragm type Metering Pumps. Dedicated Dosing Pumps
shall be provided and shall be interlocked with Centrifuge in such a way that they
Start/Stop along with Centrifuge/ Screw Press.
2) Dosing Tanks:
Design Capacity : As per requirement
Number of Units : As per requirement
Hydraulic Retention Time: Suitable for min. 8 hours of
Operation Free Board : as per design.
Annexure-3 : Revised “ Volume-2(R1)”
169
3) Dosing Pumps:
Capacity and Head : As per requirement
Type : Mechanically Actuated Diaphragm Type Metering Pump
Liquid : Polyelectrolyte Solution of 0.1%Strength
Quantity : one each per dewatering machine
8.7.4 Civil Structure for Mechanical De-watering Machines
Building of sufficient size to accommodate mechanical dewatering Units Combined
Mechanical Thickener cum Belt Press or Centrifuges (Working + Standby) shall be
constructed with sufficient floor height above Ground Level to park sludge collection
vehicle directly under the sludge discharge line of centrifuge. The room shall have a
RCC roof at a height suitable for installing EOT. Minimum floor area of the building
shall be sufficient to accommodate mechanical dewatering unit. It should be framed
RCC structure with the top roof also in RCC. The dewatered sludge shall have a
minimum solids concentration of 20% or more (measured as dry solids w/w basis) so
that it can disposed by open body Trucks/Trolleys.
8.7.5 Sludge Storage Platform
A sludge storage platform shall be provided at a suitable location within the plant area
for storage of de-watered sludge, minimum for a 7 days storage capacity. Flooring of
the platform shall be 75 mm thick PCC (1:2:4) laid over 100 mm thick stone ballast.
Level of platform shall be at least 20 cm above the level of approach road. From
sludge storage platform, the sludge shall be disposed of by the contractor.
Notes:
For Tajpura ETP
Proposed area is given in two parts approximately at 1 km distance. Hence, Process
Units and operational Buildings shall be designed accordingly.
H.T Transformer, Metering Room , D.G. MCC, PLC, Rooms needs to be designed at
both parts of area.
8.8 Operations Buildings
8.8.1 Office, PLC Room etc
The building shall be constructed to house the following as a minimum on
i. PLC/Main LT (MCC) Room –as required
ii. Office rooms for the officers and staff with Lavatory cum Toilet block of required
size/area along with sanitary fittings as decided by the Engineer –in- Charge.
- One passage app. 2m wide.
iii. Workshop cum Tool Room
iv. Stair case up to terrace will be provided.
The height of ceiling shall be minimum 3.5 M from the floor level or higher to
suit the requirement. Adequate no. of toilets and wash basin shall be provided
separately for men and women and a separate toilet attached to the office room
shall be provided. A covered service water overhead tank of capacity 5 cum
shall be provided to cater to the water requirement of building and process
requirement.
Annexure-3 : Revised “ Volume-2(R1)”
170
8.8.2 Blower Room
Sufficient area blower room with a minimum clear height of 5.00 mtr shall be
constructed to accommodate all the blowers for biological Reactors and other
requirements. Minimum space on other three sides of blower room will be 1.5 m
from the blowers. The blower room shall have sufficient ventilation, lighting and
working space. Control panels for air blower shall be placed in air conditioned
room, in blower room, if required. The room will be equipped with sufficient
capacity EOT (Min 2.0 times the weight of blower/motor) to facilitate removal of
blower/motor etc. for repairs. The room will also have rolling shutter or aluminium
glazed doors and windows.
8.8.3 Staff Quarters
The bidder shall have to construct single storey quarter for the operational staff.
The total no. of quarters and covered area shall be 80 m2. The provision in the
staff quarter consists of one bedroom, one drawing cum dinning, kitchen, store and
toilet. The construction material for walls shall be brick work in Cement Sand
mortar 1:5, RCC roof slab shall be (M 25). The door and windows shall be of
commercial hollock wood.
8.8.4 Other Buildings
One toilet block for operators, one guard room and one meter room of sufficient
size as approved by Engineer-in-Charge shall be constructed.
8.8.4.1 Painting specifications common to all the buildings
Sr.No Description Specifications
1 Roof Water Proofing Brick Bat Coba
2 Plaster
i Walls inside Cement Mortar 1:4, 20 mm thick
ii Walls outside Cement Mortar 1:4, 12.5 mm thick
iii Roof including
cantilevers
Cement Mortar 1:3, 10 mm thick
3 Painting
i External Cement based paint
ii Internal Plastic emulsion
4 Dado/ Skirting Same material as on flooring 2.10 m
high in toilet block and 0.15 m high
in all other rooms / spaces
5 Doors / windows Aluminium
Adequate number of Toilets and Washbasins shall be provided separately for Men &
Women at each floor. A covered Overhead Tank of capacity 5 m3 shall be provided
along with an Underground Water Tank of capacity 10 m3 to cater to the water
requirements of the Building
Annexure-3 : Revised “ Volume-2(R1)”
171
8.8.4.2 Schedule of Finishes
Sr.
No.
Unit Flooring Doors Windows /
Ventilators
1 MCC Room, PLC &
Control Room
Marbonite flooring of
approved make. The
size of Marbonite tiles
shall be min 600 mm x
600 mm & thickness
min 10– 12 mm
Solid Core Flush
Door with heavy
duty Brass
Fittings of
approved make
Aluminum of
approved
make
2 Reactor Air Blower
Room, Workshop &
Tool Room,
Chlorinator cum
Chlorine Tonner
House, Thickener
Dilution Water Pump
Houses, Electrical HT
Substation, DG House
IPS Flooring with
Abrasion
Resistant
Additives of approved
make
MS Rolling
Shutter of
approved make
Aluminum of
approved
make
3 Centrifuge / Thickener
cum Belt Press House
Anti-Skid Tile Flooring
of approved make
--- ---
4 Vehicle Parking Area Coloured Pre-cast
Heavy Duty Paving
Blocks with Lacquer
Finish
--- ---
5 Toilet Blocks Coloured Glazed Tiles UPVC of
approved make
UPVC of
approved
make
6 Staircase: Inside
Building
Grey Granite Flooring
of approved make
--- ---
In addition, the Building shall be provided with Passages, Wooden/Aluminum/Glass
Doors / Windows / Ventilators and Safety Equipment including Sand Buckets, Fire
Extinguishers and Fire Alarms etc. Adequate Flooring shall be provided in various
Rooms/Areas as per requirement or as per instructions of the Engineer-in-charge.
Internal & External Plaster with Painting shall be done as per instructions of the
Engineer-in-charge. Plinth Protection shall be provided along the periphery as per
specifications.
The Building shall be provided with the following:
Sr.
No.
Item of work Work
1 Personal Computer in
PLC/Control Room
2 Nos. of latest version & configuration
complete.
2 Printer in PLC/Control
Room
1 No. of A3 Size Laser colour Printer of latest
version & configuration complete.
Annexure-3 : Revised “ Volume-2(R1)”
172
3 Telecommunication
Facility
Min. 1 No Telephone Line with a Broad Band
facility. The chargers will be borne by the
Contractor up to the O & M Period.
4 Plant Model 1 No. Wall Mounted Process Model
(Electronic Plant Display Model) with Flow
Diagram (Minimum size 3 m x 1.5m)
1 No. 3D Model with display of flow direction
andlighting.
5 Air Conditioner Adequate nos. of Air conditioners shall be
provided as directed by Executive Engineer
8.9 SUB STATION (HT METER ROOM, HT PANEL ROOM, TRANSFOMER, PCC &
MCC PANEL ROOM)
Two nos. Transformers, 1 each for STP and Pumping Station of full capacity and as
per PSPCL norms shall be provided at STP area.
The Electrical Substation shall be provided to accommodate components comprising
HT Panel, Outdoor Transformers, Power Control Centres etc. Outdoor Transformers
shall be installed in open adjacent to Sub-Station building covered with fence and
gate with fire wall between two transformers as per IE rules and PSPCL norms.
Location of HT Meter Room shall be as per PSPCL norms.
Sub-Station building shall be RCC (M25) Frame and Brick Masonry Structure
equipped with Rolling Shutters, Windows/Ventilators, Exhaust Fans and Safety
Equipment’s including Sand Buckets, Fire Extinguishers and Fire Alarms etc.
complete as per PSPCL norms and IE rules. Also it shall be provided with IPS
Flooring, Internal and External Plaster with Painting and Plinth Protection along the
periphery as per specifications.
DG Set Area
The DG Set area with shed, foundation for DG, Safety Equipment’s including Sand
Buckets and Fire Extinguishers shall be provided adjacent to Sub-Station building to
accommodate DG Set including AMF Panel, Fuel Tank and other Accessories. DG
Set shall cater to entire load of STP and average flow plus other misc. load of MPS.
Separate DG Set shall be provided for STP and MPS.
8.10 Process piping / drain piping/ channels
This shall include inter connecting pipelines / channels between different units of ETP
and fulfillment of contract limits.
All pipe networks shall be designed for peak flow.
Combination of pipes and channels can be used for conveyance of waste
water as per requirement of site conditions.
The sizes of pipes shall be calculated to meet following criteria:
Annexure-3 : Revised “ Volume-2(R1)”
173
Piping: Guide Line for Velocity
Notwithstanding the above, the Tenderer shall submit a Pipe Line Schedule with Tag
No., Flow, Size, Type, Material of Construction etc. with detailed P & ID for approval of
the Engineer-in-charge prior to any further engineering or procurement/fabrication and
installation.
Generally, the Material of Construction shall be selected based on the following guide
lines. The Tenderer can make suitable selection depending on Service, Type of Flow
(i.e. Gravity or Pressurized) and Diameter of Pipe.
Piping: Guide Lines for MOC
Sr. No.
Service Design Velocity m/s
Limitations
1 Gravity Lines for Sewage & Water
0.6 – 1.2 Designed as pipe line flowing full.
2 Pressure Lines for Sewage & Water
0.6 – 1.5
3 Air (Pressurized Lines) 12 – 18
4 Scum & Sludge Lines 0.6 – 1.5 Irrespective of flow, Diameter shall not be less than 150 mm for Gravity Lines.
5 Chemical Feed Lines 0.6 – 1.5 Irrespective of flow, Diameter shall not be less than 20 mm.
Sr.
No.
Service Type of Flow MOC
1 Waste Water / Sludge Gravity RCC NP-3 Class with HDPE lining
/ DI-K9 2 Waste Water / Sludge Pressurized CI / DI K-9
3 Service Water Gravity /
Pressurized
Inside Room – CPVC /MDPE / GI
Outside Room – DI for 80mm &
above/ GI for lower sizes.
4
Air Lines: Headers,
Vertical Down-comers
Pressurized Above Water: MS "C" Class, Sand Blasted and Epoxy Painted
Under Water: SS 304
Under Ground : MS with Coating
and Wrapping
In Blower Room: Pipe Insulation
with Resin Bonded Glass wool in
Rigid Board. Kindly refer detail
Mechanical specifications.
Annexure-3 : Revised “ Volume-2(R1)”
174
Valve: Guide Line
Sr.
No. Service
Typ
e MOC
End
Connection
A Sewage / Sludge
1
Gravity /
Pressurized Knife Gate
CI Body & SS 304
Gate & SS 410
Spindle
Flanged
2 Delivery of Pump Swing
Check
CS Body & SS 304
Internals Wafer
3
Suction & Delivery of
Pump Knife Gate
CI Body & SS 304
Gate & SS 410
Spindle
Flanged
B Service Water
1 Gravity /
Pressurized Ball
CS Body & SS 304
Internals Flanged
2 Delivery of Pump Swing
Check
CS Body & SS 304
Internals Wafer
3 Suction & Delivery of
Pump Butterfly
CI Body & SS 304
Internals Flanged
C Air
1 Pressurized Ball CS Body & SS 304
Internals Flanged
2 Delivery of Blower Swing
Check
CS Body & SS 304
Internals Wafer
3 Suction & Delivery of
Blower Butterfly
CI Body & SS 304
Internals Flanged
D Chemicals
1a Gravity /
Pressurized Ball
As per Chemical
Compatibility Chart Flanged
1b Gravity /
Pressurized Diaphragm
As per Chemical
Compatibility Chart Flanged
1c Gravity /
Pressurized Plug
As per Chemical
Compatibility Chart Flanged
Notwithstanding the above, the Tenderer shall submit a Valve Schedule with Tag No.,
Flow, Size, Type, Material of Construction, End Connection etc. with detailed P &ID for
approval prior to any further engineering or procurement/fabrication and installation.
5a Air Grid Piping: Aeration
Zone
Pressurized UPVC Schedule 40
5b Air Grid Piping:
Selector Zone
Pressurized SS 304
6 Chemicals Gravity /
Pressurized
SS 304 except Chlorine & FeCl3
7 Chlorine & FeCl3 Gravity /
Pressurized
Schedule 40 UPVC
Annexure-3 : Revised “ Volume-2(R1)”
175
8.11 Security Cabins
Security Cabin of size 4.00 m x 3.00 m with washroom shall be provided at entry Gate
of the Plant. It shall be RCC (M25) Frame and Brick Masonry Structure equipped with
Doors, Windows/Ventilators, etc. complete. Also, it shall be provided with Flooring,
Internal and External Plaster with Painting and Plinth Protection along the periphery as
per specifications.
8.12 Site Development
Site development of whole land should be done by the bidder maintaining plinth level
around structures, top level of roads/pavements, lawns, landscaping etc. Lawns should
be 15 cm below top level of roads and pavements.
8.12.1 Boundary Wall
Construction of brick work boundary wall including MS Gate etc. complete in all respect
as per drawing is in the scope.
8.12.2 Roads& Pavement
Roads and pavement shall be proposed by the contractor, so as to access each and
every unit of the constructed works. These roads and footpaths shall be 4.2 m and
2.2m wide respectively. The roads/pavements shall be made of paver blocks. Cement
Concrete Kerb & Channel (1:2:4) shall be provided on both sides of the road. The Kerb
& Channel shall be 30 cm x 60 cm x 10 cm. Dowel shall be provided on both side of the
road with earth filling in proper slope and compaction as per direction of Engineer-in-
Charge.
8.12.3 Sewerage System, Drainage System and Storm Water System
The waste water collected through down take pipes of grit chamber / screen channel,
inlet chamber and other units shall be carried through RCC Pipe / uPVC Pipe upto inlet
chamber of ETP/MPS. This may require provision of pumping arrangement.
In addition to this the waste water of operation building shall also be carried to this
sewerage system. Provision shall be made for collection of sludge filtrate from sludge
platform and mechanical dewatering for its connection to proposed sewerage system.
The required no. of manholes shall be constructed as per drawing submitted by the
bidder and approved by Engineer-in-Charge before execution of the work. The bedding
and haunches of pipes shall be as per the specifications approved by the Engineer-in-
Charge.
The bidder shall also provide suitable arrangement for disposal of storm water of the
plant area.
8.12.4 Water Supply Arrangement
The bidder shall provide internal water supply scheme in the plant area. The main
water supply lines shall be of suitable size and of Ductile Iron (K-7) / MDPE/CPVC
Pipe/G.I. Class B. However, service connection to buildings / equipment / process units
will be of MDPE/CPVC. The supply of water shall be made through small tube-well to
be bored within the plant area. The bidder shall have to provide complete water supply
system including underground water storage tank of suitable capacity (subject to
minimum of 10 Cum) and over roof tanks wherever required. The water supply system
shall include making provision of hydrants / nozzles for washing of the various units /
Annexure-3 : Revised “ Volume-2(R1)”
176
pipelines. A booster pump of suitable capacity shall be provided for pumping the water
to above said units. Provision for all required pipes, specials, overflow pipes and bell
cock sluice valves shall also be included.
b) Small Tube well: It shall consist of a bore of suitable size and depth with PVC
casing pipe / filter housing a submersible pump set of suitable capacity complete in
all respect for pumping out water to meet the requirement of plant operation,
watering of plants, cleaning and staff requirement for daily use. Water should be
suitable for construction and drinking purposes.
8.13 Disposal of treated effluent
8.13.1 Treated Effluent Channel / Pipe
The treated effluent after disinfection is to be either used for irrigation or disposed of
into the adjoining drain. Hence bifurcation chamber of suitable size with 2 control gates
and weirs is required to regulate the flow as per irrigation demand. The carrying system
can be either a RCC Channel or pipe. The pipe can be RCC with HDPE lined.
In case provision of secondary pumping station is required to pump the treated waste
water into the drain or achieve water level as prescribed elsewhere in the bid
document, the necessary arrangements like construction of sump, pump chamber,
suction and delivery mains, control valves / gates and all electrical mechanical systems
shall also be in the scope of work.
8.14 Miscellaneous
8.14.1 Stairs
RCC / MS staircase (minimum 1.2 m wide) shall be provided to access all the platforms
provided/required for all the units above ground level. The tread shall be 250 mm and
rise shall not exceed 175 mm. The width of the staircase and their type shall be as
approved by Engineer-in-Chief before execution of the work.
8.14.2 Railings
Railing shall be provided along all the platforms above the ground level and staircases.
The railings shall consist of three horizontal rows of 40 mm i/d GI pipe, Class C
supported on CI pedestals 1 m high fixed at interval of 1.5 m c/c.
8.14.3 Painting, Whitewashing and Allied Works
Operations Buildings
All the units/items/equipment of the Operations Building shall be painted/coated
wherever required. All the internal surfaces of the walls and ceiling of buildings shall be
painted with plastic emulsion paint. All the external surfaces of operations building shall
be cement based paint.
Water Retaining Structures
The inner concrete surfaces of all the water retaining structures including channel shall
be painted (two coats) with approved make anticorrosive/epoxy paint.
Pipes and specials
All the MS / CI / DI pipes and specials and other equipment shall be painted with two
coats of approved make anti corrosive paints.
Annexure-3 : Revised “ Volume-2(R1)”
177
8.14.4 Lowering of ground water table during construction
The ground water table, if encountered, during construction shall be lowered sufficiently
so as to enable construction in dry conditions
8.15 Electrical & Instrumentation Works
It shall be the Contractor’s responsibility to obtain adequate incoming HT power from
State Electricity Authority (PSPCL) based on total plant load and as per PSPCL norms.
The Employer will pay the charges for obtaining the above connection whereas
necessary liaisoning for the same shall be done by the Contractor in consultation with
Engineer-in-charge.
Two nos. Transformers, 1 each for STP and Pumping Station of full capacity and as
per PSPCL norms shall be provided. These shall be step down Transformers
suitable for outdoor installation and as per specification given in Volume-2 Part-4.
The entire Plant shall be operated on 415 V, 3-Phase, 50 Hz, 4-Wire system. The
Contractor’s Scope of Work shall include the following:
Obtaining incoming HT Power from PSPCL including necessary liasoning,
documentation etc. complete.
HT Cable with Termination Kit from “Source” to the Electrical HT Substation
located at the Sewage Treatment Plant.
HT Substation including 4-Pole Structure, HT Panel, Transformers, Power
Control Centre with APFC Capacitor Panel etc. complete.
Motor Control Centres.
Silent DG Set with AMF Panel & other accessories for entire load of STP and
average flow plus other misc. load of MPS.
LT Bus-Duct
Power, Control and Instrumentation Cables including trays, ducts, support etc.
ACDB, DCDB, Battery & Battery Charger, UPS
Earthing for Electrical equipment’s as well as Instruments, PLC/SCADA.
Lightening Protection
Complete Indoor & Outdoor Lighting System.
Local Control Panel, Field JB, welding receptacles.
Local Push Button Stations near respective Drives.
Fire detection & Alarm system, plant communication.
Flow Meters at inlet, outlet & by-pass.
Level Transmitter, DO Transmitter, Pressure Gauge, Auto Valves
Online Monitoring System for raw and treated sewage quality.
CCTV System
Safety items (shock treatment chart, first aid box, CO2 fire extinguisher,
insulating mat, hand gloves, caution boards, LED signage, sand buckets,
discharge rods etc.)
All civil works required for complete installations.
Any other item / accessories required as per process requirement and for
successful completion of the Project.
Annexure-3 : Revised “ Volume-2(R1)”
178
The Contractor shall design/execute the System as per specifications (Volume-2 Part-
4), I.E. Rules and Regulations, requirements of PSPCL and other local Authorities
and actual site conditions.
Also, the Contractor shall provide PLC/SCADA based Automation for entire plant as
described in below clause.
8.16 PLC/PC/SCADA BASED AUTOMATION SYSTEM FOR ENTIRE PLANT
The complete Plant shall be designed for automatic operation through Programmable
Logic Control (PLC) and Supervisory Control and Data Acquisition (SCADA). This shall
be achieved by either individual equipment PLCs with SCADA/HMI or single PLC and
SCADA for entire Sewage Treatment including pumping stations. Operation of primary
treatment units and sludge dewatering units shall be manual however indication of
operation of primary treatment units and sludge dewatering units shall be on
PLC/SCADA. These shall be located at control room of the STP.
The plant shall have provision for operations in following modes –
i) Automatic – Auto operation through PLC/digital controller.
ii) Manual – Operator intervention through SCADA/HMI.
iii) Local – Local operation through local control panel located near equipment.
Audio Visual Alarms
Audio visual alarms shall be initiated under emergency or equipment trip conditions,
other than usual service alarms. Salient features of the proposed control system shall
be as follows:
Dynamic display of all Units, equipment and drives shall be available on
SCADA screen.
It shall Acquire, process and manage the processed data.
It shall safeguard the process by means of interlocks and alarms.
Auto/Manual operation of each drive shall be made by selecting a soft switch
on SCADA/HMI screen.
In Auto mode, each drive shall operate based on pre-set sequence and
interlock. Also automatic change over from working to standby drive shall
happen after a drive reaches pre-set hours of operation.
In Manual mode, each drive shall be operated in Local/Remote mode by
selecting a soft switch on SCADA/HMI screen. In Local mode, each drive shall
be operated from the Local Push Button Station (LPBS) located nearby. In
Remote mode, operation from LPBS shall be disabled and each drive shall be
operated manually from PLC. Also provision for working/standby selection of
drives by selecting a soft switch on SCADA screen shall be provided.
Run/Trip indication of all drives shall be displayed on SCADA/HMI screen.
Open/Close indication of all Auto Sluice Gates and Auto Valves shall be
displayed on SCADA/HMI screen.
Annunciation & Alarm facility shall be available in PLC/HMI/SCADA. In the
event of a Fault, the symbol representing the equipment/drive shall continue
flashing on SCADA/HMI screen with equipment/drive description appearing at
bottom of the SCADA/HMI screen and electric Hooter shall continue blowing
until the Fault Alarm is acknowledged.
Data logging of Running Hours of each drive, Alarms, Historical Trends of
monitored Parameters, etc. shall be envisaged in SCADA.
Annexure-3 : Revised “ Volume-2(R1)”
179
Report generation for plant performance.
The process system must have pre-configured software packages which can be
adapted to the process by parameterization.
The monitor images must be designed to be user-friendly by hierarchical breakdown
with the possibility of selective display and optimum selection possibilities.
Changing of parameters and other software units must be possible "online", i.e. with
the system running.
Different alarms colors provide information on their priorities.
For the system engineering offered, the Contractor must take measures, e.g. by the
installation of surge voltage arresters or surge voltage filters, to ensure that internal and
external surge voltages do not impair the function of his parts of the system.
The programs and data entered must be backed up in a non-volatile read-only
memory.
A limit value and plausibility check must be provided in the software of the process
station for the measured values and messages. Exceeding of limit values or deviations
detected by the above checks must trigger an event and cause a message to be sent.
Further demanded features of the process system:
Integrated, detailed error message and fault detection concept with display on
the HMI/SCADA for quick localization of faults. The system operator must be
able to identify the fault from the error.
Essentially maintenance-free
Robust against external interferences of all kinds
Proven design and solder-free connection technique
Protection of the equipment against surge voltages
Automatic fault detection and quick troubleshooting in the PLC system by
integrated, hierarchically structured diagnostic devices
Power supply in wide admissible voltage range
Simple function-oriented operation
The process system (PLC, HMI/SCADA) shall be protected against power failure by an
uninterruptible power supply (UPS). When the critical charge state of the UPS is
reached, the process system is automatically shut down.
a) Mode selector switch A mode selector switch is to be installed on the MCC or distribution board. It serves for
pre-selection between Automatic mode and Manual/Local mode.
The following switching functions must be provided:
Automatic – Manual/Local
Automatic: In this position, only automatic operation is possible; the local
switches have no function (Except emergency stop).
Local: Automatic mode cannot be started. The drives can be operated individually
without interlock with the local switches.
Local switches (LPBS)
Each drive must be equipped with a local switch positioned in such a location that the
corresponding machine or conveyor can be switched on in Manual/Local mode and can
be monitored visually at all times.
Annexure-3 : Revised “ Volume-2(R1)”
180
The local switch must have the following switching functions:
START – STOP (for drives with one direction of rotation)or
FORWARD – STOP - REVERSE (for reversible drives)
If a unit has several drives (e.g. conveyor belt drive and travel drive), the local
switches should be installed if possible in one switch box or at least installed
next to one another.
Each local switch must be adequately labeled in plain text so that no operator
errors can occur.
b) PLC The automatic start-up of the whole system, sequential operations and the automatic
shutdown, allowing for external control influences, e.g. EMERGENCY STOP, etc., is
performed by programmable logic controller (PLC).
This performs not only the control of the system, but also the display of the operating
state in the HMI/SCADA.
The interlocks of the individual process groups and their signaling must be performed
by the PLC.
A system must be selected which is sufficiently protected against external interference
in the supply, control and signaling lines. The aim is that the program can continue to
run without fault signals in the event of transient earth faults in the supply grid. In the
event of prolonged power failures, on the other hand, a controlled restart must be
triggered (under-voltage trip of the non-automatic circuit breaker).
PLC Specifications: Technical
The PLC shall be non-redundant.
PLC of individual equipment shall be selected to carry out necessary
operations without overloading the PLC memory.
The PLC shall have adequate I/O per card.
There shall be 15% spare I/O of each type.
The CPU shall not be loaded more than 60% of its capacity.
Retentively shall be 100% to save the recorded data and saving the
programmed logic, other attributes connected with system for power & system
failure.
Change in programme / modifications to programme shall be possible by a
portable laptop.
It is preferred to have all PLC’s in the plant from same manufacturer.
HMI/SCADA system
The HMI system shall be designed as a minimum 6”, color, touch-screen on the panel.
Whereas SCADA system must be computer based.
All displays must be designed by the Contractor with graphic sophistication and all
texts in the visualization system must be displayed in English.
A sub-menu for each operating mode and further menus for editing the system
parameters, fault archive, etc., must be developed. It must be as simple as possible to
switch between the various menus and to edit the system parameters.
When designing the user interface or the assignment of the function keys, attention
must be paid that the function key assignment remains the same in all sub-menus so
Annexure-3 : Revised “ Volume-2(R1)”
181
that it is possible to jump to another menu without first having to jump back to the main
menu.
It must be possible to edit the following parameters at the touch-panel and SCADA:
Operating mode
Changes in the speeds of frequency converter-controlled equipment
Start-up times
Shutdown times
Duration of the operation of warning devices
Limit values for sensors, etc.
Faults, level messages, pressed EMERGENCY STOP buttons, etc., must also be
clearly displayed at the bottom of the screen, irrespective of the selected screen page
or sub-menu.
It must be possible to output all important menu items to the printer. The corresponding
interfaces must be provided.
The display of the function plans, images, etc. is affected in direct dialog with the
system by means of the mouse and keyboard.
The central SCADA shall generate various reports to analyze plant performance. The
process is documented via the laser printer.
c) Computer hardware and software All programs required for operation of the system must be correspondingly compatible. The corresponding licenses must be supplied for the standard programs. The operating systems must be agreed upon with the Client. Minimum requirements shall meet:
CPU
1. Processor Intel i7 10th Gen
2. Processor speed 4 GHz or higher
3. Configuration Tower
4. Architecture 64 bit
5. System memory
(RAM)
16 GB
6. Hard disk 256 GB SSD+ 1 TB HDD
7. DVD Drive Combo (Read/Write)
8. Operating system Microsoft Windows 10 professional
9. Communication
ports
USB – 4 Nos., Ethernet – 1 Nos.
10. Graphic
accelerator
2 GB
11. Power supply 240V, 50Hz, 1Phase
12. Keyboard Internet Keyboard (with USB interface)
13. Mouse Optical, 3 buttons (with USB interface)
Monitor
14. Type Full HD LED color monitor
15. Screen size 24” or higher
16. Resolution 1920 x 1080
17. Power supply 240V, 50Hz, 1Phase
Annexure-3 : Revised “ Volume-2(R1)”
182
Complete Project shall operate in auto mode. As a minimum, following controls must
be considered in Bidder’s Control Philosophy:
i. Coarse screens
Each mechanical coarse screen shall be installed with ultrasonic differential level
transmitter / level switch, across it; the same shall be operated on the basis of set
differential level in SCADA. Also if differential level is not reached for certain time
period, the screen shall be operated on the basis of set time in SCADA.
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA. In manual mode the screen operation will be done from SCADA screen.
Physical switch over of screens in plant will be done by operator using manual gates.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered in
PLC for auto operation of coarse screen.
ii. Raw Sewage Sump and Pumps
The sump will employ an Ultrasonic level transmitter to measure level. The combined
operation of Raw Sewage Pumps will be dependent on rate of change of level with
reference to time. The selection of Auto/Manual and Working/Stand-by shall be made
available in SCADA. In manual mode the pump Start/Stop will be done through SCADA
screen.
A clamp on type Ultrasonic or Electromagnetic flow transmitter shall be provided at
common header of pumps for measurement of flow to sewage treatment plant. PLC
shall calculate instantaneous flow as well as cumulative flow, both shall be displayed
on SCADA.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered in
PLC for auto operation of Raw Sewage Pumps.
iii. Inlet chamber
A clamp on type Ultrasonic flow transmitter shall be provided on rising main of inlet
chamber for measurement of flow coming to Sewage Treatment Plant. PLC shall
calculate instantaneous flow as well as cumulative flow, both shall be displayed on
SCADA.
iv. Fine screens
Each mechanical fine screen shall be installed with ultrasonic differential level
transmitter / level switch, across it; the same shall be operated on the basis of set level
in SCADA. Also if level is not reached for certain time period, the screen shall be
operated on the basis set time in SCADA.
The selection of Auto/Manual and Working/Stand-by shall be made available in
SCADA. In manual mode the screen operation will be done from SCADA screen.
Physical switch over of screens in plant will be done by operator using manual gates.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered in
PLC for auto operation of fine screen.
v. Grit Chambers
Each grit chamber will consist of Detroiter (1No.), Organic Return Pump (1No.) and
Screw Conveyor for grit removal (1No.). As such Detroiter, Organic Return Pump and
Screw Conveyor will not have auto operation; these will be started and stopped from
SCADA screen as required.
Annexure-3 : Revised “ Volume-2(R1)”
183
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC for
operation of Grit chamber equipment.
vi. Anoxic Reactor
Complete operation and control of ETP plant will be done through a separate PLC and
SCADA. However it shall have necessary inputs and generate required outputs to
operate in co-ordination upstream and downstream units of balance plant.
Alternatively contractor may provide single PLC and SCADA for entire Sewage
Treatment Plant.
Necessary interlocks, controls, alarms, report generation, etc. shall be considered in
PLC for auto operation SBR basin.
Each Anoxic basins shall be equipped with Level Transmitter, DO Transmitter for
monitoring and recording of critical operation parameters through SCADA.
vii. Sludge sump and pump
An ultrasonic type level transmitter shall be used for measurement of level in sludge
sump.
Screw pumps will be used to feed sludge to Centrifuge. These will operate as per level
in sludge sump.
The selection of Auto/Manual and Working/Stand-by shall be made available in SCADA
for sludge pumps. In manual mode the Start/Stop of pump will be done from SCADA
screen.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC for
operation of chlorination system.
viii. Chlorination tank
The selection of Auto/Manual and Working/Stand-by shall be made available in SCADA
for booster pumps. In manual mode the Start/Stop of pump will be done from SCADA
screen. Though chlorinator will have standalone operation, feedback for the equipment
shall be taken to PLC and displayed SCADA for monitoring purpose.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC for
operation of chlorination system.
ix. Centrifuge/ Belt Filter Press
The drives and instruments of dewatering machines shall be connected to PLC for its
auto operation. Starting of dewatering system will be a manual process.
Necessary interlocks, alarms, report generation, etc. shall be considered in PLC for
auto operation of dewatering machines.
Annexure-3 : Revised “ Volume-2(R1)”
184
9. Construction of new IPS
The locations with flow details are as follows:
Sr
No Location of IPS
Flow
(MLD) Peak factor
1 Gaushala 30 2.25
2 Sunder Nagar 8 2.25
3 Tibba Road 12 2.25
4 Kundan Puri 5 2.25
5 Upkar Nagar 13 2.25
6 Lord Mahavir Ayurveda Hospital 43 2.25
Design requirement described here is in general for various Items. However
design requirement of only those Items shall be applicable which are required or
provided at site. If design requirement of any item is not described here then
requirement as per CPHEEO Manual / relevant IS code or prevalent as per the
department practice will be applicable as approved by Engineer-in-charge.
9.1 Components of Intermediate Pumping Station
9.1.1 Civil Works
i. Receiving Chamber ii. Screening Channel iii. Wet well/Collecting Tank iv. Panel Room v. Roads & Pavements vi. Platform /Foundation for Diesel Generating Set & Transformer vii. Cable Trench, wire mesh around transformer viii. White washing/painting etc. ix. Hand Railing x. Pumping main from IPS to STP location xi. Valve chamber/platform to house common header, all valves, NRVs etc.
i) Receiving Chamber
The deep gravity outfall sewers will discharge the raw sewage into a Receiving chamber.
The function of the Receiving chamber is to distribute the flow to screens. The Receiving
Chamber shall be designed for peak flow. The Receiving chamber shall consist of sluice
gates on upstream for flow regulation. The receiving chamber shall be of adequate size
to meet the requirements of workability inside it. C.I gate (Manually Operated) of suitable
size shall be provided at the inlet of receiving chamber. The entire construction is in
minimum M-30 grade concrete and as per IS 3370. RCC access platform minimum 1200
mm wide with GI pipe hand railing as per specifications shall be provided on one side of
the chamber:
Number of Units : 1 (One)
Min. Detention period : 30 Sec at Peak Flow
Min Free board : 0.50 m
Annexure-3 : Revised “ Volume-2(R1)”
185
ii) J Type Removable Bar Thrash Screens
Manual Trash screen to be installed in front of coarse mechanical screens to prevent
large and medium sized floating wastes from entering into intake structure of pumping
station.
The manual screen should comprise of flat bars spaced apart in vertical with 50mm
opening within a sturdy frame structure inserted in vertical guide channel. Structure
provided should be with perforated basket at its bottom and guide roller on both sides
for easy removal. Guide channel extend upto to top of platform for guiding upward
movement. The height of trash screen should be 0.5 m above sewer crown. Material of
construction should be in SS-304. Flat size shall be of 10 mm thick 50mm wide:
Sr
No Location of IPS
Flow
(MLD) Peak factor
J Type Manual Screens
1 Gaushala 30 2.25 2
2 Sunder Nagar 8 2.25 1
3 Tibba Road 12 2.25 1
4 Kundan Puri 5 2.25 1
5 Upkar Nagar 13 2.25 1
6 Lord Mahavir
Ayurveda Hospital 43
2.25 2
Velocity through Screen at Average Flow : 0.6 maximum
(m/sec)
Velocity through Screen at Peak Flow (m/sec): 1.2 maximum
Height of Mesh Screen : 0.50 m above sewer crown
Wheeled Trolley : 2 No.
All other accessories, whether specified or not, but required for completeness of contract
shall be in contractor’s scope. Railings shall be provided around the entire periphery of
the platform and structure.
The provision of EOT crane, any kind of cleaning/raking mechanism, collection
bins/portable screen container, water jetting arrangements & trolley etc. shall be
provided.
iii) Coarse Screen
One mechanical screen working and one manual screen standby upto peak flow of 1250
m3/hour and two mechanical screens with one manual screen standby each of capacity
half of the peak flow for the peak discharge more than 1250 m3/hour with 20 mm clear
spacing shall be provided.
The mechanical and manual bar screens shall be made of 10 mm thick Stainless Steel
(SS 304) flats respectively. The mechanical coarse screens shall be of Inclined Rake
Type of 20 mm opening as per the specifications detailed elsewhere in the tender. Bin
and chute arrangement shall be provided for collection of screenings in a wheel
burrow/trolley. Manually operated CI gates are provided at the upstream and
downstream end to regulate the flow.
Adequate RCC Platforms shall be provided at the upper level to enable operation. GI
hand Railings shall be provided around the entire periphery of the platform. The entire
Annexure-3 : Revised “ Volume-2(R1)”
186
structure is to be in minimum M-30 concrete and as per IS 3370 including the platform.
RCC staircase 1200 mm wide shall be provided for access from the ground level to the
top of the unit & to the operating platform.
Sr
No Location of IPS
Flow
(MLD)
Peak
factor
Mechanical coarse
Screens
Manual coarse
Screens
1 Gaushala 30 2.25 2 1
2 Sunder Nagar 8 2.25 1 1
3 Tibba Road 12 2.25 1 1
4 Kundan Puri 5 2.25 1 1
5 Upkar Nagar 13 2.25 1 1
6
Lord Mahavir
Ayurveda
Hospital
43 2.25 2 1
Velocity through Screen at Average Flow : 0.6 maximum
(m/sec)
Velocity through Screen at Peak Flow (m/sec) :1.2 maximum
Height of Screen bars upto dead plate : 1 m above sewer crown
Wheeled Trolley : 2 No.
All other accessories, whether specified or not, but required for completeness of
contract shall be in contractor’s scope.
iv) WET WELL
The Main pumping station (MPS) shall be a rectangular concrete structure. The sump
well is to be in R.C.C of minimum Grade M-30 and shall be designed for peak flow. The
maximum operational liquid level in wet well shall be such that, minimum 100mm freefall
to be maintained from Invert of Screen Chamber to Water level of wet well. The capacity
of the wet well sump should be kept such that the detention time of the sump should be
at least 5 minutes peak flow. The wet well shall be divided into two equal compartments
upto full height with sluice gates in common wall where peak flow is more than 1250
m3/hour and single wet well be constructed where the peak flow is upto 1250 m3/hour .
The pumps shall be installed equally in two compartments with a provision to install one
pump in future in each compartment. In single wet well all the pumps with standby shall
be provided with a provision of space for one pump. Area of gate(s) should be sufficient
so as to divide the flow into any of the compartments, at a velocity not more than 1.2
m/sec.
The arrangement of the Pumps shall be as per Manufacturer’s data i.e. Spacing
between the Pumps, minimum space between the Pump and Wall etc. Adequate
submergence of the pump shall be provided as per the manufactures recommendations.
The size of wet well shall be sufficient to accommodate one additional pump in each
compartment, in future. CI steps shall be fixed in the wet wells.
IS: 3370 and IS: 4111 (Part 4) shall be followed for the design and construction of Wet
Well.
Annexure-3 : Revised “ Volume-2(R1)”
187
Basis for Design
All underground or partly underground liquid containing structures shall be designed for the
following conditions:
(a) Liquid depth up to full height of wall and free board: no relief due to lateral soil
pressure from outside to be considered;
(b) Reservoir empty (i.e. no liquid or any material inside the storage area): full lateral
earth pressure at rest due to surrounding saturated soil and surcharge pressure as
applicable, shall be considered;
(c) Partition wall between two compartments of wet well to be designed as one
compartment empty and other full;
(d) Structures shall be designed for uplift in empty conditions considering the depth of
the highest water table recorded in the area.
(e) Walls shall be designed under operating conditions to resist earthquake forces
developed due to mobilization of earth and dynamic liquid loads;
Underground or partially underground structures shall also be checked against stresses
developed due to any combination of full and empty compartments with appropriate
ground/uplift pressures on the base slab.
v) Sewage Pumps
Coarse-screened sewage shall be pumped from wet well. Pump operation shall be
automatically controlled based on wet well level. There will be high level and low level
alarm and tripping system installed. It will house non clog submersible pumps, which will
always be submerged in sewage with minimum submergence as required by the
manufacturer. Pumps will have automatic coupling arrangement at discharge end, a
guide pipe and chain for easy removal and lowering of pumps. Vibration shall be limited
as per BS 4675 Part I
Type of Pumps : Submersible type non-clog design
Liquid : Raw Sewage
Specific gravity : 1.05
Solid Passage Size : Maximum 100 mm.
No of working Pumps : 4 Nos for peak flow more than 1250 m3/hr,
: 2 Nos for peak flow less than 1250 m3/hr
Capacity of Pump : Peak flow/ No of working pumps
Standby Pumps : 50% of working pumps.
VFD for pump : 1 Pump in each compartment is to have the provision of VFD for flow variation
One electrically operated 2-way movement Trolley (EOT) having capacity equal to 1.5
times the weight of heaviest part to be lifted shall be provided over the sump well for
movement of pumps. The horizontal, transverse as well vertical shall be electrically
Annexure-3 : Revised “ Volume-2(R1)”
188
operated. The gantry is to be fixed on RCC framed structure and not on a cantilever arm
from columns.
vi) Rising main
Sewage from wet well will be pumped to Shaft or STP through rising main of size
suitable to carry peak flow.
Material of rising main : Cement lined DI (K9) pipe
Size of rising main : Capable of carrying peak flow
Velocity in rising main at peak flow : Maximum 1.5 m / sec
vii) Piping & Specials
This shall include providing, laying, cutting, jointing, testing, etc. of pipes along with
specials:
(i) RCC Channels from inlet chamber of screens upto sump/ wet well.
(ii) DI K-9 Delivery line for individual pump upto common header.
(iii) Expander, Sluice valves, Bends, Non Return Valves in the individual delivery
of all the pumps. Tees and Sluice valve in the common header.
(iv) DI K-9 Common header upto Inlet of STP.
(v) The size of pipe shall be calculated so as to meet the following velocity
criteria:-
a. Minimum Velocity : 0.60 m/sec
b. Maximum Velocity : 1.5 m/sec
(vi) All other required fittings such as bends, tees etc.
(vii) Thrust block of M-20 grade, for pipe support, etc.
(viii) Necessary bypass arrangement shall be provided to be used during the
shutdown of the plant. Pipe and Valve arrangement upto suitable discharge
point shall be provided.
viii) Painting, White Washing and allied works
The internal and external surfaces of the walls and ceiling of all building structures shall
be applied with two coats of Birla / JK Wall Putty followed by two coats of primer
followed by min two coats of first quality plastic emulsion paint.
All the structural steel, pipes, specials etc shall have two coats of Epidec RTC Primer
followed by two coats of epoxy paint.
All the internal walls and base of water retaining structures of MPS shall be provided
with min two coats of coal tar epoxy.
ix) Roads & Pathways with proper drainage
Roads and Pathways shall be provided with interlocking paver blocks over 150 mm
thick and 100 mm thick respectively cement concrete of 1:4:8 in stone ballast.
Thickness of paver blocks on roads is 80 mm thick and on pathways the thickness of
paver blocks is 60 mm. Paver blocks shall confirm to specification of code IS 15658
Paver blocks will be ISI Marked.
x) IPS Panel Room
It shall be RCC framed structure and 3.5 m clear height. It shall house panels of MPS
pumps, screens, sluice gates, valves etc. It shall also house PLC Panels and HMI
Annexure-3 : Revised “ Volume-2(R1)”
189
screen for display of various parameters of IPS. Preferably the MPS panel room building
is to be adjoining to WET WELL so as to have a better monitoring.
Local Push Button Station (LPBS) shall be provided near each Pump set/ Motor for
emergency stop and start thereof. LPBS shall have Start/Stop push button with
Local/Remote Selector Switch. Each push button shall have 2NO+2NC contact for
interlocking purposes. The stop push button shall be mushroom type with stay put
feature and lockable in pressed position to avoid accidental operation of drive from MCC,
PLC during shutdown.
LPBS shall be suitable for use in outdoor open locations with minimum IP-55 degree of
protection and rain canopy.
9.1.2 Mechanical Works
i) J Type Manual Coarse screens, Manual and Mechanical Coarse Screen, Belt Conveyor for screens
ii) CI Sluice Gate shall be provided at following locations for flow control
a) Inlet of Receiving Chamber-1 No. b) Upstream of coarse screens of IPS c) Downstream of coarse screens of IPS d) RCC Partition Walls of Wet Well – 1 No for larger IPS e) Any other gate as required
iii) Non clog Submersible Centrifugal Pumps sets with motor iv) Piping works, Dismantling Joint, NRV, Sluice Valve with appurtenance v) Lifting Arrangement –Monorail with electric horizontal and vertical operation
9.1.3 Electrical, Instrumentation & Control Works
i) HT VCB Panel ii) Transformer ONAN with on load tap changer iii) Silent Diesel Generating Set with AMF Panel suitable for average flow plus
other miscellaneous load iv) Electrical Panel with
a) Incomer for normal & DG supply & interlocks power analyzer, surge protection device
b) Individual Starter Panels with VFD and soft starters for pumpset c) Automatic Power Factor Control (APFC) Capacitor Panel d) Alarm Annunciation Panel e) Feeder for other loads f) Interface with PLC & SCADA compatibility
v) HT & LT Cable, Instrument & data cable vi) Cabling system vii) Earthing & Lightening Protection viii) Lighting System (Indoor & Outdoor) ix) Junction Box for cables x) UPS for PLC xi) Instrumentation & Control
This includes supply, erection, testing and commissioning of various instruments & control
system. Brief details are as under:
Annexure-3 : Revised “ Volume-2(R1)”
190
S No Instrument Location Quantity
1. Differential Level sensor / Transmitter
Mechanical Coarse Screens As required
2. Pressure gauge Common discharge header of non-clog sewage pumps/Rising main
1
3. Radar Type level transmitter (non-contact type)
Main Collection Sump ( For level Status & level based control)
2
4. Programmable Logic Controller (PLC)
Panel Room 1
5. Any other Item As per requirement As per
requirement
PLC for IPS shall be as per control philosophy & specification.
PLC shall operate pumps based on pre-set levels of sewage in collection tank and
VFD operation. At mid-level of sewage, number of pumps as per average flow shall
operate, whereas at high level, number of pumps as per peak flow shall operate. At
low level, all pumps shall stop. Provision shall be made to operate all pumps in
rotation.
PLC cum Instrumentation Control Panel shall be provided with 6” HMI to enable
level based operation of pumps and display of level and flow.
Provision shall also be made for display of level and flow in STP, SCADA Room.
Notes:
H. T Room and Transformer shall be as per requirement
Security Room with Toilet Block shall be provided.
Annexure-3 : Revised “ Volume-2(R1)”
191
10. Design Criteria for Mechanical Dewatering of sludge generated from existing
UASB Plant at Bhattian & Balloke
Design requirement described here is in general for various Items. However design
requirement of only those Items shall be applicable which are required or provided at
site. If design requirement of any item is not described here then requirement as per
CPHEEO Manual / relevant IS code or prevalent as per the department practice will be
applicable as approved by Engineer-in-charge.
10.1 Arrangement for Mechanical Dewatering of Sludge generated from existing
111 MLD UASB plant at Bhattian.
Presently, the sludge from 9 UASB Reactors is collected in sludge sumps near the
reactors. From sludge sumps it is pumped to existing sludge drying beds in the same
premises. To save on the land occupied by sludge drying beds and manpower required
for maintaining the sludge drying beds; it is proposed to set up an arrangement for
mechanical dewatering of sludge withdrawn from UASB reactors. The indicative scope
of work is as under:-
Sr.
No. Component Details
i New Sludge
Handling Unit
Sludge withdrawal system
Sludge sump
Sludge pump houses
Mechanism for Polymer chemical/dosing
Sludge Dewatering mechanism including
building like Combined mechanical Thickener
cum Belt Press or Centrifuge + gravity sludge
thickener
Sludge storage platform
Recirculation of filtrate
Arrangement of handling/ disposal of de-
watered sludge if required to the land
earmarked by Employer.
Any other component required
ii Existing Sludge
Drying Beds
If for construction of new STP/MPS/other
units, some of the sludge drying beds are to
be dismantled, the same is included in the
scope of work. Otherwise existing Sludge
Drying Beds will remain as these are.
Sludge withdrawal from UASB unit.
Sludge withdrawal shall be either by gravity or through pumping. DI Pipes shall be
preferably used for transportation of sludge. Sludge withdrawn from various units shall
be collected in a single sludge sump and shall be fed to
a. Gravity Thickener followed by Centrifuge dewatering machine or
b. Combined Mechanical Thickener cum Belt Press.
Annexure-3 : Revised “ Volume-2(R1)”
192
i) Sludge Sump
Sludge sump shall be provided to collect the excess sludge from various units. There
shall be one common Sludge Sump. The Sump shall be equipped with coarse Bubble
Air Grid made from stainless steel pipes to facilitate mixing of contents of sludge sump
on continuous basis. Alternatively Submersible mixers of suitable numbers can be
provided
Number of Units : 1 (one) nos.
Free Board : 0.5 m
Capacity : Minimum 6 hr holding of average daily
sludge production
Minimum SWD : 3.0 m
ii) Sludge thickener unit with Centrifuge
The Gravity RCC Sludge thickener unit(s) of suitable size shall be provided for gravity
sludge thickening to reduce the capacity of Centrifuge equipment. The excess sludge
from biological Reactors / settling tanks will be taken to thickener. Thickener is
expected to produce thickened sludge with minimum dry solid concentration of 3%.
Design criteria
1. Hydraulic loading As per CPHEEO Manual
2. Solid loading As per CPHEEO Manual
3. Continuous gravity thickener shall be
circular RCC units with minimum 3.0 m
side water depth. Side depth shall be
based on three considerations.
4. Free board 600 mm
5. Settling zone 1200 mm to 1800 mm
6. Compression zone Depth required toprovide a
volume equal to twenty four
hours detention of maximum
sludge wasting.
7. The floor slope of gravity thickeners will be greater than 120 mm of vertical
distance per meter of tank radius.
Central drive arrangement shall be provided to rotate trussed rake arms
having blades to sweep the sludge into sludge hopper.
The mechanism shall include a fixed half circle Bridge, Center Assembly with Drive
Unit, Feed Well, Center Cage, Rake Arms, Walkway with Handrails, Scum Skimmer,
Scum Box, Weirs, Baffles, Anchor Bolts and such other fittings, devices, or
appurtenances as are necessary for a complete operating installation.
Sludge thickener tank shall be circular in shape with fixed bridge. The tanks shall be
designed in accordance with the design data provided earlier and as per the guideline
of Manual on Sewerage & Sewage Treatment, Ministry of Urban Development, latest
CPHEEO. Minimum side water depth shall be 3.0 m. The sludge thickener shall be of
radial flow type. At periphery the flow shall pass through SS-304 V notch weir of
minimum 2 mm thickness and then shall be collected into an annular RCC launder
provided all around the periphery of the tank. The V notch weir shall be made out of 2
mm thick Stainless Steel (min. 150 mm ht.) with clamps for making adjustments.
Annexure-3 : Revised “ Volume-2(R1)”
193
iii) Sludge Pump House(s)
Pump house shall be near sludge sump. This shall be RCC frame and brick masonry
structure. Minimum height of the pump house shall be 4 m from the plinth level. It shall
be provided with rolling shutter and doors and windows. A chain pulley block of
adequate capacity along with girder and pillar arrangement shall be provided.
The pump house shall be painted from inside and outside with approved colour and
make as directed by Engineer-in-Charge. The pump house shall house:
Pumps for feed to dewatering mechanism (working + standby)
Air blowers for Sludge Sump (working + standby) or Submersible Mixers
DWPE dosing pumps (working + standby)
iv) Chemical Dosing Tanks
Suitable number and capacity dosing tanks with required inner lining and agitators are
to be provided.
Polyelectrolyte Dosing System shall consist of Dosing Tanks equipped with Slow
Speed Agitators and Diaphragm type Metering Pumps. Polyelectrolyte shall be dosed
online at the inlet of Centrifuges. Minimum dosage of polyelectrolyte shall be 0.5-1.5
Kg/Ton of dry solids at 0.1% solution strength. The solution will be dosed using
mechanically actuated Diaphragm type Metering Pumps. Dedicated Dosing Pumps
shall be provided and shall be interlocked with Combined Mechanical Thickener cum
Belt Press /Centrifuge in such a way that they Start/Stop along with Belt Press /
Centrifuge.
Dosing Tanks:
Design Capacity : As per requirement
Number of Units : As per requirement
Hydraulic Retention Time : Suitable for min. 8 hours of Operation
Free Board : As per design.
Dosing Pumps:
Capacity and Head : As per requirement
Type : Mechanically Actuated Diaphragm
Type Metering Pump
Liquid : Polyelectrolyte Solution of 0.1%Strength
Quantity : one each per dewatering machine
v) Civil Structure for Mechanical De-watering including
Building of sufficient size to accommodate mechanical dewatering Units Combined
Mechanical Thickener cum Belt Press or Centrifuges (Working + Standby) shall be
constructed with sufficient floor height above Ground Level to park sludge collection
vehicle directly under the sludge discharge line. The building shall be framed RCC
structure have a RCC roof at a height suitable for installing EOT. The dewatered
sludge shall have a minimum solids concentration of 20% or more (measured as dry
solids w/w basis) so that it can disposed by open body Trucks/Trolleys.
Annexure-3 : Revised “ Volume-2(R1)”
194
10.2 Arrangement for Mechanical Dewatering of Sludge generated from existing 152
MLD UASB plant at Balloke.
Presently, the sludge from 12 UASB Reactors is collected in sludge sumps near the
reactors. From sludge sumps it is pumped to existing sludge drying beds in the same
premises. To save on the land occupied by sludge drying beds and manpower required
for maintaining the sludge drying beds; it is proposed to set up an arrangement for
mechanical dewatering of sludge withdrawn from UASB reactors. The indicative scope
of work is as under:-
Sr.
No. Component Details
i New Sludge
Handling Unit
Sludge withdrawal system
Sludge sump
Sludge pump houses
Mechanism for Polymer chemical/dosing
Sludge Dewatering mechanism including
building like Combined mechanical Thickener
cum Belt Press or Centrifuge + gravity sludge
thickener
Sludge storage platform
Recirculation of filtrate
Arrangement of handling/ disposal of de-
watered sludge if required to the land
earmarked by Employer.
Any other component required
ii Existing Sludge
Drying Beds
If for construction of new STP/MPS/other
units, some of the sludge drying beds are to
be dismantled, the same is included in the
scope of work. Otherwise existing Sludge
Drying Beds will remain as these are.
The bidder shall carry out assessment to ascertain the quantity and quality of sludge to
be handled and condition of the existing sludge handling systems.
Sludge withdrawal from UASB unit.
Sludge withdrawal shall be either by gravity or through pumping. DI Pipes shall be
preferably used for transportation of sludge. Sludge withdrawn from various units shall
be collected in a single sludge sump and shall be fed to
a. Gravity Thickener followed by Centrifuge dewatering machine
or
b. Combined Mechanical Thickener cum Belt Press.
i) Sludge Sump
Sludge sump shall be provided to collect the excess sludge from various units. There
shall be one common Sludge Sump. The Sump shall be equipped with coarse Bubble
Air Grid made from stainless steel pipes to facilitate mixing of contents of sludge sump
Annexure-3 : Revised “ Volume-2(R1)”
195
on continuous basis. Alternatively Submersible mixers of suitable numbers can be
provided:
Number of Units : 1 (one) nos.
Free Board : 0.5 m
Capacity : Minimum 6 hr holding of average daily
sludge production
Minimum SWD : 3.0 m
ii) Sludge thickener unit with Centrifuge
The Gravity RCC Sludge thickener unit(s) of suitable size shall be provided for gravity
sludge thickening to reduce the capacity of Centrifuge equipment. The excess sludge
from biological Reactors / settling tanks will be taken to thickener. Thickener is
expected to produce thickened sludge with minimum dry solid concentration of 3%.
Design criteria
1. Hydraulic loading As per CPHEEO Manual
2. Solid loading As per CPHEEO Manual
3. Continuous gravity thickener shall be
circular RCC units with minimum 3.0 m
side water depth. Side depth shall be
based on three considerations.
4. Free board 600 mm
5. Settling zone 1200 mm to 1800 mm
6. Compression zone Depth required to provide a
volume equal to twenty four hours
detention of maximum sludge
wasting.
7. The floor slope of gravity thickeners will be greater than 120 mm of vertical
distance per meter of tank radius.
Central drive arrangement shall be provided to rotate trussed rake arms having
blades to sweep the sludge into sludge hopper.
The mechanism shall include a fixed half circle Bridge, Center Assembly with Drive
Unit, Feed Well, Center Cage, Rake Arms, Walkway with Handrails, Scum Skimmer,
Scum Box, Weirs, Baffles, Anchor Bolts and such other fittings, devices, or
appurtenances as are necessary for a complete operating installation.
Sludge thickener tank shall be circular in shape with fixed bridge. The tanks shall be
designed in accordance with the design data provided earlier and as per the guideline
of Manual on Sewerage & Sewage Treatment, Ministry of Urban Development, latest
CPHEEO. Minimum side water depth shall be 3.0 m. The sludge thickener shall be of
radial flow type. At periphery the flow shall pass through SS-304 V notch weir of
minimum 2 mm thickness and then shall be collected into an annular RCC launder
provided all around the periphery of the tank. The V notch weir shall be made out of 2
mm thick Stainless Steel (min. 150 mm ht.) with clamps for making adjustments.
iii) Sludge Pump House(s)
Pump house shall be near sludge sump. This shall be RCC frame and brick masonry
structure. Minimum height of the pump house shall be 4 m from the plinth level. It shall
Annexure-3 : Revised “ Volume-2(R1)”
196
be provided with rolling shutter and doors and windows. A chain pulley block of
adequate capacity along with girder and pillar arrangement shall be provided.
The pump house shall be painted from inside and outside with approved colour and
make as directed by Engineer-in-Charge. The pump house shall house:
Pumps for feed to dewatering mechanism (working + standby)
Air blowers for Sludge Sump (working + standby) or Submersible Mixers
DWPE dosing pumps (working + standby)
iv) Chemical Dosing Tanks
Suitable number and capacity dosing tanks with required inner lining and agitators are
to be provided.
Polyelectrolyte Dosing System shall consist of Dosing Tanks equipped with Slow
Speed Agitators and Diaphragm type Metering Pumps. Polyelectrolyte shall be dosed
online at the inlet of Centrifuges. Minimum dosage of polyelectrolyte shall be 0.5 – 1.50
Kg/Ton of dry solids at 0.1% solution strength. The solution will be dosed using
mechanically actuated Diaphragm type Metering Pumps. Dedicated Dosing Pumps
shall be provided and shall be interlocked with Combined Mechanical Thickener cum
Belt Press /Centrifuge in such a way that they Start/Stop along with Belt Press /
Centrifuge.
Dosing Tanks:
Design Capacity : As per requirement
Number of Units : As per requirement
Hydraulic Retention Time : Suitable for min. 8 hours of Operation
Free Board : As per design.
Dosing Pumps:
Capacity and Head : As per requirement
Type : Mechanically Actuated Diaphragm Type Metering
Pump
Liquid : Polyelectrolyte Solution of 0.1%Strength
Quantity : one each per dewatering machine
v) Civil Structure for Mechanical De-watering including
Building of sufficient size to accommodate mechanical dewatering Units Combined
Mechanical Thickener cum Belt Press or Centrifuges (Working + Standby) shall be
constructed with sufficient floor height above Ground Level to park sludge collection
vehicle directly under the sludge discharge line. The building shall be framed RCC
structure have a RCC roof at a height suitable for installing EOT. The dewatered
sludge shall have a minimum solids concentration of 20% or more (measured as dry
solids w/w basis) so that it can disposed by open body Trucks/Trolleys.