ANNOUNCEMENT PHASE
07 October 2019
Dear Stakeholder,
BASIC ASSESSMENT AND PUBLIC PARTICIPATION PROCESS
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF BASIC ASEESSMENT AND PUBLIC PARTICIPATION PROCESS
The proponent, Eskom Holdings SOC Ltd, is proposing the installation and operation of a Reverse
Osmosis (RO) Plant for ash process water treatment at the Matla Power Station, Mpumalanga
Province. The RO plant will be contained entirely within the Matla Power Station property boundaries
(Portion 4 of Bakenleegte 84).
Matla Power Station is situated approximately 60km south of eMalahleni, 4km south-west of Kriel
Power Station and 12km west of the town Kriel. The proposed activity falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
BASIC ASSESSMENT PROCESS
The proposed installation and operation of the Reverse Osmosis (RO) Plant requires that an
application for Environmental Authorisation (EA) be submitted to the Department of Environment,
Forestry and Fisheries (DEFF) (previously the Department of Environmental Affairs (DEA)) as the
Competent Authority (CA). In terms of Sections 24 and 24D of the National Environmental
Management Act (NEMA), Act No. 107 of 1998 as read with Government Notices, R324-327 (as
amended), a Basic Assessment (BA) process is required for this project. The following activities are
being applied for through this process:
Government Notice Listed Activity Number
R324 – Listing Notice 3 10 and 12
R327 – Listing Notice 1 10, 14, 16, 25 and 27
Savannah Environmental (Pty) Ltd is undertaking the required BA and public participation processes
for the project on behalf of the proponent (Eskom Holdings SOC Ltd), in order to identify and assess
all potential environmental impacts associated with the project for the area as identified, and the
recommendation of appropriate mitigation and management measures to be included in the
Environmental Management Programme (EMPr).
The department and/or the organisation which you represents has been identified as a commenting
authority for the proposed project. In this regard, please can you provide us with the name and
contact details of the relevant contact person at your department who we would liaise with
regarding this project.
By registering on the project database, you will receive all information relating to the project and will
be provided with an opportunity to provide comments and input into the BA process.
Please do not hesitate to contact us should you require additional information and/or clarification
regarding the proposed project at this stage. Our team welcomes your participation and looks
forward to your involvement throughout this process.
Kind regards
Nicolene Venter
Public Participation and Social Consultant
EMAIL: [email protected]
Document attached: Registration and Comment Form
CORRESPONDENCE
1
Nicolene Venter
From: Savannah Public Process
Sent: Thursday, October 10, 2019 4:26 AM
To: Nokukhanya Khumalo
Cc: Nicolene Venter; Ronald Baloyi
Subject: RE: BASIC ASSESSMENT PROCESS: Installation and Operation of a Reverse Osmosis
Plant at Eskom's Matla Power Station
Dear Nokukhanya,
Once the basic assessment report is available, it will be uploaded onto SAHRIS.
Thank you for the reminder.
Kind regards,
Nicolene VenterPublic Participation & Social Consultant | Savannah Environmental (Pty) LtdTel: +27 (0)11 656 3237 | Cell: +27 (0)60 978 8396 | Fax: +27 (0)86 684 0547SAWEA Award for Leading Environmental Consultant for Wind Projects in 2013 & 2015
From: Nokukhanya Khumalo <[email protected]>Sent: Wednesday, October 9, 2019 9:29 AMTo: Savannah Public Process <[email protected]>Cc: Nicolene Venter <[email protected]>; Ronald Baloyi <[email protected]>Subject: RE: BASIC ASSESSMENT PROCESS: Installation and Operation of a Reverse Osmosis Plant at Eskom's MatlaPower Station
Good day
Thank you for informing SAHRA of the proposed Environmental Authorisation application. However, SAHRA does not acceptphysical and emailed notifications for commenting on proposed developments.We work on a digital platform named SAHRIS (http://www.sahra.org.za/sahris), where you will need to create a case and uploadall the documents compiled for the development application.
If a case has been created on SAHRIS please email back with the case ID number.
Kind Regards,
Nokukhanya Khumalo
From: Savannah Public Process <[email protected]>Sent: 08 October 2019 02:20 PMTo: Mzoxolo Mafuza <[email protected]>; Obed Baloyi <[email protected]>; Victoria Botha<[email protected]>; Thoko Buthelezi <[email protected]>; Sipho Chiume <[email protected]>;Anneliza Collett <[email protected]>; Robert Davel <[email protected]>; Fikile Guma<[email protected]>; Mkululeke Gumede <[email protected]>; Tinkie Holl <[email protected]>;Thulie N Khumalo <[email protected]>; Nokukhanya Khumalo <[email protected]>; StanfordMafore <[email protected]>; Nonkululeko (Mthombeni) Makua <[email protected]>;Mashudu Marubini <[email protected]>; Sandile Maseko <[email protected]>; PT Mashaine<[email protected]>; Sandile Mashile <[email protected]>; Sk Mashilo<[email protected]>; S Masoka <[email protected]>; Thabang Mathebula <[email protected]>;H.S. Mayisela <[email protected]>; NP Mbamayi <[email protected]>; a; Mbali Mhlana<[email protected]>; Gugu Mhlongo <[email protected]>; Sphamandla Mhlongo<[email protected]>; Liyanda Mjingukena <[email protected]>; Sifiso Mkhize
2
<[email protected]>; Mduduzi Mngomezulu <[email protected]>; Benjamin Moduka<[email protected]>; Bethuel Moeng <[email protected]>; KM Mohlasedi<[email protected]>; Gloria Moholi <[email protected]>; Refilwe Mokobodi<[email protected]>; Masala Mulaudzi <[email protected]>; Lulama Mxakaza<[email protected]>; Erald Nkabinde <[email protected]>; Naume Nkosi<[email protected]>; Matsidiso Ogbobo <[email protected]>; Duduzi Palmer<[email protected]>; Johanna Phetla <[email protected]>; Priya Pillay <[email protected]>;Mercy Ralushai <[email protected]>; Edwin Seitei <[email protected]>; Lwando Simunca<[email protected]>; Katie Smuts <[email protected]>; Jeanette Soko <[email protected]>; TshepisoTemo <[email protected]>; MC Theledi <[email protected]>; Stanley Tshitwamulomoni<[email protected]>; Aubrey Tshivhandekano <[email protected]>; Rika Wilken<[email protected]>; SP Xulu <[email protected]>; Michael Yorke-Hart <[email protected]>; ZodwaZimu <[email protected]>Cc: [email protected]; [email protected]: BASIC ASSESSMENT PROCESS: Installation and Operation of a Reverse Osmosis Plant at Eskom's MatlaPower Station
BASIC ASSESSMENT AND PUBLIC PARTICIPATION PROCESS
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER STATION, MPUMALANGAPROVINCE
Dear Stakeholder,
The proponent, Eskom Holdings SOC Ltd, is proposing the installation and operation of a Reverse Osmosis (RO) Plantfor ash process water treatment at the Matla Power Station, eMalahleni Local Municipality, Mpumalanga Province.
The RO plant will be contained entirely within the Matla Power Station property boundaries (Portion 4 ofBakenleegte 84).
The attached notification letter will provide you with additional information regarding this proposed project.
Kind regards,
Nicolene Venter
Public Participation and Social Consultant | Savannah Environmental (Pty) LtdTel: +27 (0)11 656 3237 | Fax: +27 (0)86 684 0547
SAWEA Award for Leading Environmental Consultant for Wind Projects in 2013 & 2015
Nokukhanya KhumaloHeritage Officer: Archaeology, Palaeontology & Meteorites Unit
South African Heritage Resources Agency- A nation united through heritage -
T: +27 21 462 4502/ 8654| C:| F:+27 21 4624509E: [email protected] | 111 Harrington Street | Cape Town |
www.sahra.org.za
BASIC ASSESSMENT REPORT NOTIFICATION
22 January 2020
Dear Stakeholder,
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF AVAILABILITY OF BASIC ASSESSMENT REPORT FOR REVIEW AND COMMENT
The proponent, Eskom Holdings SOC Ltd, is proposing the installation, operation and
decommissioning of a Reverse Osmosis (RO) Plant for ash process water treatment at the Matla
Power Station, Mpumalanga Province. The project footprint will be less than 2ha in extent and will
fall within the power station property. The proposed development also falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
In terms of Regulation 43(2) of the EIA Regulations, 2014, as amended, this letter serves to inform you
that the Basic Assessment Report (BAR) is available for your Department’s / Organisation’s review
and written comments. The BAR is also available for download from Savannah Environmental’s
website: https://www.savannahsa.com/public-documents/other/.
Please note that BAR’s review period is from Friday, 24 January 2020 to Monday, 24 February 2020
and we are looking forward receiving your Department’s / Organisation’s written comment/s on the
BAR within the 30-day review period but not later that the closing date of the review period, i.e.
Monday, 24 February 2020.
Kind regards
Nicolene Venter
Public Participation and Social Consultation
Email: [email protected]
Agri: Mpumalanga
22 January 2020
Ms Robert Davel
General Manager: Agri Mpumalanga
Postnet Suite 1869
Private Bag X9013
ERMELO
2350
By Registered Mail
Dear Mr Davel,
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF AVAILABILITY OF BASIC ASSESSMENT REPORT FOR REVIEW AND COMMENT
The proponent, Eskom Holdings SOC Ltd, is proposing the installation, operation and
decommissioning of a Reverse Osmosis (RO) Plant for ash process water treatment at the Matla
Power Station, Mpumalanga Province. The project footprint will be less than 2ha in extent and will
fall within the power station property. The proposed development also falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
In terms of Regulation 43(2) of the EIA Regulations, 2014, as amended, this letter serves to inform you
that the Basic Assessment Report (BAR) is available for Agri Mpumalanga’s review and written
comments, and a CD containing the BAR is included in this envelope. The BAR is also available for
download from Savannah Environmental’s website: https://www.savannahsa.com/public-
documents/other/.
Please note that BAR’s review period is from Friday, 24 January 2020 to Monday, 24 February 2020
and we are looking forward receiving Agri Mpumalanga’s written comment/s on the BAR within the
30-day review period but not later that the closing date of the review period, i.e. Monday,
24 February 2020.
Kind regards
Nicolene Venter
Public Participation and Social Consultation
Email: [email protected]
Proof of delivery to be included in final BA
Report
Department of Agriculture, Forestry and Fisheries
(DAFF)
22 January 2020
Ms Thoko Buthelezi
AgriLand Liaison Office
Department of Agriculture, Forestry & Fisheries
Delpen Building Office 270
Cnr Annie Botha and Union Street
RIVIERA
0084
By Courier Services
Dear Ms Buthelezi,
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF AVAILABILITY OF BASIC ASSESSMENT REPORT FOR REVIEW AND COMMENT
The proponent, Eskom Holdings SOC Ltd, is proposing the installation, operation and
decommissioning of a Reverse Osmosis (RO) Plant for ash process water treatment at the Matla
Power Station, Mpumalanga Province. The project footprint will be less than 2ha in extent and will
fall within the power station property. The proposed development also falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
In terms of Regulation 43(2) of the EIA Regulations, 2014, as amended, this letter serves to inform you
that the Basic Assessment Report (BAR) is available for your Deparmtnet’s review and written
comments, and a CD containing the BAR is included in this envelope. The BAR is also available for
download from Savannah Environmental’s website: https://www.savannahsa.com/public-
documents/other/.
Please note that BAR’s review period is from Friday, 24 January 2020 to Monday, 24 February 2020
and we are looking forward receiving your Department’s written comment/s on the BAR within the
30-day review period but not later that the closing date of the review period, i.e. Monday,
24 February 2020.
Kind regards
Nicolene Venter
Public Participation and Social Consultation
Email: [email protected]
Proof of delivery to be included in final BA
Report
Department of Environmental Affairs: Biodiversity
Conservation
23 January 2020
Mr Stanley Tshitwamulomoni
Acting Director: Biodiversity Conservation
Department of Environmental Affairs
Environmental House
473 Steve Biko Road
PRETORIA
0002
By Hand
Dear Mr Tshitwamulomoni,
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF AVAILABILITY OF BASIC ASSESSMENT REPORT FOR REVIEW AND COMMENT
The proponent, Eskom Holdings SOC Ltd, is proposing the installation, operation and
decommissioning of a Reverse Osmosis (RO) Plant for ash process water treatment at the Matla
Power Station, Mpumalanga Province. The project footprint will be less than 2ha in extent and will
fall within the power station property. The proposed development also falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
In terms of Regulation 43(2) of the EIA Regulations, 2014, as amended, this letter serves to inform you
that the Basic Assessment Report (BAR) is available for the DEA: Biodiversity Conservation Unit’s review
and written comments, and a CD containing the BAR is included in this envelope. The BAR is also
available for download from Savannah Environmental’s website:
https://www.savannahsa.com/public-documents/other/.
Please note that BAR’s review period is from Friday, 24 January 2020 to Monday, 24 February 2020
and we are looking forward receiving your Department’s written comment/s on the BAR within the
30-day review period but not later that the closing date of the review period, i.e. Monday,
24 February 2020.
Kind regards
Nicolene Venter
Public Participation and Social Consultation
Email: [email protected]
Proof of delivery to be included in final BA
Report
Department of Water and Sanitation
22 January 2020
Mr Stanford Macevele
Deputy Director: Water Quality Management
Department of Water and Sanitation
22 Rooth Street
BRONKHORSTSPRUIT
1020
By Courier Services
Dear Mr Macevele,
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF AVAILABILITY OF BASIC ASSESSMENT REPORT FOR REVIEW AND COMMENT
The proponent, Eskom Holdings SOC Ltd, is proposing the installation, operation and
decommissioning of a Reverse Osmosis (RO) Plant for ash process water treatment at the Matla
Power Station, Mpumalanga Province. The project footprint will be less than 2ha in extent and will
fall within the power station property. The proposed development also falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
In terms of Regulation 43(2) of the EIA Regulations, 2014, as amended, this letter serves to inform you
that the Basic Assessment Report (BAR) is available for your Department’s review and written
comments, and a Hard Copy of the BAR is included in this envelope. The BAR is also available for
download from Savannah Environmental’s website: https://www.savannahsa.com/public-
documents/other/.
Please note that BAR’s review period is from Friday, 24 January 2020 to Monday, 24 February 2020
and we are looking forward receiving your Department’s written comment/s on the BAR within the
30-day review period but not later that the closing date of the review period, i.e. Monday,
24 February 2020.
Kind regards
Nicolene Venter
Public Participation and Social Consultation
Email: [email protected]
Proof of delivery to be included in final BA
Report
eMalahleni Local Municipality
22 January 2020
Mr Erald Nkabinde
Manager: Environmental Management and Compliance
eMalahleni Local Municipality
Civic Centre
Cnr Mandela & Arras Streets
eMALAHLENI
1039
By Courier Services
Dear Mr Nkabnde,
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF AVAILABILITY OF BASIC ASSESSMENT REPORT FOR REVIEW AND COMMENT
The proponent, Eskom Holdings SOC Ltd, is proposing the installation, operation and
decommissioning of a Reverse Osmosis (RO) Plant for ash process water treatment at the Matla
Power Station, Mpumalanga Province. The project footprint will be less than 2ha in extent and will
fall within the power station property. The proposed development also falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
In terms of Regulation 43(2) of the EIA Regulations, 2014, as amended, this letter serves to inform you
that the Basic Assessment Report (BAR) is available for eMalahleni Local Municipality’s review and
written comments, and a CD containing the BAR is included in this envelope. The BAR is also
available for download from Savannah Environmental’s website:
https://www.savannahsa.com/public-documents/other/.
Please note that BAR’s review period is from Friday, 24 January 2020 to Monday, 24 February 2020
and we are looking forward receiving eMalahleni Local Municipality’s written comment/s on the BAR
within the 30-day review period but not later that the closing date of the review period, i.e. Monday,
24 February 2020.
Kind regards
Nicolene Venter
Public Participation and Social Consultation
Email: [email protected]
Proof of delivery to be included in final BA
Report
Eskom Holdings SOC Ltd
22 January 2020
Mr John Geeringh
Senior Environmental Advisor
Eskom Holdings SOC Ltd
Megawatt Park
Maxwell Drive
SUNNINGHILL
2157
For Collection
Dear Mr Geeringh,
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF AVAILABILITY OF BASIC ASSESSMENT REPORT FOR REVIEW AND COMMENT
The proponent, Eskom Holdings SOC Ltd, is proposing the installation, operation and
decommissioning of a Reverse Osmosis (RO) Plant for ash process water treatment at the Matla
Power Station, Mpumalanga Province. The project footprint will be less than 2ha in extent and will
fall within the power station property. The proposed development also falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
In terms of Regulation 43(2) of the EIA Regulations, 2014, as amended, this letter serves to inform you
that the Basic Assessment Report (BAR) is available for Eskom Holdings SOC Ltd’s review and written
comments, and a CD containing the BAR is included in this envelope. The BAR is also available for
download from Savannah Environmental’s website: https://www.savannahsa.com/public-
documents/other/.
Please note that BAR’s review period is from Friday, 24 January 2020 to Monday, 24 February 2020
and we are looking forward receiving Eskom Holdings SOC Ltd’s written comment/s on the BAR within
the 30-day review period but not later that the closing date of the review period, i.e. Monday,
24 February 2020.
Kind regards
Nicolene Venter
Public Participation and Social Consultation
Email: [email protected]
Nkangala District Municipality
(Commenting on behalf Commenting Authority:
Mpumalanga Department of Agriculture, Rural
Development, Land and Environmental Affairs)
22 January 2020
Ms Dieneo Tswai
Deputy Director
Nkangala District Municipality
Cnr Rosemead & Ryan Roads
Klipfontein
WITBANK
1035
By Courier Services
Dear Ms Tswai,
INSTALLATION AND OPERATION OF A REVERSE OSMOSIS PLANT AT THE MATLA POWER
STATION, MPUMALANGA PROVINCE
NOTICE OF AVAILABILITY OF BASIC ASSESSMENT REPORT FOR REVIEW AND COMMENT
The proponent, Eskom Holdings SOC Ltd, is proposing the installation, operation and
decommissioning of a Reverse Osmosis (RO) Plant for ash process water treatment at the Matla
Power Station, Mpumalanga Province. The project footprint will be less than 2ha in extent and will
fall within the power station property. The proposed development also falls within the jurisdiction of
the eMalahleni Local Municipality and within the greater Nkangala District Municipality.
In terms of Regulation 43(2) of the EIA Regulations, 2014, as amended, this letter serves to inform you
that the Basic Assessment Report (BAR) is available for Ngankgala District Municipality’s, as the
competent authority, review and written comments, and a Hard Copy and two (2) CDs containing
the BAR, are included in this envelope. The BAR is also available for download from Savannah
Environmental’s website: https://www.savannahsa.com/public-documents/other/.
Please note that BAR’s review period is from Friday, 24 January 2020 to Monday, 24 February 2020
and we are looking forward receiving Nkangala District Municipality’s written comment/s on the BAR
within the 30-day review period but not later that the closing date of the review period, i.e. Monday,
24 February 2020.
Kind regards
Nicolene Venter
Public Participation and Social Consultation
Email: [email protected]
Proof of delivery to be included in final BA
Report