annual environmental report 2012 · 4.2 noise monitoring report summary 2012 ... the principal...
TRANSCRIPT
![Page 1: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/1.jpg)
Annual Environmental
Report 2012
Company: Baxter Healthcare SA Address: Moneen Road, Castlebar, Co. Mayo Licence Register No: PO636-02
![Page 2: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/2.jpg)
Declaration
All the data and information presented in this report has been checked and certified as
being accurate. The quality of the information is assured to meet licence requirements.
Caitriona Gannon Michelle Bourke
![Page 3: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/3.jpg)
1.0 INTRODUCTION ............................................................................................................................. 1
1.1 FACILITY DETAILS .......................................................................................................................... 1 1.2 BRIEF DESCRIPTION OF THE ACTIVITIES AT THE SITE .................................................................... 1 1.3 ENVIRONMENTAL OPERATING STRUCTURE IN USE AT THE SITE ................................................... 3 1.4 COMPANY ENVIRONMENTAL POLICY ............................................................................................. 6 1.5 ORGANISATIONAL STRUCTURE ....................................................................................................... 7
2.0 SUMMARY INFORMATION ........................................................................................................ 8
2.1 SELF-MONITORING DATA ............................................................................................................... 8 2.1.1 Emissions to Sewer ................................................................................................................. 8 2.1.2 Emissions to Surface Water .................................................................................................... 9 2.1.3 Emissions to Atmosphere ...................................................................................................... 11
2.2 SUMMARY OF WASTE ARISING ..................................................................................................... 12 2.3 ENERGY AND WATER RESOURCE CONSUMPTION SUMMARY ...................................................... 12 2.4 SUMMARY OF NOTIFICATIONS OF NON-COMPLIANCES ................................................................ 13 2.5 SUMMARY OF ENVIRONMENTAL INCIDENTS ................................................................................ 14
2.5.1 Comments on Table 9 Environmental incidents .......................................................................... 17 2.6 SUMMARY OF ENVIRONMENTAL COMPLAINTS ............................................................................ 18
3.0 MANAGEMENT OF THE ACTIVITY ....................................................................................... 19
3.1 INTRODUCTION .............................................................................................................................. 19 3.2 REPORT ON PROGRESS OF ENVIRONMENTAL MANAGEMENT SYSTEM FOR 2012 ........................ 20 3.3 ENVIRONMENTAL MANAGEMENT PROGRAMME 2013 ................................................................. 28 3.4 WASTE MANAGEMENT.................................................................................................................. 35 3.5 POLLUTANT RELEASE AND TRANSFER REGISTER – REPORT FOR 2012 & PROPOSAL FOR 2013 .. 41
4.0 LICENCE-SPECIFIC REPORTS ................................................................................................ 42
4.1 ANNUAL CO2 EMISSIONS ............................................................................................................. 42 4.2 NOISE MONITORING REPORT SUMMARY 2012 ............................................................................. 43 4.3 GROUNDWATER MONITORING REPORT SUMMARY ...................................................................... 44 4.4 REPORT ON ANNUAL SOLVENT USAGE ........................................................................................ 46 4.5 RESPIROMETRY TESTING ............................................................................................................. 47 4.6 TOXICITY TESTING ....................................................................................................................... 48 4.7 API ABSENCE TESTING ................................................................................................................. 48 4.8 PROCESS RAW MATERIALS USAGE EFFICIENCY .......................................................................... 49 4.9 ENVIRONMENTAL LIABILITY STATEMENT .................................................................................... 49
![Page 4: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/4.jpg)
APPENDICES
APPENDIX A Summary of Waste Arising
APPENDIX B Baxter‟s AER /PRTR Returns
APPENDIX C Waste Contractors
APPENDIX D Baxter Products
APPENDIX E Energy Projects 2012, Energy Efficiency Audit Summary Report & Energy Business Plan 2013
APPENDIX F Bund Integrity Reports
APPENDIX G Pipe & Sump Integrity Reports
![Page 5: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/5.jpg)
1
1.0 INTRODUCTION
1.1 Facility Details
This Annual Environmental Report (AER) has been compiled for the Baxter Healthcare SA facility
located at Moneen Road, Castlebar, Co. Mayo. This facility was established in July 1972. Baxter‟s
Irish Manufacturing headquarters in Ireland and it currently operates under IPPC Licence Register
No. PO636-02. Today there are over 1,000 people employed between the Baxter facility in Castlebar
and the Baxter facility located in Swinford, Co. Mayo. The direct payroll and economic contribution
generated through Baxter Healthcare operations is significant in the Castlebar catchment and Region.
National Grid Reference
Easting 5 1 5 8 7 3 Northing 7 9 0 0 3 8
Licence details
Company Name Baxter Healthcare SA
Location Moneen Road, Castlebar, Co. Mayo
Register Number P0636-02 (Technical amendment A dated 24th November 2010)
Commencement Date 20th August 2007
Principal class of activity The use of chemical or biological process for the production of
basic pharmaceutical products
1.2 Brief Description of the Activities at the Site
Products Manufactured at the Site
Baxter Healthcare is a global medical products and services company. Through Baxter‟s subsidiaries,
the company provides critical therapies for people with life-threatening conditions. Baxter‟s products
include biopharmaceuticals, vaccines, bio-surgery products, transfusion therapies, medication
delivery and renal therapy.
The products that are currently manufactured in Baxter Castlebar can be described as follows:
Medication Delivery (MD) – these are intravenous solution products in small bag sizes
ranging from 50ml and 150ml, these products are used most frequently for drug
administration in intravenous format to patients.
Renal Therapy – these are a range of dialysis solution products for patients who suffer from
kidney failure. The principal category is peritoneal dialysis solutions that enable dialysis to
take place in the patient‟s home.
See appendix D for information on Baxter‟s products.
![Page 6: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/6.jpg)
2
Processes Used at the Site
The dialysis product processes operated at Baxter Castlebar are all similar:
The Primary containers for both medication delivery and renal products (Bags which range in
size from 50ml to 5 Litre) comprise of materials that are classed as PVC and Non-PVC. The
films used to manufacture the Non PVC Bags on site are supplied by a Baxter Healthcare
sister plant in Switzerland, while all PVC bags are received pre formed from a sister plant in
Belgium. PVC tubing for some of the renal product is extruded on site.
Dialysis solutions are prepared using sterilised water in large tanks. The ingredients are
added manually. The mixed solution is then filled into bags. The bags are enclosed in
pouches, and piping attached. The assembled product is sterilised in steam chambers. The
sterilised product is packed into cardboard boxes and despatched on wooden pallets.
The current processes are:
Twinbag Process - involves the manufacturing of Dialysis Solution, which is filled
into plastic bags, sterilised and packed.
Mainline Process - involves the manufacturing of Dialysis Solution, which is filled
into plastic bags, sterilised and packed.
Miniline Process - involves the production of a range Sterile Premixed Drugs in
intravenous (IV) Solutions.
Physioneal Process - this process is the same as the Twinbag process, except that the
product is pH compatible with the human body, and is packed in a gas barrier pouch.
Physioneal Clearflex – A renal dialysis solution filled into a Non PVC two chamber
container utilising an in-line Form Seal process.
Normal operating hours are Monday to Friday, 3 shifts, Saturday and Sunday, 2 shifts. Baxter‟s site
is provided with 24-hour security 7-days a week.
![Page 7: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/7.jpg)
3
1.3 Environmental Operating Structure in Use at the Site
Baxter Corporation has a strong commitment to Environmental Excellence and promotes a
"State of the Art" Environmental Programme. Baxter Ireland incorporated these Programmes
into its Strategic Business Plan in early 1992. The Irish Manufacturing Operations (IMO)
Environmental, Health and Safety Policy (EHS) Statement and the IMO‟s EHS
Organisational Structure are included at the end of this section.
The facility has established and maintains a documented quality system, which ensures that
the product conforms to specific requirements. This system includes the preparation and
implementation of documented quality system procedures and instructions in accordance with
the Quality Manuals, and in compliance with the applicable regulatory requirements. The
facility also operates both an environmental and a health and safety management system, both
systems are accredited to the ISO 14001 and OSHAS 18001 standards and are certified by
ERMCVS.
The facility holds a Green House Gas Permit Number, IE-GHG-133-05, Installation No. IE-
97, Activity Code E1.1. The facility holds a Police Certificate for Keeping Explosives for
Private Use Serial No. 188943, Form C 49, the explosive chemicals are 500g Ammonium
nitrate, 500g Potassium Nitrate, 225ml of Nitrobenzene, 150g Sodium Nitrite, 500g Potassium
Dichromate, 100g Potassium Chromate and 1kg Magnesium Nitrate hexahydrate . This
certificate is reviewed and re-issued on an annual basis. In addition to external requirements,
the plant also operates to Baxter Corporate requirements.
The Baxter Irish Manufacturing Operations EHS Management Programme is designed to
protect the health and safety of all our employees, the public and the environment. The
programme is an integral part of the Irish Manufacturing Operations business and its goals are
included in our business plan. The Senior Management Group define the EHS policies,
working alongside the Senior Management Team and with individual employees, implements
these policies.
The Environmental, Health & Safety Management System Procedure lays out the format to
document, achieve and maintain an Environmental, Health and Safety Management System
(EHSM) that conforms to the operation‟s environmental, health and safety policy and meets
in full the requirements of the Environmental Management Standard – ISO 14001, OHSAS
18001 Safety Management System Standard and Integrated Pollution Control Licence.
On the basis of the results from Corporate and Division/Internal Audits, EHS reviews and
Risk Assessment outcomes, we have established EHS objectives and targets. The objectives
and targets are in line with Baxter Corporate and Baxter Irish Manufacturing Operations
policy statements and are reviewed on a regular basis with the EHS Dept alongside the Senior
Management Team.
The principal EHS goals are reviewed at the EHS Management System Annual Management
Review. The goals and targets are incorporated into the Business Plans for the Operation.
Responsibility is given to individuals to oversee the implementation of the goals. Progress
made towards achieving these goals/targets is reviewed on a regular basis at the EHS
Meetings and at the Quarterly EHS Review meetings with Senior Management. It is the
responsibility of Senior Management to communicate to their reportees any
issues/recommendations from this review. EHS key performance indicators are included in
![Page 8: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/8.jpg)
4
all employees Performance Management Objectives (PMOs) specified in the company‟s
annual appraisal system.
The organisation has identified and evaluated its EHS aspects. The organisation has
identified and evaluated its EHS Risks and Hazards as per National Requirements. Risk
Assessment Master Plan shows the scope/severity/frequency of risks and their plans for
completion of risk assessments on site.
All new projects and processes are reviewed to determine whether they are acceptable
from an environmental point of view, and the means needed for preventing, or if that is
not possible, minimising environmental impact, through application of the best available
techniques. This is addressed through procedure Procedure IR36-11-02-015 on Risk
Assessment Management Plan.
Waste is minimised by a comprehensive waste management programme of recovery,
recycling and reuse, end-of-pipe or final disposal is only used where there is no other
practicable option. All Waste on site is managed through the EHS Department. The EHS
Department is responsible for sourcing all waste contractors used, obtaining all required
documentation and are responsible for tracking and maintaining all paperwork pertaining to
the waste types taken off site. As a corporate requirement, the EHS Manager carries out
Regulated Waste Management Site audits on all hazardous waste contractors on a frequency
set by Corporate procedures.
Baxter Castlebar has a very successful and long-standing Energy Reduction Quality Working
Team, which are very much, results driven. Designed to focus on energy use and through the
application of technology, skill and company wide commitment, to achieve real savings in
energy costs, improve competitiveness and as a consequent reduction in environmental
impact.
As per Schedules 1 – 4 of the IPPC licence various environmental monitoring is carried out at
Baxter to include; air, effluent, surface water, groundwater, waste analysis and noise
monitoring. Ambient monitoring of air quality, ground water and noise shows that the impact
of Baxter‟s operations is minimal. An external accredited laboratory carries out all the
wastewater analysis on a daily, weekly and monthly basis where applicable.
Baxter have developed and implemented a comprehensive emergency response plan, this plan
establishes the responsibilities and procedures for anticipated emergency situations, the
training requirements for responsible parties and an inventory of emergency response
equipment. It clearly defines roles and responsibilities of all employees in an emergency
situation. In addition to the emergency response plan, there is a fully trained emergency
response team available on every shift to deal with any emergencies that may occur.
24-hour security is provided on the site to continuously monitor all activities on site both
internal and external.
All employees receive updates at Departmental meetings pertaining to the current EHS issues
and programme. They are made aware of their individual responsibilities in relation to waste
minimisation and assistance with recycling programmes and their compliance with EHS
Procedures and Regulations. Procedures relating to the EHS Aspects are updated through
Baxter standard operating procedures within the QA system
![Page 9: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/9.jpg)
5
EHS quarterly reviews for senior managers are held at the end of each quarter to review
progress on EHS goals, targets and various EHS projects. This review also provides an update
on the current status of all monitoring and inspections carried out. Also Corporate EHS
newsletters, Division EHS, Baxtra Articles, weekly communication meetings, site specific
publications on our environmental, health & safety programme creates awareness of our EHS
programme amongst employees.
A training plan has been compiled which lists the training requirements for individual
personnel. Training records are maintained by the HR Department recording the training
sessions attended. New employees receive EHS orientation presentation (which identifies the
hazards within the plant) and tour of recycling areas, fire evacuation routes within the plant.
They also are instructed on the EHS policies and procedures we have in place and on EHS
issues in general pertaining to our operations.
![Page 10: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/10.jpg)
6
1.4 Company Environmental Policy
ENVIRONMENTAL, HEALTH & SAFETY POLICY STATEMENT Baxter‟s Irish Manufacturing Operation comprising the Castlebar and Swinford plants is committed to
Environmental, Health & Safety (EH & S) leadership and meeting all Regulatory, Division and Corporate
Requirements.
The Irish Manufacturing Operation is focused on being the leading supplier of the products we
manufacture achieving this through continuously improving quality, value, and the services we provide to
our customers and through respect for the environment.
To accomplish this, we are integrating Environmental, Health & Safety principles into all our business activities.
1. Leadership: The Irish Manufacturing Operation is committed to leadership and Continuous improvements in
respect of EH & S. We will maintain a state-of-the-art EHS programme in terms of OSHAS 18001 and the ISO-
14001 International Standard.
2. Legal Compliance: We will commit to complying with all Irish and European Union laws and regulations.
We will also commit to adhering to Corporate requirements. Baxter Healthcare Corporation has in the past and
will continue in the future to demonstrate continuous improvements in EH&S performance beyond statutory
obligations as far as is economically achievable.
3. Waste Minimisation: Baxter‟s Irish Manufacturing Operation will commit to aggressively pursuing
opportunities to minimise waste and the prevention of pollution. Specifically we will commit to reducing
hazardous and non hazardous waste against our annual targets. We will commit to maintaining an aggressive
waste cardboard, paper, plastic, batteries, fluorescent bulbs, pallets, metals, drums, electronic waste and oil
recycling programmes.
4. Energy Conservation: Through increasing energy efficiency in line with current targets, we will meet our
commitment to the Baxter corporate energy programme.
5. Accident Prevention: Through our proactive intervention programme we will commit to minimising the
number of accidental incidents at both operating facilities. We will commit to reduction in lost workday
accidents, lost workdays and recordable accidents in line with our corporate targets and also provide effective
injury management for all employees.
6. Workplace Environment: Through active ergonomics, noise reduction and air quality programmes, we will
commit to enhancing the workplace environment for all of our employees.
7. Risk Analysis/Control: We will maintain an Emergency Response Plan and risk analysis programmes to
minimise risk to personnel, the environment and company.
8. EHS Co-ordinators and Managers: The EH&S Manager has overall responsibility for EH&S protection and
the EH&S programme. In addition, each employee and particularly every manager are responsible for
compliance with this Policy.
9. Training and Audits: The Irish Manufacturing Operation will provide co-ordinated, effective EH&S
training, awareness and audit programmes to educate the staff and contractors on the company‟s EH&S policy
and procedures. We will assist our contractors, suppliers and customers to develop a similarly concerned
approach to protection of their personnel and the environment.
10. Communication: We will maintain communication links with Baxter Corporate Headquarters and Division
personnel, shareholders, authorities, community groups and neighbours as relevant in relation to EH&S affairs.
11. Public Availability: Our EHS Policy Statement is made available to the public through the EHS Department
in the Castlebar plant and the General Office Area in the Swinford plant. In addition a copy of our EH&S policy
has been made available to all employees, and is displayed in reception, on the EH&S notice boards and will be
periodically reviewed
![Page 11: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/11.jpg)
- 7 -
1.5 Organisational Structure
Figure 1: Company Organisational Chart for Environmental Management at Irish Manufacturing Operations
Alan Weiler
PLANT MANAGER
IMO
Gerry Prendergast
Engineering Director
Caitriona Gannon
EHS Manager.
Michelle Bourke
EHS Coordinator.
![Page 12: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/12.jpg)
- 8 -
2.0 SUMMARY INFORMATION
2.1 Self-Monitoring Data
2.1.1 Emissions to Sewer
Emissions to sewer were discharged from the plant in accordance with condition 4/5
and Schedule B/C of the IPPC Licence.
Baxter has one emission points to process waste (PW). The PW discharge point is
monitored for the parameters shown in Table 1. The summary table shows that for the
mass emissions for the year 2012 were in compliance with the Licensed Mass
Emissions for all parameters.
The current monitoring programme for the emissions to sewer consists of online pH,
Temperature and flow measurements and 24hour flow proportional composite samples
taken for analysis in accordance with the IPPC licence conditions
TABLE 1 SUMMARY OF MASS EMISSIONS 2011 & 2012
Parameter Mass
Emissions
for 2011
(Kg/year)
Mass
Emissions
for 2012
(Kg/year)
Licensed Mass
Emission
(kg/year)
Volume (m³) 437,035 454,987 547,500
BOD 180,802 175,005 547,500
COD 269,988 272,557 1,368,750
Suspended Solids 14,258 11,300 80,300
Ammonia (as N) 18.32 9.74 803
Total Phosphorous (as P) 52 131 1,606
Sulphate (as SO4) 13,471 26,341 54,750
Detergents (as MBAS) 301 307 4,015
Fats, Oils & Grease 2314 3961 32,120
Chloride 230,215 255,451 365,000
Comment:
Overall it can be seen that loading to sewer of each of the physical/chemical parameters
were well below the licensed mass limits for 2012.
![Page 13: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/13.jpg)
- 9 -
2.1.2 Emissions to Surface Water
Table 2 below presents a summary of the emissions to surface water for 2012.
Week Beg.
Surface West Surface
West Surface East
Surface East
COD (mg/l) pH COD (mg/l) pH Warning limit-100mg/l Action limit 150mg/l 6 - 9.5
Warning limit-100mg/l Action limit 150mg/l 6 - 9.5
31/12/2011 77 8.55 35 8.1
07/01/2012 110 7.69 35 7.94
14/01/2012 42 8.53 34 8.3
21/01/2012 38 9.1 38 8.13
28/01/2012 75 7.66 35 8.15
04/02/2012 42 7.89 33 8.15
11/02/2012 45 8.97 38 8.19
18/02/2012 100 7.85 43 8.46
25/02/2012 70 8.04 37 8.03
03/03/2012 58 8.67 37 7.96
10/03/2012 47 8.52 40 8.27
17/03/2012 47 8.65 35 8.12
24/03/2012 132 8.57 45 8.05
31/03/2012 68 9.41 8.11 47
07/04/2012 37 8.59 8.31 37
14/04/2012 50 7.98 32 7.93
21/04/2012 127 8.48 35 8.12
28/04/2012 60 9.22 47 8.01
05/05/2012 40 7.99 40 8.16
12/05/2012 43 8.61 38 8.11
19/05/2012 55 8.93 45 8.02
26/05/2012 45 8.62 44 8.2
02/06/2012 35 8.49 37 7.95
09/06/2012 38 8.6 36 8.29
16/06/2012 37 8.05 41 8.09
23/06/2012 35 8.18 42 8.33
30/06/2012 42 8.93 41 8.15
07/07/2012 45 9.25 46 7.93
14/07/2012 60.0 8.93 63.0 8.09
21/07/2012 58 8.97 56 8.05
28/07/2012 * * * *
04/08/2012 * * 53 8.02
11/08/2012 119 7.85 45 8.02
18/08/2012 62 7.33 50 7.9
25/08/2012 50 8.43 46 8.04
01/09/2012 56 7.82 42 7.9
07/09/2012 45 8.96 42 8.26
14/09/2012 40.0 8.34 36.0 8.15
![Page 14: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/14.jpg)
- 10 -
Week Beg.
Surface West Surface
West Surface East
Surface East
COD (mg/l) pH COD (mg/l) pH Warning limit-100mg/l Action limit 150mg/l 6 - 9.5
Warning limit-100mg/l Action limit 150mg/l 6 - 9.5
21/09/2012 45.0 8.47 44.0 8.20
29/09/2012 25 7.88 35 7.96
06/10/2012 37 8.6 37 8.23
13/10/2012 37 7.98 40 7.89
20/10/2012 40 9.03 32 8.18
27/10/2012 35 7.79 35 7.85
03/11/2012 35 7.89 20 8.11
10/11/2012 45 8.37 43 8.17
17/11/2012 35 8.31 36 8.01
24/11/2012 40 8.43 48 8.31
01/12/2012 42 7.85 44 7.85
08/12/2012 35 7.9 45 8.15
15/12/2012 37 8.48 37 8.22
22/12/2012 * * * *
29/12/2012 60 8.81 25 8.52
*Implies that there was no surface water sample available
In 2012 surface water discharges were monitored in accordance with Schedule C2.3 and Condition
5.
Comment: There were no incidents recorded (i.e. no action limits reached). Visual inspections
were carried out and recorded on site log book.
![Page 15: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/15.jpg)
- 11 -
2.1.3 Emissions to Atmosphere
Baxter operates a number of boilers that generate steam. The boilers are numbered as; boiler 2(A1-1),
3(A1-2), 4(A1-3) and 6(A1-5). Boiler 5 is a domestic boiler located on site for heating a small office
complex called the Annex which is not in use and the oil supply was removed in 2012. Boiler 3 was
decommissioned in December 2008 and replaced with Boiler 7.
Under Condition 6.10.2, Boiler 3 (Boiler 7) was replaced with a natural gas burning boiler in
November 2009. Boiler 4 & Boiler 6 were both converted to natural gas in December 2009. Due to
the age of Boiler 2 it was unsuitable for conversion to gas and was converted to diesel instead.
Boiler #3 (Boiler# 7) is a new boiler and as such is very efficient and reliable. As part of Condition
6.10.3 Boilers 3, 4, & 6 are now to be used as the primary boilers on-site and for boiler #2 to be a
back-up boiler.
Baxter Healthcare installed boiler economizer on our Steam boiler 6 (A1-5) in August 2012 as
approved by the EPA prior to installation. The principal change in emissions is that the efflux
temperature reduced upon installation of an economiser.
The IPPC licence limits the emissions of sulphur dioxide (SO2), nitrogen dioxide (NO2) and carbon
monoxide (CO) from the boilers. Ambient air quality was monitored in the vicinity of the facility as
part of the EIS prepared in 2002. The recorded level of all pollutants monitored was within air quality
standards.
Table 3 is a summary of the mass emissions to atmosphere from boilers 2, 3, 4 and 6. These emissions
are based on stack flow rate and stack concentration measurements conducted by Site Rite in April &
November 2012.
Table 3 shows that all the boilers are operating within the approved limits for 2012.
TABLE 3 SUMMARY OF EMISSIONS TO ATMOSPHERE
IPPC Licence
Emission
Point
Reference
Parameter
Mass
Emissions
for 2012
(Kg/year
Licensed
Mass
Emission
(kg/year)
Boiler points:
A1-5 (boiler 6)
A1-3 (boiler 4)
A1-1 (boiler 2)
A1-2 (boiler 7)
Oxides of
sulphur (as SO2) 1,049 1,006,507
Nitrogen oxides
(as NO2) 9,404 436,108
Carbon
Monoxide (CO) 40 69,414
There has been no non-compliance of Mass air emissions to the atmosphere at the Baxter plant for the
calendar year 2012.
Baxter Healthcare installed a CHP plant in late 2009. The CHP Plant comprises of two natural gas
fired Jenbacher Cogeneration Units capable of generating a combined total of 3 Mw of electrical
energy. Table 4 below represents the results of the monitoring completed on the 3rd April and on the
8th November 2012.
![Page 16: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/16.jpg)
- 12 -
TABLE 4 SUMMARY OF RESULTS FROM MONITORING THE COMBINED HEAT AND POWER PLANT (CHP)
Engine
Number Oxygen %
Nox as
(NO2)
mg/Nm3
Carbon
Monoxide
mg/Nm3
Sulphur
dioxide
mg/Nm3
Apr Nov Apr Nov Apr Nov Apr Nov
CHP 416 9.5 9.6 520.5 343 761.4 731.8 200.2 169
CHP 612 10.6 10.9 498.2 309.1 254.4 242.3 101.8 78.5
2.2 Summary of Waste Arising
Details of the individual waste sent off site for treatment including disposal and recycling by
appropriate licensed waste management contractors and total quantities of waste produced including
hazardous and non-hazardous waste for the calendar year 2012 are presented in Appendix A.
2.3 Energy and Water Resource Consumption Summary
Table‟s 5 and 6 indicate the energy and & Table 7 indicates the water use on the Baxter site for 2012.
TABLE 5 SUMMARY TABLE OF ENERGY CONSUMPTION FOR 2011 VS. 2012
Energy Source Energy Consumed 2011(MW) Energy Consumed 2012(MW)
Medium Fuel Oil 0 0 Diesel 118 743
Propane 18 (cylinders) 17 (cylinders) Natural Gas 102,093 111,182
Electricity 5,870 7,452
TABLE 6 SUMMARY TABLE OF ENERGY CONSUMPTION IN 2012
2012 Consumption of different energy streams Energy Stream Annual
Quantity
Units
Electricity consumed onsite 28,803,998 kWh
Electricity Imported 7,451,507 kWh
Electricity Generated Onsite (CHP sites only) 21,352,491 kWh
Electricity exported offsite (CHP sites only) 0 kWh
Natural Gas Total 111,181,604
kWh (Gross Calorific value
(CV))
Natural Gas for CHP 49,398,028 kWh (Gross CV)
Gasoil 68,000 Litre
TABLE 7 SUMMARY TABLE OF WATER CONSUMPTION FOR 2011VS 2012
Resource Amount Consumed 2011
(Litres)
Amount Consumed 2012
(Litres)
Water 564,876,000 612,780,187
![Page 17: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/17.jpg)
- 13 -
2.4 Summary of Notifications of Non-Compliances
Date of
Notification Non-Compliance
23/02/2012
Condition 3.6, 3.9, 8.4 and 8.5- road tankers containing cleaning agents stored in
an non designated, unbunded area, an absence of adequate local containment.
Tankers did not contain any high level alarms
23/02/2012 Condition 5.10 – Effluent monitoring not being carried out over the Christmas
shutdown period
23/02/2012
Condition 1.4 and 8.3 – Waste management and classification – the movement of
2 consigments of solution A as non hazardous. It was previously classified as
hazardous and the subsequent reclassification had not been carries out to the
satisfaction of the Agency
23/02/2012 Condition 5.10 and 11.10- Submission of reports – Delays in submitting the
quarterly reports
16/04/2012 Condition 11.1 – issues the flow meter in October 2011 not being reported by
phone of by Fax using the notification form but by including the quarterly report.
12/06/2012
Condition 3.6.2,3.6.5,8.5 and 8.9- road tankers containing cleaning agents &
sugar solution stored in an non designated, unbunded area, an absence of adequate
local containment. Tankers did not contain any high level alarms
12/06/2012 Condition 5.1 – Exceedance of ELVs for flow at the PW emission point (3
exceedances)
28/06/2012
Condition 3.6 & 6.11 - 15 bunds were visually inspected, however a liquid
retention test (LRT) was not completed, reasons for not completing a LRT were
not satisfactory, two bunds were neither visually or LRT tested.
23/07/2012 Condition 5.1 – Chloride, Sulphate & flow exceedances at PW emission point (12
chloride, 2 Sulphate and 5 Flow)
28/08/2012 Condition 5.1- Chloride and Sulphate exceedances at PW emission point (6
Chloride & 1 Sulphate)
10/10/2012 Condition 5.1- Chloride & Flow exceedances at PW emission point(3 chloride
and 9 flow)
11/12/2012
Condition 3.6.2, 8.5 & 3.9- Bunding and material- road tankers containing sugar
solution stored in an non designated, unbunded area, an absence of adequate local
containment. Tankers did not contain any high level alarms
11/12/2012 Condition 5.1- Chloride & Flow exceedances at PW emission point(4 chloride
and 3 flow)
11/12/2012 Condition 11.1 - Non-notification of incidents for exceedance of ELV‟s for
Temperature and pH at PW emission point
*Detailed Corrective and Preventative Actions plans were submitted to the EPA for the above Non-
compliances.
![Page 18: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/18.jpg)
- 14 -
Table 8 Comparison of number of Notification of Non-Compliance 2011 vs. 2012
Parameter No of Non-Compliances
in 2011
No of Non-Compliances in
2012
Volume (m³) 9 23
pH 1 0
Temperature 0 0
BOD 1 1
BOD Loading 0 1
COD 1 0
Suspended Solids 0 0
Ammonia (as N) 0 0
Total Phosphorous (as P) 0 0
Sulphate (as SO4) 0 7
Detergents (as MBAS) 0 0
Fats, Oils & Grease 0 0
Chloride 0 30
Chloride Loadings 0 19
Audit Finding 7 14
NOx 0 0
SOx 0 0
Total 19 95
2.5 Summary of Environmental Incidents
Table 9 shows the environmental incidents during 2012. The details given below show the
occasions on which one of the following occurred:
A release to atmosphere from a potential emission point.
An emission that did not adhere to the limits of the licence.
The malfunction of monitoring and control equipment leading to a breach of the
licence.
An incident that had the potential to contaminate surface or ground water, or posed an
environmental threat to either air or land.
![Page 19: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/19.jpg)
- 15 -
TABLE 9
Date Incident/Parameter Result ELV
3/01/2012 Flow 1767m3 1500m3
4/01/2012 Flow 1791m3 1500m3
06/03/2012 Chloride Loading 1063kg/day 1000kg/day
01/05/2012 EPA Spilt Sample -Chloride 930mg/l 750mg/l
05/05/2012 Flow 1630 m3 1500m3
06/05/2012 Flow 1752 m3 1500m3
14/05/2012 Flow 1546 m3 1500m3
17/05/2012 Flow 1511 m3 1500m3
05/06/2012 Flow 1584 m3 1500m3
12/06/2012 Chloride 842.4mg/l 750mg/l
19/06/2012 Chloride 855mg/l 750mg/l
20/06/2012 Flow meter malfunction n/a n/a
21/06/2012 Sulphate 112.4mg/l 100mg/l
21/06/2012 Chloride 1035mg/l 750mg/l
22/06/2012 Chloride loading 1044kg/day 1000kg/day
23/06/2012 Chloride 849.6mg/l 750mg/l
24/06/2012 Chloride 774mg/l 750mg/l
26/06/2012 Chloride 801mg/l 750mg/l
27/06/2012 Chloride loading 1004kg/day 1000kg/day
01/07/2012 Chloride 1019.7mg/l 750mg/l
02/07/2012 Chloride 1266.3mg/l 750mg/l
03/07/2012 Chloride loading 1016kg/day 1000kg/day
04/07/2012 Sulphate 116.8mg/l. 100mg/l
05/07/2012 Chloride loading 1028kg/day. 1000kg/day
10/07/2012 Chloride 2246.4mg/l 750mg/l
10/07/2012 Flow 1521 m3 1500m3
11/07/2012 Flow 1533 m3 1500m3
12/07/2012 Chloride loading 1097kg/day 1000kg/day
13/07/2012 Chloride loading 1021kg/day 1000kg/day
14/07/2012 Flow 1554 m3 1500m3
16/07/2012 Chloride loading 1046kg/day 1000kg/day
17/07/2012 Chloride 1043.1mg/l 750mg/l
18/07/2012 Chloride 853.2mg/l 750mg/l
19/07/2012 Flow 1559 m3 1500m3
19/07/2012 Chloride 781.2mg/l 750mg/l
20/07/2012 Chloride loading 1094kg/day 1000kg/day
21/07/2012 Chloride loading 1053kg/day 1000kg/day
22/07/2012 Chloride 761.4mg/l 750mg/l
29/07/2012 Chloride 1332mg/l 750mg/l
11/08/2012 Chloride 779.4mg/l 750mg/l
11/08/2012 Sulphate 134.7mg/l 100mg/l
![Page 20: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/20.jpg)
- 16 -
Date Incident/Parameter Result ELV
12/08/2012 Sulphate 108.5mg/l 100mg/l
13/08/2012 Chloride 907.2mg/l 750mg/l
16/08/2012 Chloride 799.2mg/l 750mg/l
18/08/2012 Chloride 772.2mg/l 750mg/l
19/08/2012 Chloride 756mg/l 750mg/l
20/08/2012 Chloride 990mg/l 750mg/l
21/08/2012 Chloride 754.2 750mg/l
24/08/2012 Sulphate 113.1mg/l 100mg/l
25/08/2012 Chloride 2142mg/l 750mg/l
26/08/2012 Chloride 1207.8mg/l 750mg/l
27/08/2012 Chloride 1078.2mg/l 750mg/l
28/08/2012 Chloride loading 1010kg/day 1000kg/day
03/09/2012 Sulphate 109.3mg/l 100mg/l
05/09/2012 Sulphate 112.9mg/l 100mg/l
05/09/2012 Flow 1538 m3 1500m3
08/09/2012 Flow 1587 m3 1500m3
13/09/2012 Flow 1808 m3 1500m3
13/09/2012 Chloride loading 1263kg/day 1000kg/day
14/09/2012 Flow 1581 m3 1500m3
14/09/2012 Chloride loading 1058.6kg/day 1000kg/day
21/09/2012 Flow 1583 m3 1500m3
21/09/2012 Chloride loading 1025.8kg/day 1000kg/day
27/09/2012 Flow 1506 m3 1500m3
27/09/2012 Chloride 1724.4mg/l 750mg/l
27/09/2012 Chloride loading 2597kg/day 1000kg/day
30/09/2012 Chloride 831.6mg/l 750mg/l
03/10/2012 Flow 1525 m3 1500m3
4/10/2012 Flow 1594 m3 1500m3
05/10/2012 Flow 1530 m3 1500m3
6/10/2012 Chloride loading 1006kg/day 1000kg/day
7/10/2012 Chloride 826.5 mg/l 750mg/l
7/10/2012 Chloride loading 1052kg/day 1000kg/day
12/10/2012 Flow 1567 m3 1500m3
13/10/2012 Flow 1615 m3 1500m3
18/10/2012 Flow 1513 m3 1500m3
25/10/2012 Chloride 1137.6mg/l 750mg/l
25/10/2012 Chloride loading 1507kg/day 1000kg/day
7/12/2012 Chloride 1738.8mg/l 750mg/l
7/12/2012 Chloride loading 2156kg/day 1000kg/day
20/12/2012 BOD 1598mg/l 1000mg/l
20/12/2012 BOD loading 1826.5kg/day 1500kg/day
![Page 21: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/21.jpg)
- 17 -
2.5.1 Comments on Table 9 Environmental incidents
Baxter confirms that the environmental incidents referred to in Table 9 were classed as Category one
incidents i.e. Breach of Emission Limit Values with no environmental pollution.
Baxter Healthcare in June 2012 was requested by the Agency to conduct daily monitoring of the
wastewater parameters. Baxter Healthcare was originally monitoring chloride and sulphate three
times per week.
Chloride
The investigations led Baxter to the conclusion that fixed daily amounts of chloride discharges from
our raw water treatment processes cause us to be close to our chloride emission limit. This is to say
that the regeneration cycles of the water softeners and the organic scavengers in our water treatment
area causes a discharge of salt that are close to the emission limit values.
To mitigate this Baxter has since the 20th August 2012 reduced by half the organic scavengers in our
raw water treatment process.
Sulphate
Root-cause investigations identified increase sulphate was due to cleaning of organic scavenger and
raw water tanks.
Volume
Root-cause investigations identified the following contributing factors:
Safety valve failure on line feeding hot water system into the plant leading to increase water
discharged to drain.
Change of Reverse Osmosis membrane
Increased flushing of water to drain
Cooling Towers (West and East) control set up leading to excessive discharges of water.
CAPA
Baxter Healthcare has completed corrective and preventative actions for the identified root causes and
has applied for a technical amendment with increased licence limits for volume, chloride & sulphate.
Baxter Healthcare is in the process of increasing the Wastewater treatment (WWTP) infrastructure at
the Knockthomas Site. A User Requirement Specification (URS) has been developed, to include the
increase limit in the above parameters.
Baxter Healthcare is seeking capital for the investment in the WWTP infrastructure. A project plan is
in place to have the project completed by Q1 2014. Contracts between the Mayo County Council are
Baxter Healthcare is in draft for the management of the WWTP.
![Page 22: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/22.jpg)
- 18 -
2.6 Summary of Environmental Complaints
Table 10 gives a summary of the complaints received in 2011 vs. 2012. There was one complaints
received during 2012.
TABLE 10 SUMMARY OF COMPLAINTS RECEIVED IN 2011 VS 2012
Complaint Categories Complaints Received
2011
Complaints Received
2012
Odour 0 0
Noise 0 0
Water 0 0
Procedural 0 0
Miscellaneous 1 1
Total 1 1
Summary of the miscellaneous complaint
Baxter received a complaint from Veolia Water Ireland (VWI), after a discharge on the 19th
December 2012. A BOD load of 32,750PE was measured at the Veolia composite inlet
sample. This compliant and the BOD exceedance associated was reported to the EPA in a
timely manner.
![Page 23: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/23.jpg)
- 19 -
3.0 MANAGEMENT OF THE ACTIVITY
3.1 Introduction
As part of the well-established environmental health and safety management system Baxter has set
a list of environmental objectives and targets in line with the Schedule of Objectives & Targets
outlined in their IPC licence and corporate goals and targets. Senior management define the EHS
policies and the EHS Manager, through the environmental management programme implements
these policies, goals and targets.
Baxter‟s EHS management programme is designed to protect the health and safety of all our
employees, the public and the environment. The programme is an integral part of Baxter‟s business
goals and is included in the business plan. Baxter has outlined a clear environmental target for each
of the objectives in each case taking into account realistic time-scales for completion. Goals for
each target were set with both long term and short-term goals in mind and to achieve year on year
improvement until the ultimate goal is reached.
Further goals and targets are set at EHS quarterly reviews and EHS meetings. Progress towards
achieving these goals and targets are reviewed at the EHS quarterly reviews.
Each year, subject to the Company‟s EHS management standards, each Baxter facility and
regional/business unit worldwide must prepare an EHS performance report on program status and
progress under relevant targets, objectives and other measures of performance. Each unit must
complete the annual EHS information verification process in Baxter‟s EHS Information
Management System (Insite). Information from Insite is included in the company wide report to the
Company and the public, including the annual Baxter Sustainability Report.
Monthly EHS reports detailing waste management, energy management, water consumption, and
greenhouse gas emissions are prepared after the end of each calendar month and sent to Regional
EHS Manager monthly. These reports generate an Eco-Efficiency Performance Report, which
provides graphical analysis of all environmental parameters year to date.
![Page 24: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/24.jpg)
- 20 -
3.2 Report on Progress of Environmental Management System for 2012
As part of the requirements of the IPC Licence (Condition 2.2), Baxter maintain Environmental
Management System (EMS) for the site. The EMS ensures that the requirements of the
Environmental, Health and Safety Policy are met.
The key aim of the system is to ensure that Baxter continually improves environmental
performance by setting targets. Targets should be quantifiable wherever it is practical to ensure
that real attainment is recorded against the targets.
The EMS maintains an Environmental Management Program which is prepared, reviewed and
updated annually to account for improvements resulting from the phased introduction of the
objectives and targets. Table‟s 11 – 20 detail the progress made on the EMS for 2012.
The EMS references the most significant environment aspects and associated impacts onsite.
Baxter maintains environmental documentation/communication system procedures to inform the
public on environmental performance of the facility as required by the IPPC licence.
![Page 25: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/25.jpg)
- 21 -
TABLE 11 PROGRESS REPORT ON TOTAL WASTE
Baxter aim to reduce Total Waste by 3% per unit of production and
conduct RWMS Audits
Target/Objective Baxter aim to reduce Total waste by 3% reduction in Total Waste
Generated per production unit based on end of 2011 figures.
Track API Waste separately in Divisional EHS Report.
Methods Baxter EHS Team will use best available techniques for storage,
transportation and disposal of non-hazardous waste. Regular meetings
scheduled to look at reduction type projects and compliance with waste
stream disposal.
Corrugate conversion lost team has been set up.
Re- Launch Waste Management Quality Working Team(QWT) to focus
on reduction on non-hazardous recycling rate.
Generate weight per bin per area for plastic weight in conjunction with
facilities engineering.
Continue to use FIFO policy in the labs.
Good Housekeeping practice drive – Office area‟s to have central bins,
better waste segregation and reduce amount of waste generated.
Hazardous waste training for all employees that enter the hazardous waste
shed
Responsible Person EHS Dept
Time Frame December 2012
Priority High
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs. Target
Detailed procedures are in place for the handling of all waste streams. All
employees received refresher training in the Waste Recycling/Waste
Management plans and practices. There are effective Waste Management
Systems are in place.
Good Housekeeping practice drive was rolled out – much improved
segregation on-site.
Cost of disposal of Chemical & API waste is charged to the department
generating the waste to improve awareness and accountability of waste
generation.
All EHS waste audits was carried out as required, Dangerous goods safety
advisor carried out a site audit with no major findings.
Baxter waste increased from 17.23 to 22.78 grams per production unit for
total generated without API which was to the increase disposal of
Cleaning solutions at ENVA.
Micro Lab initiated a project to reduce the amount of bio-hazardous waste
by:
1. Removing all non contaminated glass (now goes into glass
recycling bin)
2. Removing all non contaminated agar plates (now goes into
general waste)
![Page 26: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/26.jpg)
- 22 -
TABLE 12 PROGRESS REPORT ON ENERGY REDUCTION
Reason
Condition 7.2 of IPPC Licence, also Corporate Goal
Target/Objective Baxter aim to reduce the amount of energy used by 3% per production unit
based on end of 2011 figures.
Methods Means of achievement detailed in engineering procedure goals.
Implement Lean Energy Programme
Energy conservation on the Baxter site is an on going process, which
will be monitored and reported, on a quarterly basis and achieved by
Dec 2012.
Responsible Person Energy Manager
Time Frame December 2012
Priority High
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
22% decrease in energy use per production unit. Decrease primarily
due to energy reduction projects implemented and increase in
production output. The KWh/LEQ (Litre equivalent) figure
decreased from 0.81 KWh/LEQ in 2011 to 0.66 in 2012. See
appendix E, for details on Energy Projects completed in 2012.
TABLE 13 PROGRESS REPORT ON WATER USE
Reason
Condition 7.3 of IPPC Licence, also Corporate Goal
Target/Objective Baxter aim to reduce water consumption by 3% per production unit
Methods Means of achievement detailed in engineering procedure goals.
Also included as a component of quarterly environmental reviews.
Responsible Person Engineering & Facility Engineering Mgr
Time Frame December 2012
Priority High
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
Overall in 2012 a decrease of 8.2% in water usage per unit of production.
Decrease primarily due to water reduction measured taken and increase in
production output.
TABLE 14 PROGRESS REPORT ON GREEN HOUSE GAS EMISSIONS
Reason
Green House Gas Emission
Target/Objective Baxter aim to reduce GHG emissions by 3% per production unit.
Methods Means of achievement detailed in engineering procedure goals under
energy projects.
Responsible Person Engineering & Facility Engineering Mgr
Time Frame December 2012
Priority Medium
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
There was no reduction on GHG emissions. Baxter were allocated
20,623 tonnes of CO2 and Baxter emitted 20,862 tonnes of CO2
![Page 27: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/27.jpg)
- 23 -
TABLE 15 PROGRESS REPORT ON PACKAGING
Reason
Packaging Compliance Regulations.
Target/Objective Maintain reporting requirements for Essential Packaging Regulations
Methods Maintain procedures set up by the Packaging Quality working Team
(QWT) to ensure adherence to the requirements of the Packaging
Programme.
Responsible Person Product Development Manager, EHS Co-ordinator
Time Frame Dec 2012
Priority Medium
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
All new and changed packaging have been updated on the
compliance database
TABLE 16 PROGRESS REPORT ON EMISSIONS TO AIR
Reason
Legislative requirements and IPPC requirement
Target/Objective Ensure compliance with ODS regulations and phase out use of Ozone
Depleting substances R22 on site by 2014
Biannual emission monitoring for boilers & CHP
Methods Document R22 containing equipment phase out. Ensure compliance
with Regulation EC 1005-2009 & Regulation (EC) No 842/2006–
ensure all vendors have F-gas certification and C&G 2079
certification. Commission external consultant to complete boiler &
CHP monitoring biannually.
Responsible Person Maintenance Manager & EHS
Time Frame Dec 2014
Priority Medium
Monitoring Method Review annually
Achievement vs.
Target
Baxter is on target regarding the regulations. Baxter has until 2014 to
phase out R22. All Boiler & CHP emission monitoring was
completed in 2012 as per IPPC Licence requirements.
TABLE 17 PROGRESS REPORT ON UNDERGROUND DRAINS
Reason
IPPC requirement Condition 2.2.2.2 (ii) & Condition 6.11
Target/Objective Maintain underground drains in good repair
Methods Complete CCTV survey of process and foul pipelines
Carry out remediation works to process water and foul pipelines.
Inspect at least every three years
Responsible Person Facilities Engineering Manager
Time Frame Dec 2012
Priority Medium
Monitoring Method Reviewed annually
Achievement vs.
Target
See Appendix G for details of inspections completed in 2012
![Page 28: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/28.jpg)
- 24 -
TABLE 18 PROGRESS REPORT ENVIRONMENTAL EMERGENCY
Reason
Corporate EHS Requirements & legislative requirement
Target/Objective Ensure the site is fully prepared in the event of an environmental emergency
Methods Maintain Emergency Management Team
Update Site Emergency Response Plan to include specific
requirements on dealing with environmental spills and incident
reporting.
Carry out specific training with Emergency Response Team (ERT) on
dealing with chemical spills
Conduct fire drills to test site systems
Install emergency drain covers at strategic locations on site
Introduce new MSDS database resulting in easy access to hazard
information
Responsible Person EHS Dept ,
Time Frame December 2012
Priority Medium
Monitoring Method Reviewed annually
Achievement vs.
Target
ERT trained per the training plan
Drain covers installed
New sharepoint site initiated to store all MSDS
TABLE 19 PROGRESS REPORT EPA COMPLIANCE
Reason
Corporate EHS Requirements & legislative requirement
Target/Objective Meet all requirements of IPPC licence & Greenhouse Gas Permit
Methods Comply with all conditions, reporting and monitoring requirements of
the IPPC licence
Responsible Person EHS Manager
Time Frame December 2012
Priority High
Monitoring Method Reviewed annually
Achievement vs.
Target
Baxter Healthcare received a number of non compliances in 2012 from EPA
in the form of EPA inspection report. There were 7 non compliances
addressed to the satisfaction of the EPA.
On 19 December 2012 the Environmental Protection Agency prosecuted
Baxter Healthcare SA at Castlebar District Court. The Agency Agreed to
withdraw a number of charges and Baxter Healthcare SA pleaded guilty to
the following:
• Causing or permitting alterations to the activity, which did, or were likely
to, result in a material change or increase in the nature or quantity of
emissions, the raw materials used and wastes generated;
• Failing to notify the Agency as soon as practicable after the occurrence of
an emission to sewer on two separate dates which did not comply with the
requirements of its licence;
• Failing to ensure that all waste was stored in designated areas, protected as
may be appropriate, against spillage and leachate run-off and did fail to
clearly label and appropriately segregate all waste.
The court accepted the plea of Baxter Healthcare SA, convicted and fined
the company of the agreed counts and awarded agreed costs to the Agency.
![Page 29: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/29.jpg)
- 25 -
TABLE 20 PROGRESS REPORT ENVIRONMENTAL INCIDENTS OR NOV
Reason
Corporate EHS Requirements
Target/Objective 10% reduction in environmental incidents or notices of violations
Methods Continue to work with BOD QWT
Install the necessary infrastructure or outcome from engineering
studies being completed
Reduce the amount of tank heels/dumps
Responsible Person EHS Manager/Production/Engineering
Time Frame December 2012
Priority High
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
Baxter Healthcare has increased the amount of environmental incidents 19
to 95. These figures are taken from Table 8 comparison of Notification of
non compliances 2011 vs 2012.
TABLE 21 PROGRESS REPORT REGULATED WASTE MANAGEMENT SITES (RWMS)
Reason
Corporate requirement
Target/Objective Complete RWMS Audits based on Corporate Target dates
Methods EHS to carry out audits as per dated defined in the corporate audit
schedule for Regulated Waste Management site audits (RWMS).
Responsible Person EHS Manager
Time Frame December 2012
Priority Medium
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
RWMS audit were completed as per corporate schedule. The dates for
audits are also included in the EHS waste compliance package details.
TABLE 22 PROGRESS REPORT RAW MATERIALS
Reason
IPPC Requirement – Condition 7.4
Target/Objective Undertake an assessment of the efficiency of use of raw materials in all
processes on an annual basis
Methods Monitor inventories purchased and having regard to the reduction in
waste generated and through department conversion loss reporting
Responsible Person EHS Manager
Time Frame December 2012
Priority Medium
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
This project has commenced and is due to be completed Mid 2013
![Page 30: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/30.jpg)
- 26 -
TABLE 23 PROGRESS REPORT SUFACE WATER EMISSIONS
Reason
IPPC Requirement – Condition 2.2.2.2
Target/Objective COD levels in surface water discharges
Methods Review warning and action levels for surface water COD
External lab to notify EHS Department when COD is over 100mg/l
Review emergency response plan implemented in the event of the
action levels being reached.
Responsible Person EHS Department
Time Frame December 2012
Priority Medium
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
Action warning and action limits and emergency response plan were
reviewed
TABLE 24 PROGRESS REPORT TRAINING
Reason
IPPC Requirement – Condition 2.2.2.6
Target/Objective Maintain training & awareness
Methods Develop training matrix alongside HR
HR to log training on Isotrain
HR to maintain training records
Responsible Person EHS Department/HR
Time Frame December 2012
Priority High
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
Training completed as per matrix and all training logged by HR.
TABLE 25 PROGRESS REPORT BUND
Reason
IPPC Requirement – Condition 3.6
Target/Objective Programme
Methods The integrity and water tightness of all bunding structures and their
resistance to prevention by water or it her materials stored therein
must be tested and demonstrated. The results must be reported to the
Agency. This must be repeated every three years.
Responsible Person Facility Engineering
Time Frame December 2012
Priority High
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
All bund were inspected and tested – See appendix F
All bund were numbered and marked on a site drawing
The above were submitted to the Agency
![Page 31: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/31.jpg)
- 27 -
TABLE 26 PROGRESS REPORT NOISE
Reason
IPPC Requirement – Condition 6.15 & Schedule B4
Target/Objective Complete Annual Noise Survey
Methods Commission external consultant to complete and report to the EPA
once results have been obtained. Initiate corrective action if results
are out of compliance.
Responsible Person EHS Department
Time Frame December 2012
Priority Medium
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
Monitoring completed in March 2012 and report was forwarded to the EPA
TABLE 27 PROGRESS REPORT GROUNDWATER
Reason
IPPC Requirement –Condition C6(ii)
Target/Objective Complete Biannual Groundwater monitoring
Methods Commission external consultant to complete and report to the EPA
once results have been obtained. Initiate corrective action if results
are out of compliance.
Responsible Person EHS Department
Time Frame December 2012
Priority Medium
Monitoring Method Included as a component of quarterly environmental reviews.
Achievement vs.
Target
Monitoring was completed in both April and November 2012 and reports
forwarded to the EPA
![Page 32: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/32.jpg)
- 28 -
3.3 Environmental Management Programme 2013
Introduction
Baxter Healthcare has prepared this EMP Proposal for 2013 based on corporate EHS goals and
targets and on remaining actions from the 2012 EMP see Table 28 below. Some of the objectives
and targets set out in the EMP may have a time frame that extends longer than a year, as a result
some of the projects will be ongoing in 2013, with further developments planned.
![Page 33: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/33.jpg)
- 29 -
TABLE 28 ENVIRONMENTAL MANAGEMENT PROGRAMME 2013
Reason
Objective and
Targets
Means of achievement
Priority
Person
Responsible
Time
Frame
Waste
Due to Corporate
EHS goals and
Regulatory
continuous
improvement
requirements.
IPPC 2.2.2.2
Baxter aim to reduce
Total waste
(Hazardous, Non-
hazardous & Biohaz)
by 3% Generated per
production unit based
on end of 2012 Leq
figures.
Track API waste
separately in
Divisional EHS
Report
Hold Monthly mtg
with Plant Mgr,
Engineering Mgrs &
EHS
Review alongside each functional manager to ensure
reduction in no of bins generated. Shared key
outcomes and review possible improvements alongside
main producer.
Continue to review option for sending API waste for
recovery vs. Incineration vs biodegradable in
conjunction with EPA approval. (ENVA with approval
from EPA).
Re-Train all employees on waste management
procedures when new bins are relabelled. Review
status alongside Each production area.
Good House Keeping Drive – Continue to develop
better waste segregation practices around the plant.
Improve on bin facilities; promote reduction and
recycling of waste. Review as part of Gemba Walks.
Continue to use FIFO policy in labs. Review lab smalls
test procedure. Track quantities of lab smalls and
establish if reduction initiatives can be implemented.
Continue to work with all suppliers to ensure minimum
scrap waste is generated through purchasing process.
In the case of poor segregated bins ensure bins are not
collected by janitorial
Hazardous waste training for all employees that enter
the hazardous waste shed
High
Medium
Low
Medium
High
Medium
Medium
Medium
EHS &
M.Grogan
EHS
All Mgrs &
EHS
All Mgrs &
EHS
Chemistry
Lab Mgr
Purchasing
Fac Eng. Mgr
EHS
Apr-13
May-13
Feb-13
Ongoing
Jun-13
Sept-13
Ongoing
Oct-13
![Page 34: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/34.jpg)
- 30 -
TABLE 28 ENVIRONMENTAL MANAGEMENT PROGRAMME 2013
Reason
Objective and
Targets
Means of achievement
Priority
Person
Responsible
Time
Frame
Energy
Corporate EHS Goal
IPPC 2.2.2.2 & 7.2
Baxter aim to reduce
the amount of energy
used by 3% per unit
of production based
on end of 2012 Leq
figures.
Means of achievement detailed in engineering procedure
goals.
Implement Lean Energy Programme
Progress monitored as part of quarterly environmental
reviews to be approved by Director Engineering
High E. Systems
Manager Dec-13
Water
Corporate EHS Goal
IPPC 2.2.2.2 & 7.3
Reduce water
consumption per unit
of production by 3%.
Means of achievement detailed in engineering procedure
goals.
Progress monitored as part of quarterly environmental
reviews to be approved by Director Engineering
High
E. Systems
Manager
Dec-13
Greenhous
e Gas
Emissions
Corporate EHS Goal
Comply with GHG
Permit.
Means of achievement detailed in engineering procedure
goals under energy projects.
Medium
Facilities
Manager
Dec-13
Emissions
to Air
Legislative
Requirement
IPPC C1:2
Ensure compliance
with ODS
regulations and phase
out use
of Ozone Depleting
Substances R22 on
R22 on site by 2014.
Biannual emission
monitoring in boilers
and CHP
Document R22 containing equipment phase out plan.
Ensure compliance with Regulation EC 1005-2009 –
ensure all vendors have F-gas certification and C & G
2079 certification.
Commission external consultant to complete Air & CHP
monitoring
Medium
EHS
department
Maintenance
Jul-13
![Page 35: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/35.jpg)
- 31 -
TABLE 28 ENVIRONMENTAL MANAGEMENT PROGRAMME 2013
Reason
Objective and
Targets
Means of achievement
Priority
Person
Responsible
Time
Frame
Underground
drains
IPPC 2.2.2.2 (ii) Maintain
underground drains
in good repair
Complete CCTV survey of process water and foul
pipelines. Carry out remediation works to process
water and foul pipelines. Inspected at least every 3
years. Maintain underground drains in good repair
and keep drawings current.
Medium Facility
Manager Dec 13
Environmental
Emergency
Legislative
Requirement
Ensure the site is
fully prepared in
the event of an
environmental
emergency
Maintain Emergency Management Team. Refer to
annual training plan. Hold ERT meetings on a qtr
basis.
Site Emergency Response Plan includes specific
requirements on dealing with environmental spills
and incident reporting.
Specific training included for ERT team on dealing
with chemical spills
Complete gap analysis alongside Regional EHS of
other items that should be considered
Medium EHS Dec 13
Packaging
Compliance
Corporate EHS goals
and targets.
Maintain reporting
requirements for
Essential Packaging
Regulations
Maintain procedures set up by the Packaging Quality
working Team (QWT) to ensure adherence to the
requirements of the Packaging Programme.
Update the Beles 8 system based on product
development change requests IR40-08-01-078.
Medium
Product
Development
Manager
EHS Specialist
Dec 13
EPA Compliance
Legislative
Requirement
Meet all
requirements of IPPC
Licence
Comply with all conditions, reporting and monitoring
requirements of the IPPC licence
Develop/Re-Train relevant personnel on new
guidelines for IPPC licence reporting
• Inspection guidelines
• Handling/reporting complaints
• IPPC Management Responsibility
Improve channel of communications with the EPA.
Seek formal meetings to discuss sections of Licence
High
EHS Manager
Dec 13
![Page 36: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/36.jpg)
- 32 -
TABLE 28 ENVIRONMENTAL MANAGEMENT PROGRAMME 2013 CONT’D
Reason
Objective and
Targets
Means of achievement
Priority
Person
Responsible
Time
Frame
Training IPPC 2.2.2.6 Maintain training &
awareness
Revise the core training spec IR40-03-02-057 to
ensure all aspects of EHS are included
Develop training Matrix alongside HR
HR to log training on Isotrain
HR to maintain training records. Await feedback
from Regional EHS on 2013 Training Matrix.
Low
EHS
Department
HR
Mar 13
Bund
IPPC 3.6 Programme
The integrity and water tightness of all the bunding
structures and their resistance to prevention by
water or other materials stored therein must be
tested and demonstrated. The results must be
reported to the Agency. This must be repeated
every three years.
High Facility Eng.
Manager Feb 13
Noise
IPPC C6.15 & B4 Annual Noise
Survey
Commission external consultant to complete and
report to EPA once results obtained. Initiate
Corrective action if results are out of compliance
Medium EHS
Department Mar 13
Groundwater
IPPC C6(ii) Biannual Ground
water
Commission external consultant to complete.
Initiate Corrective action if results are out of
compliance
Medium EHS
Department Dec 13
Wastewater
List 1 &11 Identify & Phase out
Continue to work with laboratories to
identify/reduce/phase out List I
substances where applicable
High EHS Dec 13
Wastewater
IPPC
Emergency
Response
procedures for
maintenance
intervention
Review Operational controls and Emergency
Response procedures for maintenance intervention
Improve process effluent controls
in the case of the sump area
High Facilities Eng
Manager Mar 13
Effluent
Monitoring IPPC requirement
Reduce monitoring
days
Seek approval from the EPA to reduce the daily
monitoring to agreed frequency High EHS Apr 13
![Page 37: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/37.jpg)
- 33 -
TABLE 28 ENVIRONMENTAL MANAGEMENT PROGRAMME 2013 CONT’D
Reason
Objective and
Targets
Means of achievement
Priority
Person
Responsible
Time
Frame
RWMS
Corporate
compliance
Complete RWMS
Audits based on
Corporate Target
Dates
EHS to carry out audits as per dates defined in the
corporate audit schedule for Regulated Waste
Management Site Audits (RWMS).
To be completed in 2013
• Atlas Oil
Medium
EHS Manager Apr 13
Environmental
incidents or
NOV
Corporate EHS
goals and targets.
Mitigate number of
exceedances
Continue to work with the BOD QWT
Install the necessary infrastructure or outcome
from engineering studies being completed
Reduce the amount of tank heels/dumps
High
EHS Manager
Production
Engineering
Q1 2014
Raw Materials IPPC requirement
C7.4
Undertake an
assessment of the
efficiency of use of
raw materials in all
processes on an
annual basis
Monitor inventories purchased and compared to
previous year for inclusion in Annual Env Report.
Medium Logistics
Manager Mar 13
Surface water
emission IPPC 2.2.2.2 (i)
COD levels in
surface water
discharges.
Review warning and action levels set for surface
water COD
External Lab to notify EHS Department when
COD is over 100mg/l
Ensure procedure followed
Medium
EHS
Department
Ongoing
![Page 38: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/38.jpg)
- 34 -
TABLE 28 ENVIRONMENTAL MANAGEMENT PROGRAMME 2013 CONT’D
Reason
Objective and
Targets
Means of achievement
Priority
Person
Responsible
Time
Frame
Emissions to Air New Corp
Requirement
To log all data on
insite pertaining to
ODS etc
Facilities are required to report the following data
into the Baxter EHS Information Management
System (Insite EHS) on a monthly basis (all
environmental data categories are defined in the
Reference and Training Guide section 8.0):
• Emissions of listed air contaminants, including:
o toxic air pollutants,
o volatile organic compounds (VOCs), and
o refrigerants with ozone depleting and/or global
warming potential, including ammonia
Medium Maintenance
Manager Monthly
Bunding of Haz
waste tankers IPPC
Provide bunding for
road tankers
Submit to EPA outcome of integrity test. Await
response on report submitted on 15/2/2013 High Fac Eng Mgr Mar13
Fugitive
Emissions IPPC C6.9
Identify Fugitive
emissions
Discuss with Corporate Regional EHS and confirmed
that we do not have Fugitive emissions Medium EHS Mar 13
![Page 39: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/39.jpg)
- 35 -
3.4 Waste Management
Baxter has established and operates a comprehensive, documented waste management
system throughout the plant. Procedure Specs detail the management, and control of
Hazardous and Non-Hazardous waste on-site. The waste streams are classified in
accordance with National/European legislation. There is a segregation programme in place,
which operates throughout the whole plant. Production personnel are responsible for
primary segregation of all waste, and it is the responsibility of janitorial personnel to ensure
that all segregated waste is transferred and stored correctly in the waste storage area until
collection.
Permit details of the waste contractors used are located in Appendix C.
Details of waste records for hazardous and non-hazardous waste stream for Baxter
Healthcare site can be found in table 29. There have been no rejected consignments from
the Baxter site.
![Page 40: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/40.jpg)
- 36 -
TABLE 29 INFORMATION ON EACH WASTE STREAM
European
Waste
Catalogue
Code
Hazardous
(Yes/No) Description of Waste
Quantity
(t/year)
Disposal/
Recovery
Code
Location of
Disposal/
Recovery
Name of Waste Disposal
Recovery Contractor
Licence / Permit Reference for
Treatment Facility
20 01 01 No Cardboard/Paper 272.2 R5 Castlebar, Co.
Mayo Repulping: Feoil Freight WCP-MO-09-0075-01
15 01 02 No PVC scrap Polyethylene
scrap 820.2 R5
Clogher,
Westport,
Mayo
Bourke waste ltd WFP-MO-08-0004-01-01
WCP-MO-09-0633-01
15 01 02 No Non PVC scrap 7.1 R5 Castlebar, Co.
Mayo Reuse: Feoil Freight WCP-MO-09-0075-01
15 01 03 No Wooden pallets 10.2 R11 Castlebar, Co.
Mayo Reuse: Feoil Freight WCP-MO-09-0075-01
20 03 01 No General waste 338.3 D1
Aghalustia
Townland, Ballaghaderreen,
Co Roscommon
McGrath Industrial Waste Ballaghaderreen Landfill
Licence 59-2
20 03 01 No Kitchen waste 26.4 D1
Aghalustia Townland,
Ballaghaderreen, Co Roscommon
McGrath Industrial Waste
Ballaghaderreen Landfill Licence 59-2
20 01 08 No Kitchen recycling waste 7.8 R3
Shepherds drive,
Carnbane Industrial
Estate, Newry, Co
Down
McGrath Industrial Waste
Re-GEN Waste Ltd WML22/25
20 01 08 No Biodegradable waste 15.0 R3 Headford Road,
Galway,
McGrath Industrial waste
Carrowbrowne Landfill Site W0013-01
17 09 04 No Construction and
Delimitation 4
D1
Aghalustia
Townland,
Ballaghaderreen,
Co Roscommon
McGrath Industrial Waste
Ballaghaderreen Landfill Licence 59-2
20 01 02 No Glass 11.5 D10 Turlough Castlebar
Co. Mayo. McGrath‟s Industrial Waste WFP-MO-10-0015-01-01
20 01 40 No Metal 14.9 R4 Oranmore, Co.
Galway Galway Metal Co Ltd
WFP-09-G-0006-05
20 01 21 Yes Lamps 0.394 R4 Netherlands and
Kildare
Separation, Irish Lamp
Recycling/ Claushuis Metaalmaatschappij BV
WFP-KE-08-0348-01
![Page 41: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/41.jpg)
- 37 -
European
Waste
Catalogue
Code
Hazardous
(Yes/No) Description of Waste
Quantity
(t/year)
Disposal/
Recovery
Code
Location of
Disposal/
Recovery
Name of Waste Disposal
Recovery Contractor
Licence / Permit Reference for
Treatment Facility
07 05 01 Yes
Active Pharmaceutical
Ingredients (Aqueous solution)
212.34 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
07 05 01 Yes
Active Pharmaceutical
Ingredients (Aqueous solution)
66.442 D10
Dijle 17 a 2800
MECHELEN
Neatherland
Indaver NV MLAV1/98 00000485
07 05 13 Yes
Active Pharmaceutical
Ingredients (Contaminated solids)
& mixed packaged waste
0.763 D10 Borsigstrasse 2
22113 Hamburg Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
07 05 13 Yes
Active Pharmaceutical
Ingredients (Contaminated solids)
& mixed packaged waste
0.367 D10
Dijle 17 a 2800
MECHELEN
Neatherland
Indaver NV MLAV1/98 00000485
18 01 03 Yes
Clinical Waste (sharps, wipes,
cloths, gloves used in micro.gmo material, autoclaved material)
10.819 D9
Unit 1A, Allied Ind est, Kylemore
road, Ballyfermot, Dublin 10
Ecosafe Systems Ltd, Waste Mgt Permit: CW059
Licence 54-2
16 02 13 Yes WEEE (waste
electrical electronic equipment)
2.247 R12 (R4)
Cappincur Industrial Estate, Daingean Road, Tullamore, Co. Offaly
KMK Metals recycling Licence: 113-3
06 01 06 Yes
Other Acids (ammonium
Thiocyanate/Flocon 40)
0.607 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
![Page 42: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/42.jpg)
- 38 -
European
Waste
Catalogue
Code
Hazardous
(Yes/No) Description of Waste
Quantity
(t/year)
Disposal/
Recovery
Code
Location of
Disposal/
Recovery
Name of Waste Disposal
Recovery Contractor
Licence / Permit Reference for
Treatment Facility
14 06 02* Yes
Other halogenated solvents and solvent mixtures (Mercury
Thiocyanate)
0.244 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
14 06 02* Yes
Other halogenated solvents and solvent
mixtures (Ensolv/Betadine)
1.463 D10 Dijle 17 a 2800 MECHELEN
Neatherland
Indaver NV MLAV1/98 00000485
14 06 03* Yes Other solvents and
solvent mixtures (Cyclohexanone/DEHP)
0.934 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
15 02 02* Yes Absorbents, filter
materials (HCL/Oil/Magnaflux)
0.131 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
15 02 02* Yes Absorbents, filter
materials (HCL/Oil/Magnaflux)
1.059 D10 Dijle 17 a 2800
MECHELEN
Neatherland
Indaver NV MLAV1/98 00000485
16 05 06* Yes
Laboratory chemicals, consisting of or containing dangerous substances,
0.227 D10 Dijle 17 a 2800
MECHELEN
Neatherland
Indaver NV MLAV1/98 00000485
16 05 06* Yes
Laboratory chemicals, consisting of or
containing dangerous substances,
0.006 D15
Tolka Quay
Road
Dublin Port Indaver Ireland Ltd W0036-2
16 05 06* Yes
Laboratory chemicals, consisting of or
containing dangerous substances,
0.383 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
20 01 14* Yes Acids- Oxonia cleaning
solution 214.7 D9
Smithstown
Industrial est.
Shannon, Co. Clare
Enva Ireland W0041-01
20 01 29* Yes Acids- Oxonia cleaning
solution 708.9 D9
Smithstown Industrial est.
Shannon, Co. Clare
Enva Ireland W0041-01
16 10 01* Yes Aqueous liquid wastes containing dangerous
substances -Solution A 616.9 D9
Smithstown
Industrial est. Shannon, Co. Clare
Enva Ireland W0041-01
![Page 43: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/43.jpg)
- 39 -
European
Waste Catalogue
Code
Hazardous (Yes/No)
Description of Waste
Quantity (t/year)
Disposal/ Recovery
Code
Location of
Disposal/
Recovery
Name of Waste Disposal
Recovery Contractor
Licence / Permit Reference for
Treatment Facility
16 10 02 No Aqueous liquid wastes containing dangerous
substances -Solution A 41.3 D9
Smithstown Industrial est.
Shannon, Co. Clare
Enva Ireland W0041-01
16 05 09 No Discarded chemicals
Extraneal/Sugar Solution
673.9 D9 Smithstown
Industrial est.
Shannon, Co. Clare
Enva Ireland W0041-01
20 01 25 No Edible oil and fat 0.29 R1 Orchard Road Ind, Est, Strabane, Co.
Tyrone, BT82 9FR
Frylite LTD WML 26/26
06 01 01* Yes sulphuric acid and sulphurous acid
0.233 D10 Dijle 17 a 2800 MECHELEN
Neatherland
Indaver NV MLAV1/98 00000485
06 01 02* Yes Hydrochloric Acid 2.737 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
06 02 04* Yes Potassium/Sodium
Hydroxide 0.028 D10
Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
06 02 05* Yes Sodium Hypochlorite 0.360 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
08 03 17* Yes waste printing toner
containing dangerous substances
1.4 R3
Unit 3, Shannon
Development Ent
Ctn, Syngfield,
Birr. Ireland
Source Imaging Supplies Ltd WFP-10-OY-0181-01
15 01 10* Yes Oxonia Drums 0.031 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
16 03 03* Yes
off-specification batches and unused products Inorganic wastes containing
dangerous substances
2.874 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
16 03 05* Yes
off-specification batches and unused
products organic wastes containing
dangerous substances
10.636 D10
Dijle 17 a 2800
MECHELEN
Neatherland
Indaver NV MLAV1/98 00000485
![Page 44: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/44.jpg)
- 40 -
European
Waste Catalogue
Code
Hazardous (Yes/No)
Description of Waste
Quantity (t/year)
Disposal/ Recovery
Code
Location of
Disposal/
Recovery
Name of Waste Disposal
Recovery Contractor
Licence / Permit Reference for
Treatment Facility
16 09 03* Yes Oxidising
substances Oxonia Active
0.008 D10 Borsigstrasse 2
22113 Hamburg
Abfall-Verwertungs-
Gesellschaft mbH IB/2234/AVG/GENB-2
20 01 27* Yes
Paint, inks, adhesives and
resins containing dangerous substances
0.254 D10
Dijle 17 a 2800
MECHELEN
Neatherland
Indaver NV MLAV1/98 00000485
20 01 33* Yes Batteries 0.156 R12(R4)
Cappincur Industrial Estate, Daingean Road, Tullamore, Co. Offaly
KMK Metals recycling Licence: 113-3
16 05 08* Yes
Discarded organic chemicals consisting
of or containing dangerous substances
1.539 D10 Dijle 17 a 2800 MECHELEN Neatherland
Indaver NV MLAV1/98 00000485
16 05 04* Yes
Gases in pressure containers (including halons) containing
dangerous substances
0.058 D10 Dijle 17 a 2800 MECHELEN Neatherland
Indaver NV MLAV1/98 00000485
18 02 06 No
Chemicals order than those
mentioned in 18 02 05* (finshed product
discard)
2335 R12 Cushinsheeaune. Westport, Co.Mayo
P&D Horan Ltd WFP-MO-09-0007-01
![Page 45: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/45.jpg)
- 41 -
3.5 Pollutant Release and Transfer Register – Report for 2012 & Proposal for 2013
As per Condition 6.16 of the IPPC licence‚ the licensee shall prepare and report a PRTR for the
site.
The PRTR report for 2012 will be submitted to the Agency, electronically through the Agency‟s
web based system and also through the AER. See Appendix B.
PRTR Proposal for 2013
It is proposed to track and report the same pollutants in 2013 for the PRTR as were reported for the
year 2012.
![Page 46: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/46.jpg)
- 42 -
4.0 LICENCE-SPECIFIC REPORTS
The following licence specific report summaries are included in this section:
Annual CO2 emissions
Noise monitoring report
Groundwater monitoring summary
Review of Residuals Management Plan
Report on annual solvent usage
Respirometry Testing
Toxicity Testing
API Absence Test
4.1 Annual CO2 Emissions
The facility holds a Green House Gas Permit Number, IE-GHG-133-05, Installation No.
IE-97, Activity Code E1.1.The annual CO2 emissions are calculated using the mass
balance approach, by adding the tonnes of CO2 emitted due to Medium Fuel Oil (MFO),
Natural Gas (Nat Gas), Light Fuel oil (LFO) and Liquid Petroleum Gas (LPG). The CO2
allocation to Baxter for 2012 was 20,623 tonnes of CO2. The verified annual installation
emissions report was submitted to the Agency in March 2012, this confirmed a total of
20,862 tonnes of cO2 emitted in 2012. Table 30 below summarises the total CO2
emissions from the Baxter plant for 2012.
TABLE 30 DETAILED SUMMARY OF 2012 CO2 EMISSIONS FROM THE BAXTER PLANT
Fuel type Activity data Units Weighted
Net Calorific Value
Units Weighted
Emission factor
Units Oxidation
factor Total CO2 as
tonnes )
Nat Gas 9598208.5 NM3 0.000037 Tj/NM3 57.0 tCO2/TJ 1 20634.6
LFO (Diesel)
0.06604412 KTonnes 43.31 TJ/KTonnes 73.3 tCO2/TJ 1 209.7
LPG (cooker)
0.0052915 KTonnes 47.16 TJ/KTonnes 63.7 tCO2/TJ 1 15.90
LPG (bottle)
0.0005664 KTonnes 47.16 TJ/KTonnes 63.7 tCO2/TJ 1 1.70
Total emissions (sum of fossil fuel emissions & fossil fraction of mixed fuels)
Tonnes of CO2 20,862
Subject to Condition 1.4 of the GHG Permit carbon dioxide from Schedule 1 activities
shall only be emitted to the atmosphere from the emission points as listed in Tables 31
and 32 below:
![Page 47: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/47.jpg)
- 43 -
TABLE 31 CARBON DIOXIDE EMISSION POINTS
Emission Point
Reference
Emission Point
Description
Thermal Input
Capacity
Capacity Units
A1-1 No. 2 Boiler Stack 7.2 Mw
A1-2 No. 7 Boiler Stack 9.0 Mw
A1-3 No. 4 Boiler Stack 9.0 Mw
A1-5 No. 6 Boiler Stack 14.6 Mw
CHP CHP 1 & 2 2.8 Mw
Carbon dioxide from Schedule 1 activities may also be emitted to atmosphere from
the minor emission points listed in Table 32 below.
TABLE 32 CARBON DIOXIDE MINOR EMISSION POINTS
Emission Point
Reference
Emission Point
Description
Thermal Input
Capacity
Capacity Units
A1-4 No. 5 Boiler Stack 0.15 Mw
SBG-1 Exhaust Standby Generator 1 0.024 Mw
SBG-2 Exhaust Standby Generator 2 0.192 Mw
PU-1 Exhaust of Firewater Pump Engine 0.083 Mw
CK-1 LPG Cooker 0.1 Mw
A3-7 Exhaust of Atomic Absorption Unit < 0.1 Mw
A3-8 Exhaust of Atomic Absorption Unit < 0.1 Mw
A3-11 Exhaust of Atomic Absorption Unit < 0.1 Mw
Exhaust of Atomic Absorption Unit
4.2 Noise Monitoring Report Summary 2012
The Noise Monitoring survey was carried out on the 22nd & 23rd March 2012 as per
Condition 6.15. The survey methodology followed the Environmental Protection Agency
(EPA) “Environmental Noise Survey Guidance Document” (2003), EPA “Guidance Note
for Noise in Relation to Scheduled Activities” (2006), and ISO 1996 “Description and
measurement of environmental noise”. The plant was in normal production throughout
the survey.
The results of the noise monitoring indicated that their was no environmental noise issues
at the noise sensitive receptors associated with operations at the Baxter Healthcare
Facility. Daytime and nighttime noise limits were complied with at all noise sensitive
locations with regard to Baxter noise emissions. Frequency analysis data indicated that
operations at Baxter Healthcare do not give rise to a tonal noise impact at the nearest
residential properties.
Noise levels at the house locations in 2012 were similar to the results for the 2011 survey,
and there is no evidence of a systematic change in emissions
![Page 48: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/48.jpg)
- 44 -
4.3 Groundwater Monitoring Report Summary
Bi-annual groundwater monitoring was carried out in April and November 2012. It is
noted that the groundwater is not used as a potable supply. However, in the absence of
any relevant Irish groundwater quality standards the analytical results are discussed with
reference to background levels, using the EPA Interim Guideline Values (EPA IGV‟s)
and the Drinking water MAC‟s.
Findings and Conclusions as submitted to the EPA.
Field measurements (i.e. temperature, pH and electrical conductivity) are within the
expected range for these parameters.
The concentrations of sodium and chloride showed no significant change since previous
sampling rounds, except for chloride in MW2 and remain below the Drinking Water
Standards values.
Ammonium concentration in MW4 exceeded the limit of 0.3mg/l for drinking water and
also the EPA IGV of 0.15mg/l in September and October 1.02mg/l & 1.13mg/l
respectively. The desktop assessment completed in August 2010 concluded that an off-
site source (hydraulically up-gradient of MW4) to the west and north-west of the Baxter
facility was contributing to the elevated ammonia concentrations.
An elevated COD level was detected in MW 2-4 in October, with a value of 13mg/l.
However this concentration does not indicate significant contamination.
Slight increase in DRO concentrations of 0.02mg/l were detected in MW3. As none of
the petroleum indicator parameters were detected it is likely the hydrocarbons detected
are of a natural origin or related to another source.
The concentrations of the hydrocarbon indicator parameters have shown no change since
the 2006 monitoring round, as concentrations of all parameters were below the laboratory
detection limits.
Supplementary Investigative Analysis
To further investigate the trend of the increasing ammonia concentration in MW4,
additional analysis for nitrate, nitrite, total coliforms and faecal coliforms was carried out
in November 2012 by Envest Environmental Ltd.
A nitrate concentration of 0.8mg/l was detected in the groundwater sample collected from
MW4. This is very low and well below the EPA IGV for nitrate of 25mg/l. A low nitrate
value is normally accompanied by an elevated ammonia concentration as the reduced
nitrate is transformed to ammonium with the loss of the oxygen molecule.
A nitrite concentration of <0.02mg/l was detected in the groundwater sample colleted
from MW4. If significant pollution was present, then a measurable nitrite concentration
would be detected and this would be accompanied by elevated ammonia, chloride,
sodium or potassium. The sodium concentration in MW4 was 12.1mg/l (significantly
![Page 49: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/49.jpg)
- 45 -
below the EPA IGV of 150mg/l) and the chloride concentration was detected as 13.6mg/l
(significantly below the EPA IGV of 30mg/l).
Total and faecal coliforms were determined as being 0 (zero) CFU/100ml and <1
CFU/100ml respectively in the groundwater sample analysed from MW4.
A groundwater level survey was undertaken at the site in conjunction with this biannual
monitoring event. The wells were surveyed relative to an arbitrary site datum so that a
contour map could be prepared to confirm the flow direction at the site.
MW1 MW2 MW3 MW4
Groundwater Level
The groundwater flow direction was confirmed to be in a south easterly direction and this
is illustrated in Figure 2 below:
Therefore from the consultants review of the long-term monitoring of groundwater at the
site and interpretation of the most recent site data, it is their opinion that groundwater
coming onto the site in the vicinity of MW4 has slightly elevated concentrations of
ammonia and therefore they consider the source of elevated ammonia in MW4 to be
hydraulically upgradient i.e. an off-site source.
![Page 50: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/50.jpg)
- 46 -
4.4 Report on Annual Solvent Usage
Table 33 below represents the volume of solvents purchased in 2012.
Table 33 Volume of solvents purchased in 2012
Solvent Name Volume Purchased in
2012
Cyclohexanon 1170 kgs
DEHP (Di-ethylhexylphthalate) 200 kgs
IPA (Propan-2-ol) – Sterile 70/30
IPA sprays
7,200 litres
IPA (Propan-2-ol) – non-sterile 70/30
IPA sprays
1,536 litres
Pago (Solvent W15 blue) 860 litres
Ensolv 546 kgs
Acetonitrile 600 litres
Acetic Acid 12 litres
Acetic Anhydride 22.5 litres
Ethanol 12 litres
Methanol 258 litres
Formaldehyde 5 litres
Chloroform 20 litres
![Page 51: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/51.jpg)
- 47 -
4.5 Respirometry Testing
As per EPA requirements, Baxter Healthcare carried out respirometry testing in
December 2012. A sample of process effluent, together with activated sludge from
Castlebar Municipal Waste water Treatment Plant, was collected and tested to investigate
the inhibitory effect (if any) of Baxter‟s process effluent on the respiration rate of the
activated sludge micro-organisms. The test data demonstrated that process effluent from
the Baxter facility exhibited no inhibitory effect on activated sludge from Castlebar
Municipal Waste Water Treatment Plant. Testing SE1 This result indicates that the Baxter Healthcare SA trade effluent sample was inherently
biodegradable and treatable by the microbes in the activated sludge in the Baxter annex plant
at Castlebar WWTP.
As per the EPA request a sample of Solution A (Alconox and Multichlor) and Oxonia
cleaning agents (at the Baxter Healthcare working strength) was individually tested on the
sludge from the Castlebar WWTP.
A grab sample of trade effluent at location PW (Process Waste) was taken on the 10th
December 2012.
Based on the results of this test in Table 34, we can consider the possible impact of a
direct discharge of Solution or Oxonia cleaning agents to the Castlebar Municipal WWTP
(by-passing the Baxter annex WWTP)
Table 34 Respirometry Testing of Cleaning Agents
Respirometry Testing of Cleaning Agents
Cleaning Agent I.T. %v/v Working
strength
I.T. Kg of cleaning
discharged directly
Oxonia 0.02 to 0.03 8 to 12
Solution A
Multichlor
Alconox
1
480
424
All test data was sent to the EPA and is available on file in the EHS Department.
![Page 52: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/52.jpg)
- 48 -
4.6 Toxicity Testing
As per EPA requirements, Baxter Healthcare carried out Toxicity testing in January 2012.
The toxicity testing was carried out on:
1) The waste cleaning solutions stream Oxonia and solution A (Alconox &
Multichlor) prior to mixing.
2) A mixed effluent sample from emission point Process Waste (PW)
The test methods used were:
Method 6.1 based on ISO 6431:1996/Cor.1:1998: „water quality – determination
of inhibition of the mobility of Daphnia magna Straus (Cladocera, Crustacea)-
Acute toxicity test‟.
Method 6.2 based on ISO 11348-3:2007:‟Water quality-determination of
inhibitory effect of water samples on the light emission of Vibrio Fischeri
(Luminescent bacteria test)- Part 3:Method using freeze-dried bacteria‟
Table 35 Toxicity Testing of Emissions to Sewer (Process Waste (PW)) and cleaning agents
Toxicity Testing
Sample Name Test Parameter Concentration
%vol./vol.
Toxic Units
Baxter Process
20.01.2012
48h EC50 to Daphnia
magna
>100 <1
30 min EC50 to Vibrio
fischeri
38.3 2.6
Solution A
48h EC50 to Daphnia
magna
5.7 17.5
30 min EC50 to Vibrio
fischeri
2.3 43.5
Oxonia
48h EC50 to Daphnia
magna
0.053 1887
30 min EC50 to Vibrio
fischeri
0.063 1587
* 30 min EC50 to Vibrio
fischeri
0.060 1667
*30 min EC50 to Vibrio fischeri (pH adjusted, 7.4)
All test data was sent to the EPA and is available on file in the EHS Department.
4.7 API Absence testing
As per Condition 3.2 Pharmaceutical actives are to be tested annually. The sample was
collected on a 24 hour flow proportional sampler and taken at 8.00am on the 4th
December. The sample was sent to an external laboratory for testing. Table 36 below
provides the results of the analysis which confirms that Baxter Healthcare Effluent does
not contain API‟s.T
Table 36 API Absence Testing of Emissions to Sewer – Process Waste (PW)
API Absence Test Baxter Process 4/12/12
Bupivacaine HCL [18010-40-7] mg/l <1.00
Ciprofloxacin [85721-33-1] mg/l <2.00
Gentamicin [1405-41-0] mg/l <2.00
Metronidazole [443-48-17] mg/l <1.00
![Page 53: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/53.jpg)
- 49 -
4.8 Process Raw Materials Usage Efficiency
As per IPPC licence condition 7.4, an assessment of the efficiency of use of raw materials
was carried out in 2012. This assessment focused on the key areas of water, energy and
raw material conservation. See progress report for Waste, Energy & water in Table 11 to
13 for further details.
4.9 Environmental Liability Statement
As per Condition 12.3 “The licensee shall as part of the AER provide an annual
statement as to the measures taken or adopted at the site in relation to the prevention of
environmental damage, and the financial provisions in place in relation to the
underwriting of costs for remedial actions following anticipated events or
accidents/incidents, as may be associated with the carrying on of the activity”.
In the event of a permanent closure or partial closure of the site a reserve financial
provision consisting of a charge on the profit & loss to cover the anticipated closure costs
will cover the cost of closure or down sizing, by agreement with the Agency. The items
allowed for and included in any such closure provision would include the cost of draining
of plant and equipment, removal of waste substances, securing the site, and provision for
a return to an acceptable status.
Baxter Healthcare SA confirms that at the time of permanent closure or partial closure of
the Baxter licensed facility (Register 636-02) financial provisions will be made available
in accordance with the site‟s de-commissioning management plan.
![Page 54: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/54.jpg)
- 50 -
APPENDIX A
SUMMARY OF WASTE ARISING
![Page 55: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/55.jpg)
- 51 -
SUMMARY OF WASTE ARISING
Waste 2007 2008 2009 2010 2011 2012
Total quantity of waste produced in calendar year(Tonnes)
1429.33 1674.82 1669.53 1706.77 2642.91 4102.33
total quantity of waste disposed of on-site
0 0 0 0 0 0
total quantity of waste disposed of off-site
294.06 336.94 505 358.01 1506.733 2950.443
total quantity of waste recovered on-site
0 0 0 0 0 0
total quantity of waste recovered off-site
1023.67 1337.88 1165.53 1348.76 1136.181 1151.887
2007 2008 2009 2010 2011 2012
Quantity of non-hazardous waste produced in calendar year
1308.5 1461.47 1544.79 1522.23 1643.51 1859.24
quantity of non-hazardous waste disposed of on-site
- - - - - -
quantity of non-hazardous waste disposed of off-site
- - - - - 1855.043
quantity of non-hazardous waste recovered on-site
- - - - - -
quantity of non-hazardous waste recovered off-site
- - - - - 4.197
2007 2008 2009 2010 2011 2012
Quantity of hazardous waste produced in calendar year (Tonnes)
120.82 213.35 125 184.538 1008.5 2243.09
quantity of hazardous waste disposed of on-site
0 0 0 0 0 0
quantity of hazardous waste disposed of off-site
120.82 213.35 125 184.538 1008.5 1095.4
quantity of hazardous waste recovered on-site
0 0 0 0 0 0
quantity of hazardous waste recovered off-site
- - - - - 1147.69
![Page 56: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/56.jpg)
- 52 -
APPENDIX B
BAXTERS AER/PRTR RETURNS
![Page 57: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/57.jpg)
- 53 -
![Page 58: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/58.jpg)
- 54 -
![Page 59: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/59.jpg)
- 55 -
![Page 60: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/60.jpg)
- 56 -
![Page 61: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/61.jpg)
- 57 -
![Page 62: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/62.jpg)
- 58 -
![Page 63: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/63.jpg)
- 59 -
APPENDIX C
Waste Contractors
![Page 64: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/64.jpg)
- 60 -
WASTE CONTRACTORS USED IN 2012
Waste Contractor Waste Licence No. Collection Permit No.
AVG IB/2234/AVG/GENB-2 N/A
EcoSafe 054-2 WCP-DC-09-1203-01
Feoil Freight WFP-MO-11-0019-01 WCP-MO-09-0075-01
Galway Metal WFP-09-G-0006-05 WCP-LK-08-589-01
Irish Lamps WFP-KE-08-0348-01 WCP-DC-08-1115-01
Iggy Madden Transport N/A WCP-MO-08-0590-02
KMK Metals 113-3 WCP-OY-08-0607-01
Bourke Waste Ltd WFP-MO-08-0004-01-
01
WCP-MO-09-0633-01
Cunningham Transport N/A WCP-MO-09-0638-01
JP Ryan N/A WCP-CK-09-0696-01
McGrath Industrial WFP-MO-10-0015-01-
01
WCP-MO-09-0002-02
Trevor Ratcliff N/A WCP-DC-08-1130-01
Indaver - Ireland W0036-02 N/A
Indaver - NV MLAV1/98 00000485 N/A
ENVA Ireland W0041-01 WCP-DC-08-1116-01
P & D Horan’s WFP-MO-09-0007-01 WCP-MO-09-0297-001
Frylite LN/11/63 WCP-DC-10-1297
Source Imaging WFP-10-OY-0181-01 N/A
Guinan Haulage N/A WCP-OY-09-626-02
Ravenhill Couriers Ltd N/A WCP-OY-09-620-01
![Page 65: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/65.jpg)
- 61 -
APPENDIX D
Baxter Products
![Page 66: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/66.jpg)
- 62 -
![Page 67: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/67.jpg)
- 63 -
![Page 68: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/68.jpg)
- 64 -
APPENDIX E
Energy Efficiency Audit Report
Summary
&
Energy Projects 2012
![Page 69: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/69.jpg)
- 65 -
Energy Audit Report Summary
![Page 70: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/70.jpg)
- 66 -
![Page 71: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/71.jpg)
- 67 -
Energy Program Business Plan 2013
![Page 72: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/72.jpg)
- 68 -
Energy Projects 2012
Year Completed
Project Description Cost (K€) Annualized Savings(K€)
Simple Payback
Savings (K€) in year
completed
Annual KWh
savings (Gas)
Annual KWh
savings (Electricity)
2012 Insulate Condensate return lines
38 19 2.00 15 551,229
2012 Boiler 6 Economizer 182 48 3.79 12 1,600,000
2012 Raw water Booster Pump Upgrade
66 20 3.30 7 181,818
2012 High efficiency lighting 12 3.8 3.16 0 34,545
Total 2012 298 90.8 3.28 34 2,151,229 216,364
![Page 73: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/73.jpg)
- 69 -
APPENDIX F
Bund Integrity Testing Reports
![Page 74: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/74.jpg)
- 70 -
![Page 75: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/75.jpg)
- 71 -
![Page 76: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/76.jpg)
- 72 -
![Page 77: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/77.jpg)
- 73 -
![Page 78: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/78.jpg)
- 74 -
![Page 79: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/79.jpg)
- 75 -
![Page 80: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/80.jpg)
- 76 -
![Page 81: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/81.jpg)
- 77 -
![Page 82: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/82.jpg)
- 78 -
![Page 83: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/83.jpg)
- 79 -
![Page 84: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/84.jpg)
- 80 -
![Page 85: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/85.jpg)
- 81 -
![Page 86: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/86.jpg)
- 82 -
![Page 87: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/87.jpg)
- 83 -
![Page 88: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/88.jpg)
- 84 -
![Page 89: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/89.jpg)
- 85 -
![Page 90: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/90.jpg)
- 86 -
![Page 91: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/91.jpg)
- 87 -
![Page 92: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/92.jpg)
- 88 -
![Page 93: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/93.jpg)
- 89 -
![Page 94: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/94.jpg)
- 90 -
![Page 95: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/95.jpg)
- 91 -
![Page 96: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/96.jpg)
- 92 -
![Page 97: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/97.jpg)
- 93 -
![Page 98: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/98.jpg)
- 94 -
![Page 99: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/99.jpg)
- 95 -
![Page 100: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/100.jpg)
- 96 -
![Page 101: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/101.jpg)
- 97 -
![Page 102: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/102.jpg)
- 98 -
![Page 103: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/103.jpg)
- 99 -
![Page 104: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/104.jpg)
- 100 -
![Page 105: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/105.jpg)
- 101 -
![Page 106: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/106.jpg)
- 102 -
![Page 107: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/107.jpg)
- 103 -
![Page 108: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/108.jpg)
- 104 -
![Page 109: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/109.jpg)
- 105 -
![Page 110: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/110.jpg)
- 106 -
![Page 111: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/111.jpg)
- 107 -
APPENDIX G
Pipe and Sump Integrity Testing
Reports
![Page 112: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/112.jpg)
- 108 -
Internal Pipe Integrity Testing Report
![Page 113: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/113.jpg)
- 109 -
Internal Pipe Integrity Testing Report
![Page 114: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/114.jpg)
- 110 -
Internal Pipe Integrity Testing Report
Sump Integrity Testing Report
![Page 115: Annual Environmental Report 2012 · 4.2 NOISE MONITORING REPORT SUMMARY 2012 ... The principal category is peritoneal dialysis solutions that enable dialysis to ... "State of the](https://reader034.vdocument.in/reader034/viewer/2022042319/5f088dd17e708231d422958d/html5/thumbnails/115.jpg)
- 111 -
External Pipe Integrity Testing Report