“preview copy only” · 2013-10-01 · • the ofc tension requires that a back-guy be provided...

124
Preferred method for crossing OFC where traction masts change side: 2 NOTES: A messenger wire is required in terms of Electrical Safety Instructions 906.17 The OFC tension requires that a back-guy be provided for the wooden pole on which it anchors. The messenger wire crossing at right angle need not be significantly tensioned. OFC Earth wire Catenary/contact wires Stay wire “PREVIEW COPY ONLY”

Upload: others

Post on 06-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

Preferred method for crossing OFC where traction masts change side: 2

NOTES:• A messenger wire is required in terms of Electrical Safety Instructions 906.17• The OFC tension requires that a back-guy be provided for the wooden pole on which it anchors.• The messenger wire crossing at right angle need not be significantly tensioned.

OFCEarth wireCatenary/contact wiresStay wire

“PREVIEW COPY ONLY”

Page 2: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

Preferred method for crossing OFC where traction masts change side

NOTES:• A messenger wire is required in terms of Electrical Safety Instructions 906.17• The OFC tension requires that a back-guy be provided for the OHTE mast on which it anchors.• The messenger wire crossing at right angle need not be significantly tensioned.

OFCEarth wireCatenary/contact wiresStay wire

“PREVIEW COPY ONLY”

Page 3: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 4: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 5: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 6: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 7: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 8: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 9: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 10: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 11: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 12: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 13: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 14: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 15: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 16: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 17: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 18: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

1

TRANSNET LIMITED

(Registration no. 1990/00900//06)

SAFETY ARRANGEMENTS AND PROCEDURAL COMPLIANCE

WITH THE OCCUPATIONAL HEALTH AND SAFETY ACT

(ACT 85 OF 1993) AND APPLICABLE REGULATIONS

1. General

1.1 The Contractor and Transnet Limited (hereinafter referred to as “Transnet”) are

individual employers, each in its own right, with their respective duties and

obligations set out in the Occupational Health and Safety Act, Act 85 of 1993 (the

Act) and applicable Regulations.

1.2 The Contractor accepts, in terms of the General Conditions of Contract and in terms of

the Act, his obligations as an employer in respect of all persons in his employ, other

persons on the premises or the Site or place of work or on the work to be executed by

him, and under his control. He shall, before commencement with the execution of the

contract work, comply with the provisions set out in the Act, and shall implement and

maintain a Health and Safety Plan as described in the Construction Regulations, 2003

and as approved by Transnet, on the Site and place of work for the duration of the

Contract.

1.3 The Contractor accepts his obligation to complying fully with the Act and applicable

Regulations notwithstanding the omission of some of the provisions of the Act and the

Regulations from this document.

1.4 Transnet accepts, in terms of the Act, its obligations as an employer of its own

employees working on or associated with the site or place of work, and the Contractor

and Technical Officer or his deputy shall at all times, co-operate in respect of the

health and safety management of the site, and shall agree on the practical

arrangements and procedures to be implemented and maintained during execution of

the Works.

1.5 In the event of any discrepancies between any legislation and this specification, the

applicable legislation will take precedence.

2. Definitions

2.1 In this Specification any word or expression to which a meaning has been assigned in

the Construction Regulations, shall have the meaning so assigned to it, unless the

context otherwise indicates: -

2.2 The work included in this Contract shall for the purposes of compliance with the Act

be deemed to be "Construction Work", which, in terms of the Construction

Regulations, 2003 means any work in connection with: -

(a) the erection, maintenance, alteration, renovation, repair, demolition or

dismantling of or addition to a building or any similar structure;

“PREVIEW COPY ONLY”

Page 19: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

2

(b) the installation, erection, dismantling or maintenance of fixed plant where such

work includes the risk of a person falling;

(c) the construction, maintenance, demolition or dismantling of any bridge, dam,

canal, road, railway, runway, sewer or water reticulation system or any similar

civil engineering structure; or

(d) the moving of earth, clearing of land, the making of an excavation, piling, or

any similar type of work;

2.3 “competent person” in relation to construction work, means any person having the

knowledge, training and experience specific to the work or task being performed:

Provided that where appropriate qualifications and training are registered as per the

South African Qualifications Authority Act, 1995 these qualifications and training

shall be deemed to be the required qualifications and training;

2.4 “contractor” means principal contractor and “subcontractor” means contractor as

defined by the Construction Regulations, 2003.

2.5 “fall protection plan” means a documented plan, of all risks relating to working from

an elevated position, considering the nature of work undertaken, and setting out the

procedures and methods applied to eliminate the risk;

2.6 “health and safety file” means a file, or other record in permanent form, containing

the information required to be kept on site in accordance with the Act and applicable

Regulations;

2.7 “Health and Safety Plan ” means a documented plan which addresses the hazards

identified and include safe work procedures to mitigate, reduce or control the hazards

identified;

2.8 “Risk Assessment” means a programme to determine any risk associated with any

hazard at a construction site, in order to identify the steps needed to be taken to

remove, reduce or control such hazard;

2.9 “the Act” means the Occupational Health and Safety Act No. 85 of 1993.

3. Procedural Compliance

3.1 The Contractor who intends to carry out any construction work shall, before carrying

out such work, notify the Provincial Director in writing if the construction work:-

(a) includes the demolition of a structure exceeding a height of 3 metres; or

(b) includes the use of explosives to perform construction work; or

(c) includes the dismantling of fixed plant at a height greater than 3m,

and shall also notify the Provincial Director in writing when the construction work

exceeds 30 days or will involve more than 300 person days of construction work and

if the construction work:-

(a) includes excavation work deeper than 1m; or

“PREVIEW COPY ONLY”

Page 20: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

3

(b) includes working at a height greater than 3 metres above ground or a landing.

3.2 The notification to the Provincial Director shall be on a form similar to Annexure A of

the Construction Regulations, 2003, also shown in Annexure 1 of this Specification.

The Contractor shall ensure that a copy of the completed notification form is kept on

site for inspection by an inspector, Technical Officer or employee.

3.3 The Contractor shall, in accordance with the Act and applicable Regulations, make all

the necessary appointments of competent persons in writing on a form similar to

Annexure 2 of this Specification and deliver copies thereof to the Technical Officer.

Copies should also be retained on the health and safety file.

3.4 Subcontractors shall also make the above written appointments and the Contractor

shall deliver copies thereof to the Technical Officer.

3.5 In the case of a self-employed Contractor or any subcontractor who has the

appropriate competencies and supervises the work himself, the appointment of a

construction supervisor in terms of regulation 6.1 of the Construction Regulations,

2003 will not be necessary. The Contractor shall in such a case execute and sign a

declaration, as in Annexure 3, by which he personally undertakes the duties and

obligations of the "Chief Executive Officer" in terms of section 16(1) of the Act.

3.6 The Contractor shall, before commencing any work, obtain from the Technical Officer

an access certificate as in Annexure 4 executed and signed by him, permitting and

limiting access to the designated site or place of work by the Contractor and any

subcontractors under his control.

3.7 Procedural compliance with Act and Regulations, as above, shall also apply to any

subcontractors as employers in their own right. The Contractor shall furnish the

Technical Officer with full particulars of such subcontractors and shall ensure that

they comply with the Act and Regulations and Protekon's safety requirements and

procedures.

4. Special Permits

Where special permits are required before work may be carried out such as for

hotwork, isolation permits, work permits and occupations, the Contractor shall apply

to the Technical Officer or the relevant authority for such permits to be issued. The

Contractor shall strictly comply with the conditions and requirements pertaining to the

issue of such permits.

5. Health and Safety Programme

5.1 The Tenderer shall, with his tender, submit a Health and Safety Programme setting out

the practical arrangements and procedures to be implemented by him to ensure

compliance by him with the Act and Regulations and particularly in respect of: -

(i) The provision, as far as is reasonably practical, of a working environment that is

safe and without risk to the health of his employees and subcontractors in terms

of section 8 of the Act;

“PREVIEW COPY ONLY”

Page 21: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

4

(ii) the execution of the contract work in such a manner as to ensure in terms of

section 9 of the Act that persons other than those in the Contractor's

employment, who may be directly affected by the contract work are not thereby

exposed to hazards to their health and safety;

(iii) ensuring, as far as is reasonably practical, in terms of section 37 of the Act that

no employee or subcontractor of the Contractor does or omits to do any act

which would be an offence for the Contractor to do or omit to do.

5.2 The Contractor's Health and Safety Programme shall be based on a risk assessment in

respect of the hazards to health and safety of his employees and other persons under

his control that are associated with or directly affected by the Contractor's activities in

performing the contract work and shall establish precautionary measures as are

reasonable and practical in protecting the safety and health of such employees and

persons.

5.3 The Contractor shall cause a risk assessment contemplated in clause 5.2 above to be

performed by a competent person, appointed in writing, before commencement of any

Construction Work and reviewed during construction. The Risk Assessments shall

form part of the Health and Safety programme to be applied on the site and shall

include at least the following:

(a) The identification of the risks and hazards that persons may be exposed to;

(b) the analysis and evaluation of the hazards identified;

(c) a documented Health and Safety Plan, including safe work procedures to

mitigate, reduce or control the risks identified;

(d) a monitoring and review plan.

5.4 The Health and Safety Plan shall include full particulars in respect of: -

(a) The safety management structure to be instituted on site or place of work and

the names of the Contractor's health and safety representatives and members of

safety committees where applicable;

(b) the safe working methods and procedures to be implemented to ensure the work

is performed in compliance with the Act and Regulations;

(c) the safety equipment, devices and clothing to be made available by the

Contractor to his employees;

(d) the site access control measures pertaining to health and safety to be

implemented;

(e) the arrangements in respect of communication of health and safety related

matters and incidents between the Contractor, his employees, subcontractors

and the Technical Officer with particular reference to the reporting of incidents

in compliance with Section 24 and General Administrative Regulation 8 of the

Act and with the pertinent clause of the General Conditions of Contract

forming part of the Contract and

“PREVIEW COPY ONLY”

Page 22: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

5

(f) the introduction of control measures for ensuring that the Safety Plan is

maintained and monitored for the duration of the Contract.

5.4 The Health and Safety programme shall be subject to the Technical Officer's approval

and he may, in consultation with the Contractor, order that additional and/or

supplementary practical arrangements and procedures be implemented and maintained

by the Contractor or that different working methods or safety equipment be used or

safety clothes be issued which, in the Technical Officer's opinion, are necessary to

ensure full compliance by the Contractor with his obligations as an employer in terms

of the Act and Regulations. The Technical Officer or his deputy shall be allowed to

attend meetings of the Contractor's safety committee as an observer.

5.5 The Contractor shall take reasonable steps to ensure that each subcontractor’s Health

and Safety Plan is implemented and maintained on the construction site: Provided that

the steps taken, shall include periodic audits at intervals mutually agreed to between

the them, but at least once every month.

5.6 The Contractor shall stop any subcontractor from executing any construction work,

which is not in accordance with the Contractor’s, and/or subcontractor’s Health and

Safety Plan for the site or which poses a threat to the health and safety of persons.

5.7 The Contractor shall ensure that a copy of the Health and Safety Plan is available on

site for inspection by an inspector, Technical Officer, agent, subcontractor, employee,

registered employee organisation, health and safety representative or any member of

the health and safety committee.

5.8 The Contractor shall consult with the health and safety committee or, if no health and

safety committee exists, with a representative group of employees, on the

development, monitoring and review of the Risk Assessment.

5.9 The Contractor shall ensure that all employees under his control are informed,

instructed and trained by a competent person regarding any hazard and the related work

procedures before any work commences, and thereafter at such times as may be

determined in the Risk Assessment.

5.10 The Contractor shall ensure that all subcontractors are informed regarding any hazard

as stipulated in the Risk Assessment before any work commences, and thereafter at

such times as may be determined in the Risk Assessment.

5.11 The Contractor shall ensure that all visitors to a construction site undergoes health and

safety induction pertaining to the hazards prevalent on the site and shall be provided

with the necessary personal protective equipment.

6. Fall Protection Plan

6.1 In the event of the risk and hazard identification, as required in terms of clause 5.3 of

this Specification, revealing risks relating to working from an elevated position the

contractor shall cause the designation of a competent person, responsible for the

preparation of a fall protection plan;

“PREVIEW COPY ONLY”

Page 23: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

6

6.2 The Contractor shall implement, maintain and monitor the fall protection plan for the

duration of Contract. The Contractor shall also take such steps to ensure the

continued adherence to the fall protection plan.

6.3 The fall protection plan shall include:-

(a) A Risk Assessment of all work carried out from an elevated position;

(b) the procedures and methods to address all the identified risks per location;

(c) the evaluation of the employees physical and psychological fitness necessary

to work at elevated positions;

(d) the training of employees working from elevated positions; and

(e) the procedure addressing the inspection, testing and maintenance of all fall

protection equipment.

7. Hazards and Potential Hazardous Situations

The Contractor and the Technical Officer shall immediately notify one another of any

hazardous or potentially hazardous situations which may arise during performance of

the Contract by the Contractor or any subcontractor and, in particular, of such hazards

as may be caused by the design, execution and/or location and any other aspect

pertaining to the contract work.

8. Health and Safety File

8.1 The Contractor shall ensure that a health and safety file is opened and kept on site and

shall include all documentation required as per the Act and applicable regulations, and

made available to an inspector, the Technical Officer, or subcontractor upon request.

8.2 The Contractor shall ensure that a copy of the both his Health and Safety Plan as well

as any subcontractor’s Health and Safety Plan is available on request to an employee,

inspector, contractor or the Technical Officer.

8.3 The Contractor shall hand over a consolidated health and safety file to the Technical

Officer upon completion of the Construction Work and shall in addition to

documentation mentioned in the Act and applicable Regulations include a record of all

drawings, designs, materials used and other similar information concerning the

completed structure.

“PREVIEW COPY ONLY”

Page 24: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

7

ANNEXURE 1

OCCUPATIONAL HEALTH AND SAFETY ACT, 1993

Regulation 3(1) of the Construction Regulations

NOTIFICATION OF CONSTRUCTION WORK

1(a) Name and postal address of principal contractor:

_____________________________________________________________________

(b) Name and tel. no of principal contractor’s contact person:

_____________________________________________________________________

2. Principal contractor’s compensation registration number: _____________________________

3.(a) Name and postal address of client:

_____________________________________________________________________

(b) Name and tel no of client’s contact person or agent:

_____________________________________________________________________

4.(a) Name and postal address of designer(s) for the project:

_____________________________________________________________________

(b) Name and tel. no of designer(s) contact person:

____________________________________________________________________

5. Name and telephone number of principal contractor’s construction supervisor on site appointed

in terms of regulation 6(1).

_____________________________________________________________________

6. Name/s of principal contractor’s construction sub-ordinate supervisors on site appointed in

terms of regulation 6(2).

____________________________________________________________

7. Exact physical address of the construction site or site office:

_____________________________________________________________________

8. Nature of the construction work:

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

_____________________________________________________________________

9. Expected commencement date: _______________________

10. Expected completion date: ___________________________

“PREVIEW COPY ONLY”

Page 25: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

8

11. Estimated maximum number of persons on the construction site: _______________________

12. Planned number of contractors on the construction site accountable to the principle contractor:

___________________

13. Name(s) of contractors already chosen.

___________________

___________________

___________________

___________________

___________________

___________________

___________________

_______________________ _________________

Principal Contractor Date

_______________________ _________________

Client Date

* THIS DOCUMENT IS TO BE FORWARDED TO THE OFFICE OF THE DEPARTMENT

OF LABOUR PRIOR TO COMMENCEMENT OF WORK ON SITE.

* ALL PRINCIPAL CONTRACTORS THAT QUALIFY TO NOTIFY MUST DO SO EVEN

IF ANOTHER PRINCIPAL CONTRACTOR ON THE SAME SITE HAD DONE SO PRIOR

TO THE COMMENCEMENT OF WORK.

“PREVIEW COPY ONLY”

Page 26: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

9

ANNEXURE 2

(COMPANY LETTER HEAD)

OCCUPATIONAL HEALTH AND SAFETY ACT, 1993 (ACT 85 OF 1993) :

SECTION/REGULATION: __________________________________________

REQUIRED COMPETENCY: ________________________________________

In terms of ________________________________________ I,

representing the Employer) do hereby appoint

As the Competent Person on the premises at

(physical address) to assist in compliance with the Act and the applicable Regulations.

Your designated area/s is/are as follows :-

Date : ____________________________________

Signature :- ____________________________________

Designation :- ____________________________________

ACCEPTANCE OF DESIGNATION

I, do hereby accept this Designation and acknowledge that I

understand the requirements of this appointment.

Date : ____________________________________

Signature :- ____________________________________

Designation :- ____________________________________

“PREVIEW COPY ONLY”

Page 27: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

10

ANNEXURE 3

(COMPANY LETTER HEAD)

OCCUPATIONAL HEALTH AND SAFETY ACT, 1993 (ACT 85 OF 1993) :

DECLARATION

In terms of the above Act I, am personally assuming the duties

and obligations as Chief Executive Officer, defined in Section 1 of the Act and in terms of Section 16(1), I will,

as far as is reasonably practicable, ensure that the duties and obligations of the Employer as contemplated in the

above Act are properly discharged.

Signature :- ____________________________________

Date : ____________________________________

“PREVIEW COPY ONLY”

Page 28: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E.4E Transnet (Jan 2004)

11

ANNEXURE 4

(LETTER HEAD OF BUSINESS DIVISION OR UNIT OF TRANSNET LIMITED)

SITE ACCESS CERTIFICATE

Access to : (Area)

Name of Contractor/Builder :-

Contract/Order No.:

The contract works site/area described above are made available to you for the carrying out of associated works

In terms of your contract/order with

(company)

Kindly note that you are at all times responsible for the control and safety of the Works Site, and for persons

under your control having access to the site.

As from the date hereof you will be responsible for compliance with the requirements of the Occupational Health

and Safety Act, 1993 (Act 85 of 1993) as amended, and all conditions of the Contract pertaining to the site of the

works as defined and demarcated in the contract documents including the plans of the site or work areas forming

part thereof.

Signed : ____________________________________ Date : _______________________

TECHNICAL OFFICER

ACKNOWLEDGEMENT OF RECEIPT

Name of Contractor/Builder :- I,

do hereby acknowledge and accept the duties

and obligations in respect of the Safety of the site/area of Work in terms of the Occupational Health and

Safety Act; Act 85 of 1993.

Name : ____________________________________ Designation : _______________________

Signature : _________________________________ Date : _______________________

“PREVIEW COPY ONLY”

Page 29: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 1 of 19

TRANSNET SPECIFICATION E7/1

SPECIFICATION FOR GENERAL WORK AND WORKS ON, OVER,

UNDER OR ADJACENT TO RAILWAY LINES AND NEAR HIGH

VOLTAGE EQUIPMENT

(This specification shall be used in network operator contracts)

Authorised: Designation Name

Date: June 2009

Circulation Restricted To:

The network operators and Relevant Third Parties

© This document as a whole is protected by copyright. The information herein is the sole property of Transnet Ltd. It may not

be used, disclosed or reproduced in part or in whole in any manner whatsoever, except with the written permission of and in

a manner permitted by the proprietors.

“PREVIEW COPY ONLY”

Page 30: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 2 of 19

CONTENTS

CLAUSE PAGES NO'S.

1. SCOPE 3

DEFINITIONS 3

2. PART A – GENERAL SPECIFICATION 4

AUTHORITY OF OFFICERS OF THE NETWORK OPERATOR 3

3. CONTRACTOR'S REPRESENTATIVES 4

4. OCCUPATIONS AND WORK PERMITS 4

5. SPEED RESTRICTIONS AND PROTECTION 4

6. ROADS ON THE NETWORK OPERATOR’S PROPERTY 5

7. CLEARANCES 5

8. STACKING OF MATERIAL 5

9. EXCAVATION, SHORING, DEWATERING AND DRAINAGE 5

10. FALSEWORK FOR STRUCTURES 5

11. PILING 6

12. UNDERGROUND SERVICES 6

13. BLASTING 6

14. RAIL TROLLEYS 6

15. SIGNAL TRACK CIRCUITS 6

16. PENALTY FOR DELAYS TO TRAINS 6

17. SURVEY BEACONS AND PEGS 7

18. TEMPORARY LEVEL CROSSINGS 8

19. COMPLETION OF THE WORKS 8

20. PROTECTION OF PERSONS AND PROPERTY 9

21. INTERFERENCE WITH THE NETWORK OPERATOR'S ASSETS AND WORK ON OPEN LINES 9

22. ACCESS, RIGHTS-OF-WAY AND CAMPSITES 10

23. SUPERVISION 10

24. HOUSING OF EMPLOYEES 11

25. SAMPLING AND TESTING OF MATERIAL AND INSTALLATIONS 11

PART B – ADDITIONAL SPECIFICATION FOR WORK NEAR

HIGH-VOLTAGE ELECTRICAL EQUIPMENT

17. General 12

18. Work on buildings of fixed structures 7

19. Work done on or outside of rolling stock, including loading and unloading 7

20. Use of equipment 8

21. Carrying and handling material and equipment 8

22. Precautions to be taken when erecting or removing poles, antennae and trees 8

23. Use of water 9

24. Use of construction plant 9

25. Work performed under dead conditions under cover of a work permit 9

26. Traction return circuits in rails 9

27. Blasting 9

28. High-voltage electrical equipment not maintained and/or operated by the network operator 10

APPENDIXES

1. Horizontal clearances 1065mm gauge 19

2. Vertical clearances 1065mm gauge 20

3. Clearances 610mm gauge 21

4. Platform clearances 22

“PREVIEW COPY ONLY”

Page 31: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 3 of 19

1.0 SCOPE

1.1 This specification covers the network operator’s requirements for general work and works on, over, under or

adjacent to railway lines and near high voltage equipment.

2.0 DEFINITIONS

The following definitions shall apply:

“Authorised Person” - A person whether an employee of the network operator or not, who has been specially

authorised to undertake specific duties in terms of Transnet’ publication Electrical Safety Instructions, and

who holds a certificate or letter of authority to that effect.

“Barrier” Any device designed to restrict access to "live" high-voltage electrical equipment.

“Bond” - A short conductor installed to provide electrical continuity.

“Contractor” - Any person or organisation appointed by the network operator to carry out work on its behalf.

“Contract Supervisor” - The person or juristic person appointed by the network operator from time to time as

the Contract Supervisor, to administer the Contractor's performance and execution of the Works according

to the powers and rights held by and obligations placed upon the Contract Supervisor in terms of the

Contract.

“Dead” - Isolated and earthed.

“Electrical Officer (Contracts)” - The person appointed in writing by the Project Manager in terms of this

specification as the person who shall be consulted by the Contractor in all electrical matters to ensure that

adequate safety precautions are taken by the Contractor.

“Executive Officer” - The person appointed by the network operator from time to time as the Executive

Officer to act according to the rights and powers held by and obligations placed upon him in terms of the

Contract.

“High-Voltage” - A voltage normally exceeding 1000 volts.

“Live” - A conductor is said to be “live" when it is at a potential different from that of the earth or any other

conductor of the system of which it forms a part.

“Near” - To be in such a position that a person's body or the tools he is using or any equipment he is

handling may come within 3 metres of “live” exposed high-voltage electrical equipment.

“Occupation” - An authorisation granted by the network operator for work to be carried out under specified

conditions on, over under or adjacent to railway lines.

“Occupation Between Trains” - An occupation during an interval between successive trains.

“Project Manager” – As defined in the special conditions of the contract. The person or juristic person

appointed by the network operator from time to time as the Project Manager, to administer the Contract

according to the powers and rights held by and obligations placed upon him in terms of the Contract.

“Responsible Representative” - The responsible person in charge, appointed by a contractor, who has

undergone specific training (and holds a certificate) to supervise (general or direct) staff under his control

perform general work or to work on, over, under or adjacent to railway lines and in the vicinity of high-voltage

electrical equipment.

“Total Occupation” - An occupation for a period when trains are not to traverse the section of line covered by

the occupation.

“Work on” - Work undertaken on or so close to the equipment that the specified working clearances to the

“live” equipment cannot be maintained.

“Work Permit” - A combined written application and authority to proceed with work on or near dead electrical

equipment. “PREVIEW COPY ONLY”

Page 32: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 4 of 19

3.0 PART A - GENERAL SPECIFICATION

AUTHORITY OF OFFICERS OF TRANSNET

3.1 The Contractor shall co-operate with the officers of the network operator and shall comply with all

instructions issued and restrictions imposed with respect to the Works which bear on the existence and

operation of the network operator's railway lines and high-voltage equipment.

3.2 Without limiting the generality of the provisions of clause 3.1, any duly authorised representative of the

network operator, having identified himself, may stop the work if, in his opinion, the safe passage of trains or

the safety of the network operator’s assets or any person is affected. CONSIDERATIONS OF SAFETY

SHALL TAKE PRECEDENCE OVER ALL OTHER CONSIDERATIONS.

4.0 CONTRACTOR'S REPRESENTATIVES

4.1 The Contractor shall nominate Responsible Representatives of whom at least one shall be available at any

hour for call-out in cases of emergency. The Contractor shall provide the Contract Supervisor with the

names, addresses and telephone numbers of the representatives.

4.2 The Contractor guarantees that he has satisfied himself that the Responsible Representative is fully

conversant with this specification and that he shall comply with all his obligations in respect thereof.

5.0 OCCUPATIONS AND WORK PERMITS

5.1 Work to be done during total occupation or during an occupation between trains or under a work permit shall

be done in a manner decided by the Contract Supervisor and at times to suit the network operator

requirements.

5.2 The Contractor shall organise the Works in a manner which will minimise the number and duration of

occupations and work permits required.

5.3 The network operator will not be liable for any financial or other loss suffered by the Contractor arising from

his failure to complete any work scheduled during the period of an occupation or work permit.

5.4 The Contractor shall submit to the Contract Supervisor, in writing, requests for occupations or work permits

together with details of the work to be undertaken, at least 21 days before they are required. The network

operator does not undertake to grant an occupation or work permit for any particular date, time or duration.

5.5 the network operator reserves the right to cancel any occupation or work permit at any time before or during

the period of occupation or work permit. If, due to cancellation or change in date or time, the Contractor is not

permitted to start work under conditions of total occupation or work permit at the time arranged, all costs

caused by the cancellation shall be born by the Contractor except as provided for in clauses 4.6 to 4.8.

5.6 When the Contractor is notified less than 2 hours before the scheduled starting time that the occupation or

work permit is cancelled, he may claim reimbursement of his direct financial losses caused by the loss of

working time up to the time his labour and plant are employed on other work, but not exceeding the period of

the cancelled occupation or work permit.

5.7 When the Contractor is notified less than 2 hours before the schedule starting time, or during an occupation

or work permit, that the duration of the occupation or work permit is reduced, he may claim reimbursement of

his direct financial losses caused by the loss of working time due to the reduced duration of the occupation or

work permit.

5.8 Reimbursement the Contractor for any loss of working time in terms of clause 5.6 and 5.7, shall be subject to

his claims being submitted within 14 days of the event with full details of labour and plant involved, and

provided that the Contract Supervisor certifies that no other work on which the labour and plant could be

employed was immediately available.

5.9 Before starting any work for which an occupation has been arranged, the Contractor shall obtain from the

Contract Supervisor written confirmation of the date, time and duration of the occupation.

5.10 Before starting any work for which a work permit has been arranged, the Responsible Representative shall

read and sign portion C of the Work Permit, signifying that he is aware of the work boundaries within which

work may be undertaken. After the work for which the permit was granted has been completed, or when the

work permit is due to be terminated, or if the permit is cancelled after the start, the same person who signed

portion C shall sign portion D of the Work Permit, thereby acknowledging that he is aware that the electrical

equipment is to be made “live”. The Contractor shall advise all his workmen accordingly.

“PREVIEW COPY ONLY”

Page 33: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 5 of 19

6.0 SPEED RESTRICTIONS AND PROTECTION

6.1 When speed restrictions are imposed by the network operator because of the Contractor's activities, the

Contractor shall organise and carry out his work so as to permit the removal of the restrictions as soon as

possible.

6.2 When the Contract Supervisor considers protection to be necessary the Contractor shall, unless otherwise

agreed, provide all protection including flagmen, other personnel and all equipment for the protection of the

network operator's and the Contractor's personnel and assets, the public and including trains.

6.2.1 The network operator will provide training free of charge of the Contractor's flagmen and other personnel

performing protection duties. The Contractor shall consult with the Contract Supervisor, whenever he

considers that protection will be necessary, taking into account the minimum permissible clearances set out

in appendixes 1 to 4.

6.3 The Contractor shall appoint a Responsible Representative to receive and transmit any instruction which

may be given by the network operator personnel providing protection.

7.0 ROADS AND ROADS ON THE NETWORK OPERATOR’S PROPERTY

7.1 The Contractor shall take every reasonable precaution to prevent damage to any roads or bridges used to

obtain access to the site, and shall select routes, use vehicles, and restrict loads so that any extraordinary

traffic as may arise from the moving of plant or material to or from the site shall be limited as far as is

reasonably possible.

7.2 The Contractor shall not occupy or interfere in any way with the free use of any public or private road,

right-of-way, path or street unless the Contract Supervisor has obtained the approval of the road authority

concerned.

8.0 CLEARANCES

8.1 No temporary works shall encroach on the appropriate minimum clearances set out in Appendixes 1 to 4.

9.0 STACKING OF MATERIAL

9.1 The Contractor shall not stack any material closer than 3m from the centre line of any railway line without

prior approval of the Contract Supervisor.

10.0 EXCAVATION, SHORING, DEWATERING AND DRAINAGE

10.1 Unless otherwise approved by the Contract Supervisor any excavation adjacent to a railway line shall not

encroach on the hatched area shown in Figure 1.

10.2 The Contractor shall provide at his own cost any shoring, dewatering or drainage of any excavation unless

otherwise stipulated elsewhere in the Contract.

10.3 Where required by the Contract Supervisor, drawings of shoring for any excavation under or adjacent to a

railway line shall be submitted and permission to proceed, obtained before the excavation is commenced.

10.4 The Contractor shall prevent ingress of water to the excavation but where water does enter, he shall dispose

of it as directed by the Contract Supervisor.

10.5 The Contractor shall not block, obstruct or damage any existing drains either above or below ground level

unless he has made adequate prior arrangements to deal with drainage.

11.0 FALSEWORK FOR STRUCTURES

11.1 Drawings of falsework for the construction of any structure over, under or adjacent to any railway line shall be

submitted to the Contract Supervisor and his permission to proceed obtained before the falsework is

erected. Each drawing shall be given a title and a distinguishing number and shall be signed by a registered

professional engineer certifying that he has checked the design of the falsework and that the drawings are

“PREVIEW COPY ONLY”

Page 34: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 6 of 19

correct and in accordance with the design.

11.2 After the falsework has been erected and before any load is applied, the Contractor shall submit to the

Contract Supervisor a certificate signed by a registered professional engineer certifying that he has checked

the falsework and that it has been erected in accordance with the drawings. Titles and numbers of the

drawings shall be stated in the certificate. Notwithstanding permission given by the Contract Supervisor to

proceed, the Contractor shall be entirely responsible for the safety and adequacy of the falsework.

12.0 PILING

12.1 The Contract Supervisor will specify the conditions under which piles may be installed on the network

operator property.

13.0 UNDERGROUND SERVICES

13.1 No pegs or stakes shall be driven or any excavation made before the Contractor has established that there

are no underground services which may be damaged thereby.

13.2 Any damage shall be reported immediately to the Contract Supervisor, or to the official in charge at the

nearest station, or to the traffic controller in the case of centralised traffic control.

14.0 BLASTING AND USE OF EXPLOSIVES

14.1 When blasting within 500m of a railway line, the Contractor shall observe the requirements stipulated in

this specification.

14.2 No blasting shall be carried out except with the prior written permission of the Contract Supervisor and

under such conditions as he may impose.

14.3 On electrified lines the Contractor shall also obtain the permission of the Electrical Officer (Contracts) before

blasting, and shall give at least 21 days notice of his intention to blast. No blasting shall be done in the vicinity

of electrified lines unless a member of the network operator's electrical personnel is present.

14.4 The Contractor shall arrange for the supply, transport storage and use of explosives.

14.5 The Contractor shall have labour, tools and plant, to the satisfaction of the Contract Supervisor, available

on the site to clear immediately any stones or debris deposited on the track or formation by blasting, and

to repair any damage to the track or formation immediately after blasting. Repairs to the track shall be

carried out only under the supervision of a duly authorised representative of the network operator.

14.6 The Contractor shall notify the Contract Supervisor of his intention to blast at least 21 days before the

commencement of any blasting operations.

14.7 Before any blasting is undertaken, the Contractor and the Contract Supervisor shall jointly examine and

measure up any buildings, houses or structures in the vicinity of the proposed blasting to establish the

extent of any existing cracking or damage to such structures, etc. The Contractor, shall, subject to the

provisions stipulated in the Contract Insurance Policy, make good any deterioration of such buildings,

houses, or structures, which, in the opinion of the Contract Supervisor, was directly caused by the

blasting.

14.8 After completion of the blasting the Contractor shall obtain a written clearance from each landowner in the

vicinity of the blasting operations to the effect that all claims for compensation in respect of damage

caused by the blasting operations to their respective properties, have been settled.

14.9 The provisions of clause 23 of the E.5, General Conditions of Contract or clause 21 of the E.5 (MW),

General Conditions of Contract for Maintenance Work, shall apply to all blasting operations undertaken in

terms of the Contract.

14.10 The Contractor shall provide proof that he has complied with the provisions of clauses 10.17.1 to 10.17.4 of

the Explosives Regulations (Act 26 of 1956 as amended).

14.11 Blasting within 500m of a railway line will only be permitted during intervals between trains. A person

appointed by the Contract Supervisor, assisted by flagmen with the necessary protective equipment, will be

in communication with the controlling railway station.

Only this person will be authorised to give the Contractor permission to blast, and the Contractor shall obey

his instructions implicitly regarding the time during which blasting may take place.

“PREVIEW COPY ONLY”

Page 35: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 7 of 19

14.12 The flagmen described in clause14.11, where provided by the network operator, are for the protection of

trains and the network operator’s property only, and their presence does not relieve the Contractor in any

manner of his responsibilities in terms of Explosives Act or Regulations, or any obligation in terms of this

Contract.

14.13 The person described in clause 14.11 will record in a book provided and retained by the network operator’s

the dates and times -

(i) when each request is made by him to the controlling station for permission to blast;

(ii) when blasting may take place;

(iii) when blasting actually takes place; and

(iv) when he advises the controlling station that the line is safe for the passage of trains.

14.14 Before each blast the Contractor shall record in the same book, the details of the blast to be carried out. The

person appointed by the Contract Supervisor and the person who will do the blasting shall both sign the book

whenever an entry described in clause 14.13 is made.

15.0 RAIL TROLLEYS

15.1 The use of rail trolleys or trestle trolleys on a railway line for working on high voltage equipment will be

permitted only if approved by the Contract Supervisor and under the conditions stipulated by him.

15.2 All costs in connection with such trolley working requested by the Contractor shall, unless otherwise agreed,

be borne by the Contractor, excluding the costs of any train protection services normally provided free of

charge by the network operator.

16.0 SIGNAL TRACK CIRCUITS

16.1 Where signal track circuits are installed, the Contractor shall ensure that no material capable of conducting

an electrical current makes contact between rails of railway line/lines.

16.2 No signal connections on track-circuited tracks shall be severed without the Contract Supervisor's

knowledge and consent.

17.0 PENALTY FOR DELAYS TO TRAINS

17.1 If any trains are delayed by the Contractor and the Contract Supervisor is satisfied that the delay was

avoidable, a penalty will be imposed on the Contractor of R5000 per hour or part thereof for the period of

delay, irrespective of the number of trains delayed.

18.0 SURVEY BEACONS AND PEGS

18.1 The Contractor shall not on any account move or damage any beacon, bench mark, reference mark,

signal or trigonometrical station in the execution of the WORKS without the written approval of the

Contract Supervisor.

Should the Contractor be responsible for any such occurrence, he shall report the circumstances to the

Contract Supervisor who will arrange with the Director-General of Surveys for replacement of the beacon

or mark at the cost of the Contractor.

18.2 The Contractor shall not move or damage any cadastral or mining beacon without the written approval of

the Contract Supervisor and before it has been referenced by a registered land surveyor. Any old

boundary beacon, which becomes an internal beacon on creation of new boundaries, shall not be moved

without the written approval of the Contract Supervisor.

Should the Contractor move or damage any cadastral or mining beacon without authority, he shall be

responsible for having it replaced, at his cost, by a land surveyor.

18.3 The Contractor shall preserve all pegs and bench marks. Such survey points shall not be removed

without the written approval of the Contract Supervisor. Should any peg or benchmark be removed

without authority, the Contract Supervisor will arrange for its replacement and the cost will be recovered

from the Contractor. No claim will be considered for delay in replacing any such peg or bench mark.

Each peg replaced shall be checked by the Contractor.

18.4 Where a new boundary has been established, beacons on the fence line shall not be disturbed, and fence

posts or anchors may not be placed or excavations made within 0,6 m of any beacon without the prior

“PREVIEW COPY ONLY”

Page 36: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 8 of 19

written approval of the Contract Supervisor.

19.0 TEMPORARY LEVEL CROSSINGS

19.1 The Contract Supervisor may, on request of the Contractor, and if necessary for the purpose of execution

of the WORKS, permit the construction of a temporary level crossing over a railway a line at a position

approved by the Contract Supervisor and at the Contractor's cost. The period for which the temporary

level crossing is permitted will be at the discretion of the Contract Supervisor.

19.2 The network operator will, at its own cost, provide protection and supervise the construction of the road

over the track(s) and for a distance of 3 metres beyond the outermost rails, as well as the erection of all

road signs and height gauges.

The Contractor shall exercise extreme caution in carrying out this work, especially in respect of damage

to tracks, services, overhead power and communications routes and contact with “live” overhead

electrical equipment.

All the network operator’s electrical, telecommunications and train authorisation system service deviations

or alterations to accommodate the level crossing will be done by the network operator at its own cost. All

other work required by the Contract Supervisor to establish the temporary level crossing, including

protection, deviation or support of other services and drainage, shall be carried out by the Contractor at

his own cost.

19.3 The Contractor shall take all necessary steps including the provision of gates, locks and, where

necessary, watchmen to restrict the use of the temporary level crossing to himself and his employees, his

subcontractors and their employees, the staff of the network operator and to such other persons as the

Contract Supervisor may permit and of whose identity the Contractor will be advised. If so ordered by the

Contract Supervisor, the Contractor shall provide persons to control road traffic using the temporary level

crossing. Such persons shall stop all road traffic when any approaching train is within seven hundred and

fifty metres of the temporary level crossing, and shall not allow road traffic to proceed over it until the lines

are clear.

19.4 The Contractor shall maintain the temporary level crossing in good condition for the period it is in use.

Maintenance of the portion of the temporary level crossing over the tracks and three metres beyond the

outermost rail shall be done under the supervision and protection of the network operator, and at the cost

of the Contractor.

19.5 When the temporary level crossing is no longer required by the Contractor, or permitted by the network

operator, the Contractor shall remove it and restore the site to its original condition. Work over the tracks

and up to three metres beyond the outermost tracks will be supervised by the network operator.

Such supervision and restoration of the network operator electrical, telecommunication and signalling

services to their original position will be undertaken by the network operator at its own cost. The

Contractor at his own cost shall restore other services.

20.0 COMPLETION OF THE WORKS

20.1 The whole of the WORKS, including all alterations, extras, additions and omissions, shall be completed

and delivered to the network operator by the stipulated date or such extended date of completion as may

have been determined in terms of the contract.

20.2 When the WORKS or portions thereof have been completed to the satisfaction of the Contract Supervisor

and left in a clean, neat and tidy condition, the Contract Supervisor will give the Contractor a

CERTIFICATE OF COMPLETION confirming that the WORKS or portions thereof have been completed

and stating the date on which the defects liability and maintenance period referred to in the contract is to

commence. Separate CERTIFICATES OF COMPLETION will be given for completed portions of the

WORKS in cases where completion of such portions is specified in the Contract as being required before

the completion of the entire WORKS, or for completed portions of the WORKS taken over by the network

operator in terms of clause 20.1 hereof. Until the Contract Supervisor, issues a CERTIFICATE

OF COMPLETION, the WORKS or specified portions thereof shall not be deemed to have been

completed.

20.3 On receipt of a CERTIFICATE OF COMPLETION for the entire WORKS or the finally completed portion

thereof the Contractor shall, unless otherwise ordered by the Contract Supervisor, remove from the site all

construction plant, material and temporary works not required for making good of defects in the WORKS

or portions thereof covered by such CERTIFICATE, other than material which is the property of the

“PREVIEW COPY ONLY”

Page 37: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 9 of 19

network operator.

20.4 After expiry of the defects liability and maintenance period the Contractor shall remove all the remaining

construction plant and material from the site, other than material which is the property of the network

operator, and leave the site in a clean, neat and tidy condition.

21.0 PROTECTION OF PERSONS AND PROPERTY

21.1 The Contractor shall provide and maintain all lights, guards, barriers, fencing and watchmen when and

where necessary or as required by the Contract Supervisor or by any statutory authority, for the protection

of the WORKS and for the safety and convenience of the public.

Red, yellow, green or blue lights and red, yellow, green or white flags shall not be used by the Contractor

in such a position that they can be mistaken for railway signals. The Contractor shall obtain the

permission of the Port Captain before installing any light within the precincts of a port.

21.2 The Contractor shall take all the requisite measures and precautions during the course of the WORKS to:

(i) protect the public and property of the public,

(ii) protect the property and workmen of both the network operator and the Contractor,

(iii) avoid damage to and prevent trespass on adjoining properties, and

(iv) ensure compliance with any instruction issued by the Contract Supervisor or other authorised

person, and with any stipulation embodied in the contract documents which affects the safety of any

person or thing.

21.3 The network operator will provide, at its own cost, protection for the safe working of trains during such

operations as the Contract Supervisor may consider necessary. Protection by the network operator for

any purpose whatsoever, does not absolve the Contractor of his responsibilities in terms of the Contract.

21.4 The Contractor shall take all precautions and appoint guards, watchmen and compound managers for

prevention of disorder among and misconduct by the persons employed on the WORKS and by any other

persons, whether employees or not, on the site of the WORKS and for the preservation of the peace and

protection of persons and property in the neighbourhood of the WORKS. Any relocation of camps

because of disorder shall be at the Contractor's expense.

21.5 All operations necessary for the execution of the WORKS, including the provision of any temporary works

and camping sites, shall be carried out so as not to cause veldt fires, ground and environmental pollution,

soil erosion or restriction of or interference with streams, furrows, drains and water supplies.

If the original surface of the ground is disturbed in connection with the WORKS, it shall be made good by

the Contractor to the satisfaction of the land owner, occupier or responsible authority. The Contractor

shall take all reasonable steps to minimise noise and disturbance when carrying out the WORKS,

including work permitted outside normal working hours.

21.6 Dumping of waste or excess materials by the Contractor shall, in urban areas, be done under the direction

and control of, and at sites made available by the local authority. Dumping outside local authority

boundaries shall be done only with the express permission and under the direction and control of the

Contract Supervisor. The Contractor shall comply with environmental protection measures and

specifications stipulated by the Contract Supervisor and/or local and environmental authorities.

22.0 INTERFERENCE WITH THE NETWORK OPERATOR'S ASSETS AND WORK ON OPEN LINES

22.1 The Contractor shall not interfere in any manner whatsoever with an open line, nor shall he carry out any

work or perform any act which affects the security, use or safety of an open line except with the authority

of the Contract Supervisor and in the presence of a duly authorised representative of the network

operator.

22.2 The Contractor shall not carry out any work or operate any plant, or place any material whatsoever nearer

than three metres from the centre line of any open line except with the written permission of the Contract

Supervisor and subject to such conditions as he may impose.

22.3 Care must be taken not to interfere with or damage any services such as overhead wire routes, cables or

pipes, except as provided for the work specified. The Contractor will be held responsible for any damage

to or interruption of such services arising from any act or omission on his part or of any of his employees,

or persons engaged by him on the WORKS. The cost of repairing, replacing or restoring the services, as

“PREVIEW COPY ONLY”

Page 38: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 10 of 19

well as all other costs arising from any damage to services, shall be borne by, and will be recovered from

the Contractor.

22.4 Authority granted by the Contract Supervisor and the presence of an authorised representative of the

network operator in terms hereof, shall not relieve the Contractor of his duty to comply with this

specification.

23.0 ACCESS, RIGHTS-OF-WAY AND CAMPSITES

23.1 Where entry onto the network operator's property is restricted, permission to enter will be given only for

the purpose of carrying out the WORKS and will be subject to the terms and conditions lay down by the

network operator.

23.2 The Contractor shall arrange for campsites, workplaces and access thereto as well as for any right-of-way

over private property to the site of the WORKS, and for access within the boundaries of the network

operator's property. The owners of private property to be traversed shall be approached and treated with

tact and courtesy by the Contractor, who shall, if necessary, obtain a letter of introduction to such

property owners from the Contract Supervisor.

The Contractor shall be responsible for the closing of all gates on roads and tracks used by him or his

employees. Except with the prior approval of the Contract Supervisor and the owner or occupier of any

private land to be traversed, the Contractor shall not cut, lower, damage, remove or otherwise interfere

with any fence or gate which is either on the network operator's property or on private property and which

restricts access to the WORKS. Where such approval has been given, the Contractor shall prevent entry

of animals or unauthorised persons onto the network operator's or private property, and shall make the

fences safe against trespass at the close of each day's work.

23.3 The Contractor shall take all reasonable steps to confine the movement of vehicles and plant to the

approved right-of-way to minimise damage to property, crops and natural vegetation.

23.4 When access is no longer required, and before completion of the WORKS, the Contractor shall repair,

restore or replace any fence or gate damaged during execution of the WORKS to the satisfaction of the

Contract Supervisor and shall furnish the Contract Supervisor with a certificate signed by the owner and

occupier of land over which he has gained access to a campsite, workplace and the WORKS, certifying

that the owner and occupier have no claim against the Contractor or the network operator arising from the

Contractor's use of the land. Should the Contractor be unable to obtain the required certificate, he shall

report the circumstances to the Contract Supervisor.

24.0 SUPERVISION

24.1 The Contract Supervisor will provide overall technical superintendence of the WORKS, and may direct the

Contractor in terms of the provisions of the Contract or in respect of any measures which the Contract

Supervisor may require for the operations of the network operator, the safety of trains, property and

workmen of the network operator, and for the safety of other property and persons. The Contractor shall

carry out the directions of the Contract Supervisor. The superintendence exercised by the Contract

Supervisor, including any agreement, approval, refusal or withdrawal of any approval given, shall not

relieve the Contractor of any of his duties and liabilities under the Contract, and shall not imply any

assumption by the network operator or by the Contract Supervisor of the legal and other responsibilities of

the Contractor in carrying out the WORKS.

24.2 The Contract Supervisor may delegate to any deputy or other person, any of his duties or functions under

the Contract. On receiving notice in writing of such delegation, the Contractor shall recognise and obey

the deputy or person to whom any such duties or functions have been delegated as if he were the

Contract Supervisor.

24.3 The Contractor shall exercise supervision over the WORKS at all times when work is performed or shall

be represented by an agent having full power and authority to act on behalf of the Contractor. Such agent

shall be competent and responsible, and have adequate experience in carrying out work of a similar

nature to the WORKS, and shall exercise personal supervision on behalf of the Contractor. The Contract

Supervisor shall be notified in writing of such appointment which will be subject to his approval.

24.4 The Contractor or his duly authorised agent shall be available on the site at all times while the WORKS

are in progress to receive the orders and directions of the Contract Supervisor.

25.0 HOUSING OF EMPLOYEES

“PREVIEW COPY ONLY”

Page 39: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 11 of 19

25.1 The Contractor shall, where necessary, make his own arrangements for suitable housing of his

employees. Where temporary housing is permitted by the Contract Supervisor on any part of the site, the

Contractor shall provide suitable sanitation, lighting and potable water supplies in terms of the

requirements of the local authority or the current the network operator specification; Minimum Communal

Health Requirements in Areas outside the Jurisdiction of a Local Authority - E.4B, as applicable.

25.2 Fouling the area inside or outside the network operator's boundaries shall be prevented. The Contractor

will be called upon by the Contract Supervisor to dispose of any foul or waste matter generated by the

Contractor.

26.0 SAMPLING AND TESTING OF MATERIAL AND INSTALLATIONS

26.1 The Contractor shall furnish such samples or prototypes of materials or equipment as may be called for

by the Contract Supervisor who may, in his discretion, require the Contractor to subject any such samples

or prototypes to appropriate tests.

When required by the Contract Supervisor, the Contractor shall afford every facility for the inspection and

testing of such materials or equipment and shall supply all material, instruments, assistance and facilities

that may be required for the purpose of such inspection or tests.

26.2 Only materials and equipment, which comply in all respects with the approved samples and prototypes,

shall be brought on to the site or used on the WORKS. Material and equipment, which do not comply in

all respects with the approved samples and prototypes, may be rejected by the Contract Supervisor. The

Contractor, at his own cost, shall remove and replace any rejected material or equipment together with

that portion of the WORKS affected by it.

26.3 The Contractor shall arrange to carry out such further tests on completed works and equipment installed

as ordered by the Contract Supervisor.

26.4 The direct cost of any sampling and testing ordered that is different from and/or additional to testing and

sampling stipulated in the Project Specification, shall be reimbursed to the Contractor save in the event

that the materials and workmanship tested do not comply with the Contract or where previous testing and

sampling done by the Contractor did not comply with specified procedures or methods.

26.5 The approval by the Contract Supervisor of any materials or equipment shall not relieve the Contractor of

his obligation to comply fully with the contract specifications for the complete WORKS.

“PREVIEW COPY ONLY”

Page 40: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 12 of 19

PART B - SPECIFICATION FOR WORK NEAR HIGH-VOLTAGE ELECTRICAL EQUIPMENT

27.0 GENERAL

27.1 This specification is based on the contents of Transnet’s publication ELECTRICAL SAFETY

INSTRUCTIONS, as amended, a copy of which will be made available on loan to the Contractor for the

duration of the contract.

These instructions apply to all work near “live” high-voltage equipment maintained and/or operated by the

network operator, and the onus rests on the Contractor to ensure that he obtains a copy.

27.2 This specification must be read in conjunction with and not in lieu of the Electrical Safety Instructions.

27.3 The Contractor's attention is drawn in particular to the contents of Part I, Sections 1 and 2 of the Electrical

Safety Instructions.

27.4 The Electrical Safety Instructions cover the minimum safety precautions which must be taken to ensure safe

working on or near high-voltage electrical equipment, and must be observed at all times. Should additional

safety measures be considered necessary because of peculiar local conditions, these may be ordered by

and at the discretion of the Electrical Officer (Contracts).

27.5 The Contractor shall obtain the approval of the Electrical Officer (Contracts) before any work is done which

causes or could cause any portion of a person's body or the tools he is using or any equipment he is

handling, to come within 3 metres of any “live” high-voltage equipment.

27.6 The Contractor shall regard all high-voltage equipment as “live” unless a work permit is in force.

27.7 Safety precautions taken or barriers erected shall comply with the requirements of the Electrical Officer

(Contracts), and shall be approved by him before the work to be protected is undertaken by the Contractor.

The Contractor shall unless otherwise agreed, bear the cost of the provision of the barriers and other safety

precautions required, including the attendance of the network operator’s staff where this is necessary.

27.8 No barrier shall be removed unless authorised by the Electrical Officer (Contracts).

28.0 WORK ON BUILDINGS OR FIXED STRUCTURES

28.1 Before any work is carried out or measurements are taken on any part of a building, fixed structure or

earthworks of any kind above ground level situated within 3 metres of “live” high-voltage equipment, the

Electrical Officer (Contracts) shall be consulted to ascertain the conditions under which the work may be

carried out.

28.2 No barrier erected to comply with the requirements of the Electrical Officer (Contracts) shall be used as

temporary staging or shuttering for any part of the Works.

28.3 The shuttering for bridge piers, abutments, retaining walls or parapets adjacent to or over any track may be

permitted to serve as a barrier, provided that it extends at least 2,5 metres above any working level in the

case of piers, abutments and retaining walls and 1,5 metres above any working level in the case of parapets.

29.0 WORK DONE ON OR OUTSIDE OF ROLLING STOCK, INCLUDING LOADING OR UNLOADING

29.1 No person shall stand, climb or work whilst on any platform, surface or foothold higher than the normal

unrestricted places of access, namely-

(i) the floor level of open deck rail wagons;

(ii) external walkways on diesel, steam and electric locomotives, steam heat vans, etc. and

(iii) walkways between coaches and locomotives.

(iv) The vehicle decks of road-rail vehicles, on-track maintenance machines and material trains

under “live” electrical equipment, are to be treated as “restricted access ways” in terms of the Electrical

Safety Instructions. When in these positions, no person may raise his hands or any equipment or

material he is handling above his head.

29.2 In cases where the Contractor operates his own rail mounted equipment, he shall arrange for the walkways

on this plant to be inspected by the Electrical Officer (Contracts) and approved, before commencement of

work.

“PREVIEW COPY ONLY”

Page 41: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 13 of 19

29.3 The handling of long lengths of material such as metal pipes, reinforcing bars, etc should be avoided, but if

essential they shall be handled as nearly as possible in a horizontal position below head height.

29.4 The Responsible Representative shall warn all persons under his control of the danger of being near “live”

high-voltage equipment, and shall ensure that the warning is fully understood.

29.5 Unauthorised staff working on these platforms must be directly supervised by an authorised person in

terms of clause 607.1.3 of the Electrical Safety Instructions. A Category C Certificate of Authority must be

obtained by Track Masters, Track Inspectors and on-track contractors’ supervisors. These grades must

attend the Permanent Way Supervisor electrical safety module (PWS) or Permanent Way Contractor

electrical safety module (PWC) training. A letter of training must then be issued by the School of Rail.

29.6 Where the conditions in 29.1 to 29.3 cannot be observed the Electrical Officer (Contracts), shall be notified.

He will arrange for suitable Safety measures to be taken. The Electrical Officer (Contracts), may in his

discretion and in appropriate circumstances, arrange for a suitable employee of the Contractor to be

specially trained by the network operator and at the Contractor’s cost, as an Authorised Person to work

closer than 3 metres from “live” overhead conductors and under such conditions as may be imposed by the

Senior responsible Electrical Engineer in the network operator.

30.0 USE OF EQUIPMENT

30.1 Measuring Tapes and Devices

30.1.1 Measuring tapes may be used near “live” high-voltage equipment provided that no part of any tape or a

person's body comes within 3 metres of the “live” equipment.

30.1.2 In windy conditions the distance shall be increased to ensure that if the tape should fall it will not be blown

nearer than 3 metres from the “live” high-voltage equipment.

30.1.3 Special measuring devices longer than 2 metres such as survey staves and rods may be used if these are of

non-conducting material and approved by the responsible Electrical Engineer in the network operator, but

these devices must not be used within 3 metres of “live” high-voltage equipment in rainy or wet conditions.

30.1.4 The assistance of the Electrical Officer (Contracts) shall be requested when measurements within the limits

defined in 30.1.1 to 30.1.3 are required.

30.1.5 The restrictions described in 30.1.1 to 30.1.3 do not apply on a bridge deck between permanent parapets nor

in other situations where a barrier effectively prevents contact with the “live” high-voltage equipment.

30.2 Portable Ladders

30.2.1 Any type of portable ladder longer then 2 metres may only be used near “live” high-voltage equipment under

the direct supervision of the Responsible Representative. He shall ensure that the ladder is always used in

such a manner that the distance from the base of the ladder to any “live” high-voltage equipment is greater

than the fully extended length of the ladder plus 3 metres. Where these conditions cannot be observed, the

Electrical Officer (Contracts) shall be advised, and he will arrange for suitable safety measures to be taken.

31.0 CARRYING AND HANDLING MATERIAL AND EQUIPMENT

31.1 Pipes, scaffolding, iron sheets, reinforcing bars and other material which exceeds 2 metres in length shall be

carried completely below head height near “live” high-voltage equipment. For maximum safety such material

should be carried by two or more persons so as to maintain it as nearly as possible in a horizontal position.

The utmost care must be taken to ensure that no part of the material comes within 3 metres of any “live”

high-voltage equipment.

31.2 Long lengths of wire or cable shall never be run out in conditions where a part of a wire or cable can come

within 3 metres of any “live” high-voltage equipment unless the Electrical Officer (Contracts) has been

advised and has approved appropriate safety precautions.

31.3 The presence of overhead power lines shall always be taken account of especially when communications

lines or cables or aerial cables, stay wires, etc. are being erected above ground level.

32.0 PRECAUTIONS TO BE TAKEN WHEN ERECTING OR REMOVING POLES, ANTENNAE, TREES ETC.

32.1 A pole may be handled for the purpose of erection or removal near high-voltage equipment under the

following conditions:

(i) If the distance between the point at which the pole is to be erected or removed and the nearest “live” high-

“PREVIEW COPY ONLY”

Page 42: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 14 of 19

voltage equipment is more than the length of the pole plus 3 metres, the work shall be supervised by the

Responsible Representative.

(ii) If the distance described in (i) is less than the length of the pole plus 3 metres, the Electrical Officer

(Contracts) shall be consulted to arrange for an Authorised Person to supervise the work and to ensure that

the pole is earthed where possible. The pole shall be kept in contact with the point of erection, and adequate

precautions shall be taken to prevent contact with “live” high-voltage equipment.

32.2 The cost of supervision by an Authorised Person and the provision of earthing shall, unless otherwise

agreed, be borne by the Contractor.

32.3 The provisions of clauses 32.1 and 32.2 shall also apply to the erection or removal of columns, antennae,

trees, posts, etc.

33.0 USE OF WATER

33.1 No water shall be used in the form of a jet if it can make contact with any “live” high-voltage equipment or

with any person working on such equipment.

34.0 USE OF CONSTRUCTION PLANT

34.1 "Construction plant" entails all types of plant including cranes, piling frames, boring machines, excavators,

draglines, dewatering equipment and road vehicles with or without lifting equipment.

34.2 When work is being undertaken in such a position that it is possible for construction plant or its load to come

within 3 metres of “live” high-voltage equipment, the Electrical Officer (Contracts) shall be consulted. He will

arrange for an Authorised Person to supervise the work and to ensure that the plant is adequately earthed.

The Electrical Officer (Contracts) will decide whether further safety measures are necessary.

34.3 The cost of any supervision by an Authorised Person and the provision of earthing shall, unless otherwise

agreed, be borne by the Contractor.

34.4 When loads are handled by cranes, non-metallic rope hand lines shall be used, affixed to such loads so as

to prevent their swinging and coming within 3 metres of “live” high-voltage equipment.

34.5 Clauses 34.1 to 34.4 shall apply mutatis mutandis to the use of maintenance machines of any nature.

35.0 WORK PERFORMED UNDER DEAD CONDITIONS UNDER COVER OF A WORK PERMIT

35.1 If the Responsible Representative finds that the work cannot be done in safety with the high-voltage electrical

equipment “live”, he shall consult the Electrical Officer (Contracts) who will decide on the action to be taken.

35.2 If a work permit is issued the Responsible Representative shall-

(i) before commencement of work ensure that the limits within which work may be carried out have been

explained to him by the Authorised Person who issued the permit to him, and that he fully understands these

limits.

(ii) sign portion C of the permit before commencement of work;

(iii) explain to all persons under his control the limits within which work may be carried out, and ensure that

they fully understand these limits;

(iv) care for the safety of all persons under his control whilst work is in progress; and

(v) withdraw all personnel under his control from the equipment on completion of the work before he signs

portion D of the work permit.

36.0 TRACTION RETURN CIRCUITS IN RAILS

36.1 DANGEROUS CONDITIONS CAN BE CREATED BY REMOVING OR SEVERING ANY BOND.

36.2 Broken rails with an air gap between the ends, and joints at which fishplates are removed under "broken

bond" conditions, are potentially lethal. The rails on either side of an air gap between rail ends on electrified

lines shall not be touched simultaneously until rendered safe by the network operator personnel.

36.3 The Contractor shall not break any permanent bonds between rails or between rails and any structure. He

shall give the Contract Supervisor at least 7 days written notice when removal of such bonds is necessary.

36.4 No work on the track which involves interference with the traction return rail circuit either by cutting or

“PREVIEW COPY ONLY”

Page 43: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 15 of 19

removing the rails, or by removal of bonds shall be done unless the Electrical Officer (Contracts) is

consulted. He will take such precautions as may be necessary to ensure continuity of the return circuit before

permitting the work to be commenced.

37.0 HIGH-VOLTAGE ELECTRICAL EQUIPMENT NOT MAINTAINED AND/OR OPERATED BY THE

NETWORK OPERATOR

Where the work is undertaken on or near high-voltage electrical equipment which is not maintained and/or

operated by the network operator, the Occupational Health and Safety Act No. 85 of 1993, and Regulations

and Instructions, or the Mines Health and Safety Act (Act 29 of 1996), shall apply.

Such equipment includes:-

(i) Eskom and municipal equipment;

(ii) The Contractor's own power supplies; and

(iii) Electrical equipment being installed but not yet taken over from the Contractor.

END

“PREVIEW COPY ONLY”

Page 44: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 16 of 19

APPENDIX 1

HORIZONTAL CLEARANCES 1065mm GAUGE

Comment [JC1]: Check latest drawings

“PREVIEW COPY ONLY”

Page 45: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 17 of 19

APPENDIX 2

VERTICAL CLEARANCES 1065mm GAUGE

“PREVIEW COPY ONLY”

Page 46: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 18 of 19

APPENDIX 3

CLEARANCES 610mm GAUGE

“PREVIEW COPY ONLY”

Page 47: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

E7/1 Issue 2010

Transnet Limited Registration Number 1990/00900/06 Page 19 of 19

APPENDIX 4

PLATFORM CLEARANCES

“PREVIEW COPY ONLY”

Page 48: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 49: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

“PREVIEW COPY ONLY”

Page 50: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE

Doc. No. : PRC-00112

Author : F Nel Page 1 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

WRITTEN SAFE WORK PROCEDURE FOR ERECTION OF

SELF-SUPPORTING OPTICAL FIBRE CABLE ON AC OHTE

PRC-00112 APRIL 2008

Revision 2.00

NON-DISCLOSURE OF INFORMATION

Information contained in this document is proprietary in nature and/or protected by copyright.

Please obtain written permission from the Author prior to reproducing this document, in whole or in part.

“PREVIEW COPY ONLY”

Page 51: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 2 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

TABLE OF CONTENTS

I DOCUMENT AUTHORISATION............................................................4

II DISTRIBUTION ...................................................................................4

III DOCUMENT CHANGE HISTORY .........................................................4

IV CHANGES SINCE LAST REVISION......................................................4

V ABBREVIATIONS, ACRONYMS AND DEFINITIONS .............................5

VI RELEVANT DOCUMENTATION ...........................................................5

1. SPECIFIC RISKS IDENTIFIED FOR THIS PROCEDURE ......................6

1.1 Specific Risks Associated with the OFC Construction Activity ..6

1.2 Scope and Purpose ...................................................................6

1.3 The following Annexures Form Part of these Instructions and Procedure ..........................................................................7

2. GENERAL SAFETY PRECAUTIONS .....................................................8

3. INSTALLATION (Methodology) ...........................................................10

3.3 Erection of OFC on AC Traction Masts....................................10

3.4 Cable Slack.............................................................................12

3.6 Intermediate Poles ..................................................................13

3.7 Underground Installation........................................................13

ANNEXURE 1 : SAFE WORKING PROCEDURE, PHOTOGRAPHS ..............15

DAILY SAFETY WORK INSTRUCTIONS FOR THE INSTALLATION OF OPTICAL FIBRE CABLE ON OHTE....................................................19

4. GENERAL .........................................................................................19

5. REGULATIONS WITH REGARD TO SAFETY CLOTHING....................19

6. FLAGMEN.........................................................................................19

7. RULES THAT ARE APPLICABLE WHEN WORK IS DONE NEXT TO THE RAILWAY LINE.....................................................................20

8. SAFETY ASPECTS.............................................................................20

9. ELECTRICAL SHOCK........................................................................21

ELECTRICAL SHOCK INCIDENT AWARENESS .........................................24

10. CERTIFICATION................................................................................24

“PREVIEW COPY ONLY”

Page 52: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 3 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

11. WORK NOT PERMITTED WHILE ELECTRICAL EQUIPMENT IS "LIVE" ...........................................................................................25

12. WORK ON THE OUTSIDE OF ROLLING STOCK (INCLUDING LOADING OR UNLOADING) ..............................................................25

13. WORK PERMITS ...............................................................................26

14. WORK TO CLEARANCE FROM..........................................................27

15. IN GENERAL.....................................................................................27

“PREVIEW COPY ONLY”

Page 53: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 4 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

I DOCUMENT AUTHORISATION

FUNCTION NAME TITLE & DIVISION SIGNATURE DATE

Compiled by :

BG Nel Technologist, Quality Assurance

Reviewed by :

FJ Nel Head of Department, Technical Execution

Authorised by :

ML Nuttall Divisional Manager, Transmission

Approved : CF du Toit Senior Engineer, Infrastructure Electrical (OHTE)

II DISTRIBUTION

Once updated, a copy of the latest revision will be published in the document management system in use. E-mail to this effect will be sent to the relevant personnel or heads of department.

III DOCUMENT CHANGE HISTORY

ISSUE NO. DATE ISSUED ISSUED BY HISTORY DESCRIPTION

1.00 April 2008 Technical Execution New document

2.00 June 2008 Technical Execution Addition of OHTE requirements

IV CHANGES SINCE LAST REVISION

CLAUSE DESCRIPTION

Document Addition of OHTE requirements

“PREVIEW COPY ONLY”

Page 54: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 5 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

V ABBREVIATIONS, ACRONYMS AND DEFINITIONS

ABBREVIATIONS

AND ACRONYMS DESCRIPTION

AC Alternating Current

As-Build Drawings Final drawings of a site and/or route installation of transmission infrastructure as presented to the customer at handover.

BS British Standard

DC Direct Current

GPS Global Positioning Satellite (a system whereby the latitude and longitude co-ordinates of any site on earth can be determined via a GPS receiver)

HDPE High Density Polyethylene

kV Kilo-volt

Nm Newton Meters

OFC Optical Fibre Cable

OHTE Overhead Traction Equipment

OTDR Optical Time Domain Reflectometer

PPE Personal Protective Equipment

QAD Quality Assurance Department

SOP Standard Operating Procedure

UV Ultra Violet

SPECIFICATIONS

SPECIFICATION NO. DESCRIPTION

SPC-00575 Specification for the erection of self support OFC on overhead track structures.

SPC-00029 Specification for trenching, laying and hauling in of telecommunication cables.

VI RELEVANT DOCUMENTATION

RELEVANT DOCUMENT

NO. DESCRIPTION

INS-00007 Risk, PPE, Clearances

Document Electrical Shock Incident Awareness

Document Safe Work Procedure : Step-by-Step of how to Raise the OFC Bracket Past Backstraps

“PREVIEW COPY ONLY”

Page 55: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 6 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

1. SPECIFIC RISKS IDENTIFIED FOR THIS PROCEDURE

1.1 Specific Risks Associated with the OFC Construction Activity

1.1.1 The erector will be handling insulated tools (poles) which could make direct contact with "live" equipment.

1.1.2 The erector will be manipulating conductive brackets near "live" electrical equipment. Should such a bracket bridge out an insulator, the mast structure will become "live" and a person can be electrocuted.

1.1.3 Strong winds and rain may cause the workman to loose control of the installation tools – (work in strong winds and rain prohibited).

1.1.4 In tunnels, under bridges and in station yards the "live" equipment do not follow the usual open line structure pattern and safe working clearances may be compromised.

1.1.5 The removal of trees which foul the route near the "live" OHTE.

1.1.6 The erecting of additional OFC support poles in the rail servitude near the "live" electrification equipment (specifically the use of vehicle mounted cranes)..

1.1.7 Passing trains.

1.2 Scope and Purpose

1.2.1 This safe work procedure covers the erection of self-supporting optical fibre cable on 25 kV and 50 kV AC overhead high tension electrification (OHTE) masts for Freight Rail, a Division of Transnet Limited.

1.2.1.1 The installation methodology is to use special brackets and insulated tools (sticks) to do these installations "remotely" i.e. from formation level.

1.2.1.2 Where possible, construction will mostly take place under live traction power conditions and with the normal operation of train services.

1.2.1.3 This procedure generally covers safety precautions and safe working procedures during construction.

1.2.1.4 The Electrical Officer (Contracts) appointed for the section shall at his own discretion decide if any procedure is safe or not and inform the Transport Telecom, Project Manager or Supervisor accordingly.

“PREVIEW COPY ONLY”

Page 56: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 7 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

1.2.2 The objective is to install the major component of the cable above ground. Underground sections should be kept to a minimum. Underground trenches, Rail Pipe Crossings and Pipe and Chamber systems may be required or utilised where these exist.

1.2.3 To avoid additional splices the same optical fibre cable must be utilised for aerial and buried sections. The OFC will be of the all-dielectric aerial self-support type. On AC sections OFC with anti-tracking sheath shall be used.

1.2.4 This document focuses on safety and safe work procedures and must be read in conjunction with Specification SPC-00575 for the Engineering Requirements for the Installation of Optical Fibres on overhead track structures. Please note that although some sections and clauses are similar, this document does not replace above specification. For any safety related requirement, this document takes preference.

1.2.5 This procedure also sets the minimum standards for materials, tools and techniques to be used in aerial optical fibre cable installations, and may not be deviated from without the permission of the Transport Telecom, Project Manager and Electrical Officer (Contracts).

1.2.6 Where reference is made to approved materials, tools or techniques, this approval must be obtained from Transport Telecom, Project Manager, who will co-ordinate any necessary interfacing with the Electrical Officer (Contracts) and relevant authorities.

1.3 The following Annexures Form Part of these Instructions and Procedure

1.3.1 E7/1 : Specification for works on, over, under or adjacent to railway lines and near high voltage equipment.

1.3.2 E.4E : Safety arrangements and procedural compliance with the occupational health and safety Act; Act 85 of 1983 and regulations.

1.3.3 Annexure 1 : Safe working procedure, photographs and methodology (with DVD) on Safety Shield and tools (Installation procedure to remotely install cable support to traction masts in AC electrified sections).

1.3.4 DVD on Electrical Safety Awareness.

1.3.5 Daily Safety Work Instruction for the Installation of Optical Fibre Cable on OHTE (INS-00007).

1.3.6 Electrical Shock Incident Awareness.

1.3.7 Contractors Induction to Safe Working Procedures.

“PREVIEW COPY ONLY”

Page 57: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 8 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

1.3.8 Installation Guidelines for the safe positioning of OFC on OHTE structures from Senior Manager Electrical (Infra Maintenance) (S.PL&T) 1 CAO/13/3/1/6 of 9 November 2001.

2. GENERAL SAFETY PRECAUTIONS

2.1 Due to the proximity of live conductors the installer must ensure that his employees installing the cable on the masts obtain a Category C certificate from the relevant authorities before any work can be carried out on the masts.

2.2 The Contractor's employees must be trained for competence and understanding of the basic electrical safety requirements. The certificate obtained will not be transferable. The cost of the training will be borne by the Installer or Freight Rail as stipulated in the contract document.

2.2.1 The supervisor of the team must have a Letter of Training in his possession on site. This letter of training involves successful completion of the INFR and COM modules presented at accredited Training Schools. INFR involves supervision of staff in the permanent way environment and COM involves signing of work permits, which is required when installing fly-over crossings. On successful completion of the person will hold a yellow SPOORNET 436 card.

2.2.2 All workers who will handle the OFC or associated brackets on the electrification structures must hold a valid Category C certificate. This requires (a) successful attendance of a 5-day course held at an accredited

Training School, and (b) certification by an examining officer appointed for each

infrastructure depot. In completion the person will have a G-Green certificate, which must be carried on his person.

2.2.3 An Electrical Officer (Contracts), being an official from the Infrastructure Depot, must be appointed for every contract. The Contract's Project Manager must advise the contractor who this person is and arrange initial consultation between the parties.

2.2.4 Whenever OFC cables must cross over the Electrification, a work permit must be arranged. The electrical Officer (Contracts) must be consulted to ensure that timeous arrangements are made. This notice period can be 3 weeks or longer.

2.2.5 Flagmen must be deployed in terms of the General Appendix Chapter 11.

2.3 The installer and his employees installing the cable must be fully conversant with the Electrical Safety Instructions, Transnet specifications E.7/1 and E.4E and other safety documentation and instructions referred to in this document.

“PREVIEW COPY ONLY”

Page 58: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 9 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

2.4 A person authorized with a Category C certificate must maintain the prescribed clearance for the electrification voltage applicable.

2.5 The brackets to be fitted to OHTE masts by means of remote tools (sticks) must always be "under control" by the workmen using the tools to prevent accidental "flash-over" (possible bridging-out of insulators).

2.5.1 Where the face of the mast is open (not obstructed) the bracket must be opened marginally to allow easy sliding up the mast, without the risk of the bracket dislodging from the mast.

2.5.2 Where the mast is fitted with one or two backstraps and the OFC bracket must be lifted past these backstraps, a safety shield with ring (as per the safe working procedure) must be used to keep the tools "under control".

2.6 In all instances where the safety of workmen is jeopardised, electrical permits and/or track occupations must be requested. The Electrical Officer (Contracts) will decide where occupations are required. Notification could be required up to four (4) weeks in advance.

2.7 Under bridges where live cross span wires are involved and at make off masts and where the live conductors approach the optical fibre cable very closely, a standard warning board must be fitted. Electrical personnel must be approached to arrange for a work permit to fit the cable and warning boards.

2.8 No attempt must be made to install the cable in windy conditions, especially when the sag (before tensioning) is blown in the direction of the track. Supervisors must use their discretion in this regard.

2.9 No metal ladders will be allowed for construction but only wooden or fibreglass ladders.

2.10 Remote AC bracket installation tool (sticks) must be kept clean may not be used in wet or rainy conditions. This tool must be tested for 50 kV isolation and approved by Freight Rail, Technology Management Department and carry a marking to that effect.

2.11 Hard hats, protective clothing and safety boots must be worn during construction.

2.12 Optical fibres are extremely thin and can easily penetrate skin and eyes. Any off cuts or bare pieces of fibre must be properly disposed of in sealed containers. Optical fibres are categorised as hazardous materials and require special disposal measures.

“PREVIEW COPY ONLY”

Page 59: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 10 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

2.13 Care must be taken whilst testing as the laser in test equipment produces an invisible light, which can cause permanent eye damage. All fibres should be treated as "lit".

2.14 All personnel involved in the installation and testing must be made aware of the above safety aspects by attending the "Induction Training" and viewing the relevant Freight Rail Safety DVDs and any other materials that the Project Manager deems necessary.

2.15 A Safety Plan as required by Freight Rail must be submitted before any work may commence. Details of the Safety plan may be obtained from the Project Manager.

2.16 A Site Safety File as required by Freight Rail must be available on site and kept current. Details and content of the Site Safety File may be obtained from the Project Manager.

2.17 The Installer must comply with the "Installation Work Procedures for the Installation of Optical Fibre Cable" (latest version).

3. INSTALLATION (Methodology)

3.1 This portion is included to allow the Project Supervisor and Electrical Officer (Contracts) to identify safety and risk situations before work commences and recommends specific requirements.

3.2 Preparation must be carried out on the route on which the cable is to be erected. Trees, bushes and grass must be cut so that work can be carried out without any obstacles. The aerial route must be at least three (3) metres clear of bush and trees within the reserve. Where excessive trees or bush, which could become a fire hazard, are encountered, an alternative route must be chosen. Tree branches overhanging the cable must be removed.

3.3 Erection of OFC on AC Traction Masts

3.3.1 Fit the universal multipurpose bracket at ±1,5 metres above ground level.

3.3.2 Fit a pulley/sling on every suspension bracket (at a working height) for a distance equivalent to the length of the cable to be hauled in.

3.3.3 Place the OFC drum with cable away from the mast where the cable will pass through the first pulley/sling. This would prevent the cable from bending too much whilst being hauled. Under no circumstances should the cable be bent excessively. The OFC drum should be placed on cable jacks with an axle. The rate of the hauling should be controlled from this point.

“PREVIEW COPY ONLY”

Page 60: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 11 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

3.3.4 The cable must be fed off the drum according to the speed with which the cable is hauled. Care must be taken that the cable is not tightening between the drum and the first pulley. A constant tension must be maintained on the cable by braking of the cable drum when necessary. Tension must be maintained to ensure minimum OFC contact with the ground.

3.3.5 OFC hauling should be avoided on very windy days, especially if the wind blows the cable in the direction of the track.

3.3.6 The hauling team must haul the cable evenly and slowly to prevent the cable from jerking which can result injuring workers or in broken fibres.

3.3.7 Good communication between persons at the drum, alongside the cable-end and the hauling team, is absolutely essential and must be available at all times. If communication breaks down, the hauling must be stopped immediately until such time that the communication had been re-established.

3.3.8 When hauling the cable, a person, in full communication with the team, must walk alongside the cable-end to ensure that the cable is taking the designated route. The OFC must not twist, especially at angle-masts where the possibility of twisting is great. When the cable starts twisting, hauling must be stopped immediately. The cause of the problem must then be pinpointed and rectified.

3.3.9 The cable sag and tension under normal installation conditions may vary around bends. Special care must be taken when the cable is removed from the pulley or sling and placed onto the termination fitting so that the cable does not exceed the prescribed tension.

3.3.10 A termination bracket and fitting (dead end) must be installed at the beginning of each length. Where only false terminations occur in a cable section the cable must be tensioned sequentially for every false termination section.

3.3.11 The cable shall be tensioned by means of an approved device at the far end and the tension shall be continually monitored not to exceed the parameters provided by the cable manufacturer.

3.3.12 On sections with a number of angle masts, it may be required to tension the cable over shorter distances. In this case care should be taken not to damage the cable at the intermediate tensioning points.

“PREVIEW COPY ONLY”

Page 61: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 12 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

3.3.13 Sufficient time shall be allowed for the tensioned cable to settle. This time is when there is no longer a movement on the tensioning scale. When the correct tension has been achieved, the suspension (PLP) and termination (PLP) fittings shall be fitted.

3.3.14 The cable must be marked at all anchor points in an approved manner to indicate possible slippage.

3.3.15 The site supervisor must record the final stringing tensions and terminated span lengths on a control sheet. The site supervisor must submit these sheets with the site diaries for scrutiny and retention.

3.3.16 Once tensioning and splicing of the cable is completed, the suspension brackets shall be moved sequentially and incrementally up the masts in at least three steps with various lengths of installation tools to the correct final position on the mast. Note that although approved non-conductive tools will be used, the installation teams shall avoid touching any high voltage carrying infrastructure at all times.

3.3.17 The splicing team must strive to keep-up with the hauling team. If this is not the case, additional labour will be is required to lower and raise the cable especially for splicing purposes.

3.4 Cable Slack

3.4.1 At positions where it may be required to accumulate cable slack due to the nature of the route, this slack must always be coiled in a figure of eight to avoid twisting of the cable. In muddy or dusty conditions the figure of eight must be done on a ground sheet to avoid soiling of the cable.

3.4.2 After the hauling process, sufficient slack must be left for splicing purposes. Less cable slack is required for AC-type joint splicing as the joint closure is moved up with the cable, but sufficient slack must however be left for splicing purposes.

3.4.3 Ten (10) metres OFC on the hauling end, must be cut off by the installation team. The installer must ensure that this length is cut off during the installation process.

3.4.4 The slack shall be coiled in two separate coils of minimum 500 mm diameter, tied with UV stabilised coated stainless steel cable ties at four positions and secured on the PLP dead-end. See drawing TC 000172 for details.

3.4.5 A small amount of slack only, between 250 mm and 300 mm (sag), must be allowed at false terminations.

“PREVIEW COPY ONLY”

Page 62: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 13 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

3.5 In order to avoid sharp angles in the vertical plane when going over or under bridges a gradual increase or decrease of the route shall be obtained by adjusting the suspension brackets upwards or downwards on the masts, but only as directed by the Electrical Officer (Contracts).

3.6 Intermediate Poles

3.6.1 Intermediate telephone poles (where required) must be installed where span lengths exceed 70 metres or where the cable veers away from the track for any reason. Intermediate poles must be of the wooden, steel or concrete telephone type. The ground clearance of the suspended cable must not be less than 7,0 metres.

3.6.2 Where the intermediate wooden pole is in the danger of burning, a 2 metre high-galvanised metal sleeve must be fitted around the base of the pole. In high theft areas, concrete poles may be required.

3.6.3 The Project Manager must obtain approval from the Electrical Officer (Contracts) for the erection of intermediate wooden, steel or concrete poles in the vicinity of electrified tracks. If the pole is planted closer to the OHTE than its length (in the case of the pole falling over), permits (dead orders) must be arranged in conjunction with the Electrical Officer (Contracts).

3.6.4 To make the poles more visible at night, a reflective band of UV resistant material must be fixed to the pole next to service or other roads at 1,5 metres above ground level. Pole stays must also be fitted with reflective boards.

3.7 Underground Installation

3.7.1 At all instances where it becomes necessary to install the cable underground the cable must be protected as follows :

3.7.1.1 High-density polyethylene conduit of minimum 40 mm diameter.

3.7.1.2 Approved concrete slabs placed longitudinally over the cable and duct if a depth of 800 mm cannot be achieved.

3.7.1.3 A combination of the methods above, depending on the class of protection required.

3.7.2 To protect workmen and other parties, open trenches must be barricaded if left open overnight or for a considerable time. In general pedestrian areas, illumination shall be used after dark as stipulated in specification No. SPC-00029.

“PREVIEW COPY ONLY”

Page 63: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 14 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

3.7.3 Warning tape with a distinctive marking, i.e. "optic fibre cable" must be installed above the cable and 300 mm below ground level.

3.7.4 Track crossings must be in accordance with specification E7/1 and Specification SPC-00029. On specific lines, Transnet could insist on doing the track crossings themselves.

3.7.5 Cable markers must be provided and planted wherever the cable is laid in the ground. Cable markers must be planted as stipulated in specification No. SPC-00029. The fibre optic marker shall have a distinctive mark, i.e. OFC, and must be painted yellow.

Continued on next page

“PREVIEW COPY ONLY”

Page 64: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 15 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

ANNEXURE 1 : SAFE WORKING PROCEDURE, PHOTOGRAPHS

SAFE WORK PROCEDURE

Installation procedure to remotely install cable support to traction masts in AC electrified traction section.

Rev 1.00

March 2008

NOTE : This procedure and the Safety Fitting DVD must be viewed simultaneously.

Example of the safety shield.

This unit must be used to safeguard the installation of a cable bracket. The shield must be used on traction masts fitted with back straps. The purpose of the shield with ring is to prevent "flashover" and guide the cable tools when the cable bracket needs to be lifted over a back strap.

The safety shield in the final clamped position, before the tools are inserted through the ring.

“PREVIEW COPY ONLY”

Page 65: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 16 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

Example of a remote installation tool. (Link Stick). The profile of the cutout prevents the bracket from dislocating from the tool.

Remote cable support bracket and remote installation tools, lifting the cable to designated height.

Location of back straps indicated. Where necessary the bracket and cable must be lifted past these back straps.

“PREVIEW COPY ONLY”

Page 66: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 17 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

Step 1) by using the ETSA – mast (I-beam) as a guide, slide the cable bracket and cable to the lower end of the back strap and temporarily secure the unit.

In the same manner slide the safety shield and ring up to the cable support bracket and secure the unit.

Loosen the cable support bracket and lift the bracket from position "A" to "B". “PREVIEW COPY O

NLY”

Page 67: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 18 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

By using the guide ring of the safety bracket to guide the Link Sticks, move the cable bracket to the final clamping position on the mast.

Clamp the cable bracket to the allocated position on the mast.

Remove the Link Sticks

“PREVIEW COPY ONLY”

Page 68: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 19 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

Unlock the safety shield and slide it down the mast. Remove the safety shield.

DAILY SAFETY WORK INSTRUCTIONS FOR THE INSTALLATION OF OPTICAL FIBRE CABLE ON OHTE

4. GENERAL

4.1 These safety rules must be conveyed every morning in a very simple manner to all workmen.

4.2 A translator must be used to translate and explain the rules to co-workers.

4.3 In the case of new workers or workers that have no previous experience of work next to railway lines or on electrification traction masts, assurance should be obtained that these workers have a proper understanding of these safety rules.

5. REGULATIONS WITH REGARD TO SAFETY CLOTHING

5.1 All workers must wear safety boots when working with heavy materials. Safety boots can prevent an injury if a heavy object drops on a worker's foot.

5.2 Reflective safety vests must be worn at all times to assist train divers and flagmen with visibility and assist to warn workers timeously. Nametags and Employer Name must be attached to safety vest.

5.3 Safety helmets must be worn when workers are exposed to falling objects and on all "Construction" sites.

6. FLAGMEN

6.1 Flagmen must blow a whistle or hooter when a train approaches.

6.2 Workers must ascertain themselves on which track and from which direction the train approaches, before standing clear.

“PREVIEW COPY ONLY”

Page 69: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 20 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

6.3 Emphasis must be placed that MOST ACCIDENTS occur when workers stand clear from one train and accidentally move in front of another passing train.

7. RULES THAT ARE APPLICABLE WHEN WORK IS DONE NEXT TO THE RAILWAY LINE

7.1 The second MOST injuries occur when passing trains hit tools and equipment used by workmen. Tools like picks, shovels and materials like cable, clamps and cable sticks must never be placed on or near railway lines.

7.2 All work must stop when a train passes the work site. Workers, tools and materials must be kept at a safe distance.

7.3 A suitable certified person must determine if it is safe to work on a ladder. If it is not safe, the certified worker must carry out the work.

7.4 Only fibreglass ladders will be allowed.

7.5 Workers must not cross the tracks unnecessarily, but remain on the side where the work is being carried out. Works may NOT sit or rest on the railway line.

8. SAFETY ASPECTS

8.1 It must be explained to all workers how dangerous the overhead lines are. If any metal object should touch the wire, the metal will conduct electricity and cause serous injury or death.

8.2 Thus NO metal ladders are allowed.

8.3 When carrying metal materials like "ducting" or metal pipes, it must be carried horizontally by at least two (2) workers.

8.4 It must be emphasised that non-metallic objects like wooden poles will conduct electricity in wet weather conditions.

8.5 No person will be allowed to work on an electrification mast without a valid C-Category certificate.

8.6 Any person using push-up sticks must be in possession of a valid C-Category certificate.

8.7 Under NO circumstances must work be carried out on electrical traction masts when they are or wet and damp.

8.8 For the fitting of push-up brackets, push-up sticks must be constructed of Transnet approved materials (pantograph sticks).

8.9 The push-up sticks must be clean and dry or else it may conduct electricity. Regardless, contact with the overhead traction conductors must be avoided at ALL

times.

“PREVIEW COPY ONLY”

Page 70: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 21 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

9. ELECTRICAL SHOCK

9.1 Remember all overhead wires are dangerous. All wires must be treated as live!

9.2 Breakdowns of electric wires must be treated as "live and dangerous" STAY CLEAR!!!!

9.3 Treatment of electrical shock when person still in contact with live equipment :

� Keep hand off + call the doctor

� Advise electrical control : 1. Have power switched off.

2. Section to be earthed.

3. Work permit to be issued

� Apply fist aid when safe.

9.4 The voltage of overhead and underground power lines must always be considered dangerous, even with the line "earthed".

9.5 Ladders must always be used in such a manner that the distance from the base of ladder to any "live" equipment is greater than the fully extended length of ladder, plus three (3) metres.

9.6 Ladders must be secured to the mast at the top with safety strap. Ladder carriers / General Workers must hold ladders in position to prevent slipping.

9.7 When working within signal gantry make sure that you take up a safe potion to ensure that no portion of your body, tools or equipment hang or project beyond or below the restricted barriers provided.

9.8 Do not leave the gantry access way.

9.9 Category "C" safe working clearances form "live" high voltage electrical equipment :

3 kV DC – 900 mm . 25 kV AC – 1,2 m . 50 kV AC – 1,7 m .

9.10 Workers must present "C" certificate at any time on request.

“PREVIEW COPY ONLY”

Page 71: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 22 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

NB : This portion MUST be placed on

the Site Safety File

FIBRE OPTIC INSTALLATION TEAM DAILY PERSONNEL SAFETY CHECK LIST AND INFORMATION SESSION

PROJECT NO. :

PROJECT DESCRIPTION :

SECTION :

DATE : TEAM : NO. OF WORKERS :

I HEREBY CERTIFY THAT THE SAFETY CLEARANCES WITHIN WHICH WORK MAY BE CARRIED

OUT ARE EXPLAINED TO ME IN DETAIL.

NAME :

(Team leader)

DATE : TIME :

NAME :

NAME :

NAME :

NAME :

NAME :

NAME :

NAME :

NAME :

NAME :

NAME :

NAME OF PERSON GIVING INSTRUCTION :

NAME OF INTERPRETER :

“PREVIEW COPY ONLY”

Page 72: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 23 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

A. PROTECTIVE CLOTHING CHECK

YES NO REMARKS

Reflective Vests

Safety Shoes

Gloves

Sun Glasses

Hard Hats

B. EQUIPMENT CHECK

NUMBER YES NO REMARKS

Ladder

Ladder

Ladder

Safety Belt

Safety Belt

Safety Belt

First Aid Kit

First Aid Kit

“PREVIEW COPY ONLY”

Page 73: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 24 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

C. IMPORTANT TELEPHONE NUMBERS

NAME TEL. NO.

Team Supervisor

Regional Engineer

(Electrical)

Maintenance Manager

(Electrical)

Electrical Officer in

charge

Electrical Control

Office

ELECTRICAL SHOCK INCIDENT AWARENESS

10. CERTIFICATION

10.1 It is of the utmost importance that candidates be correctly assessed as to their temperamental suitability, their theoretical knowledge, practical competence and intimate knowledge of the high voltage equipment in the particular area for which the certificate of authority will be valid.

10.2 The candidate has attended the applicable prescribed training courses and has passed the relevant qualifying examinations.

10.3 The candidate is in possession of all relevant instruction and regulation books and has access to all relevant electrical diagrams and drawings.

10.4 The candidate has received adequate additional local training in the work situation on the relevant equipment (to be specified on the certificate of authority) and has had reasonable time and opportunity to acquaint him with the equipment and layout of the area.

10.5 Special attention should be afforded to the candidate's ability to apply portable earth connections and the correct use of earthing devices.

10.6 For working on "live" 3 kV DC overhead track equipment, special attention should be given to the candidate's observance of clearances as laid down in clause 603.1 of the Electrical Safety Instructions. The candidate must be tested to ensure thorough acquaintance with all electrical hazards involved when doing "live" working.

10.7 The Departmental Head shall maintain a database for certificates and letters of authority.

“PREVIEW COPY ONLY”

Page 74: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 25 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

10.8 The officer who issues, renews or withdraws a certificate or letter of authority shall advise the database maintainer.

10.9 The officer who issues, renews or withdraws certificates of authority that includes switching must also advise "Control".

10.10 "Control" shall keep an accurate and complete record of such certificates.

10.11 Each depot or office from which certificates or letters of authority are issued shall depute a specific person to be responsible for keeping a complete and accurate record of all certificates and letters of authority. This person must ensure that authorised employees attend refresher courses before their authorities expire.

10.12 The officer who issues, renews or withdraws a certificate or letter of authority shall advise the person responsible for keeping the record of any issues, renewals or withdrawals.

10.13 A copy of the advice shall be placed on the employee's staff file and copies shall also be sent to the department concerned for retention on the employee's control office file and to the department responsible for the training.

10.14 A check of the certificates and letters of authority shall be arranged annually by the depot engineer / Technical Manager to ensure that the records kept at depots are correct.

11. WORK NOT PERMITTED WHILE ELECTRICAL EQUIPMENT IS "LIVE"

11.1 All electrical equipment and all electric wires may be "live" and dangerous and must not be touched. Even loose or broken wires lying on the ground may still be "live" and must be avoided.

11.2 No person may climb any pole or structure which supports exposed "live" overhead wires or electrical equipment.

11.3 No person may climb, ride or work on the roof of, or on the top of any load or equipment carried on any rail or road vehicle or any machine under exposed "live" overhead wires.

12. WORK ON THE OUTSIDE OF ROLLING STOCK (INCLUDING LOADING OR UNLOADING)

12.1 No person may stand, climb or work whilst on any platform, surface or foothold higher than the normal unrestricted access way, namely –

12.1.1 the floor level of wagons,

12.1.2 external walkways on diesel, steam and electric locomotives, steam heat vans, etc. and

“PREVIEW COPY ONLY”

Page 75: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 26 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

12.1.3 walkways between passenger coaches and locomotives.

12.2 When in the above positions –

12.2.1 no person may raise his hands or any equipment he is handling above his head,

12.2.2 the handling of long lengths of material such as metal pipes, etc. should be avoided, and only if essential must be handled as close as possible to the horizontal position below head height,

12.2.3 responsible persons must always warn all persons under their control against the dangers involved with exposed "live" wires,

12.2.4 no person may whilst on electric rolling stock approach or work on any part of the pantograph, hooter or other roof equipment, except the headlight, and

12.2.5 train personnel may give the recognised hand signals from the floor and steps of wagons and recognised positions on locomotives not higher than footplate level.

13. WORK PERMITS

NOTE : A work permit is a written application and an authority to proceed with work on high-voltage electrical equipment after it has been isolated and earthed. It is an assurance that the equipment has been made "dead" and that it will not again be made "live" until the permit has been cancelled.

13.1 Work on high-voltage electrical equipment which has been isolated and earthed may only be undertaken under cover of a work permit, unless otherwise provided in these instructions.

13.2 Work boundaries within which work may be carried out must be pointed out to personnel in the most suitable manner. The method used must take into account the competence of the personnel concerned.

NOTE : A work permit will provide safety to personnel only if the work boundaries within which work may be carried out are completely clear to all persons concerned and are constantly observed by them.

13.3 The work boundaries can be pointed out by using a physical means of identification, e.g. the earth connections where they can be placed in conspicuous positions, warning notices, flags or conspicuously coloured tapes suitably attached to the overhead equipment. In cases of particular danger the work boundaries concerned must be effectively marked at suitable intervals, e.g. in a yard where a "live" line may overlap a work permit area.

“PREVIEW COPY ONLY”

Page 76: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

PROCEDURE SAFE WORK : ERECTION OF SELF-SUPPORTING OPTICAL

FIBRE CABLE ON AC OHTE REVISION 2.00

Doc. No. : PRC-00112

Author : F Nel Page 27 of 27 I:\ad\CrtlDocs\PRC\PRC-00112 Safe Work for Erection of Self Supporting

Optical Fibre Cable on AC OHTE Rev 1.doc

14. WORK TO CLEARANCE FROM

14.1 An authorised person, category A or C, or a person issued with a letter of authority may undertake work to clearance from exposed "live" high-voltage electrical equipment under the following conditions :

14.1.1 The authorised person must select a safe working position on or close to the de-energised equipment or structures where he is required to work.

14.1.2 The person must choose a safe route to and from this working position.

14.1.3 While in the safe working position and moving to and from it, the person must ensure that with outstretched arms, no part of his body or the tools or equipment he is handling, come within the safe clearances to adjacent exposed "live" high-voltage electrical equipment laid down in the following table :

SAFE CLEARANCE (ANNEXURE 6.1) TRACTION SYSTEM

CATEGORY A CATEGORY C

3 kV DC 600 mm 900 mm

25 kV AC 900 mm 1,2 m

50 kV AC 1,4 m 1,7 m

NOTE : The clearances given in this table are the minimum safe working distances. The greatest care must always be taken when working near exposed "live" equipment, and whenever possible greater clearances should be observed. Where working barriers can be used this should be done in preference to working at the clearances permitted.

14.1.4 Where safe working clearances cannot be observed from the exposed "live" equipment, approved portable working barriers must be employed by all persons in all cases, or work must be done with the equipment "dead" under cover of a work permit.

15. IN GENERAL

15.1 Place ladders in a safe position and keep them steady.

15.2 When you see that someone is working unsafely ensure that you go through the STOP process.

15.3 We must create a culture where we look after each other.

END OF DOCUMENT

“PREVIEW COPY ONLY”

Page 77: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

DO

NO

T S

CA

LE /

IF IN

DO

UB

T A

SK

2006

0146

7

RA

ILW

AY

BR

AC

KE

TP

RO

JEC

T N

UM

BE

R

LaserFab

THIS

DO

CU

ME

NT

ISTH

E P

RO

PE

RTY

OF

LAS

ER

FAB

AN

D M

AY

NO

T B

E C

OP

IED

OR

TAM

PE

RE

D W

ITH

WIT

HO

UT

CO

NS

EN

TP

RO

TEC

TED

BY

SA

DE

SIG

NS

RE

GIS

TRA

TIO

N N

o.

DC

I-B

EA

M T

ER

MIN

ATI

ON

DE

SC

RIP

TIO

N

Q20

4009

PA

RT

NU

MB

ER

AS

SE

MB

LEP

RO

CE

SS

THE

RM

AL

DIF

FUS

ION

FIN

ISH

MIL

D S

TEE

LM

ATE

RIA

L

1 O

F 1

SH

EE

T N

UM

BE

R

21/0

4/20

08LA

ST

UP

DA

TED

:1

RE

VIS

ION

:

21/0

4/20

08LA

ST

ISS

UE

D:

PD

FFO

RM

AT

AV

AIL

AB

LE:

YE

SIS

SU

ED

:21

/04/

2008

DA

TE:

A

PP

RO

VE

D B

Y:

M. S

TRA

PP

AZZ

ON

DR

AW

N B

Y:

“PREVIEW COPY ONLY”

Page 78: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable Route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 1 of 15

A Division of Transnet Limited

Registration Number 1990/000900/06

MAIN SPECIFICATION

INSTALLATION AND HAND_OVER OF OPTICAL FIBRE CABLE SPUR ROUTES

Pyramid - Musina

Specification Number BBF 2425 October 2011

Revision 1.00

NON-DISCLOSURE OF INFORMATION

Information contained in this document is proprietary in nature and/or protected by copyright.

Please obtain written permission from the Author prior to reproducing this document, in whole or in part.

“PREVIEW COPY ONLY”

Page 79: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 2 of 15

TABLE OF CONTENTS

I DOCUMENT AUTHORISATION............................................................3

II DISTRIBUTION ...................................................................................3

III DOCUMENT CHANGE HISTORY .........................................................3

IV CHANGES SINCE LAST REVISION......................................................3

V ABBREVIATIONS, ACRONYMS AND DEFINITIONS .............................3

VI RELEVANT DOCUMENTATION ...........................................................4

1. INTRODUCTION..................................................................................5

2. SCOPE OF WORK ...............................................................................6

3. TENDER REQUIREMENTS..................................................................8

4. SPECIFICATIONS................................................................................9

5. DRAWINGS ...........................................................................................

6. INSTALLATIONS..................................................................................9

7. PRE-TESTING, SPLICING AND TERMINATIONError! Bookmark not defined.

7.1 Drum Testing.............................Error! Bookmark not defined.

7.2 Post Installation Testing .........................................................11

8. FINAL TESTING AND COMMISSIONING ...........................................12

9. INSPECTION AND ACCEPTANCE......................................................12

ANNEXURE A............................................................................................13

“PREVIEW COPY ONLY”

Page 80: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 3 of 15

I DOCUMENT AUTHORISATION

FUNCTION NAME TITLE & DIVISION SIGNATURE DATE

Compiled by : Francois Nel Divisional Manager , Technical Execution Infra Telecoms HO

Authorised by :

Eric van der Merwe

Operations Manager, Transmission Infra Telecoms HO

II DISTRIBUTION

Once updated, a copy of the latest revision will be published in the document management system in use. E-mail to this effect will be sent to the relevant personnel or heads of department.

III DOCUMENT CHANGE HISTORY

ISSUE NO. DATE ISSUED ISSUED BY HISTORY

DESCRIPTION

1.00 October 2011 Technical Execution New document

IV CHANGES SINCE LAST REVISION

CLAUSE DESCRIPTION

None None

V ABBREVIATIONS, ACRONYMS AND DEFINITIONS

ABBREVIATIONS AND ACRONYMS

DESCRIPTION

AC Alternating Current

CSTA Corrugated Steel Tape Armoured

BOQ/BOM Bill of Quantities/Bill of Materials

DC Direct Current

NOC National Operations Centre

ODF Optical Distribution Frame

OFC Optical Fibre Cable

OHS Occupational Health and safety

OHTE Over Head Traction Equipment

PE Polyethylene

QAD Quality Assurance Department

RFQ Request For Quotation

STP Standard Test Procedure

TFR-T Transnet Freight Rail Telecoms

“PREVIEW COPY ONLY”

Page 81: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 4 of 15

VI RELEVANT DOCUMENTATION

VII Specifications

DOCUMENT NO.

DESCRIPTION LOCATION

SPC-00029 Trenching, laying and hauling in of communication cables

Document Control Centre

SPC-00033 Specification for Optical Fibre Testing Equipment

Document Control Centre

SPC-00571 Single Mode Optical Fibres (for information only)

Document Control Centre

SPC-00573 OFC make-up (for information only) Document Control Centre

SPC-00575 Specification for the Erection of Self-Supporting Optical Fibre Cable on traction Masts

Document Control Centre

SPC-00588 Specification for OFC Ducts Document Control Centre

SPC-00587 Specification for Horizontal directional Drilling

Document Control Centre

SPC-01242 Specification for Wooden Poles Document Control Centre

SPC-01279 Specification for Erection of Wooden Pole Routes

Document Control Centre

Work Procedures

The following Written Safe Work Procedures must be considered to be embodied within this Specification :

PRC-00112 Written Safe Work Procedure for the erection of self supporting Optical Fibre on AC OHTE (including all associated documents)

Document Control Centre

SOP-0H00 (Provisional)

Safe Work Procedure for working in confined spaces

Document Control Centre

E7/1 Works on, over, under or adjacent to railway lines and near high voltage equipment.

Document Control Centre

E.4E Compliance with the Occupational Health and Safety Act (Act 85 of 1993)

Document Control Centre “PREVIEW COPY ONLY”

Page 82: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 5 of 15

1. INTRODUCTION

1.1 TFR Telecom intends to install 23 short optical fibre spur cable routes in the sections Pyramid – Musina in the Northern Province. These spur cables are required to connect wayside equipment to an Infraco owned backbone optical cable. Optical fibres have been allocated for TFR use. Therefore TFR is issuing this RFQ (Request for Quotation) for the installation of Aerial Optical Cable on Electrification Traction Masts (OHTE), Aerial Optical Cable on pole routes and Underground Duct Optical Cable Installations in the sections mentioned below.

1.2 This RFT is issued for one Contract for installation and hand-over of 24 fibre single mode optical fibre spur cables in the following sections :

SECTION SPUR SITES

TYPE INST.

PYRAMID – POLOKWANE (24 fibre OFC Aerial ADSS)

POLOKWANE – MUSINA (24 Fibre OFC UNDERGROUND CSTA)

18

5

Aerial OHTE 25 kV AC and short Pole Routes

Underground trench, lay and backfill

Total 23

1.3 The existing OFC installation between Pyramid and Polokwane is aerial ADSS on 25 kV OHTE masts and between Polokwane and Musina, directly buried underground CSTA installations. The existing backbone OFC is carrying high capacity broadband services for Infraco and must not be interfered with in any way. This RFQ is for the installation of the OFC spurs only.

1.4 Completion of the Works is expected by March 2012. TFR will free issue sufficient Optical Fibre Cable (as indicated on the BoQ) for work to commence during January 2012. All Labour, OFC suspension brackets, OFC Suspension hardware, general and miscellaneous materials must be supplied by the successful Contractor.

“PREVIEW COPY ONLY”

Page 83: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 6 of 15

1.5 OFC installations are required overhead on electrification traction masts (OHTE) with 25 kV AC Traction Voltage (electrification) and therefore the remote support bracket and remote method of installation (by means of insulated rods) must be used. Short additional wooden pole routes, single poles, underground sections and installations into existing and new underground cable ducts are also required and called for in this RFQ.

1.6 Emphasis is placed on safety and safe working procedures and Contractors shall adhere to all instructions and procedures issued with this enquiry, especially the Written Safe Working Procedure PRC-00112 and all its associated documents as well as provisional SOP 0H00 for working in confined spaces (if applicable). The climbing of OHTE masts on AC electrified sections is strictly forbidden.

1.7 Tenderers shall comply with the specific requirements of Transnet’s E7/1 and E.4E Documents included.

1.8 The spur cables are required at intermediate wayside locations as indicated on the attached drawing sheets.

1.9 The work must be planned to ensure minimal interruption to normal train services. Underground track crossings must be executed by means of the “directional drilling” method specified. Overhead track crossings will be accepted if carried out as per the methods attached to this specification.

1.10 To expedite the tendering process, a Bill of Quantities (BoQ) is attached for the works. The BoQ is as accurate as can be established at this stage. Tenderers are required to quote in accordance with the BoQ. The BoQ will be supplied in .xls format and tenderers must complete the columns provided.

1.11 Tenderers must specify their installation capacity, proficiency, and ability to carry out the work, keeping in mind the deadline required. TFR will award the contract at its own discression, in accordance with CIDB stipulations.

2. SCOPE OF WORK

2.1 The project must be completed as a complete project with its own individual deliverable. Completed sites may be handed over at TFR’s discretion.

2.2 The 24-fibre, Anti-Tracking, single mode aerial OFC will be free issued by TFR-T. The 24 fibre underground CSTA OFC will be free issued by TFR-T. The OFC supplied will be “fit for purpose” for the purpose intended.

2.3 The aerial OFC cable is available at Pretoria and the underground cable at Polokwane. Tenderers must allow for transport of the OFC to the various sites of work.

2.4 All OFC "short lead" installation and miscellaneous materials i.e., cable support brackets, cable support hardware (dead-ends, tangents), metal and PE ducts, protection blocks, cable markers, building entry hardware, etc. must be supplied by the successful Contractor.

“PREVIEW COPY ONLY”

Page 84: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 7 of 15

2.5 Optical fibre cable jointing, splicing and termination accessories will be supplied, installed and commissioned by TFR.

2.6 All other consumable installation materials i.e. Unistrut, Warning tapes, Sista Foam, Rawl bolts, nuts, concrete, straps, cable ties, etc. must be included and supplied by the Contractor as consumables. A provision for consumables is made in the BoQ.

2.7 Sign-off of the re-survey by the Electrical Officer and TFR Supervisor is required before installation commences. On-site deviations from the agreed survey will only be allowed with the consent and instruction by both parties above.

2.8 Final "As Built" sheets, in the format required, must be submitted on completion of the work. The Notice of Completion Certificate will not be issued by TFR-T until all “As Built” documentation has been submitted.

2.9 The successful tenderer will be responsible for site camps and the transportation of the cable and materials to/from the various site camps, direct to the sites of work. The Contractor must ensure that the correct materials and quantities allocated for a specific section is taken out to camp/site and accept full responsibility for such materials once it has been removed from storage.

2.10 Tenderers must note that the OFC drums will be stored at Pretoria (ADSS) and Polokwane (UG CSTA) and all OFC drums will be pre-tested by TFR in accordance with PRC-00107 before they are taken out for installation. Caution must be exercised in OFC transportation to site. Full responsibility is placed on the Contractor for the safe transportation of the drums "to site".

2.11 The optical fibre cable is supplied on wooden drums in various lengths and at the sites indicated in this specification.

2.12 Tenderers must state their experience in the installation of self-supporting optical fibre cables on OHTE, wooden pole route and underground duct installations as well as the provision of quality installations. The Tenderer's response to this requirement will be a deciding factor during the adjudication of the tender.

2.13 Portions of the 25 kV AC electrification mast installations also entail the erection of short wooden pole routes or single poles and the suspension of the OFC on these poles to intermediate sites. In this regard strict adherence to the requirements of the Electrical Officer is required.

2.14 Wooden poles must be supported by stays and struts and where necessary the poles must be concreted in position. Poles must be erected vertically. The metal trunking containing the OFC must be protected by means of a protection block at the bottom of the pole.

2.15 OHTE installation, wooden pole routes and underground installations must comply with TFR-T Specifications. Tenderers must state their expertise in this area of construction and provide a reference list of OHTE, wooden pole and underground routes successfully completed.

“PREVIEW COPY ONLY”

Page 85: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 8 of 15

2.16 Other portions of the work will also entail civil construction works like excavations, hand trenching, sub ducting, backfilling and compaction, constructing pipe and draw-pit systems, directional drilling, track pipe crossings, bush clearing, tree felling, etc. Tenderers must also state their expertise in this area of civil construction and provide a reference list of works successfully completed.

2.17 All underground OFC must be placed in 32 mm OFC specific sub-duct and where the duct is directly buried, indicated by means of marker tape above the sub-duct and cable markers as per the appropriate specification. The preferred method of installing underground OFC in continuous ducts is by “blowing in” the OFC.

2.18 The contractor must be equipped with the required plant and the certificated personnel to carry out the work. Personnel qualifications must be provided with tender documents.

3. TENDER REQUIREMENTS

3.1 Only Tenderers registered with the CIDB (Construction Industry Development Board) will be eligible for this RFQ. A CIDB rating equivalent to the tender amount will be required. CIDB Certificates must be presented with tender documents.

3.2 Tenders will be adjudicated as per method 4 of the CIDB.

3.3 NB: A clause-by-clause statement of compliance is required for this and all embodied specifications. Specifications marked “for information only” shall be “noted as read”.

3.4 Tenderers must quote for all aspects of the work and materials as per this RFQ, Specification and BoQ. If certain work or materials are not quoted for, this must be clearly stated.

3.5 Tenderers must quote separately for alternative items or changes they may recommend.

3.6 Due to the time constraint, Tenderers must state their expertise in projects completed exactly similar to the Works described in this specification and must submit a reference list. Tenderers must have the necessary certificated persons and the correct installation plant and tools to complete this work. The tenderer's response to this requirement will be a deciding factor during the adjudication of this RFQ.

3.7 Tenderers must allow and include overtime and week-end work.

3.8 If the tenderer intend to use sub-contractors, the names, experience and capacity of these sub-contractors must be provided in the tender documents. The type of contractual agreement between main and sub-contractor must be stated. TFR reserves the right to decline any sub-contractor proposed, based on the required criteria.

“PREVIEW COPY ONLY”

Page 86: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 9 of 15

3.9 The successful Contractor must supply "as built" information (based on revision of the survey sheets) on completion of the Works. As build documentation must include GPS co-ordinates of all joints, slack, crossing places and other important events.

3.10 Should the cost of certain material items offered be excessive in TFRT's opinion, TFRT reserve the right to supply any of the material quoted for, free of charge.

3.11 Tenderers must familiarise themselves with the requirements stipulated in the RFQ Document as well as all other documents, annexures and specifications referred to in the RFQ document and this specification.

3.12 Any item or requirement that is not clear to the tenderer must be clarified with the TFR-T Project Manager before submission of tenders.

3.13 The material and labour to be supplied by the Contractor must be derived from the BoQ (Annexure A). TFR-T's BoQ format must be used to supply this information. Soft copies in Excel format will be provided.

3.14 Any materials, installation and other items excluded from the BoQs, but required to complete the installations in the Tenderer's opinion must be shown separately in the RFQ Response.

4. SPECIFICATIONS

4.1 All materials and installations must comply with the incorporated specifications. Attached specifications must be considered to be embodied as part of this specification.

5. Clause-by-clause statements of compliance, where applicable, are mandatory for Specifications and Work Procedures indicated under section VI.

5.1 The following drawings must be considered to be embodied within this specification :

5.1.1 Bracket drawings for remote AC installation (Annexure C).

5.1.2 All spur site drawings included in Specifications above.

5.1.3 All annexures to this specification:

� Annexure A – Bill of Quantities.

6. INSTALLATIONS

6.1 The CBI 24-fibre, ADSS, Anti-Tracking aerial self-supporting optical fibre cable parameters are as follows :

6.1.1 Mass of cable : 78 kg/km .

6.1.2 Installation tensile force not to be exceeded : 1,5 kN .

“PREVIEW COPY ONLY”

Page 87: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 10 of 15

6.1.3 Outside diameter : 10,5 mm .

6.1.4 Minimum bending radius : 130 mm .

6.1.5 Nominal delivery length : 4 000 m .

6.2 The TFR approved Laserfab remote installation bracket is specified for steel OHTE masts. The brackets must be adequately protected against corrosion. Full details of the protection offered must be provided.

6.3 All PLP fittings (dead-ends and tangent supports) shall be of the “allu-clad” type.

6.4 The "Remote" AC cable installation technique must be used. The climbing of masts on AC sections is prohibited for safety reasons.

6.5 Wooden poles may be climbed by adhering to the safety requirements and where the required clearances can be obtained. It must be kept in mind that maintenance must be generally carried out under “live” conditions by means of the “remote” method.

6.6 Certain work could be carried out in confined spaces (manholes or cable vaults) and special precaution must be taken for the safety of workers (see SOP “working in confined spaces”).

6.7 Tenderers must take specific note of the safety aspects as depicted in Written Safe Work Procedure PRC-00112 as well as the safety arrangements and instructions attached thereto and procedural compliance with the Occupational Health and Safety Act; Act 85 of 1993 and regulations. A full Statement of Compliance must be submitted for WSWP PRC-00112, and this compliance document must be included in the Site Safety File.

“PREVIEW COPY ONLY”

Page 88: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 11 of 15

6.8 An Occupational Health and Safety Plan must be outlined in the tender document and submitted to the Project Manager by the successful contractor before work commences. The Safety Plan must also be placed on the Contractor’s Site Safety File.

6.9 Safety induction by TFR OHTE officers is required before commencement of work. Minimum safety clearances from live electrical conductors and Safety Instructions and Guidelines must be observed and exercised at all times.

6.10 Sufficient Certificated employees to work on OHTE structures must be in the Contractors employment during construction works. The names of certificated employees must be provided with the Tender.

6.11 The Contractor must be equipped with all the required plant, tools, safety equipment and PPE (Personal Protective Equipment) to effectively and safely carry out the Works.

6.12 Where electrical and track occupations are required, these must be arranged by the Contractor with the TFR-T Supervisor and Electrical Officer. Overtime and weekend work will be required depending on the occupations program.

6.13 Maximum benefit must be gained from normal electrical and track occupations requested by other departments. It is therefore imperative that the TFR-T Supervisor and Contractor’s Supervisor attend the regular “occupation” meetings arranged by Train Operations.

6.14 Contractors must note that TFR-T will utilize one TFR-T supervisor / inspector at any time during the contract period to inspect the progress and quality of the Contractor's work. This person is not available on a full time basis (on site) and will make scheduled and random site visits.

6.15 The successful Contractor must appoint a Site Supervisor for the duration of the contract. The Site Supervisor must be “in charge” on site for the full duration of the contract.

6.16 TFR-T will provide the Contractor's site supervisor with a site instruction book. The Contractor must supply his own site diary. These books must be kept updated at all times and copies handed over to the TFR-T Project Manager at monthly progress meetings.

6.17 Contractors must take note that Freight Rail Perway or OHTE must approve and supervise all underground and overhead (boom or other) rail (track) crossings.

6.18 Post Installation Testing

Post installation testing will be carried out by TFR at the 1550 nm wavelength in compliance with TFR Standard Test Procedure No. PRC-00106. Therefore emphasis is placed on the correct installation techniques to enable TFR-T to obtain the results required.

“PREVIEW COPY ONLY”

Page 89: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 12 of 15

7. FINAL TESTING AND COMMISSIONING

7.1 TFR will be responsible for the final testing of all installations/sections and if found defective, tenderers must allow for return to site to rectify faults.

8. INSPECTION AND ACCEPTANCE

8.1 The Site Supervisor and the Project Manager will carry out progress, quality and safety inspections at random during the duration of the Works.

8.2 Quality Assurance, the Project Manager, Project Supervisor and the Contractor must jointly carry out final acceptance. The Contractor must advise the Project Manager two (2) weeks in advance that the work is ready for inspection / acceptance.

8.3 Outstanding observations and small defects (snags), not affecting system functionality, as indicated by the Project Manager at the final inspection, must be corrected by the Contractor within one month of acceptance (Acceptance implies the issue of a Notice of Completion Certificate).

8.4 The contractor shall guarantee his installation for a period of 12 months after the issue of a “Notice of Completion” certificate.

8.5 The Project Manager will issue a "Notice of Completion" certificate at his own discretion on completion of the Works or on pre-determined functional sections of the Works.

End of specification

“PREVIEW COPY ONLY”

Page 90: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 13 of 15

ANNEXURE A

BILL OF QUANTITIES FOR THE SECTIONS :

Pyramid - Musina

ATTACHED AS .XLS SHEET

“PREVIEW COPY ONLY”

Page 91: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 14 of 15

ANNEXURE B

OFC SPUR CABLE SITES AND LAYOUT :

1 SITE DRAWINGS

2 LAYOUT ATTACHED TO BOM

“PREVIEW COPY ONLY”

Page 92: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

SPECIFICATION BBF

2425

OPTICAL FIBRE SPUR CABLE ROUTES

PYRAMID - MUSINA REVISION 1.00

Uncontrolled Copy

Doc. No. BBF 2425 Author : Francois Nel i:\ad\ttspec\Format (ISO)\Transnet Freight Rail\SPC-01319 Supply Installation and

Commissioning Optical Fibre Cable route Saldaha ~ Sishen (Main Spec) Rev 1.doc COMMERCIAL-IN-CONFIDENCE Page 15 of 15

ANNEXURE C

PROPOSED OFC BRACKET FOR 25 KV AC STEEL OHTE MASTS :

Pyramid - Musina

ATTACHED

“PREVIEW COPY ONLY”

Page 93: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 1 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

TABLE OF CONTENTS

Section

No.

Description Page

No.

Table of contents 1 1 Purpose 2 2

3 Reference documents Definitions and Abbreviations

2 2

4 Responsibilities and authorities 4 5.

5.1 5.1.1 5.1.1.1 5.1.1.25.1.1.3 5.1.1.4 6.0 7.0

Procedure

4 4 6 6 6 6 6 6 6

COMPILED BY: SIGNATURE:

APPROVED BY: SIGNATURE:

“PREVIEW COPY ONLY”

Page 94: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 2 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

1. PURPOSE

The purpose of this document is to:

• Sets forth the requirements necessary for working in confined spaces at

TFR to prevent exposure of personnel to dangerous air contamination,

oxygen deficiency, and physical hazards associated with confined

spaces. Confined spaces include, but are not limited to, tanks, ducts,

pipelines, sumps, sewers, trenches, vaults, and similar spaces not

intended for continuous human occupancy and meeting the criteria

described in General Safety Regulations, regulation 5.

• Ensuring the proper authorization of designated work.

• Making clear the exact identity, nature and extent of the work activity and

the hazards involved, including limitations on the extent of the work and

the times during which the work can be carried out.

• Specifying the precautions to be taken, including safe isolation from

potential risks such as exposure to hazardous substances, moving

equipment and electricity.

• Ensuring the individual in charge of operations is fully aware of work

activities taking place.

• Providing a system of continuous control and a record of showing the

nature of the work and that necessary precautionary checks have been

satisfactorily completed.

• Providing necessary information on related/interactive work activities and

satisfactory completion and handover of authorized work.

“PREVIEW COPY ONLY”

Page 95: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 3 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

2. REFERENCE DOCUMENTS

Guide to conducting an occupational health risk assessment as required in

the occupational health and safety act, regulations for hazardous chemical

substances – 1995 Prepared by the Institute of Occupational Hygienists of

Southern Africa (IOHSA);

Plog, Barbara, A.: Fundamentals of Industrial Hygiene. Chicago, National

Safety Council, 4th Edition, 1996;

Occupational Health and Safety Act, Act 85 of 1993

3. DEFINITIONS AND ABBREVIATIONS

3.1 Definitions

Procedure: formal documentation pertaining to a major

business/operating-/technical/engineering process, which will include

reference to instructions, product, equipment or process specifications, to

implement the principles of a policy. It also defines the roles and

responsibilities of those covered by the procedure;

Work Instruction (SOP): an exact description of an activity, which is a

component of a major process, to which reference will be made within a

procedure;

Attendant (standby): An individual stationed outside one or more confined

spaces to monitor authorized entrants, and who performs all attendants’

duties assigned in the confined-space program.

Confined space. A space that (1) is large enough and so configured that

an employee can enter bodily, (2) has limited or restricted means for entry

or exit (e.g., tanks, vessels, vaults, pits), and (3) is not designed for

continuous occupancy.

Entry: The action by which a person passes through an opening into a

permit-required confined space. Entry is considered to have occurred as

soon as any body part of the entrant’s body breaks the plane of an opening

into the space.

Entry permit: The written permit that must be completed and posted at the

worksite before a confined space is entered (see Appendix A).

“PREVIEW COPY ONLY”

Page 96: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 4 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

Hazardous atmosphere: An atmosphere that may expose employees to

the risk of death, injury, or illness from one of the following: Flammable gas,

vapor, or mist exceeding 10% of its lower explosive limit (LEL), Airborne

combustible dust at a concentration that meets or exceed its LEL,

Atmospheric oxygen concentration below 19.5% or above 23.5%,

Atmospheric concentration that exceeds the OEL, STEL, ceiling, or the

manufacturer’s recommendations on the Material Safety Data Sheet

(MSDS);

Non-permit confined space: A confined space that does not contain, or,

with respect to atmospheric hazards, have the potential to contain, any

hazard capable of causing death or serious physical harm.

Note: These spaces become permit-required confined spaces if hazards

are brought in or exposed by the work. Examples include gasoline-

powered earth compactors (carbon monoxide); solvent-based coatings,

epoxies, and paints; open sewer lines in the bottom of trenches;

contaminated soil; welding; etc.

Occupational Exposure Limits: means a limit value set by the Minister

for a stress factor in the workplace.

3.2 Abbreviations

SOP: Safety operating procedure

SANS: South African National Standard

OHS Act: Occupational Health and Safety Act (Act 85 of 1993)

TFR: Transnet Freight Rail “PREVIEW COPY ONLY”

Page 97: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 5 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

4. RESPONSIBILITIES AND AUTHORITIES

Senior

Management

- Must ensure that this procedure is implemented and adhered

to.

Line

Management

- Must ensure that the requirements of the Act and Asbestos

regulations are implemented and maintained.

Nominated

Safety

Manager

- Must ensure that the requirements of the Act and Asbestos

regulations are implemented and maintained.

- Must ensure that this procedure is implemented and adhered

to.

Safety

Specialist

- Ensure the Asbestos inventory report is correct and oversee the

implementation of any recommendations.

“PREVIEW COPY ONLY”

Page 98: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 6 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

5. RISK MANAGEMENT

Hazardous Chemical Substances Regulation 5 requires the employer to

conduct the assessment with regards to the potential exposure to Hazardous

Chemical Substances, in which the health and safety risks to which employees

may be exposed while they are at work, and record the hazards identified and

significant risk assessed. As far as reasonably practicable attempts will be

made to first of all to eliminate the risk, thereafter to control the risk, then to

minimise the risk and thereafter, insofar as the risk remains, to provide personal

protective equipment and to implement a programme to monitor the risk.

A risk assessment will be carried out to assist in deciding on appropriate action

and formulating a management plan.

The risk assessment will be carried out in two parts: the first is a material

assessment which assesses the condition of the material and the likelihood of it

releasing fibres if disturbed; the second part is a priority assessment which

takes into account maintenance activities, likelihood of disturbance, human

exposure potential, occupant activity or visitors.

All possible relevant information such as incident statistics, research reports,

manufacturer’s specifications, approvals, design criteria and performance figure

for all relevant equipment will be obtained and considered for risk assessment.

Before an assessment can be made, the relevant health and safety

representative or relevant health and safety committee will be consulted and

thereafter inform them in writing of the arrangements made for the assessment,

give them reasonable time to comment thereon and ensure that the results of

the assessment are made available to them for comment.

“PREVIEW COPY ONLY”

Page 99: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 7 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

Occupational health risk assessment will be conducted as follows:

“PREVIEW COPY ONLY”

Page 100: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 8 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

6. PROCEDURE

This procedure applies to all TFR employees and any worker under the technical

supervision of a TFR employee. Permit authorisation is required before any

person enters a confined space. A confined space is defined as “any place,

including any chamber, tank, vat, silo, pit, trench, pipe, sewer, flue, well or other

similar space in which, by virtue of its enclosed nature, there arises a reasonably

foreseeable specified risk.

Sub-contractors may elect in their Safety Plan to comply with these procedures; in

which case, this policy is applicable. If the sub-contractor chooses to use their

own Health and Safety Plan for confined space procedures, it must be reviewed

and approved by Safety Manager, before work may commence. The safety plan

must contain procedures, which meet OHS Act requirements for entering permit-

required confined spaces, and include the completion of a permit form.

6.1 CLASSIFICATION

6.1.1 Confined space requiring permit to work with high or susceptible

risks

Confined Spaces that requires permit to work are confined spaces where actual

hazards have been identified, or where the probability of a hazard is significant.

Evaluation using the Confined Space Entry Permit (Appendix A) is required.

Both the confined space trained on-site supervisor and a TFR Occupational

hygienist/Technologist must sign the permit. In cases where radiological

hazards are present, a Radiation Protection Officer/specialist’s signature is

required for approval before any work can commence and where there are

electrical cables, an Electrical Supervisor’s signature is required for approval.

6.1.2 Confined space requiring permit to work with low risks

For confined spaces where a permit is required, but hazards have been

evaluated as low risk, the confined space trained on-site supervisor may

approve a procedural confined space permit and the following conditions must

be met:

“PREVIEW COPY ONLY”

Page 101: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 9 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

• The TFR employees or contract employees who have completed Confined

Space Entry Hazards Training program will conduct the work.

• The entry permit must be completed and signed by a confined space trained

on-site supervisor and TFR Occupational hygienist/Technologist.

• All conditions for a permit-required confined space are met.

6.1.3 Non-permit required confined spaces

Confined spaces that do not contain hazards, nor have a potential to contain

hazards, do not require an approved Confined Space Entry Permit. However, a

permit must be completed by the confined space trained on-site supervisor,

and, if hazards are found not to exist, clearly marked as a “Non-permit Space”

and posted at the work site. “Non-permit Space” must be approved by the TFR

Occupational hygienist/Technologist.

6.5 Confined-space entry work permit system

A Confined Space Entry Work Permit (see Appendix A) must be completed for

all confined-spaces before entry. This permit documents in writing the

location(s) and type of work to be done, certifies that all existing hazards have

been evaluated by the responsible qualified person(s), and ensures that

necessary control measures have been taken to protect the health and safety

of the employees. Non-permit confined spaces must be identified as such by

documenting that chemical and physical hazards (e.g., oxygen levels, etc.) do

not exist and by writing “Non-Permit Space” in bold print across the work permit.

Permits will expire when the entrance is closed or at the end of the 8-hour work

shift, whichever is sooner.

6.3 Confined-space team

All person(s) entering the space (entrant) should be listed and the designated

standby (attendant) person(s). If applicable, the rotation by the designated

attendant(s) with personnel working in the confined space must be specified.

6.4 Requirements completed prior to entry

a) Detailed health and safety risk assessment should be conducted prior

“PREVIEW COPY ONLY”

Page 102: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 10 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

to commencement of work.

b) If high electrical lines are present in the confined space, the Electrical

Supervisor (or designee) must approve the entry permit.

c) Lockout and tagout/blockout must be done in accordance with TFR

lockout and tagout procedures.

d) Lines, pipes, etc., must be blanked/capped to the extent feasible

before the confined space is entered.

e) If mechanical ventilation is required, site-specific details, such as the

direction of airflow and the placement of the air intake, must be

documented in the “Additional Information” section. The air supply

must be from a clean source: exhaust from vehicles, cranes, earth

compactors, and other potential sources of contaminants must be

considered when locating the blower.

f) The confined space must be emptied and purged of all hazardous

materials to the extent possible prior to entry. A fresh air blower

ventilation system shall be set up and in operation before and during

all inspection and maintenance procedures. If hazardous materials

have been identified or will be used in the confined space, an

Occupational hygienist/Technologist must be present to determine

their concentrations and approve the permit. If these materials

exceed, or have the possibility to exceed the Occupational Exposure

Limits, rescue equipments (e.g., hoist, lifelines, and harness) are

required, and the standby must be CPR trained.

g) Continuous air monitoring will be required for confined space that

cannot be isolated from potential contaminants. For example, flowing

sewers often cannot be blanked off, and continuous air monitoring is

required.

h) When entrance covers are removed, temporary barriers that will

protect the entrants from external hazards, such as vehicles, and

protect pedestrians from falling into the opening must guard

openings.

i) A fire extinguisher must be present if “hot work” is being performed.

“PREVIEW COPY ONLY”

Page 103: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 11 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

j) If ionizing radiation may be present, radiation levels must be

monitored by radiation protection officer/specialist.

k) Required personal protective equipment should be specified before

entering into the confined space as also determined during the risk

assessment. If respiratory protection is required, site-specific details,

such as the type of respirator and cartridges, must be specified.

l) At least one standby person must be present at all times while the

high-risk confined space is occupied. The primary responsibility of the

standby personnel is the health and safety of the occupants in the

confined space. Standby personnel must be in constant visual/radio

contact with the occupants and must immediately notify the TFR Fire

Department and Occupational Health department if there are any

problems. The standby person should always summon emergency

rescue workers, and may never enter a confined space to attempt a

rescue. However, the standby can initiate a non-entry rescue, such

as by operating a hoist or lift.

m) If “hot work” will be performed, a Fire Safety Permit, available from

the Fire Department, must be completed and posted at the entrance

to the space prior to the start of work. All confined spaces become

permit-required confined spaces when hot work is performed in them.

In addition, welding gas cylinders may never be brought into a

confined space.

n) Personnel entering the space must receive confined-space training

prior to entering a permit-required or procedural confined space.

o) Additional lighting equipment may be needed to enable employees to

see well enough to work safely and to exit the space quickly in an

emergency, in these instances, explosion-proof lighting will be

required.

p) The explosion-proof gas monitor must be calibrated monthly and

function checked prior to each daily use. Monitoring the air inside a

confined space should be conducted prior to entering and be

conducted by a competent person. Testing a confined space for

“PREVIEW COPY ONLY”

Page 104: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 12 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

atmospheric hazards should be done remotely before entering, and

should be done in this order: (1) ensure that proper oxygen levels are

present, (2) ensure that combustible gases are not present, (3)

ensure that toxic gases are below the Occupational exposure limit.

Common toxic gases in a confined space could be Hydrogen Sulfide

(H2S) and Carbon Monoxide (CO), but other toxic compounds could

be present.

q) Minimum health and safety equipment required before confined

space entry:

� approved gas detector (properly calibrated and that is in operation

the entire time the employee is in the confined space. This is

necessary due to the possibility of a rapid change in the confined

space atmosphere);

� fresh air blower;

� safety harness, rope, and tripod safety system (A safety harness

and lifeline which is attached to the tripod safety retrieval system);

� an approved hard hat; and

� emergency Action Plan

6.5 Confined-space monitoring procedure

In a confined space it is important to take samples at the top, middle and

bottom to locate varying concentrations of gases and vapours. There are

some gases lighter than air (i.e. methane and other combustible gases)

that can be found at the top of a confined space. There are other gases

that are heavier than air (i.e. hydrogen sulfide) that can settle near the

bottom of a confined space, and still other gases that are the same

weight as air (i.e. carbon monoxide) that can be found throughout a

confined space.

Take air samples at several levels within the confined space and

continuously monitor the space due to the fact that conditions can

change. The confined space must be tested at three levels for each

atmospheric condition. Each level must be tested for a minimum of 60

“PREVIEW COPY ONLY”

Page 105: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 13 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

seconds. The gas detector itself can be lowered into the confined space

atmosphere with a safety line

As the remote air monitoring is completed and the area is safe for entry,

confined space entry permits should be completed and followed. After

the initial entry, monitoring the air in the confined space should be

continuous. A confined space entry attendant or standby should carry

out the continuous monitoring. Conditions in a confined space can

change without warning, due to leakage, toxic vapor release, or

disturbing the contents of the space.

Testing must include: -

• Oxygen content must be at least 19.5% in the confined space,

measured at all levels (bottom, middle, and top). The safe oxygen

level is between 19.5% and 21%. Confined space should not be

entered if the oxygen level is below 19.5% or above 21%. Due to the

extreme danger of suffocation in confined spaces, constant and

continuous oxygen monitoring is required throughout each work

period. Oxygen content above 23% can cause explosions or vigorous

burning of flammable materials, including hair or clothing.

• In circumstances where risk assessment has identified a significant

possibility for the presence of fuels, combustion products, methane

and/or biological action (e.g. oxyacetylene cutting, decontamination of

fuel tanks, sewage systems etc.) the following tests should also be

carried out: -

� Explosive/flammable vapours – limit < 2% LEL (measure

flammability at all levels of the confined space (bottom, middle,

and top). Flammability is measured in terms of the Lower

Explosive Limit (LEL). This is the smallest concentration of a

combustible gas in air that will explode when it contacts a spark or

open flame)

� Hydrogen Sulphide – limit 10ppm (8hour TWA)

� Carbon dioxide – limit 30ppm (8 hour TWA)

Procedure to be followed:

“PREVIEW COPY ONLY”

Page 106: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 14 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

� Record hazard identification of area and/or confined space to be

entered. Reference to additional Permits to Work must be recorded.

� Identify reason for confined space entry

� Confirmation that all necessary isolation and pre-entry activities have

been carried out. Authorised persons are restricted to those who have

received information, instruction and training in this and related Permit

to Work procedures.

� The atmosphere within the confined space must be tested and

confirmed as safe before entry is permitted. Normal practice will be to

test for oxygen content however it may be necessary to test for

flammable/explosive vapours and H2S, with additional parameters

tested if identified as potentially present during the risk assessment

process. Personnel authorised to carry out gas testing are any

competent person deemed competent by the Safety Manager or

Occupational Hygienist.

� A standby man must be present at all times when personnel are in the

confined space, with additional precautions specified to meet

identified risks, e.g. RPE, harness/lift gear, flame proof lighting etc.

First aid, resuscitation and emergency communication equipment

should be made available for circumstances where access to medical

treatment may be restricted and/or a need for such equipment is

identified during the risk assessment process. All equipment must be

checked and verified as fit for use before entry of the confined space

takes place.

� No person shall enter a confined space to retrieve someone who is

unconscious without having required personnel above ground to

assist. The person entering the confined space for rescue purposes

must be equipped with the required rescue equipment and follow the

specific rescue procedure.

� Confined space authorised person to confirm pre-entry checks have

been completed satisfactorily. If breathing apparatus is required

specify type.

“PREVIEW COPY ONLY”

Page 107: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 15 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

� The person carrying out the work or the supervisor to confirm

acceptance of conditions imposed by the permit.

� All personnel entering the confined space must confirm acceptance of

the conditions imposed by the permit.

� The permit must be returned at the end of the day or on completion of

the work. Should it be necessary to carry on work the following day a

new work permit should be issued. The person carrying out the work

or the supervisor must sign the permit to indicate that all equipment

has been withdrawn or made safe.

� The authorised person must cancel the permit by signing it off.

“PREVIEW COPY ONLY”

Page 108: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 16 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

Appendix A. Confined Space Entry Work Permit

JOB INFORMATION

Permit start date and time Permit end date and time

Site Location/Description

Task

TYPE OF CONFINED SPACE

Low Risk High Risk

Standby List confined space team:

Entrants

REQUIREMENTS REQUIRED PRIOR TO ENTRY:

YES NO YES NO

Risk assessment conducted Fire extinguisher

Electrical lines present Radiation

Lockout/tagout completed PPE

Lines blanked/capped Radio contact

Ventilation Emergency plan

Hazardous materials identified Hot work permit

Standby CPR trained Confined space training

Lifelines (e.g. hoist, tripod, harness) Lighting explosion proof

Gas monitoring conducted Special instructions

Secure area/barriers

MONITORING RESULTS

Instrument Model and serial number

Instrument calibration date

Instrument calibration reading

Oxygen %

Flammability %

Other Contaminants:

ADDITIONAL INFORMATION

APPROVAL SIGNATURES

Supervisor Date:

Occupational Hygienist/Technologist Date:

“PREVIEW COPY ONLY”

Page 109: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 1 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

TABLE OF CONTENTS

Section

No.

Description Page

No.

Table of contents 1 1 Purpose 2 2

3 Reference documents Definitions and Abbreviations

2 2

4 Responsibilities and authorities 4 5.

5.1 5.1.1 5.1.1.1 5.1.1.25.1.1.3 5.1.1.4 6.0 7.0

Procedure

4 4 6 6 6 6 6 6 6

COMPILED BY: SIGNATURE:

APPROVED BY: SIGNATURE:

“PREVIEW COPY ONLY”

Page 110: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 2 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

1. PURPOSE

The purpose of this document is to:

• Sets forth the requirements necessary for working in confined spaces at

TFR to prevent exposure of personnel to dangerous air contamination,

oxygen deficiency, and physical hazards associated with confined

spaces. Confined spaces include, but are not limited to, tanks, ducts,

pipelines, sumps, sewers, trenches, vaults, and similar spaces not

intended for continuous human occupancy and meeting the criteria

described in General Safety Regulations, regulation 5.

• Ensuring the proper authorization of designated work.

• Making clear the exact identity, nature and extent of the work activity and

the hazards involved, including limitations on the extent of the work and

the times during which the work can be carried out.

• Specifying the precautions to be taken, including safe isolation from

potential risks such as exposure to hazardous substances, moving

equipment and electricity.

• Ensuring the individual in charge of operations is fully aware of work

activities taking place.

• Providing a system of continuous control and a record of showing the

nature of the work and that necessary precautionary checks have been

satisfactorily completed.

• Providing necessary information on related/interactive work activities and

satisfactory completion and handover of authorized work.

“PREVIEW COPY ONLY”

Page 111: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 3 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

2. REFERENCE DOCUMENTS

Guide to conducting an occupational health risk assessment as required in

the occupational health and safety act, regulations for hazardous chemical

substances – 1995 Prepared by the Institute of Occupational Hygienists of

Southern Africa (IOHSA);

Plog, Barbara, A.: Fundamentals of Industrial Hygiene. Chicago, National

Safety Council, 4th Edition, 1996;

Occupational Health and Safety Act, Act 85 of 1993

3. DEFINITIONS AND ABBREVIATIONS

3.1 Definitions

Procedure: formal documentation pertaining to a major

business/operating-/technical/engineering process, which will include

reference to instructions, product, equipment or process specifications, to

implement the principles of a policy. It also defines the roles and

responsibilities of those covered by the procedure;

Work Instruction (SOP): an exact description of an activity, which is a

component of a major process, to which reference will be made within a

procedure;

Attendant (standby): An individual stationed outside one or more confined

spaces to monitor authorized entrants, and who performs all attendants’

duties assigned in the confined-space program.

Confined space. A space that (1) is large enough and so configured that

an employee can enter bodily, (2) has limited or restricted means for entry

or exit (e.g., tanks, vessels, vaults, pits), and (3) is not designed for

continuous occupancy.

Entry: The action by which a person passes through an opening into a

permit-required confined space. Entry is considered to have occurred as

soon as any body part of the entrant’s body breaks the plane of an opening

into the space.

Entry permit: The written permit that must be completed and posted at the

worksite before a confined space is entered (see Appendix A).

“PREVIEW COPY ONLY”

Page 112: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 4 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

Hazardous atmosphere: An atmosphere that may expose employees to

the risk of death, injury, or illness from one of the following: Flammable gas,

vapor, or mist exceeding 10% of its lower explosive limit (LEL), Airborne

combustible dust at a concentration that meets or exceed its LEL,

Atmospheric oxygen concentration below 19.5% or above 23.5%,

Atmospheric concentration that exceeds the OEL, STEL, ceiling, or the

manufacturer’s recommendations on the Material Safety Data Sheet

(MSDS);

Non-permit confined space: A confined space that does not contain, or,

with respect to atmospheric hazards, have the potential to contain, any

hazard capable of causing death or serious physical harm.

Note: These spaces become permit-required confined spaces if hazards

are brought in or exposed by the work. Examples include gasoline-

powered earth compactors (carbon monoxide); solvent-based coatings,

epoxies, and paints; open sewer lines in the bottom of trenches;

contaminated soil; welding; etc.

Occupational Exposure Limits: means a limit value set by the Minister

for a stress factor in the workplace.

3.2 Abbreviations

SOP: Safety operating procedure

SANS: South African National Standard

OHS Act: Occupational Health and Safety Act (Act 85 of 1993)

TFR: Transnet Freight Rail “PREVIEW COPY ONLY”

Page 113: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 5 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

4. RESPONSIBILITIES AND AUTHORITIES

Senior

Management

- Must ensure that this procedure is implemented and adhered

to.

Line

Management

- Must ensure that the requirements of the Act and Asbestos

regulations are implemented and maintained.

Nominated

Safety

Manager

- Must ensure that the requirements of the Act and Asbestos

regulations are implemented and maintained.

- Must ensure that this procedure is implemented and adhered

to.

Safety

Specialist

- Ensure the Asbestos inventory report is correct and oversee the

implementation of any recommendations.

“PREVIEW COPY ONLY”

Page 114: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 6 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

5. RISK MANAGEMENT

Hazardous Chemical Substances Regulation 5 requires the employer to

conduct the assessment with regards to the potential exposure to Hazardous

Chemical Substances, in which the health and safety risks to which employees

may be exposed while they are at work, and record the hazards identified and

significant risk assessed. As far as reasonably practicable attempts will be

made to first of all to eliminate the risk, thereafter to control the risk, then to

minimise the risk and thereafter, insofar as the risk remains, to provide personal

protective equipment and to implement a programme to monitor the risk.

A risk assessment will be carried out to assist in deciding on appropriate action

and formulating a management plan.

The risk assessment will be carried out in two parts: the first is a material

assessment which assesses the condition of the material and the likelihood of it

releasing fibres if disturbed; the second part is a priority assessment which

takes into account maintenance activities, likelihood of disturbance, human

exposure potential, occupant activity or visitors.

All possible relevant information such as incident statistics, research reports,

manufacturer’s specifications, approvals, design criteria and performance figure

for all relevant equipment will be obtained and considered for risk assessment.

Before an assessment can be made, the relevant health and safety

representative or relevant health and safety committee will be consulted and

thereafter inform them in writing of the arrangements made for the assessment,

give them reasonable time to comment thereon and ensure that the results of

the assessment are made available to them for comment.

“PREVIEW COPY ONLY”

Page 115: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 7 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

Occupational health risk assessment will be conducted as follows:

“PREVIEW COPY ONLY”

Page 116: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 8 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

6. PROCEDURE

This procedure applies to all TFR employees and any worker under the technical

supervision of a TFR employee. Permit authorisation is required before any

person enters a confined space. A confined space is defined as “any place,

including any chamber, tank, vat, silo, pit, trench, pipe, sewer, flue, well or other

similar space in which, by virtue of its enclosed nature, there arises a reasonably

foreseeable specified risk.

Sub-contractors may elect in their Safety Plan to comply with these procedures; in

which case, this policy is applicable. If the sub-contractor chooses to use their

own Health and Safety Plan for confined space procedures, it must be reviewed

and approved by Safety Manager, before work may commence. The safety plan

must contain procedures, which meet OHS Act requirements for entering permit-

required confined spaces, and include the completion of a permit form.

6.1 CLASSIFICATION

6.1.1 Confined space requiring permit to work with high or susceptible

risks

Confined Spaces that requires permit to work are confined spaces where actual

hazards have been identified, or where the probability of a hazard is significant.

Evaluation using the Confined Space Entry Permit (Appendix A) is required.

Both the confined space trained on-site supervisor and a TFR Occupational

hygienist/Technologist must sign the permit. In cases where radiological

hazards are present, a Radiation Protection Officer/specialist’s signature is

required for approval before any work can commence and where there are

electrical cables, an Electrical Supervisor’s signature is required for approval.

6.1.2 Confined space requiring permit to work with low risks

For confined spaces where a permit is required, but hazards have been

evaluated as low risk, the confined space trained on-site supervisor may

approve a procedural confined space permit and the following conditions must

be met:

“PREVIEW COPY ONLY”

Page 117: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 9 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

• The TFR employees or contract employees who have completed Confined

Space Entry Hazards Training program will conduct the work.

• The entry permit must be completed and signed by a confined space trained

on-site supervisor and TFR Occupational hygienist/Technologist.

• All conditions for a permit-required confined space are met.

6.1.3 Non-permit required confined spaces

Confined spaces that do not contain hazards, nor have a potential to contain

hazards, do not require an approved Confined Space Entry Permit. However, a

permit must be completed by the confined space trained on-site supervisor,

and, if hazards are found not to exist, clearly marked as a “Non-permit Space”

and posted at the work site. “Non-permit Space” must be approved by the TFR

Occupational hygienist/Technologist.

6.5 Confined-space entry work permit system

A Confined Space Entry Work Permit (see Appendix A) must be completed for

all confined-spaces before entry. This permit documents in writing the

location(s) and type of work to be done, certifies that all existing hazards have

been evaluated by the responsible qualified person(s), and ensures that

necessary control measures have been taken to protect the health and safety

of the employees. Non-permit confined spaces must be identified as such by

documenting that chemical and physical hazards (e.g., oxygen levels, etc.) do

not exist and by writing “Non-Permit Space” in bold print across the work permit.

Permits will expire when the entrance is closed or at the end of the 8-hour work

shift, whichever is sooner.

6.3 Confined-space team

All person(s) entering the space (entrant) should be listed and the designated

standby (attendant) person(s). If applicable, the rotation by the designated

attendant(s) with personnel working in the confined space must be specified.

6.4 Requirements completed prior to entry

a) Detailed health and safety risk assessment should be conducted prior

“PREVIEW COPY ONLY”

Page 118: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 10 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

to commencement of work.

b) If high electrical lines are present in the confined space, the Electrical

Supervisor (or designee) must approve the entry permit.

c) Lockout and tagout/blockout must be done in accordance with TFR

lockout and tagout procedures.

d) Lines, pipes, etc., must be blanked/capped to the extent feasible

before the confined space is entered.

e) If mechanical ventilation is required, site-specific details, such as the

direction of airflow and the placement of the air intake, must be

documented in the “Additional Information” section. The air supply

must be from a clean source: exhaust from vehicles, cranes, earth

compactors, and other potential sources of contaminants must be

considered when locating the blower.

f) The confined space must be emptied and purged of all hazardous

materials to the extent possible prior to entry. A fresh air blower

ventilation system shall be set up and in operation before and during

all inspection and maintenance procedures. If hazardous materials

have been identified or will be used in the confined space, an

Occupational hygienist/Technologist must be present to determine

their concentrations and approve the permit. If these materials

exceed, or have the possibility to exceed the Occupational Exposure

Limits, rescue equipments (e.g., hoist, lifelines, and harness) are

required, and the standby must be CPR trained.

g) Continuous air monitoring will be required for confined space that

cannot be isolated from potential contaminants. For example, flowing

sewers often cannot be blanked off, and continuous air monitoring is

required.

h) When entrance covers are removed, temporary barriers that will

protect the entrants from external hazards, such as vehicles, and

protect pedestrians from falling into the opening must guard

openings.

i) A fire extinguisher must be present if “hot work” is being performed.

“PREVIEW COPY ONLY”

Page 119: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 11 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

j) If ionizing radiation may be present, radiation levels must be

monitored by radiation protection officer/specialist.

k) Required personal protective equipment should be specified before

entering into the confined space as also determined during the risk

assessment. If respiratory protection is required, site-specific details,

such as the type of respirator and cartridges, must be specified.

l) At least one standby person must be present at all times while the

high-risk confined space is occupied. The primary responsibility of the

standby personnel is the health and safety of the occupants in the

confined space. Standby personnel must be in constant visual/radio

contact with the occupants and must immediately notify the TFR Fire

Department and Occupational Health department if there are any

problems. The standby person should always summon emergency

rescue workers, and may never enter a confined space to attempt a

rescue. However, the standby can initiate a non-entry rescue, such

as by operating a hoist or lift.

m) If “hot work” will be performed, a Fire Safety Permit, available from

the Fire Department, must be completed and posted at the entrance

to the space prior to the start of work. All confined spaces become

permit-required confined spaces when hot work is performed in them.

In addition, welding gas cylinders may never be brought into a

confined space.

n) Personnel entering the space must receive confined-space training

prior to entering a permit-required or procedural confined space.

o) Additional lighting equipment may be needed to enable employees to

see well enough to work safely and to exit the space quickly in an

emergency, in these instances, explosion-proof lighting will be

required.

p) The explosion-proof gas monitor must be calibrated monthly and

function checked prior to each daily use. Monitoring the air inside a

confined space should be conducted prior to entering and be

conducted by a competent person. Testing a confined space for

“PREVIEW COPY ONLY”

Page 120: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 12 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

atmospheric hazards should be done remotely before entering, and

should be done in this order: (1) ensure that proper oxygen levels are

present, (2) ensure that combustible gases are not present, (3)

ensure that toxic gases are below the Occupational exposure limit.

Common toxic gases in a confined space could be Hydrogen Sulfide

(H2S) and Carbon Monoxide (CO), but other toxic compounds could

be present.

q) Minimum health and safety equipment required before confined

space entry:

� approved gas detector (properly calibrated and that is in operation

the entire time the employee is in the confined space. This is

necessary due to the possibility of a rapid change in the confined

space atmosphere);

� fresh air blower;

� safety harness, rope, and tripod safety system (A safety harness

and lifeline which is attached to the tripod safety retrieval system);

� an approved hard hat; and

� emergency Action Plan

6.5 Confined-space monitoring procedure

In a confined space it is important to take samples at the top, middle and

bottom to locate varying concentrations of gases and vapours. There are

some gases lighter than air (i.e. methane and other combustible gases)

that can be found at the top of a confined space. There are other gases

that are heavier than air (i.e. hydrogen sulfide) that can settle near the

bottom of a confined space, and still other gases that are the same

weight as air (i.e. carbon monoxide) that can be found throughout a

confined space.

Take air samples at several levels within the confined space and

continuously monitor the space due to the fact that conditions can

change. The confined space must be tested at three levels for each

atmospheric condition. Each level must be tested for a minimum of 60

“PREVIEW COPY ONLY”

Page 121: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 13 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

seconds. The gas detector itself can be lowered into the confined space

atmosphere with a safety line

As the remote air monitoring is completed and the area is safe for entry,

confined space entry permits should be completed and followed. After

the initial entry, monitoring the air in the confined space should be

continuous. A confined space entry attendant or standby should carry

out the continuous monitoring. Conditions in a confined space can

change without warning, due to leakage, toxic vapor release, or

disturbing the contents of the space.

Testing must include: -

• Oxygen content must be at least 19.5% in the confined space,

measured at all levels (bottom, middle, and top). The safe oxygen

level is between 19.5% and 21%. Confined space should not be

entered if the oxygen level is below 19.5% or above 21%. Due to the

extreme danger of suffocation in confined spaces, constant and

continuous oxygen monitoring is required throughout each work

period. Oxygen content above 23% can cause explosions or vigorous

burning of flammable materials, including hair or clothing.

• In circumstances where risk assessment has identified a significant

possibility for the presence of fuels, combustion products, methane

and/or biological action (e.g. oxyacetylene cutting, decontamination of

fuel tanks, sewage systems etc.) the following tests should also be

carried out: -

� Explosive/flammable vapours – limit < 2% LEL (measure

flammability at all levels of the confined space (bottom, middle,

and top). Flammability is measured in terms of the Lower

Explosive Limit (LEL). This is the smallest concentration of a

combustible gas in air that will explode when it contacts a spark or

open flame)

� Hydrogen Sulphide – limit 10ppm (8hour TWA)

� Carbon dioxide – limit 30ppm (8 hour TWA)

Procedure to be followed:

“PREVIEW COPY ONLY”

Page 122: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 14 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

� Record hazard identification of area and/or confined space to be

entered. Reference to additional Permits to Work must be recorded.

� Identify reason for confined space entry

� Confirmation that all necessary isolation and pre-entry activities have

been carried out. Authorised persons are restricted to those who have

received information, instruction and training in this and related Permit

to Work procedures.

� The atmosphere within the confined space must be tested and

confirmed as safe before entry is permitted. Normal practice will be to

test for oxygen content however it may be necessary to test for

flammable/explosive vapours and H2S, with additional parameters

tested if identified as potentially present during the risk assessment

process. Personnel authorised to carry out gas testing are any

competent person deemed competent by the Safety Manager or

Occupational Hygienist.

� A standby man must be present at all times when personnel are in the

confined space, with additional precautions specified to meet

identified risks, e.g. RPE, harness/lift gear, flame proof lighting etc.

First aid, resuscitation and emergency communication equipment

should be made available for circumstances where access to medical

treatment may be restricted and/or a need for such equipment is

identified during the risk assessment process. All equipment must be

checked and verified as fit for use before entry of the confined space

takes place.

� No person shall enter a confined space to retrieve someone who is

unconscious without having required personnel above ground to

assist. The person entering the confined space for rescue purposes

must be equipped with the required rescue equipment and follow the

specific rescue procedure.

� Confined space authorised person to confirm pre-entry checks have

been completed satisfactorily. If breathing apparatus is required

specify type.

“PREVIEW COPY ONLY”

Page 123: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 15 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

� The person carrying out the work or the supervisor to confirm

acceptance of conditions imposed by the permit.

� All personnel entering the confined space must confirm acceptance of

the conditions imposed by the permit.

� The permit must be returned at the end of the day or on completion of

the work. Should it be necessary to carry on work the following day a

new work permit should be issued. The person carrying out the work

or the supervisor must sign the permit to indicate that all equipment

has been withdrawn or made safe.

� The authorised person must cancel the permit by signing it off.

“PREVIEW COPY ONLY”

Page 124: “PREVIEW COPY ONLY” · 2013-10-01 · • The OFC tension requires that a back-guy be provided for the wooden ... canal, road, railway, runway, sewer or water reticulation system

STANDARD OPERATING PROCEDURE DOCUMENT: SOP-OH 00???

REVISION: 00-01

CONFINED SPACE DATE: 01/01/2008

PAGE: 16 OF 16

THE REGISTERED RECIPIENT IS RESPONSIBLE FOR DESTROYING ALL SUPERCEDED

DOCUMENTS

Appendix A. Confined Space Entry Work Permit

JOB INFORMATION

Permit start date and time Permit end date and time

Site Location/Description

Task

TYPE OF CONFINED SPACE

Low Risk High Risk

Standby List confined space team:

Entrants

REQUIREMENTS REQUIRED PRIOR TO ENTRY:

YES NO YES NO

Risk assessment conducted Fire extinguisher

Electrical lines present Radiation

Lockout/tagout completed PPE

Lines blanked/capped Radio contact

Ventilation Emergency plan

Hazardous materials identified Hot work permit

Standby CPR trained Confined space training

Lifelines (e.g. hoist, tripod, harness) Lighting explosion proof

Gas monitoring conducted Special instructions

Secure area/barriers

MONITORING RESULTS

Instrument Model and serial number

Instrument calibration date

Instrument calibration reading

Oxygen %

Flammability %

Other Contaminants:

ADDITIONAL INFORMATION

APPROVAL SIGNATURES

Supervisor Date:

Occupational Hygienist/Technologist Date:

“PREVIEW COPY ONLY”