API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management. Don Wells Hess Corporation. History / Status. Document released in 2009 Specificatio n contains: Life Cycle Process ( LCP ) Define, Plan, Implement, Feedback ( DPIF ) Loop 12 Key Practices ( KP ) - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/1.jpg)
API 17NSubsea Production System Reliability, Integrity,
and Technical Risk Management
Don WellsHess Corporation
![Page 2: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/2.jpg)
History / Status
• Document released in 2009• Specification contains:
– Life Cycle Process (LCP)– Define, Plan, Implement,
Feedback (DPIF) Loop– 12 Key Practices (KP)– Technology Qualification
Process– Technology Readiness Level
![Page 3: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/3.jpg)
Initial Plan / Path Forward
• Process– Split into 5 subgroups (now 6)– Industry Leaders– Common Template
• Introduce IM into the scope of 17N:– Define IM– Expand the Life Cycle Processes– Reassessment through remediation– Define TRL progression
![Page 4: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/4.jpg)
Detail
• Expand the Life Cycle Process– Provides balance and depth to the document– Communication of goals & requirements
4
Feasibility
Concept Selection
FEED Detailed Design
Manufacturing & Assembly
SIT, Installation, & Commissioning Operation
Decommissioning
![Page 5: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/5.jpg)
Detail
• Change to a Dual-DPIF loop– Add Remediation cycle – Facilitates Integrity Management
![Page 6: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/6.jpg)
Specification Development(Greenfield Projects)
Define Goals and Requirements
KP1
Planning and Organisation
KP2
Design and Deliver for reliability and Integrtity
KP3
Evaluate ResultsKP3
Feedback and AssuranceKP4
Verification and Validation KP6
Project risk managementKP7
Risk and RAM AnalysisKP5
Supply Chain Management
KP10
Management of ChangeKP11
Performance tracking and data management
KP9
Core Processes
Qualification of Technology
KP8
Organisational LearningKP12
Supporting Processes
![Page 7: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/7.jpg)
Defineü SegmentsüRisksüMitigations
Planü Inspections üMonitoring ü Testing
Implementü Data collectionü Data analysisü Performance
evaluation
Evaluate ü Analyse dataü Evaluate against
requirements
Feedback üAssuranceü Lessons Learnt
Are Requirements
met?
DefineüCorrective actions üRemediation actionsüQualification actionsü Intervention actions
PlanüCorrective actionsüRemediation actionsüQualification actionsü Intervention actions
Implementü Interventionü Changesü Performance
improvement
Evaluate ü TestsüChange implementedüAgainst requirements
Operational Reliability and Integrity
Assurance cycle
Remediation and corrective action cycle
Specification Development(Brownfield Projects)
..and acceptance
criterion
![Page 8: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/8.jpg)
Deadline for comments on ‘November 1st
issue’
December 10thNovember 1st
Issue of complete document (Main section and ALL
Annexes)
October 14thAugust 21st January 31st
Final API RP 17N Issue
Deadline for comments on ‘August 21st
issue’
Issue of document (Main
section and Annexes A & C)
API RP 17N Meeting to discuss high level
comments and comments from decomworld
conference
API RP 17N Meeting November 1st to introduce
comments spread sheet and close out outstanding
comments.
API RP 17N Meetings
Key dates
October 15th October 28th January 13th
Meeting to close out outstanding comments.
Current Progress
• Progressed Plan as Presented in Previous Meetings
![Page 9: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/9.jpg)
Progress
• Workshop held in Washington– Solicited Input from outside of 17N – Minutes and Summary Document distributed to all
participants– Feedback incorporated into 17N
![Page 10: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/10.jpg)
Progress
• Workgroups Submitted Input – Using Common Template
• Edited into a Single Document– Astrimar
• Circulated for Comment within 17N Committee– 3 rounds, 1,000+– Last Comments Due Dec 10th – Clarification Discussions at Jan 13th meeting
![Page 11: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/11.jpg)
Progress
• Comments have been Prioritized – Are currently being included
• Not full Fidelity for all comments / subjects– Decommissioning– Obsolescence– Field Life Extension– Human Factors– Configuration Management / MOC
– Final Document Due January 31+
![Page 12: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/12.jpg)
17Q History• Plans for API 17Q
– Last meeting, we were asked to blend 17Q into 17N– Work indicated that this was not best approach– Rationale
• Different Subjects• Qualification Not Unique to 17N• Expect Revision at a Different Rate
– Qualification /Verification details from 17N will be Incorporated into 17Q
![Page 13: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/13.jpg)
17Q Plans• Path Forward
– 17Q Committee to establish current Status• January 30th
– Define an “Ideal” version– Define a “Minimum” version– Make decision on Path Forward
• Minimum Version of Document – with planned future revision
• Ideal Version plus Technical Report & Work Plan• Organizational Needs• Funding Needs• Schedule
![Page 14: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/14.jpg)
Plans
• Original Plans included a “Pre-Ballot” Workshop– Change of Plans
• Not a New Document• Large Active Committee• Potential to Circulate to Washington Workshop attendees
– OK?
• OTC Paper submitted– Presentation as part of API 17 Session
![Page 15: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/15.jpg)
Next
• Complete Planned Activities– Deliver Summary Report on Completion
• Recommended Next Steps
• Issue Document to API • Format, Ballot, etc.
Question• How do we “Deliver” to Industry
– API University– Industry Training
![Page 16: API 17N Subsea Production System Reliability, Integrity, and Technical Risk Management](https://reader035.vdocument.in/reader035/viewer/2022062423/56814e7e550346895dbc1b9b/html5/thumbnails/16.jpg)
Thanks You’s
• To Everyone Involved– Workgroup Leaders– Participants– Workshop Attendees– Astrimar– BSEE
• Large Amount of Effort by everyone• Large amount of detail developed, considered and
Worked• Even with the Growth in Scope, effort continued and
quality maintained• A great deal of quality work was completed!