app 11.3 transmission unit cost study snc lavalin
Embed Size (px)
TRANSCRIPT
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
1/38
Deliverable 2
Unit Cost Estimates for Transmission Lines
and Facilit ies in Northern Ontario and
the Far North
Presented to
Ontario Power Authority
October 18, 2011
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
2/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 2 of 38
NOTICE
This document contains the expression of the professional opinion of SNC-Lavalin Inc.
(“SLI”) as to the matters set out herein, using its professional judgment and reasonable
care. It is to be read in the context of the agreement dated June 24,2011(the
“Agreement”) between SLI and * (the “OPA”), the methodology, procedures andtechniques used, SLI’s assumptions, and the circumstances and constrains under which
its mandate was performed. This document is written solely for the purpose stated in
the Agreement, and for the sole and exclusive benefit of the OPA, whose remedies are
limited to those set out in the Agreement. This document is meant to be read as a
whole, and sections or parts thereof should thus not be read or relied upon out of
context.
SLI, in preparing the cost estimates, has exercised due care consistent with the
intended level of accuracy, using its professional judgment and reasonable care, and is
thus of the opinion that there is a high probability that actual costs will fall within thespecified error margin. However, no warranty should be implied as to the accuracy of
estimates. Unless expressly stated otherwise, assumptions, data and information
supplied by or gathered from other sources (including the OPA, other consultants,
testing laboratories and equipment suppliers, etc.) upon which SLI’s opinion as set out
herein is based on has not been verified by SLI; therefore SLI makes no representation
as to its accuracy and disclaims all liability with respect thereto.
SLI disclaims any liability to the OPA and to third parties in respect of the publication,
reference, quoting, or distribution of this report or any of its contents to and reliance
thereon by any third party.
SNC-Lavalin as the selected proponent having entered into this agreement through the
Response For Proposal (RFP) process and in accordance with terms set out within said
proposal, shall not be precluded from participating in bidding on any other requests in relation to
this, or any other work associated with this proposal.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
3/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 3 of 38
TABLE OF CONTENTS
1. Overview ............................................................................................................................. 4
2. Study Methodologies and Assumptions .............................................................................. 4
3. Unit Cost Findings, including summarized results as provided in Tables 3, 4, 5 .................. 9
4.
Supporting Evidence and Benchmarks ..............................................................................18
APPENDICES ...........................................................................................................................20
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
4/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 4 of 38
This report provides unit cost estimates for transmission lines and facilities in NorthernOntario and the Far North.
1. Overview
For the purposes of this study the delineation between “Northern Ontario” and the “Far
North” will be used as defined by the Ontario Ministry of Natural Resources (see Map 1
in Appendix 1). Northern Ontario includes the region north of Sudbury from Manitoba to
Quebec extending to the Far North Boundary. Most of this area is currently connected
to the grid and most communities have all season road access. In the Far North, there
are 26 remote communities (communities not accessible by all-season roads) and theTown of Pickle Lake. The majority of communities in the Far North are not connected to
the grid and are powered by local diesel systems. Of these remote communities there
are 20 which are located north of Pickle Lake, for which the OPA has been directed to
develop a plan for transmission connection.
For the purposes of this study, it is assumed that public lands are owned by the Crown
and access rights must be acquired from the Crown. The project cost information,
therefore will not include considerations of First Nations Impact-Benefit Agreements as
they are difficult to quantify and are assumed to be settled through consultation and
negotiation within the context of any specific project.
This deliverable will identify and summarize each facility type and cost category, the
costs of building transmission lines and facilities in the remote areas of the Far North
separately from the rest of Northern Ontario. Some of the conditions that are expected
to be encountered in remote locations include lack of road access or limited seasonal
road access, reduced work seasons for completing EAs and other development and
construction work and operating in rough undeveloped terrain.
2. Study Methodologies and Assumptions
Remote community connections include development of transmission line corridors to
enable grid connection. In order to select the line options and the location of
transformer stations it will be necessary to map a full range of environmental criteria as
well as the surficial geology so that sensitive features or areas can be avoided. Some
of the general environmental criteria which can be mapped to assist with the route
selection include:
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
5/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 5 of 38
• Ecological Areas of Concern (Vegetation/Wildlife);
• Land-cover/Land-use;
• Species at Risk Habitat/Breeding Areas;
• Land Ownership;
• Road Networks;
• Existing Transmission Lines;
• Watercourses and Waterbodies;
• Surficial geology;
• Mineral Deposits;
• Archaeological Sites;• National Parks, Provincial Parks and Conservation Reserves;
• Woodland Caribou Herds and Migration Routes; and
• Communities/Populated Places.
3.1.2. Right-of-Way and Site Acquisition Cost
Land will be required to accommodate the ROW for the transmission lines and
associated facilities for the projects. From the review of the preliminary corridors for the
transmission lines, and due to the fact that the study area is located in a remote region
of northern Ontario, we have assumed the lands required for the projects will primarilybe “Public Land”. Public (Crown) lands owned by the province and are under the
jurisdiction of the Ministry of Natural Resources (MNR) with respect to their control and
management. Under this scenario, the MNR policy for Utility Corridors on Public Lands
(Policy 4.10.03, October 2006) is applicable to the projects. This policy provides a
standardized approach to granting of tenure and establishment and collection of rent for
the occupation of public land by utility companies. The annual rental formula is based
on land value per hectare (ha), multiplied by the area occupied, multiplied by impact on
fee simple (75% for transmission lines and facilities) and multiplied by the annual rate of
return (8-10 %). For costing purposes we have assumed the following ROW widths for
the project in the study.
LINE DESCRIPTION ROW, in meters (typical)
2-cct 230 kV, lattice towers 40
1-cct 230 kV, lattice towers 30
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
6/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 6 of 38
1-cct 230 kV, H-frame wood poles 30
2-cct 115 kV, lattice towers 30
1-cct 115 kV, H-frame wood poles 30
1-cct 115 kV, single wood pole 20
NOTE: ROW width is a function of span length, line voltage, height of the structures.
For example using the 1-circuit 230 kV transmission line option from Ignace to PickleLake with a length of 295 Km and assumed ROW width of 30 m, the following cost
estimate (annual rental) is derived.
Land – $1,062,000 (1,180 ha x market value of $1,200/ha for northwest Ontario) x 75 %
(impact on the fee simple) x 10% (established/assumed rate of return by MNR) =
$79,650 annually or $270 per Km.
The above formula has also been applied to determine annual rental cost for site
facilities (e.g., transformer stations).
Annual rental cost for crown land required for the transmission line project andassociated facilities is presented in Tables 1 thru 4. These costs are not included in the
total cost or the unit costs per kilometer.
3. General Engineering Considerations
• 2011 unit costs for Project Management, Engineering Procurement Management,
Project Controls, Construction Management, Quality, Safety and Environmentalsupport were provided by the SNC-Lavalin procurement group
• All construction activities were estimated per unit cost/activity as per our defined
Work Breakdown Structure (WBS).• The cost of tower steelwork is assumed to be $3.00 per kg. This was developed
from a current 5 year term agreement with an existing supplier and is based upon
today’s market prices (as with all commodities, current pricing is no guarantee of
future trends) with the addition of transportation costs.
• Allowances were included for stand down due to bad weather.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
7/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 7 of 38
• Helicopter rates used:
o Foundation work: $5000 per hour
o Assembly and Erection: $7,500 per hour
o Stringing: $5,000 per hour
• Camp accommodation rate is $200 per day per man (food, showers, laundrywashing etc)
• Productivity in winter from November to February has been reduced by 20%. Afurther 20% allowance has been included for exceptional weather during
December and January.
Assumptions of the cost estimates to supply Northern Ontario
• To develop the unit rates the route lengths considered are:
o 230kV 300 km
o 115kV 200 km
o 44kV 50 km
o 25kV 50 km
• Excluding tower steelwork, a 3% allowance is included on top of standard
Delivered Duty Paid (DDP) prices for transportation of materials.• Adequate road infrastructure exists the length of the line routes
• There is no adequate road infrastructure intersecting the line routes
• Terrain is considered level or gently rolling
• Soil condition is considered rock
• Geo-tech boreholes every fourth structure
• Heavy brushing for 50% line routes
• Three marshaling yards each 2.5 acre located along the 230kV and 115kV line
routes
• No marshalling yard for 44kV and 25kV
• Installation of 5 meter wide temporary access road for 50% of the line routes
• Helicopters assist in construction activities of the 230kV and 115kV
• Helicopters will not support the construction activities of the 44kV and 25kV
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
8/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 8 of 38
Assumptions of the cost estimates to supply the Far North
• To develop the unit rates the route lengths considered are:
o 230kV 200 km
o 115kV 200 km
o 44kV 50 km
o 25kV 50 km
• A 25% allowance is included on top of standard DDP prices for transportation ofmaterials.
•
There is no adequate road infrastructure existing the length of the line routes andno adequate road infrastructure intersecting the line routes
• Terrain is considered level or gently rolling
• Soil condition is considered rock and muskeg
• Geo-tech boreholes every fourth structure
• Heavy brushing for 75% line routes
• Three marshaling yards each 2.5 acre located along the 230kV and 115kV lineroutes
• No marshalling yard for 44kV and 25kV
• 5 meter wide temporary access road for 100% length of line is assumed
• Helicopters will fully support all construction activities
Fibre Optic Communications Options:
• All substation schemes in these estimates are considered to have protection,
telecom and SCADA. As the most economic solution the telecom considered is
fiber optic. As such the fiber optic infrastructure cost is included in all substation
schemes, in the “Total Cost”. The cost is not presented separately.
•
The telecom identified in the substation schemes must be supported by atransmission infrastructure. This fibre optic infrastructure on the transmission
and distribution lines is separate from the commercial communications
equipment discussed below.
• Commercial fibre optic equipment in the substation schemes has not been
considered.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
9/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 9 of 38
• For transmission line estimates, the base cost has been presented with the cost
of overhead steel earth wire only and the cost of Power Line Carrier (PLC)
facilities. Cost for the fibre optic infrastructure required for substation telecom
requirements is shown separately in the column labeled “Cost of Fibre Optic
Comms”. This cost includes one 48 fibre OPGW, accessories and repeater
stations, which is sufficient for substation requirements only. Some spare fibres
may be available for commercial use, but accessories and repeater stations
would have to be modified or added to allow for commercial fibre optic
applications.
Exclusions:
For the purposes of this study, the following factors were not included in the estimates:
• Disbursements to land owners/occupiers
• Type testing and third party quality testing and inspection
• Environmental mitigation
4. Unit Cost Findings, including summarized results as provided in Tables 3, 4, 5
Development work estimates shown in the applicable cost tables were based on theidentified routes and assumed transformer stations locations for the purpose ofcompleting environmental assessments, securing all environmental permits/approvalsand obtain land tenure for the transmission lines and facilities identified in NorthernOntario and the Far North.
Single Line Diagrams (SLD) were developed in order to prepare detailed technical datarequired for the estimates. These SLDs were the basis of cost tables 4 and 5, and areincluded in Appendix 3.
3.1 Unit Cost Findings for Northern Ontario
The study findings for lines and facilities in Northern Ontario are summarized in the costtables shown below.
Assumptions used in the development of the estimates are outlined in section 2.Technical details used in the estimates are included in Appendix 2.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
10/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 10 of 38
Cost estimates in Northern Ontario are generally higher than in the Southern part of theprovince due to the lesser availability of infrastructure and higher transportation costsfor labour, equipment and material. Whereas construction in Southern Ontario is notusually affected much by winter weather, more severe winter weather in NorthernOntario will reduce productivity. Foundation installations in Southern Ontario aregenerally less costly to work with due to the soil conditions than in Northern Ontariowhere bedrock are frequently found in many parts.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
11/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 11 of 38
Table 3A – Unit Costs per kilometer for new lines in Northern Ontario.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
12/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 12 of 38
Table 4A – Unit Costs for new Transmission Facilities i n Northern Ontario
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
13/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 13 of 38
Table 5A – Detailed Description of New Transmission Facilities in Northern Ontario
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
14/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 14 of 38
3.2 Unit Cost Findings for the Far North
The study findings for lines and facilities in the Far North are summarized in the costtables shown below.
Assumptions used in the development of the estimates were outlined in section2. Fortechnical details used in the estimates refer to Appendix 2.
It was expected that cost estimates in the Far North are generally higher than inNorthern Ontario. The Far North generally has limited infrastructure causing significantlyhigher transportation costs for labour, equipment and material. More construction
access will be required in the Far North adding to the higher cost, or, where not possibledue to muskeg for example, winter construction will be required. Winter constructionhowever, affects productivity to a much higher extent than in Northern Ontario; reduceddaylight reduces work hours as well.
Foundation installation in the Far North is also expected to be costlier due to permafrostand muskeg conditions.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
15/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 15 of 38
Table 3B – Unit Costs per ki lometer for new lines in the Far North.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
16/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 16 of 38
Table 4B – Unit Costs for new Transmission Facilities in the Far North
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
17/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 17 of 38
Table 5B – Detailed Description of New Transmission Facilities in the Far North
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
18/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 18 of 38
5. Supporting Evidence and Benchmarks
Detailed parameters used in the development of the cost estimates are included in
Appendix 2.
Given our extensive exposure to the Transmission and Distribution markets,ongoing work within the province and complimentary relationships within thegeographical study area, we are confident of the basis of the estimates producedwithin the constraints of this submission.
The cost estimates for Northern Ontario and The Far North are comparable (withinthe constraints of this submission and without breaching commercialconfidentialities) with the following studies by SNC Lavalin:
• The Northland Study ( 2011)
• The Nishnawabe Aski Development Fund (NADF) Study in Northern Ontario(2009, basis of estimate 2007)
• Goldcorp’s Red Lake Project (2011)
All of the above projects utilized a single circuit 115kV transmission line H-framedesign, although each project, as with almost any transmission project contained
unique characteristics, such as timing, specifications, access, constructionmethodologies and location.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
19/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 19 of 38
Level of construction difficulty and cost impact comparisons throughout the threeregions of the province.
Activ ity /Cond iti ons Southern Ontario CostImpact
Northern Ontario CostImpact
The Far North CostImpact
Access Direct access to Right of Way 1 In areas terrain restricts access.Muskeg. Lack of roads.
1.2 Terrain greatly restricts access.Significant muskeg. Nosupporting infrastructure.
1.5
Soil conditions Till type. Possibly augerfoundations.
1 Mixture: Till, broken rock, muskegand permafrost.
1.2 Mixture: Broken rock, muskegand permafrost.
1.5
Average Difficult Very difficultWeather Yearlong installation.
Unaffected by winter1 Yearlong installation but in areas
terrain restricts installation towinter. Some severe winterconditions. Inefficiencies duringwinter.
1.2 Terrain greatly restrictsinstallation to winter. Longerfreezing periods and moresevere winter conditions.
1.5
Average Difficult Very difficult
Transportation ofresources
Project locations within reachof central developed areas.
1 Terrain and remoteness providessome restrictions. Somespecialized transport required.Inefficiencies.
1.2 Difficult terrain and remote.Inefficiencies. Costly specialtransportation required.
1.5
Average Difficult Very difficult
Transportation ofequipment andmaterial
Project locations within reachof central developed areasand logistic resources.
1 Terrain and remoteness providessome restrictions. Logisticresources not readily availableand some specialized transportrequired.
1.2 Difficult terrain and remote.Costly logistics. Specializedtransport required.
1.5
Average Difficult Very difficult
Local logistics Local accommodations readilyavailable.
1 Requires fully equippedconstruction camps.
1.2 Requires fully equippedconstruction camps. Costly dueto remoteness.
1.5
Average Difficult Very difficult
Staging areas andConstruction yards
Minimal preparation and effort.In direct reach of developedareas.
1 Staging areas required. Terrainrestricts direct delivery.
1.2 Staging areas required. Terrainand remoteness restricts directdelivery.
1.5
Average Difficult Very difficult
OVERALL Least difficult to construct. Average.
1 Average to difficult constructability. 1.2 Most difficult to construct. 1.5
Average costmultiplier
1 1.2 1.5
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
20/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 20 of 38
APPENDICES
Appendix 1 – Northern Ontario and The Far North Delineation map.
Appendix 2 – Single Line Diagrams
Appendix 3 – Design Considerations
Appendix 4 – Environmental Assessment
Appendix 5 – Maps
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
21/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 21 of 38
APPENDIX 1
Northern Ontario and the Far North
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
22/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 22 of 38
APPENDIX 2
The Single Line Diagrams (SLD) shown in this appendix were developed in order toprepare detailed technical data required for the estimates. These SLDs were the basisof cost tables 4 and 5.
SLD 1: 230/115Kv 250MVA, 230/115Kv 125MVA Substation
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
23/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 23 of 38
SLD 2: 114/44Kv 20MW, 115/25Kv 10MW, 44/25Kv 5MW SubstationNote: Same SLD is used for Table 2 and Table 4
SLD 3: 115Kv Single Tap-3 Terminations
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
24/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 24 of 38
SLD 4: 115Kv Single Tap-1 TerminationNote: Same SLD is used for 230Kv and 115Kv Single Tap- 1 Termination
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
25/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 25 of 38
APPENDIX 3
Design considerations included in the estimate scope:
Table 3: Unit Cost Per Kilometer for New Lines in Northern Ontario and the Far
North
230Kv S/C & D/C (Lattice) transmission lines
• The tower weight is estimated based on preliminary design of the Hydro 1“X” tower family
•
220 meter ruling span; within the “X” tower family parameters• 1 x 795 ACSR conductor
• Concrete drilled pile foundations; four per tower, 2.1meter diameter,
8meter depth
115Kv S/C (Wood pole) transmission lines
• Standard wood pole; Western Red Cedar Pole (WRC)
• 120 meter ruling span; within the WRC parameters for a single
• 120 meter ruling span; within the WRC parameters for a twin pole
structure
• 1 x 477 ACSR conductor per phase
• Wood pole are direct buried, supported with anchor included for 50% oftangents and 100% of angles/dead ends
• 10% screw pile foundations are included to support structures in abnormalconditions
44Kv S/C (Wood pole) transmission lines
• Standard wood pole; Western Red Cedar Pole (WRC)
• 120 meter ruling span; within the WRC parameters 1 x 336 ACSR
conductor
• Wood pole are direct buried, supported with anchor included for 50% of
tangents and 100% of angles/dead ends• 10% screw pile foundations are included to support structures in abnormal
conditions
25Kv S/C (Wood pole) transmission lines
• Standard wood pole; Western Red Cedar Pole (WRC)
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
26/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 26 of 38
• 120 meter ruling span; within the WRC parameters 3/0 Pigeon ACSRconductor
• Wood pole are direct buried, supported with anchor included for 50% oftangents and 100% of angles/dead ends
• 10% screw pile foundations are included to support structures in abnormalconditions.
Table 4: Unit Cost for New Transmission Facilities in Northern Ontario and theFar North
• For the estimate the substation scopes considered are:230/115Kv 250MVA Auto Transformer TS Substation
• Site development is approximately 100 x 70 meters
• 100 meter access road
• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 1 x 250MVA 230/115Kv LTC Transformer
• 1 x 245Kv, 1200A, Live Tank Circuit Breaker
• 3 x 230Kv CVT• 1 x 230Kv Motor Operated Air Switch c/w Grounding Switch
• 3 x 240Kv Surge Arrestors
• 4 x 115Kv, 2000A, Dead Tank Circuit Breaker
• 8 x 115Kv Manually Operated Air Switch
• 9 x 115Kv CVT
• Control building
• Install SCADA, Telecom, P&C system
• Install 2 x Station Service Transformers for substation loads
• Install DC Charger and Battery System for P&C
230/115Kv 125MVA Auto Transformer TS Substation
• Site development is approximately 100 x 70 meters
• 100 meter access road
• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
27/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 27 of 38
• 1 x 125MVA 230/115Kv LTC Transformer
• 1 x 245Kv, 1200A, Live Tank Circuit Breaker
• 3 x 230Kv CVT
• 1 x 230Kv Motor Operated Air Switch c/w Grounding Switch
• 3 x 240Kv Surge Arrestors
• 4 x 115Kv, 2000A, Dead Tank Circuit Breaker
• 8 x 115Kv Manually Operated Air Switch
• 9 x 115Kv CVT
• Control building
•
Install SCADA, Telecom, P&C system• Install 2 x Station Service Transformers for substation loads
• Install DC Charger and Battery System for P&C
114/44Kv 10MVA Step Down TS Substation
• Site development is approximately 60 x 40 meters
• 100 meter access road
• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 1 x 10 MVA 115/44Kv LTC Transformer• 1 x 115Kv, 600A, Dead Tank Circuit Breaker
• 3 x 115Kv CVT
• 3 x 44kv PT
• 1 x 115Kv Motor Operated Air Switch c/w Grounding Switch
• 6 x 96Kv Surge Arrestors
• 3 x 44Kv, 600A Circuit Breaker
• 6 x 44Kv Manually Operated Air Switch
• 1 x 44Kv Bypass Fuse Switch
• Control building
• Install SCADA, Telecom, and P&C system
• Install Station Service Transformer for substation loads
• Install DC Charger and Battery System for P&C
114/44Kv 5 MVA Step Down TS Substation
• Site development is approximately 60 x 40 meters
• 100 meter access road
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
28/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 28 of 38
• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 1 x 5 MVA 115/44Kv LTC Transformer
• 1 x 115Kv, 600A, Dead Tank Circuit Breaker
• 3 x 115Kv CVT
• 3 x 44kv PT
• 1 x 115Kv Motor Operated Air Switch c/w Grounding Switch
• 6 x 96Kv Surge Arrestors
•
3 x 44Kv, 600A Circuit Breaker• 6 x 44Kv Manually Operated Air Switch
• 1 x 44Kv Bypass Fuse Switch
• Control building
• Install SCADA, Telecom, and P&C system
• Install Station Service Transformer for substation loads
• Install DC Charger and Battery System for P&C
115/25Kv 5 MVA Substation
• Site development is approximately 60 x 40 meters
• 100 meter access road• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 1 x 5 MVA 115/25Kv LTC Transformer
• 1 x 115Kv, 600A, Dead Tank Circuit Breaker
• 3 x 115Kv CVT
• 1 x 115Kv Motor Operated Air Switch c/w Grounding Switch
• 6 x 96Kv Surge Arrestors
• 3 x indoor GIS 25Kv, 600A Circuit Breakers
• Control building
• Install SCADA, Telecom, and P&C system
• Install Station Service Transformer for substation loads
• Install DC Charger and Battery System for P&C
115/25Kv 3 MVA Substation
• Site development is approximately 60 x 40 meters
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
29/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 29 of 38
• 100 meter access road
• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 1 x 3 MVA 115/25Kv LTC Transformer
• 1 x 115Kv, 600A, Dead Tank Circuit Breaker
• 3 x 115Kv CVT
• 1 x 115Kv Motor Operated Air Switch c/w Grounding Switch
• 6 x 96Kv Surge Arrestors
•
3 x indoor GIS 25Kv, 600A Circuit Breakers• Control building
• Install SCADA, Telecom, and P&C system
o Install Station Service Transformer for substation loads
o Install DC Charger and Battery System for P&C
44/25Kv 2 MVA Substation
• Site development is approximately 60 x 40 meters
• 100 meter access road
• 110% Oil Containment
• Screw pile foundations for muskeg• Spread footing foundations for rock
• 1 x 2MVA 44/25Kv LTC Transformer
• 1 x 44Kv, 600A Circuit Breaker
• 3 x 44Kv CVT
• 1 x 44Kv Motor Operated Air Switch c/w Grounding Switch
• 6 x 44Kv Surge Arrestors
• 3 x indoor GIS 25Kv, 600A Circuit Breakers
• Control building
•
Install SCADA, Telecom, and P&C system• Install Station Service Transformer for substation loads
• Install DC Charger and Battery System for P&C
230Kv Single Tap – 3 Termination Substation
• Site development is approximately 70 x 70 meters
• 100 meter access road
• 110% Oil Containment
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
30/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 30 of 38
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 4 x 245Kv, 1200A, Live Tank Circuit Breaker
• 12 x 230Kv CVT
• 12 x 230Kv CT
• 4 x 230Kv Motor Operated Air Switch c/w Grounding Switch
• 3 x 230Kv Surge Arrestors
• 8 x 230Kv Manually Operated Air Switch
• Control building
•
Install SCADA, Telecom, P&C system• Install 2 x Station Service Transformers for substation loads
• Install DC Charger and Battery System for P&C
230Kv Single Tap – 1 Termination Substation
• Site development is approximately 60 x 40 meters
• 100 meter access road
• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 1 x 245Kv, 1200A, Live Tank Circuit Breaker• 3 x 230Kv CVT
• 3 x 230Kv CT
• 2 x 230Kv Motor Operated Air Switch c/w Grounding Switch
• 3 x 230Kv Surge Arrestors
• Control building
• Install SCADA, Telecom, P&C system
• Install Station Service Transformer for substation loads
• Install DC Charger and Battery System for P&C
115Kv Single Tap – 3 Termination Substation• Site development is approximately 70 x 70 meters
• 100 meter access road
• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 4 x 115Kv, 600A, Dead Tank Circuit Breaker
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
31/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 31 of 38
• 12 x 115Kv CVT
• 4 x 115Kv Motor Operated Air Switch c/w Grounding Switch
• 12 x 115Kv Surge Arrestors
• 8 x 115Kv Manually Operated Air Switch
• Control building
• Install SCADA, Telecom, P&C system
• Install 2 x Station Service Transformers for substation loads
• Install DC Charger and Battery System for P&C
115Kv Single Tap – 1 Termination Substation
• Site development is approximately 60 x 40 meters
• 100 meter access road
• 110% Oil Containment
• Screw pile foundations for muskeg
• Spread footing foundations for rock
• 1 x 115Kv, 600A, Dead Tank Circuit Breaker
• 3 x 115Kv CVT
• 2 x 115kkV Motor Operated Air Switch c/w Grounding Switch
• 3 x 115Kv Surge Arrestors
• Control building• Install SCADA, Telecom, P&C system
• Install Station Service Transformers for substation loads
• Install DC Charger and Battery System for P&C
Table 5: Detailed Description of New Transmission Facilities in Northern Ontarioand the Far North
For the estimate the substation scopes considered are:
One Incremental 230/115Kv 250MVA Line Termination
• 1 x 115Kv, 1200A, Dead Tank Circuit Breaker
• 2 x 115Kv Manually Operated Air Switch
• Modify the existing bus and install 1 x dead end structure
• Update and modify the SCADA, Telecom, and P&C system
Spare Onsite 230/115Kv 250MVA Transformer (not connected)
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
32/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 32 of 38
• 1 x 230/115Kv 250MVA LTC Auto Transformer
• 110% oil containment transformer foundation
One Incremental 230/115Kv 125MVA Line Termination
• 1 x 115Kv, 1200A, Dead Tank Circuit Breaker
• 2 x 115Kv Manually Operated Air Switch
• Modify the existing bus and install 1 x dead end structure
• Update and modify the SCADA, Telecom, and P&C system
Spare Onsite 230/115Kv 125MVA Transformer (not connected)
• 1 x 230/115Kv 125MVA LTC Auto Transformer• 110% oil containment transformer foundation
One Incremental 114/44Kv 5MVA Line Termination
• 1 x 44Kv, 600A, Dead Tank Circuit Breaker
• 1 x 44Kv bypass switch with fuse
• Modify the existing bus and install 1 x dead end structure
• Update and modify the SCADA and P&C system
Spare Onsite 115/44Kv 5MVA Transformer (not connected)
• 1 x 115/44Kv 5MVA LTC Transformer• 110% oil containment transformer foundation
One Incremental 114/44Kv 3MVA Line Termination
• 1 x 44Kv, 600A, Dead Tank Circuit Breaker
• 1 x 44Kv bypass switch with fuse
• Modify the existing bus
• Update and modify the SCADA and P&C system
Spare Onsite 115/44Kv 3MVA Transformer (not connected)
•
1 x 115/44Kv 3MVA LTC Transformer• 110% oil containment transformer foundation
One Incremental 114/25Kv 5MVA Line Termination
• 1 x indoor GIS 25Kv, 600A Circuit Breakers
• 1 x 25Kv bypass switch with fuse
• Update and modify the SCADA and P&C system
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
33/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 33 of 38
Spare Onsite 115/25Kv 5MVA Transformer (not connected)
• 1 x 115/25Kv 5MVA LTC Transformer
• 110% oil containment transformer foundation
One Incremental 114/25Kv 3MVA Line Termination
• 1 x indoor GIS 25Kv, 600A Circuit Breakers
• 1 x 25Kv bypass switch with fuse
• Update and modify the SCADA and P&C system
Spare Onsite 115/25Kv 3MVA Transformer (not connected)
• 1 x 115/25Kv 3MVA LTC Transformer
• 110% oil containment transformer foundation
One Incremental 44/25Kv 2MVA Line Termination
• 1 x indoor GIS 25Kv, 600A Circuit Breakers
• 1 x 25Kv bypass switch with fuse
• Update and modify the SCADA and P&C system
Spare Onsite 44/25Kv 2MVA Transformer (not connected)
• 1 x 44/25Kv 2MVA LTC Transformer
• 110% oil containment transformer foundation
One Incremental 230Kv Single Tap
• 2 x 245Kv, 1200A, Live Tank Circuit Breaker
• 6 x 245Kv CT
• 6 x 245kv CVT
• 4 x 245Kv, Manually Operated Air Switch
• Modify existing bus and install dead end structures.
• Modify and upgrade SCADA, Telecom, and P&C system
One Incremental 115Kv Single Tap• 2 x 115Kv, 600A, Dead Tank Circuit Breaker
• 6 x 115Kv CVT
• 4 x 115Kv, Manually Operated Air Switch
• Modify existing bus and install dead end structures
• Modify and upgrade SCADA, Telecom, and P&C system
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
34/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 34 of 38
APPENDIX 4
ENVIRONMENTAL ASSESSMENT
The Ontario Ministry of the Environment (MOE) has developed environmental
assessment (EA) requirements for electricity projects. These requirements are set out in
Regulation 116/01 (referred to as the “Electricity Projects Regulation”), made under the
Environmental Assessment Act (EAA). In the MOE “Guide to Environmental
Assessment Requirements for the Electricity Projects” (MOE Guidelines), the subject
230 kV transmission line options are considered a Category C type project. Category C
projects are major projects with known significant environmental effects. These projectsrequire an Individual EA and must be approved by the Minister in accordance with
subsection 5(1) and 5 (2) of the EAA.
There is a potential for the 230 kV line options to also "trigger" an environmental
assessment screening under the Canadian Environmental Assessment Act (CEAA),
should a federal authority perform one or more of the following: grant money or any
other form of financial assistance to the project; lease/sell land; or issue a
permit/approval. However, for purposes of the cost estimate at this time we have
excluded any environmental assessment requirements under the CEAA.
The proposed 115 kV line options fall within the types of projects covered by the “ClassEnvironmental Assessment for Minor Transmission Facilities” (Class EA, Ontario Hydro,
1992) document, approved under the Ontario Environmental Assessment Act. As such,
an environmental assessment study is required for the 115 kV transmission lines to be
conducted in accordance with planning and design process described in the Class EAdocument.
The identified OPA transformer and distribution stations, and SVC, Statcom or otherfacilities associated with the 115 or 230 kV options to supply Pickle Lake and remote
northern communities are assumed to be included in the environmental assessment
process.The 44 kV and 25 kV remote distribution lines do not require completion of an EA.
However, the work would be subject to numerous permits/approval and licenses from
regulatory agencies and are assumed to involve the preparation of a natural heritageexisting conditions and impact study to evaluate the routes and to fulfill permitting
requirements. As well, engagement of remote aboriginal communities on specificrouting options is also assumed to be required.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
35/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 35 of 38
Individual Environmental Assessment
Key work components for the Individual EA required for the 230 kV transmission line
options, and assumed in the SLI cost estimate, include the following:
All 230kV transmission lines will require an Individual EA, which is an extensive
undertaking involving numerous initiatives and requirements.
Class Environmental Assessment
The MOE Guidelines stipulate that 115 kV transmission lines and associated facilities(e.g., transformer station) are required to complete an environmental assessment inaccordance with the process set out in the Class Environmental Assessment for MinorTransmission Facilities (Class EA) as approved under the EA Act. Projects subject tothe Class EA are consistent with the screening level assessment process outlined underthe Electricity Projects Regulation (O. Reg. 116/01) for Category B type projects.Typically these types of projects have predictable range of effects, can be readilymitigated and are a proponent-driven self assessment process.
The scope of the environmental assessment for the 115 kV line options would involvesimilar work components as an Individual EA, however the assessment is assumed to
be less rigorous and would exclude Step 1 noted above (i.e., preparation of Terms ofReference). In general, the Class EA planning and design process includes thefollowing major steps:
1. Identify need/justification and purpose;
2. Collect relevant environmental, social and technical information;
3. Evaluate and compare site/route alternatives;
4. Identify and provide project description of the preferred design/solution;
5. Identify and assess environmental effects, including mitigation and impactmanagement measures to reduce negative environmental effects; and
6. Preparation of an Environmental Study Report (ESR) to document the EAprocess.
Consultation with external government agencies, public, Aboriginal communities aremandatory throughout the process.
Environmental Approvals, Permits and Authorizations
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
36/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 36 of 38
The proposed high voltage transmission lines to supply Pickle Lake and 44/25 kVdistribution lines to remote communities will require a number of environmental permits,
approval and authorizations under federal and provincial laws in addition to the
completion of an EA, where applicable.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
37/38
Revision: Final ReportDate: 19 October 2011
North West Ontario Transmission Cost StudyOntario Power Authority
Deliverable 2
Page 37 of 38
APPENDIX 5
The following maps are included in this report:
1. First Nations map
2. Geology map.
3. Land cover map.
4. Permafrost map.
-
8/17/2019 App 11.3 Transmission Unit Cost Study SNC Lavalin
38/38
SNC-Lavalin T&D
195 The West Mall
Toronto, ON
M9C 5K1
Phone: (416) 201 5939
Fax: (416) 231 5356E-mail: