appendix a application modifications original …= 41 t5 22.80 ... ’typical flotation trench owg....

39
APPENDIX A Application Modifications ORIGINAL PROPOSAL REVISED PROPOSAL Wetlands placement of an at-grade 24" diameter no changes pipeline within a number of small wetland areas, both inland and tidal Pipeline Installation: Horizontal Directional Drill Methodology installation of a sub-grade 24" diameter no changes pipeline at Juniper Point utilizing the horizontal directional drilling (HDD) method to a point approximately 3500 feet offshore in Long Island Sound Exit Pit Details excavation by clamshell bucket of a an HDD excavation by clamshell bucket of an HDD exit-pit: exit pit: ¯ 20’ deep x 250’ wide x 300’ long ¯ 18’ deep x 130" wide x 301’ long ¯ sidecasting/stockpiling of such ¯ removal of 5.300 cubic yards of sediment within a 65’ area on three sediment to be disposed of at an sides of such pit open water disposal site ¯ backfill the HDD exit hole with bank-run gravel Spoil Mound Warning Signage installation of illuminated navigation eliminated warning signage placed atop temporary timber piles along the route where sediment is stockpiled below the waterline

Upload: doandiep

Post on 08-Mar-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

APPENDIX A

Application Modifications

ORIGINAL PROPOSAL REVISED PROPOSAL

Wetlands

placement of an at-grade 24" diameter no changespipeline within a number of smallwetland areas, both inland and tidal

Pipeline Installation: Horizontal Directional Drill Methodology

installation of a sub-grade 24" diameterno changespipeline at Juniper Point utilizing thehorizontal directional drilling (HDD)method to a point approximately 3500feet offshore in Long Island Sound

Exit Pit Details

excavation by clamshell bucket of a an HDDexcavation by clamshell bucket of an HDDexit-pit: exit pit:

¯ 20’ deep x 250’ wide x 300’ long ¯ 18’ deep x 130" wide x 301’ long¯ sidecasting/stockpiling of such ¯ removal of 5.300 cubic yards of

sediment within a 65’ area on three sediment to be disposed of at ansides of such pit open water disposal site

¯ backfill the HDD exit hole withbank-run gravel

Spoil Mound Warning Signage

installation of illuminated navigationeliminatedwarning signage placed atop temporarytimber piles along the route where sedimentis stockpiled below the waterline

Page 2: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

Drilling Fluid Containment SystemNo details provided

Pipeline Installation: Trench Methodology

installation of a sub-grade 24" diameterinstallation of a sub-grade 24" diameterpipeline by excavating with a clamshellpipeline by excavating with a clamshellbucket from the HDD exit-pit to a location atbucket from the HDD exit-pit to a location atapproximately milepost 12 to create a trench:approximately milepost 12 to create a trench:

¯5" deep x 50’ wide x 5808’ long ¯ 5’ deep x 37" wide x 5851’ long¯ sidecast and stockpile sediments in ¯ remove a maximum of 23,000 cubic

mounds which extend over 60’ in both yards of sediment to be disposed ofdirections from the trench at an open water disposal site

¯pipe burial depth 3’ ¯ pipe burial depth 18"¯ backfill by plowing sidecast material ¯ backfill with new material consisting

back into the trench of bank run gravel

Pipeline Installation: Plow Methodology

installation of a sub-grade 24" diameter installation of a sub-grade 24" diameterpipeline by utilizing a sub-sea plow for pipeline by utilizing a sub-sea plow forapproximately 9 miles from milepost 12 to approximately 9 miles from milepost 12 tothe state line between Connecticut and New the state line between Connecticut and NewYork to create a trench: York to create a trench:

¯ 5" deep trench x 25’ wide at the top of ¯ 5’ deep trench x 25" wide at the top ofslope slope

¯ sidecasts sediment mounds ¯ sidecasts sediment moundsapproximately 25’ wide on either side approximately 25" wide on either side

¯ four subsea plow passes ¯ three subsea plow passes¯ 3" burial ¯ 2’ burial

Temporary Mooring Structures

none identified installation of four temporary mooring pilesat the HDD exit hole

Page 3: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

APPENDIX B

PLANS OF PROPOSEDPIPELINE ROUTE

From DEP R. 73 and 93

Page 4: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

-~OUND

50’Pso.~cr C~v~o S~tv~c~mc.

24" OD 0AS FICELiNEALlOt,MINT ±N2 PROFILE

Page 5: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

SCALE ~N FEET

Islander~l ~East

PLOW SECTIONGREATER THAN20 FT WATER DEPTH

g

P~o~c’r ComstmTma

CONNECTICUT ARE,:

Owo. NO. kAD 03

Page 6: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

ELEVATION

HDD EXIT HOLEVZRT SCALE: ~’- 30"

Page 7: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

PIAN

Islander~b~aSt’ ’ =, :,~i~l__

REVISIONS

PROPOSED 24" PIPELINE INSTALLATION

FROM BRANFORD, CONNECTICUTTO LONG ISLAND, NEW YORK

DRAWN BY: K.M.A, CHECKED BY: J,H.E.

OATE: 12-A-O1 APPROVED BY:

SCALE: AS SHOW~ SHEET: 2 of 21REV

DWG. NO. Sheet 101 of ~20 I)

Page 8: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

283

LONG IS~ND SOUND -- - ~ Ij

FROM BRANFORD, CONN~CTICU~TO LONG ISLAND, NEW YORK

LEGEND

DRA’,~N BY: K.MA CHECKED BY:

DATE: 12-4-01 APPROVED BY:

SCALE: AS SHOWN SHEET: 3 of 21REV

DWG. NO. Sheet 102 of 120 [)

Page 9: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

LONG ISLAND SOUND

PLAN

REVISIONS

PROPOSED 24+ PIPELINE INSTALLATIOFFROM BRANFORD, CONNECTICUT

TO LONG ISLAND, NEW YORK

DRAWN BY: K.M A. CHECKED BY: JH E

DAIZ: 12-4 01 APPROVED BY:

Page 10: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

LONG ISLAND ~OUND

Islander~l~East

PLAN

REV?SIONS

PROPOS[O 24" PIP~LINE INSTALLATIONFROM BRANFORD, CONNECTICUT

TO LONG ISLAND, NEW YORK

DRAWN BY: KM A. CHECKED BY: d

DATE: 12-4-01 APPROVED BY:

DWG. NO. She,~,t 104 OF 120 [)

Page 11: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

Islnnder~Fklst !

LONG ISLAND SOUND

PLAN

)ROPOSED 24" PIPELINE INSTALLATIONFROM BRANFORD, CONNECTICUT

TO LONG ISLAND, NEW YORK

ORA’�~I BY: K.M.A. CHECKED BY: J,H E,

DATE: 12-4-D1 APPROVED BY:

SCALE: AS SHOWNSHEET: 6 of 21

NO. Sheet ~05 ot 120 D

Page 12: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

LONG ISLAND SOUND

PLAN

DWG, NO. Sheet 106 of 120 ()

Page 13: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

LONG ISLAND SOUND

7O

PLAN

REVISIONS

DRAWN BY: K.M.A. CHECKED BY: JH.E

DATE: 12-4 01 APPROV[D BY:

OWG. NO. Sheet 10~ of 120 [~

Page 14: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

LONG ISLAND SOUND

LEGEND

Isla nder~ItEast

PLAN

REVISIONS

~ROPOSED 24" PIPELINE INSTALLATIONFROM BRANFORO, CONNECTICUT

TO LONG ISLAND, NEW YORK

DRAWN BY: K,MA, CHECKED BY: J.HE

DATE: 12-5-01 APPROVED BY:

SCALE: AS SHOWN SHEET: 9 of 21

DWG, NO. Sheet 10~ OF 120 I)

Page 15: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

LONG ISLAND SOUND

PLaN

PROPOSED 24" PIPELINE INSTALLATIO~FROM BRANFORD, CONNECTICUT

TO LONG ISLAND, NEW YORK DWG. NO. %hee[ 109 of 120

Page 16: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

LONG ISLAND SOUND

PLAN

PROPOSED 24" PIPELINE INSTALLATIONFROM BRANFORD. CONNECTICUT

TO LONG iSlAND, NEW YORKRE~SIONS

LEGEND

DRAWN BY: K.M.A CHECKED BY: JH.E.

DATE: 12-5-01 APPROVED BY:

SCALE: AS SHOWNSHEET: 11 of 21

DWG. NO. Sheet 110 of 120 [)

Page 17: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

APPENDIX C

HDD SEGMENT

From DEP R. 7 and 93

Page 18: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

HDD LA YOUT: SUPPORT VESSELS

Page 19: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

DIRECTIONAL DRILLING SHORE TO WATER (GENERAL LAYOUT)NOT TO SCALE

I~lander~ LONG ISLAND SOUND ORAWN BY: K.M.A. CHK’D. BY: J.H.E.

TYPICAL DIRECTIONAL DRILLING DATE: 12-31-01 APPRV, BY:

SHORE TO WATER DWG, NO. SK-4 I’@

Page 20: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

I

{TOE OF

MOOR)NG PIUNGS(REiWOVE PRIOR TO BACKFILL)

HDO EXiT POINT

LONG.= 72 46 01.25

Y= 14,992,t 53.34’LAT,= 41 t5 22.80

SLOUCH AREA

±250’

PLAN

(TOP OF SLOPE) "-~

PROFILE"

(TOE OF SLOPE)~

130’

SECTION~SCALE: N.T.S. G.

(’fop OF SLOPE)

Islander ~1~

LONG ISLAND SOUNDNEARSHORE CONNECTICUT

DRILLED CROSSING ~Xff POINTDRAWN BY: K.M.A. CHK’D. BY: J.H.E.DATE: 1-2-02 APPRV. BY:

DWG. NO. SK-IO I~’

Page 21: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

APPENDIX D

FLOTATION TRENCH

From DEP R. 7

Page 22: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

TYPICAL FLOTATION TRENCH CROSS-SECTIONSCALE: N,T,S.

NOTE: THIS TRENCH REQUIRED IN SHALLOW AREAS TO ACHIEVE MINIMUM BARGE FLOTATION DEPTH OF 8 FEET.

I~aasnder~ LONG ISLAND SOUND DRAWN CHK’D. BY: J.H,E.FOR COMMENT

DATE: I-I-02PRELIMINARy APPRV BY:A 1-3-02 K,MA

’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~

Page 23: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

APPENDIX E

TASKFORCE TECHNICALPRESENTATIONS

Page 24: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 1 of 11

PresentationsHOME WELCOME ABOUT US EDUCATION ENERGY SOLUTIONS ENERGY INFORMATION POLICY

Technical PresentationsTask Force/Working Group

Executive Order 26, Public Act 02-95

May 17, 2002Task Force/Working GroupOrganizational Meeting

Commissioner Donald W. Dowries,Department of Public Utility Control

Commissioner Arthur J. Rocque, Jr.,Department of Environmental Protection

Joel M. Rinebold, Executive DirectorInstitute for Sustainable Energy

Overview and Intent of Ex~ecutiv~eOr~der 2~6

June 6, 2002Workshop Training

Tom KileyNew England Gas Association

Craig KazinISO New England

Betsey WingfieldConnecticut DEP

Provided in/brmation regarding electric andgas dispatch, market thctors, rate design andsystem design

Provided information regardingenvironmentaland natural resource criteria relevant todecision-making processes for energyrelated facilities including activities in oraffecting Long Island Sound

Public Input:

htt~://www.easternct.edu/depts/sustainenergy/taskF~rceW~rkingGr~up/tfwgPresentati~ns.htm11/20/2006

Page 25: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 2 of 11

June 10June 11June 12June 13June 25

Community of Norwalk Public HearingCommunity of Clinton Public HearingCommunity of Hartford Public HearingCommunity of Danbury Public HearingCommunity of Bridgeport Public Hearing

July 8, 2002Investigation of habitat and oyster beds

John VolkDepartment of Agriculture

John CurtisDepartment of Agriculture

Mike LudwigNational Marine Fisheries Service

Aquaculture

Aquaculture

Marine Fisheries

July 16, 2002Investigation of fisheries and ecological habitat

Milan BullConnecticut Audubon

Rich JacobsonConnecticut DEP

Habitat

Riparian buffers/fisheries

July 18, 2002Energy Issues Presentation

Senator Donald WilliamsRepresentative Jessie Stratton Overview & intent of Public Act 02-95

Attorney General Richard Blumenthal Regional needs

Consumer Counsel Mary Healey Consumer Issues

Harold W. BordenPSEG Power Generation

Chris JamesConnecticut DEP

Air Permitting for Distributed Generation( 252 KB~)

http://www.easternct.edu/depts/sustainenergy/taskForceWorkingGroup/t fwgPresentations.htm11/20/2006

Page 26: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 3 of 11

Joel GordesSolar Design Service

Security

Dan SoslandEnvironment Northeast

Conservation and Load Management

Charlotte Pyle, PhD., USDA Vernal Pools, Landscape Fragmentation,Natural Resources Conservation Service Invasive Species

David SmallMetropolitan District Commission Massachusetts ROWManagement

Dr. Mark MitchellConnecticut Environmental Justice

CoalitionEnvironmental Justice

Cynthia JenningsAttorney at Law

Environmental Equity

David Brown, ScD.Environment & Human Health Inc.

Human Health Concept

September 4, 2002(Joint Task Force/Working Group)

Cindy JacobsDepartment of Public Utility Control

Role of the Department of Public UtilityControl

Craig Kazin, ISO New EnglandRich Kowalski, ISO New England

Richard Soderman, CL&PBruce Blakely, CL&P

ISO-NE Electric Transmission Planning~’fQr_Connecticut and New En_glland~ andforec asfi ng(25OKB)LPD .F_)

Electric Use ForecastingA1.38 MB) (PDF)

S.Derek Phelps, Executive DirectorConnecticut Siting Council (CSC)

Jurisdiction of the CSC, and work levels

httn://www.easternct.edu/deots/sustainenerl~y/taskForceWorkingGroup/t fwgPresentations.htm11/20/2006

Page 27: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 4 of 11

September 4, 2002(Task Force)

Randy Mathura Gas Pipeline Review and CertificationProcessFederal Energy Regulatory Commission 4~ KB) (PDF)

Eric Johnson, ISO New EnglandRich Kowalski, ISO New England Status of transmission project and proposals

September 10, 2002(’Working Gronp)

Walter ZengerEPRI

Cable technologies and land-basedapplications(895 KB) (PDF)

John EngelhardtUSI

USI experience and installation issues

additional material (928KB) (PDF~

Greg SullivanNStar

Boston Edison lines and experience

John MillerTransEnergie

Direct current experience in Australia

additional material (2.53 MB) (PDF~

Mike McCarthyAmerican Superconductor

Future cable technologies(29~

September 12, 2002(Task Force)

Ed GonzalesDuke Energy Company Natural Gas Pipeline Installations

Dave WarmanIroquois Gas Transmission System

Long Island Sound installation andexperience

http://v~w.eastemct.edu~depts/sustainenergy/taskF~rceW~rkingGr~up/tfwgPresentati~ns.htm11/20/2006

Page 28: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 5 of 11

John MillerTransEnergie

Electric Transmission Line Installations

Roger ZaklukiewiczCL&P

Status of existing 138-kV line

September 18, 2002(Working Group)

Michael SmalecSNG/CNG

Overview of Distributed Generation (DG)

John TroccioliUTC Fuel Cells

Fuel Cell Technology

Jim WattsIngersoll-Rand

Microturbine Technolog~~_.28) MB (PDF)

Janet BesserLexecon

Issues and Implementation of DG(132 KB) (PDF)

John MutchlerCL&P

CL&P Programs-C&LM( 75~D_F~’~additional material (65KB)(PDF)

Joseph HebertUnited Illuminating

U~I ~_a_ms-Conservation & Load Mngmt.{2! 4~P~F~I

Cindy Jacobs, DPUCChris James, DEP

New England Demand Response Initiative( 1.98 MB) (PDF)

Craig KazinISO New England

ISO New England Demand ResponseProgram

http://www.easternct.edu/depts/sustainenergy/taskF~rceW~rkingGr~up/tfwgPresentati~ns.htm11/20/2006

Page 29: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 6 of 11

Devang PatelNXEGEN

Load Dispatch(4.98 MB) (PDF)

September 19, 2002(Task Force)

John VolkDepartment of Agriculture

Environmental Review-aquaculture

David SimpsonConnecticut DEP Fisheries

Mark JohnsonConnecticut DEP Fisheries

Environmental Review-marine fisheries(2,031 KB) (PDF)

Dr. Frank BohlenUniversity of Connecticut

Sedimentation Modeling ( 10,502 KB)

Mike LudwigNational Marine Fisheries Service Environmental Review-essential fish habitat

(558 KB) (PDF)

October 1, 2002(Joint Task Force/Working Group)

Rich KowalskiISO-New England

Regional Transmission Expansion Plan

(597KB)(PDF)

S.Derek Phelps, Executive DirectorConnecticut Siting Council

Application requirements, publicneed/benefit and cumulative environmentaleffects

Scott MillerFERC, Office of Markets, Tariffs, and

Rates

Standard Market Design 5~531 K__B_)_LP~

(Working Group)

Robert Carberry Overhead transmission line clearance

http://www.easternct.edu/depts/sustainenergy/taskF~rceW~rkingGr~up/tfwgPresentati~ns.htm11/20/2006

Page 30: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 7 of 11

CL&P considerations (558 KB) (PDF)

Robert JontosLand-Tech Consultants Potential environmental impacts associated

with utility construction (644 KB)(PDF)additional material ~645 KB) (_P~

(Task Force)

Robert DukeThe Surety Association of America

S.Derek Phelps, Executive DirectorConnecticut Siting Council

Betsey WingfieldDEP

Natural resource performance bonds

Statutory authority to impose bondingrequirements

Statutory authority to impose bondingrequirements; bonding requirements fordirectional drilling

October 17, 2002(Joint Task Force/Working Group)

David Schlissel, Synapse EnergyEconomics IncPaul Peterson, Synapse Energy EconomicsInc.Susan Tierney

Lexicon Inc.

Public Need Standard(135 KB)(PDF)

Public Benefit Standard (231 KB) (PDFI

Paul DeCotis, Executive DirectorNew York State Energy Researchand Development Authority

Regional Energy Issues

October 30, 2002(Joint Task Force/Working Group)

Thomas Kirk, Wisvest

David Damer, Wisvest

Electric generation !markets)C914 KB)(PDF)

Electric generation (environment)

http~//www.eastemct.edu/depts/sustainenergy/taskF~rceW~rkingGr~up/tfwgPresentati~ns.htm11/20/2006

Page 31: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 8 of 11

Gabe SternCT Municipal Electrical Energy

CooperativeDr. Gary Ginsberg

Department of Public Health

Electric generation

Toxicity of insulating fluids

October 30, 2002(Task Force)

Dr. Ellen CoolLevitan & Associates, Inc.

Review of natural.gas pipeline infrastructu(170 KB)(PDF)

November 6, 2002(Joint Task Force/Working Group)

Mark DeCaprioDEP

Marika TatsutaniNortheast States for Coordinated Air

UseManagement

Environmental risk assessment and clean-uofinsulating fluids

Regional air issues(573 KB)(PDF)

November 6, 2002(Joint Task Force)

David BlattDEP

Ralph LewisState Geologist

Submerged lands leasing(2.53 MB~ P~D~3

Geology of Long Island Sound

November 13, 2002(Task Force)

Roger ZaklukiewiczCL&P

Common utility corridor (electrictransmissioncables)

Edward Gonzales, Duke EnergyJoe Reinemann, Islander EastDave Warman, Iroquois Gas

Common utility corridor (natural gaspipelines)-(516KB) (PDF)

http://www.eastemct.edu/depts/sustainenergy/taskForceWorkingGroup/t fwgPresentations.htm11/20/2006

Page 32: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 9 of 11

Dr. Mathew CordaroCenter for Management AnalysisLong Island University

Feasibility study on re-powering KeySpan’Long Island electric generating plants

November 21, 2002(Joint Task Force/Working Group)

Chairman Donald W. Downes, DPUCCommissioner Arthur J. Rocque, Jr., DEP

Presentation on Planning Authority

November 21, 2002(Working Group)

Tom MichelmanXenergy

Status of Energy Audit for the City ofNorwalk

November 21, 2002(Task Force)

Lar~y WilliamsRobert Gmnfield

Common utility corridor (fishing operations)

November 25, 2002(Joint Task Force/Working Group)

John PlunkettOptimal Energy, Inc.

Integrating conservation and load managementin transmission planning (267 KB) (PDF)

November 25, 2002(Working Group)

Robert ForresterWoodland Coalition

Dr. Richard SteinCommittee for Responsible Energy

Application process and alternatives

November 25, 2002(Task Force)

Joe WyzikEl Paso

Presentation on the proposed Blue Atlanticproject (2,145 KB) (PDF)

http://www.easternct.edu/depts/sustainenergy/taskF~rceW~rkingGr~up/tfwgPresentati~ns.htm11/20/2006

Page 33: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 10 of 11

January 22, 2003(Task Force)

James DedesNormandeau Associates, Inc.

Inventory of environmental data andidentification of data gaps/162 KB) (PDF)

February 5, 2003(Task Force)

Dr. Ellen CoolLevitan & Associates

Discussion of energy management in New Yotand New England.

February 28, 2003(Task Force)

Attorney General Richard Blumenthal Discussion of legal issues.

Dan ZaweskiLong Island Power Authority

Discussion of the LIPA Energy Plan anddistributed generation programs on Long IslantNew York/976 KB) (PDF)

David ManningKeySpan Corporation

Electric Generation and natural gas supply onLong Island (344 KB) (PDF)

Regional natural gas supply (1,971 KB)Tom Kiley

Northeast Gas Association

March 6, 2003(Task Force)

Ann RodneyU.S. Environmental Protection Agency

Discussion of EIS for dredge dj_sposal sitesin Long Island Sound (~3 324 KB~

Richard KayUniversity of ConnecticutSchool of Law

Discussion of commerce clause.

http~//www.eastemct.edu/depts/sustainenergy/taskF~rceW~rkingGr~up/tfwgPresentati~ns.htm11/20/2006

Page 34: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

The Institute for Sustainable Energy Task Force Working Group Presentations Page 11 of 11

March 12, 2003(Task Force)

DavidHopp

Larry Williams

James DedesNormandeau Associates

Effects of pipeline installation onshellfishing operations.

Status of the work by Levitan]Normandea~on the environmental portion of the scopeof work

March 25, 2003(Task Force)

First Selectman Anthony DaRosTown of Branford

Discussion of intervenor funds

Leah LopezSave the Sound

Discussion of intervenor funds

Dave WarmanIroquois Gas Transmission System, L.P.

Environmental review and permitting o!the Eastchester Extension project(11,693 KB) (PDF)

Environmental review and permitting otKent Sanders the Eastchester Extension projectNew York StateDepartment of Environmental Conservation (2,851 KB) (PDF)

Web Master I Search I Disclaimer I Site Map..~

i!~!iOFFICE: Foster Building, 670-676 Main Street, 4th Floor, Willimantic CT 06226MAILING ADDRESS: 83 Windham Street, Willimantic CT 06226

Phone (860) 465-0251 Fax: (860) 465-0261ISE Home ECSU Home

http://www.eastemct.edu/depts/sustainenergy/taskForceWorkingGroup/t fwgPresentations.htm11/20/2006

Page 35: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

APPENDIX F

PLOW SEGMENT

From DEP R. 7

Page 36: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

~) 2001, Natural Resource Group, I~c

|slander~~_Figure 6

Typical Offshore Pipeline Bury Barge (Subsea Plow)

DATE: (T~23/0,1

DRAWN ~Y: JRFLANNERY

Page 37: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

/TOW

NATURAL BOttOM

SPO~LMOUND

PLOW SHARE

MOUND

;APTURE ROLLERBO×

PIPELINE

±75’

TYPICAL PIPE TRENCH CROSS-SECTION

BY TOWED PLOW LOWERING METHODNOT TO SCALE

COMMENTPRELIMINARY

LONG ISLAND SOUNDTOWED PLOW METHODTYPICAL PIPE TRENCH

DRAWN BY: K.M.A. I CHK’D. BY:DATE: 1-17-02 L~ BY:

DWG. NO. SK- 1 2

Page 38: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

APPENDIX G

DIRECT BOTTOMDISTURBANCE

Page 39: APPENDIX A Application Modifications ORIGINAL …= 41 t5 22.80 ... ’TYPICAL FLOTATION TRENCH OWG. NO. SK-7 I~~ ... Fuel Cell Technology Jim Watts Ingersoll-Rand Microturbine Technolog~

Town & State Shellfish Bed ImpactsDirect Bottom Disturbance

Beds impacted in 3 7 f~ buffer zone of Dredge Area

Islander East Pipeline Sections